Professional Documents
Culture Documents
Transmission Planning
Transmission Planning
GENERATION
TRANSMISSION
TRANSMISSION
DISTRIBUTION 1 DISTRIBUTION 2
DISTRIBUTION
Electric Industry Reforms
1. Separation of generation and transmission
functions
2. Privatization of state-owned enterprises
3. Creation of new companies and creation of
competitive wholesale and retail markets
4. Application of performance-based
regulation (PBR) to the regulated segments
Electric Industry Reforms
Regulated
Transmission
Regulated
Distribution
Competitive
Generation
Competitive
Retail
2. Transmission Planning
Process
Need for Transmission Planning
System Reliability
Generator
Entry Power Quality
Island
Interconnection
Load
Growth
Plan Preparation
For integration
in the Philippine
Energy Plan
(PEP)
13,209 MW
Total Philippines as of June 2016
Min
12%
Vis
14%
Luz
74%
Mindanao
System Peak Demand Forecast
LUZON GRID
17,500
16,442
Average Growth Rate: 4.15%
15,500
13,495
13,500
MW
11,071
11,500
8,928
9,500
7,500
2015 2020 2025 2030
Generation Capacity
Geothermal
9.5%
Coal
Oil-Based 34.9%
16.8%
Hydro
Natural Gas
17.4%
15.5%
GN Power Expansion
1,200 MW (2019/2020) SBPL Coal
500 MW (2019)
Pagbilao 3 Coal
420 MW (2017)
Pagbilao CC
600 MW (2017)
Generation Capacity Additions
Generation plan
is a key
component of
the transmission
planning
process
Other Planning Data
Voltage
500 kV 982
± 350 kV 905
230 kV 5,548
138 kV 6,264
115 kV 192
69 kV 6,162
circuit-kilometers
Planning Methodology
(Simplified)
Develop generation
dispatch and system
loading scenarios
53% of
Luzon’s load or
about
40% of the
country’s load
Planning Criteria
Planning for Redundancy:
N-1 Contingency
Voltage Limits:
Normal Conditions & N-1 Contingencies:
Steady-state voltage range: +/- 5% of nominal for all
voltages levels
Planning Criteria
Short-circuit limits
Fault level at all nodes shall be within
equipment rating
System Stability
The grid remains stable after a transient
disturbance or any N-1 contingency for all
forecasted load conditions
Planning Methodology
(Simplified)
• Field investigation
6. Selection of • Preparation of conceptual design
Project • Cost estimates
• Economic evaluation
Developments
1. Market-based transmission planning
2. Probabilistic planning – scenario development & project
prioritization
CASTILLEJOS HERMOSA
EHV
SAN JOSE EHV
Major Projects
in Luzon
MARILAO
RP ENERGY
BARAS
500 kV Backbone
MARIVELES EHV Stage by Stage Implementation
TAGUIG
EHV
DASMARINAS
EHV
SILANG
TAYABAS
ALAMINOS EHV ATIMONAN
CALACA
PAGBILAO
EHV
STA. MARIA
Legend:
500 kV line
230 kV line
SIMLONG
ILIJAN
Major Project in Visayas
Cebu-Negros-
Panay 230 kV
Backbone
Major Project in Mindanao
Mindanao
230 kV
Backbone
energization
Planning Challenges
1. Uncertainties of some inputs
2. Lead time for transmission project
construction
3. Right-of-way issues
4. Environmental concerns
5. Policy and regulations
• Transmission plans require
approval of the Department of
Energy (DOE)
www.ngcp.ph