Professional Documents
Culture Documents
Rising Mail Design
Rising Mail Design
Rising Mail Design
A. Design Data:
1 Water Requirement:
Population Year Water Demand
A) Initial 252.00 KLD
B) Intermediate 252.00 KLD
C) Ultimate 252.00 KLD
CALCULATIONS:
1st 15 years 2nd 15 years
Discharge at starting of period Qs1 252 KLD Qs2 252 KLD
Discharge at ending of 10 yrs Qe1 252 KLD Qe2 252 KLD
Average discharge Qav1 252 KLD Qav2 252 KLD
Average pumping hours
T1 14.00 hrs T2 14 hrs
during period
V = 143.534 CR r0.6575S0.5525
h = [L(Q / CR)1.81]/994.62D4.81
in which,
V = velocity of flow in m/s.
CR = pipe roughness coefficient, ( 1 for smooth pipes; < 1 for rough pipes);
r = hydraulic radius in m;
s = friction slope;
D = internal diameter of pipe in m;
h = friction head loss in m;
L = length of pipe in m; and
Q = flow in pipe in m3 / s
Roughnes
Dia of Hydraulic Head
1 st stage Dia of pipe s Total
S.No. pipe Gradient Loss per Velocity (m/s)
Flow (cum/s) (m) Coefficien Losses (m)
(mm) (m) 1000m
t (CR)
1 0.005 100 0.1 0.03 1 4.44 0.64 1.333
2 0.005 150 0.15 0.04 1 0.632 0.28 0.190
3 0.005 200 0.2 0.05 1 0.159 0.16 0.048
4 0.005 250 0.25 0.06 1 0.055 0.10 0.017
5 0.005 300 0.3 0.08 1 0.023 0.07 0.007
Roughnes
Dia of Hydraulic Head
2 st stage Dia of pipe s Total
S.No. pipe Gradient Loss per Velocity (m/s)
Flow (cum/s) (m) Coefficien Losses (m)
(mm) (m) 1000m
t (CR)
1 0.005 100 0.1 0.03 1 4.441 0.64 1.333
2 0.005 150 0.15 0.04 1 0.632 0.28 0.190
3 0.005 200 0.2 0.05 1 0.159 0.16 0.048
4 0.005 250 0.25 0.06 1 0.055 0.10 0.017
5 0.005 300 0.3 0.08 1 0.023 0.07 0.007
Kilowatts & cost of pump sets required for different pipe diameter and pipe cost
1st stage flow 2st stage flow Total
Cost of
Diameter of cost of
S.No. Class of pipe Pumping Total Pumping pipe per
Pipe KW pipe Rs.
Total Losses (H1) cost Rs. Losses KW required cost Rs. unit m
required Lacs
Lacs (H2) Lacs
1 100 DI K9 66.466 6.516 0.977 66.466 6.516 0.977 1,191.41 3.574
2 150 DI K9 65.209 6.393 0.959 65.209 6.393 0.959 1,728.48 5.185
3 200 DI K9 65.053 6.378 0.957 65.053 6.378 0.957 2,332.32 6.997
4 250 DI K9 65.019 6.374 0.956 65.019 6.374 0.956 3,103.50 9.311
5 300 DI K9 65.008 6.373 0.956 65.008 6.373 0.956 3,877.60 11.633
C. Annual Cost in Rs. Of electrical energy @ Rs.6.00 per unit (KWT hours of pumping x average days per year x 6.00)
1st Stage Flow
30680.16 x KW 1
=
2nd Stage
30680.16 x KW 2
Flow =
Pump Cost
D.
