FORTACERO S.A DE C.V.

CORTE 2

Partida Descripción KG
3 POLIN CO. 6X2X.75 C12(.105) 6M 11,100.00
22 HSS 6" X 6" X .250" A500°B 12.20 MTS 1,926.24
HSS 6" x 3/8, acero estructural A-500 Gr. B, tramo
24 5,252.44
de 12.20 m.
30 HSS 8" X 8" X .500" A500°B 12.20 MTS 1,744.31
34 HSS 8" X 4" X 5/16" 1,272.00
49 IPR 12"x40 lb/ft 760.00
60 IPR 16"X 67 lb/ft 3,995.47
65 IPR 18"X35 lb/ft 5,353.64
86 IPR 6"X 9 lb/ft 8,191.89
95 PLACA 1 1/4" X 8' X 20' A-572°50 8,508.00
102 PLACA 1/2" X 6' X 20' A-572°50 TEMPER 32,731.60
PLACA 1/4"X 8´ X 40´ A-572°50 TEMPER 244.80
PLACA 5/8"X 8´ X 40´ A-572°50 TEMPER 477.50
PLACA 7/8"X 8´ X 40´ A-572°50 TEMPER 853.20

TOTALES 82,411.09
PRIMERA ORDEN DE SUMINISTRO -15,226.46
TOTAL DE MATERIAL EN ORDEN SUMINISTRO
AUTORIZADA 611,467.00

TOTAL DE MATERIAL RECIBIDO 548,284.00

MATERIAL FALTANTE 63,183.00

MATERIAL ENTREGADO
MATERIAL EN ESPERA DE SUMINISTRO
MATERIAL FALTANTE

GRAFICO DE ENTREGAS

63,183.00 kg

548,284.00 kg
FORTACERO S.A DE C.V.
TRAMO 6 FRENTE 3 ENTREGA 1 ENTREGA 2 ENTREGA 3 ENTREGA 4 ENTREGA 5 ENTREGADO FALTANTE
Partida Descripción pzas KG pzas KG pzas KG pzas KG pzas KG KG KG
3 POLIN CO. 6X2X.75 C12(.105) 6M 369.00 11,100.00 11,100.00 0.00
9 HSS 10"X 10" 1/2" 7.00 7,938.00 7,938.00 0.00
20 HSS 16" X 16" 5/8" 5.00 11,570.00 11,570.00 0.00
22 HSS 6" X 6" X .250" A500°B 12.20 MTS 13.00 4,498.00 4,498.00 0.00
24 HSS 6" x 3/8, acero estructural A-500 Gr. B, tramo de 12.20 m. 14.00 7,000.00 21.00 10,500.00 17,500.00 0.00
26 HSS 6" x 4" x 5/16, acero estructural A-500 Gr. B, tramo de 12.20 m. 18.00 6,264.00 6,264.00 0.00
30 HSS 8" X 8" X .500" A500°B 12.20 MTS 7.00 6,216.00 8.00 7,104.00 13,320.00 0.00
34 HSS 8" X 4" X 5/16" 3.00 1,272.00 1,272.00 0.00
45 IPR 12"x14 lb/ft 61.00 15,740.00 15,740.00 8,367.20
49 IPR 12"x40 lb/ft 1.00 760.00 760.00 0.00
50 IPR 14"x22 lb/ft 30.00 12,040.00 12,040.00 11,896.40
60 IPR 16"X 67 lb/ft 24.00 29,085.00 6.00 7,260.00 36,345.00 0.00
65 IPR 18"X35 lb/ft 14.00 9,060.00 9,060.00 0.00
71 IPR 21"X44 lb/ft 35.00 28,005.00 3.00 2,460.00 30,465.00 4,820.00
75 IPR 21"X73 lb/ft 27.00 35,620.00 35,620.00 0.00
78 IPR 24"X55 Lb/ft 15.00 15,240.00 15,240.00 7,020.00
80 IPR 24"X68 Lb/ft 14.00 17,232.00 17,232.00 13,630.00
83 IPR 27"X84 lb/ft 16.00 24,260.00 24,260.00 0.00
86 IPR 6"X 9 lb/ft 55.00 9,025.00 9,025.00 0.00
95 PLACA 1 1/4" X 8' X 20' A-572°50 3.00 22,420.00 22,420.00 0.00
100 PLACA 1 " X 6' X 20' A-572°50 14.00 85,910.00 85,910.00 22,900.00
102 PLACA 1/2" X 6' X 20' A-572°50 TEMPER 14.00 41,815.00 41,815.00 0.00
115 PLACA 3/4" X 6' X 20' A-572°50 TEMPER 10.00 44,870.00 44,870.00 1,685.00
130 PTR 3" X 3/16" 53.00 3,255.00 3,255.00 0.00
TOTALES 88,070.00 86,685.00 46,416.00 221,086.00 35,262.00 477,519.00 70,318.60

