Technical Information

Scheduling time

Area of application
This document applies to: International
Mechanical Induction Installation Update Precast concrete tower – Installation
Electrical Rotor blade Grid connection Concrete repair Precast concrete tower – Prestressing

E-10 E-26 E-40/6.44 E2 E-66 E-82 E-115


E-12 E-30 E-40/6.44 E3 E-66/18.66 E-82 E2 E-126
E-15 E-30/3.30 E-44 E-66/18.70 E-82 E3

© Copyright ENERCON GmbH. All rights reserved


E-16 E-32 E-48 E-66/20.70 E-82 E4
E-17 E-33 E-53 E-70 E4 E-92
E-18 E-40 E-58/10.58 E-70 E4-2 E-101
E-20 E-40/6.44 E-58/12.58 E-70 E4-3 E-112

CS12 CS20 CS32 CS44b CS58b CS70b CS112a


CS16 CS30 CS40 CS48a CS66 CS82a CS126a
CS17 CS31a CS44a CS58a CS70a CS101a

Document details
Document ID TD-esc-02-de-en-11-033 Rev002 Scheduling time

Confidentiality INTERNAL

Date Language DCC Plant/department


2015-06-18 en DD Service Deutschland GmbH / Mechanical Engineering / Electrical Engineering

TD-esc-02-de-en-11-033 Rev002 Scheduling time i of ii


Technical Information
Scheduling time
Revision table
Revision Date Section Change
000 2011-07-09 - Document created
001 2013-01-22 2 Time added/changed
002 2015-06-18 1 Updated according to latest situation
Time for 4-year mechanical maintenance added
2
Time added/changed

© Copyright ENERCON GmbH. All rights reserved


- Document title changed

TD-esc-02-de-en-11-033 Rev002 Scheduling time ii of ii


Technical Information
Scheduling time

1 General information
This Technical Information document provides an overview of how much time has to be scheduled for maintenance of the various WEC types. The sched-
uled maintenance times are indicated in man-hours.
This time is based on carrying out maintenance under the following conditions:
 Performing all work steps according to instructions (including optional maintenance activities and ancillary tasks such as e.g. climbing).
 All necessary measuring instruments, materials and equipment are available.
 No faults.
Under other conditions, schedule shorter or longer hours.

© Copyright ENERCON GmbH. All rights reserved


According to the maintenance instructions, extensive cleaning work lasting more than 0.5 man hours (e.g. if a large amount of grease leaks in the spinner
area) and paintwork on surfaces larger than 100 cm² should be recorded separately on the service report. Repairing defects, carrying out updates, retrofit-
ting and remaining tasks are also considered as separate tasks. For this type of work, separate orders need be created by Technical Service Dispatch or
requested by Field Service staff and the time accordingly documented.

TD-esc-02-de-en-11-033 Rev002 Scheduling time 1 of 3


Technical Information
Scheduling time
2 Scheduling time
Type Mechanical 4-year mechanical Electrical
Visual maintenance Grease maintenance
WEC type maintenance maintenance maintenance
E-10, E-20 Discontinued Discontinued 6.00 Discontinued 11.00
E-15, E-16 Discontinued 2.00 6.00 Discontinued Discontinued
E-17, E-18 Discontinued 2.00 6.00 8.00 Discontinued
E-30 2.00 5.00 11.00 15.00 15.00

© Copyright ENERCON GmbH. All rights reserved


E-30/3.30 and E-33 2.00 5.00 8.00 10.00 12.00
E-32/33 2.00 7.00 12.00 16.00 12.00
E-40 3.00 6.00 12.00 16.00 11.00
E-44/E-48/E-53 2.50 5.00 10.00 14.00 11.00
E-58 4.00 9.00 12.00 16.00 18.00
E-66 4.00 9.00 12.00 16.00 18.00
E-70 E4/E-70 E4-2/E-70 E4-3 3.00 8.00 12.00 18.00 20.00
E-82 3.00 8.00 12.00 18.00 21.00
E-82 E2/E-82 E3/E-82 E4 3.00 8.00 12.00 18.00 21.00
E-92 3.00 8.00 12.00 14.00 21.00
E-101 6.00 10.00 20.00 24.00 28.00
E-112 8.00 13.00 56.00 66.00 55.00
E-115 12.00 16.00 26.00 30.00 30.00
E-126 8.00 14.00 100.00 110.00 100.00

TD-esc-02-de-en-11-033 Rev002 Scheduling time 2 of 3


Technical Information
Scheduling time
3 Points of contact
Service technicians Technical Service Dispatch
Technical Service Dispatch ESC Electrical or Mechanical Engineering Department

© Copyright ENERCON GmbH. All rights reserved


TD-esc-02-de-en-11-033 Rev002 Scheduling time 3 of 3