TD Esc 02 de en 11 007 Rev001a WEC Task Completion Notification
TD Esc 02 de en 11 007 Rev001a WEC Task Completion Notification
TD Esc 02 de en 11 007 Rev001a WEC Task Completion Notification
Electrical Rotor blade Grid connection Concrete repair Precast concrete tower – Prestressing
CS101a
CS112a
CS126a
SCADA
CS44b
CS58b
CS70b
CS31a
CS44a
CS48a
CS58a
CS70a
CS82a
CS12
CS16
CS17
CS20
CS30
CS32
CS40
CS66
BF 83 17 01 BF 97 20 01 BF 98 25 01 BF 112 24 01 BF 131 36 02 BF 137 24 02 BF 97 20 03
Confidentiality INTERNAL
Revision table
Revision Date Section Change
000 2011-02-24 - Document created
Confirmation text messages added for precast
3.4 Content of concrete tower finishing work (inside) and precast
001 2011-04-13 confirmation text
concrete tower grouting.
message
Service hoist installation added
001a 2015-07-27 WEC types added to scope of application
Page 1 of 5
ENERCON GmbH
Technical Information Dreekamp 5 26605 Aurich
WEC task completion notification Phone: +49 (4941) 927-0
Fax: +49 (4941) 927-109
General information
To improve planning, notification of work completion (installation, grid connection, pre-commissioning,
commissioning, service hoist installation, 300 h maintenance, updates, concrete tower pre-assembly,
completion of concrete tower assembly & precast concrete tower prestressing and grouting) is sent to
Aurich by text message. This notification of completion / feedback has to be sent from all sites worldwide
after completion of each of the listed tasks.
This document replaces the following Technical Information documents:
s-me-02-ger-xxx-08-001 (WEC task completion notification)
i-me-02-ger-xxx-08-005 (WEC task completion notification) and
i-ct-02-ger-xxx-09-003 (WEC task completion notification).
The contents of this document have been updated.
1.1 Time
Notifications must be sent on the same day the work has been completed.
For installation, do not send a completion notification unless the WEC has been completely
installed with the rotor blades.
Page 2 of 5
ENERCON GmbH
Technical Information Dreekamp 5 26605 Aurich
WEC task completion notification Phone: +49 (4941) 927-0
Fax: +49 (4941) 927-109
Do not enter any other text into the e-mail (no greetings, explanations or e-mail signature);
otherwise, this will also be sent per text message (max. 160 characters).
Page 3 of 5
ENERCON GmbH
Technical Information Dreekamp 5 26605 Aurich
WEC task completion notification Phone: +49 (4941) 927-0
Fax: +49 (4941) 927-109
To ensure that the messages can be committed correctly to the database in Aurich, the
templates below must be used without modifications.
Replace the “xxxx” with the respective details. For dates, use the DD.MM.YY format.
It is essential that the date is identical to the final date on the respective report sheet!
For updates, do not enter the serial number. Enter the WBS (PSP) element (the preceding “S”
stands for Service).
Precast concrete tower *1#Prestressing W-0XXXX-XXX start XX.XX.XX end XX.XX.XX Team
prestressing XXXXXX
Precast concrete tower *1#Grouting W-0XXXX-XXX start XX.XX.XX end XX.XX.XX Team
grouting XXXXXX
Page 4 of 5
ENERCON GmbH
Technical Information Dreekamp 5 26605 Aurich
WEC task completion notification Phone: +49 (4941) 927-0
Fax: +49 (4941) 927-109
Service hoist *1#service hoist W-0XXXX-XXX start XX.XX.XX end XX.XX.XX Team
installation XXXXXX
Example: *1#Commissioning W-03925-001 start 31.01.11 end 03.02.11 Team Jones / Smith
Page 5 of 5