TOTAL DE MATERIAL EN ORDEN SUMINISTRO


AUTORIZADA 547,837.60

TOTAL DE MATERIAL RECIBIDO 477,519.00

MATERIAL FALTANTE 70,318.60

MATERIAL ENTREGADO
MATERIAL EN ESPERA DE SUMINISTRO
MATERIAL FALTANTE

GRAFICO DE ENTREGAS

70,318.60 kg

477,519.00 kg
FORTACERO S.A DE C.V.
TRAMO 6 FRENTE 3 ENTREGA 1 ENTREGA 2 ENTREGA 3 ENTREGA 4 ENTREGA 5 ENTREGADO FALTANTE
Partida Descripción KG pzas KG pzas KG pzas KG pzas KG pzas KG KG KG
3 POLIN CO. 6X2X.75 C12(.105) 6M 11,100.00 369.00 11,100.00 11,100.00 0.00
9 HSS 10"X 10" 1/2" 7,938.00 7.00 7,938.00 7,938.00 0.00
20 HSS 16" X 16" 5/8" 11,570.00 5.00 11,570.00 11,570.00 0.00
22 HSS 6" X 6" X .250" A500°B 12.20 MTS 4,498.00 13.00 4,498.00 4,498.00 0.00
24 HSS 6" x 3/8, acero estructural A-500 Gr. B, tramo de 12.20 m. 17,500.00 14.00 7,000.00 21.00 10,500.00 17,500.00 0.00
26 HSS 6" x 4" x 5/16, acero estructural A-500 Gr. B, tramo de 12.20 m. 6,264.00 18.00 6,264.00 6,264.00 0.00
30 HSS 8" X 8" X .500" A500°B 12.20 MTS 13,320.00 7.00 6,216.00 8.00 7,104.00 13,320.00 0.00
34 HSS 8" X 4" X 5/16" 1,272.00 3.00 1,272.00 1,272.00 0.00
45 IPR 12"x14 lb/ft 24,107.20 61.00 15,740.00 15,740.00 8,367.20
49 IPR 12"x40 lb/ft 760.00 1.00 760.00 760.00 0.00
50 IPR 14"x22 lb/ft 23,936.40 30.00 12,040.00 12,040.00 11,896.40
60 IPR 16"X 67 lb/ft 36,345.00 24.00 29,085.00 6.00 7,260.00 36,345.00 0.00
65 IPR 18"X35 lb/ft 9,060.00 14.00 9,060.00 9,060.00 0.00
71 IPR 21"X44 lb/ft 35,285.00 35.00 28,005.00 3.00 2,460.00 30,465.00 4,820.00
75 IPR 21"X73 lb/ft 35,620.00 27.00 35,620.00 35,620.00 0.00
78 IPR 24"X55 Lb/ft 22,260.00 15.00 15,240.00 15,240.00 7,020.00
80 IPR 24"X68 Lb/ft 30,862.00 14.00 17,232.00 17,232.00 13,630.00
83 IPR 27"X84 lb/ft 24,260.00 16.00 24,260.00 24,260.00 0.00
86 IPR 6"X 9 lb/ft 9,025.00 55.00 9,025.00 9,025.00 0.00
95 PLACA 1 1/4" X 8' X 20' A-572°50 22,420.00 3.00 22,420.00 22,420.00 0.00
100 PLACA 1 " X 6' X 20' A-572°50 108,900.00 14.00 85,910.00 85,910.00 22,990.00
102 PLACA 1/2" X 6' X 20' A-572°50 TEMPER 41,815.00 14.00 41,815.00 41,815.00 0.00
115 PLACA 3/4" X 6' X 20' A-572°50 TEMPER 46,555.00 10.00 44,870.00 44,870.00 1,685.00
130 PTR 3" X 3/16" 3,255.00 53.00 3,255.00 3,255.00 0.00
TOTALES 547,927.60 88,070.00 86,685.00 46,416.00 221,086.00 35,262.00 477,519.00 70,408.60

TOTAL DE MATERIAL EN ORDEN SUMINISTRO


AUTORIZADA 547,927.60 KG

TOTAL DE MATERIAL RECIBIDO 477,519.00 KG

MATERIAL FALTANTE 70,408.60 KG

MATERIAL ENTREGADO
MATERIAL EN ESPERA DE SUMINISTRO
MATERIAL FALTANTE

GRAFICO DE ENTREGAS

70,408.60 kg

477,519.00 kg