Technical information

Handling Permit to work


as per EN 50110 Part 1 fpr MV/HV systems

Area of application
This document applies to: switching authorised persons who are employees of ENERCON

Mechanical Induction Installation Update Precast concrete tower – Installation


Electrical Rotor blade Grid connection Concrete repair Precast concrete tower – Prestressing

E-10 E-26 E-40/6.44 E2 E-66 E-82 E-112


E-12 E-30 E-40/6.44 E3 E-66/18.66 E-82 E2 E-115
E-15 E-30/3.30 E-44 E-66/18.70 E-82 E3 E-115 E2
E-16 E-32 E-48 E-66/20.70 E-82 E4 E-126
E-17 E-33 E-53 E-70 E4 E-92 E-126 E2
E-18 E-40 E-58/10.58 E-70 E4-2 E-101 E-126 EP4
E-20 E-40/6.44 E1 E-58/12.58 E-70 E4-3 E-101 E2

Battery Charging System HV_Sub MewaCt1 PDI_1 SCADA_ESLD


CLC HYDRO MSpg.-Erf PDI_2 SI
Display MCU MV_Dis RTU SOLAR
FCU METEO MV_Spc SAI STATCOM
GDA MewaBI1 MV_Sub SCADA_DOS HV_Sub

Document details

© ENERCON GmbH. All rights reserved.


Document ID TD-esc-02-de-en-16-005 Rev000a Handling Permit to work as per EN 50110 Part 1 for
MV_HV systems

Confidentiality INTERNAL

Date Language DCC Plant/department


2016-04-22 en DD Service Deutschland GmbH/Grid Operation

Revision table
Revision Date Section Change
000 2016-02-25 - Document created
000a 2016-04-22 - corrected numbering

TD-esc-02-de-en-16-005 Rev000a Handling Permit to work as per EN 50110 Part 1 for MV_HV systems i of ii
Technical information
Handling Permit to work
as per EN 50110 Part 1 fpr MV/HV systems

Table of contents
1 General information ...............................................................................................................1
1.1 When to carry out work .....................................................................................................1
1.2 Reason for the instructions ................................................................................................1
2 Preparatory work ....................................................................................................................1
3 Required work steps ..............................................................................................................1
3.1 Issuing of the “Permit to work” ...........................................................................................1
3.2 Filling out the form .............................................................................................................2
3.3 Filing the form ...................................................................................................................5
4 Contact....................................................................................................................................5

© ENERCON GmbH. All rights reserved.

TD-esc-02-de-en-16-005 Rev000a Handling Permit to work as per EN 50110 Part 1 for MV_HV systems ii of ii
Technical information
Handling Permit to work
as per EN 50110 Part 1 fpr MV/HV systems

1 General information
This document replaces Technical Instruction document TD-GO-01-ger-xxx-14-024. Its content has
been updated according to the most recent findings.
This information describes how to handle the “Permit to work” form (TD-esc-03-de-xx-16-005).

1.1 When to carry out work


The tasks described in this information must be carried out every time the “Permit to work”
is issued.

1.2 Reason for the instructions


According the EN50110 part 1 after completion of the work safety a permission to start work has to
be granted to the workers.
This means for every work in the MV/HV area a permission to start work needs to be given.
It doesn`t matter if this is an electrical or non- electrical task.
Only the nominated person in control of the work activity is allowed to issue the permission to start
work.
To avoid mix-ups and misunderstandings between the cooperating parties involved on site the
permission to start work has to be handed out in written form.

© ENERCON GmbH. All rights reserved.


2 Preparatory work
Before the issuing of the “Permit to work” you must adhere to the procedure instructions “Work
supervision on MV/HV premises” (TD-GO-05-xx-008).
Also the instruction for safe use (BA_bl_1040) “Working in medium-voltage and high-voltage are-
as” must be known and understood.

3 Required work steps

3.1 Issuing of the “Permit to work”


The switching authorisation dispatcher of the Grid Operation department defines the responsibili-
ties during the switching conversation.
In case of a line switching operation the switching authorised technician additionally makes a note
in the “Switching order documentation” form (TD-esc-03-de-xx-16-036).
The responsibilities can be seen then in this document.
If the decision during the conversation has been made, that the ENERCON employee who is carry-
ing out the switching operations is responsible for the work activity, then he has to give the permis-
sion to start work.
This is generally the case if for the work safety only a switching off procedure of the MV transform-
er is necessary.
When line switching operation is required, it’s possible that the responsibility for the work activity
e.g. lies on the customer side.
The permission to start work has to be documented in the “Permit to work” form
(TD-esc-03-de-xx-16-037).
The document number from the header of the form has to be provided to the Grid Operation coor-
dinator during the switching conversation, because it has to be entered in the database.
After the document has been filled out and signed by both, the worker as well as the person grant-
ing the permission, the worker has to get the duplicate of the form.
The nominated person in control of the work activity keeps the original paper.

TD-esc-02-de-en-16-005 Rev000a Handling Permit to work as per EN 50110 Part 1 for MV_HV systems 1 of 5
Technical information
Handling Permit to work
as per EN 50110 Part 1 fpr MV/HV systems

The “Permit to work” form (TD-esc-03-de-xx-16-037) is allowed to use only if the


switching authorised ENERCON employee is the nominated person in control of the work
activity.

After finishing the task the “Permit to work” has to be returned to the nominated person in control of
the work activity in writing.
If there is no chance that the person who has issued the “Permit to work” is receiving back this
permission, he has to deposit this form at a suitable place.
The switching authorised technician who takes over the responsibility and will be the nominated
person in control of the work activity then, has therefore the possibility to get back the permission
on the original document.
This measure avoids misunderstandings and mix-ups during the switching on procedure.

3.2 Filling out the form

© ENERCON GmbH. All rights reserved.


Enter the location:
e.g. - Name of the wind farm
- Name of the transmission substation
Enter the wind turbine:
e.g. - WEC serial number
- MV substation

Enter the work site or facility part:


e.g. - Medium-voltage transformer
Enter the exact designation,
- Medium-voltage switchgear
if available.
- Low voltage distribution

Enter the task to be carried out:


e.g. - Repair of medium-voltage transformer
- Repair of switchgear

Enter the switch-off point(s):


e.g. - Switchgear panel 3
- MV substation panel 2
TD-esc-02-de-en-16-005 Rev000a Handling Permit to work as per EN 50110 Part 1 for MV_HV systems 2 of 5
Technical information
Handling Permit to work
as per EN 50110 Part 1 fpr MV/HV systems

Date and time / The 5 safety rules:


Fill in the date and time of issuing of the “Permit to work”.
Cross out the not applicable words in the sentence: ”The 5 safety rules ...”.

From:
Fill in full name, complete company name (e.g. WEA Service Nord-West),
Enter the telephone number and signature of the party issuing the “Permit to work”.

© ENERCON GmbH. All rights reserved.


To:
Fill in full name, complete company name (e.g. company XYZ),
Enter the telephone number and signature of the party receiving the
“Permit to work”.

Place:
Fill in the location of the safety measure here.
- Serial number of the wind turbine including panel name.
- MV substation, including panel name
- Transmission substation, including panel name

Measure:
Measures in accordance with the five safety rules can be filled in this field.
e.g. - Earthing switch panel 3 switched on
- Earthing switch panel 3 locked with padlock
Transmission Substation:
- Disconnector of panel -C01 blocked
- Local/remote switch of panel -E01 set to local

TD-esc-02-de-en-16-005 Rev000a Handling Permit to work as per EN 50110 Part 1 for MV_HV systems 3 of 5
Technical information
Handling Permit to work
as per EN 50110 Part 1 fpr MV/HV systems

Date / time:
Fill in the date and time of establishing (installing) the occupational health and safety
measures.

For works like cable measurements it is also possible to fill in at point 8, 9 and 10 the
temporally removing of the occupational health and safety measures.

© ENERCON GmbH. All rights reserved.


Date and time:
Fill in the date and time of the returning of the “Permit to work”.

From:
Fill in full name, complete company name (e.g. Cable Technics Corp.),
telephone number and signature of the party giving back the “Permit to work”.

To:
Fill in full name, complete company name (e.g. WEA Service Nord-West),
telephone number and signature of the switching authorised
ENERCON technician, who has to get back the “Permit to work”.

Permit for energisation issued:


After finishing the work and giving back the „Permit to work“ mark “Yes”, if a
permit for energisation can be given.
If a energisation is not possible, mark “No”. The reason has to be documented in
the comments (15). In such cases contact the respective Grid Operation department
to clarify how to proceed. Finally the “Permit to work” remains unaffected and can be
given back.

In cases of work without electrical background section 14 has not necessarily to be filled
out.

TD-esc-02-de-en-16-005 Rev000a Handling Permit to work as per EN 50110 Part 1 for MV_HV systems 4 of 5
Technical information
Handling Permit to work
as per EN 50110 Part 1 fpr MV/HV systems

Comments:
Fill in important additional information.
e.g. - Reconnection currently not possible, because of ……
- Instruction for transformer room provided after disconnection
- Work at a height in excess of 2m not permitted

If safety measures have been taken by other parties, this has to be noted separately in the com-

© ENERCON GmbH. All rights reserved.


ments. Have this confirmed with a signature if possible.

3.3 Filing the form


After the “Permit to work” has been returned, the signed original document has to be filed in the
“Grid Operation instructions + forms” folder for a period of one year.

4 Contact
Switching authorised employees Switching authorised Grid Operation coordinators
Switching authorised Grid Operation coordinators Operational Administration at Grid Operation

TD-esc-02-de-en-16-005 Rev000a Handling Permit to work as per EN 50110 Part 1 for MV_HV systems 5 of 5