Capitalized
Pn = C =
Po(1+r)n
Po = C/(1+r)n
Where,
Po = Initial Capitalized Investment
C = Amount needed after 10 years to purchase the second stage Pumping set
r = Rate of Compound Interest = 10% per year
n = no. of
years = 10
Po = C/ 2.594
E. Energy charges capitalized
CC = CR {(1-
(1+r)-n)/n}
For values r = 10% and n = 10 years
CC = 7.606 CR
Therefore,
CC 1st Stage = 7.606 CR 1st Stage
CC 2nd Stage = 7.606 CR 2nd Stage
Present Energy Charges (CP) for 2nd stage capitalized value i.e. for CC 2nd stage
CP = CC 2nd Stage/2.594
50.000
Total of Capitalized cost for 20 years
43.29
45.000 40.97
38.68
40.000 35.94 36.94
35.000
30.000
25.000
20.000
15.000
10.000
5.000
0.000
100 150 200 250 300
Dia of Pipe in mm
A. Design Data:
1 Water Requirement:
Population Year Water Demand
A) Initial 504.00 KLD
B) Intermediate 504.00 KLD
C) Ultimate 504.00 KLD
CALCULATIONS:
1st 15 years 2nd 15 years
Discharge at starting of period Qs1 504 KLD Qs2 504 KLD
Discharge at ending of 10 yrs Qe1 504 KLD Qe2 504 KLD
Average discharge Qav1 504 KLD Qav2 504 KLD
Average pumping hours
T1 14.00 hrs T2 14 hrs
during period
V = 143.534 CR r0.6575S0.5525
h = [L(Q / CR)1.81]/994.62D4.81
in which,
V = velocity of flow in m/s.
CR = pipe roughness coefficient, ( 1 for smooth pipes; < 1 for rough pipes);
r = hydraulic radius in m;
s = friction slope;
D = internal diameter of pipe in m;
h = friction head loss in m;
L = length of pipe in m; and
Q = flow in pipe in m3 / s
Roughnes
Dia of Hydraulic Head
1 st stage Dia of pipe s Total
S.No. pipe Gradient Loss per Velocity (m/s)
Flow (cum/s) (m) Coefficien Losses (m)
(mm) (m) 1000m
t (CR)
1 0.01 100 0.1 0.03 1 15.57 1.27 4.672
2 0.01 150 0.15 0.04 1 2.215 0.57 0.665
3 0.01 200 0.2 0.05 1 0.556 0.32 0.167
4 0.01 250 0.25 0.06 1 0.190 0.20 0.057
5 0.01 300 0.3 0.08 1 0.079 0.14 0.024
Roughnes
Dia of Hydraulic Head
2 st stage Dia of pipe s Total
S.No. pipe Gradient Loss per Velocity (m/s)
Flow (cum/s) (m) Coefficien Losses (m)
(mm) (m) 1000m
t (CR)
1 0.01 100 0.1 0.03 1 15.572 1.27 4.672
2 0.01 150 0.15 0.04 1 2.215 0.57 0.665
3 0.01 200 0.2 0.05 1 0.556 0.32 0.167
4 0.01 250 0.25 0.06 1 0.190 0.20 0.057
5 0.01 300 0.3 0.08 1 0.079 0.14 0.024
Kilowatts & cost of pump sets required for different pipe diameter and pipe cost
1st stage flow 2st stage flow Total
Cost of
Diameter of cost of
S.No. Class of pipe Pumping Total Pumping pipe per
Pipe KW pipe Rs.
Total Losses (H1) cost Rs. Losses KW required cost Rs. unit m
required Lacs
Lacs (H2) Lacs
1 100 DI K9 69.139 13.557 2.034 69.139 13.557 2.034 1,191.41 3.574
2 150 DI K9 64.732 12.692 1.904 64.732 12.692 1.904 1,728.48 5.185
3 200 DI K9 64.184 12.585 1.888 64.184 12.585 1.888 2,332.32 6.997
4 250 DI K9 64.063 12.561 1.884 64.063 12.561 1.884 3,103.50 9.311
5 300 DI K9 64.026 12.554 1.883 64.026 12.554 1.883 3,877.60 11.633
C. Annual Cost in Rs. Of electrical energy @ Rs.6.00 per unit (KWT hours of pumping x average days per year x 6.00)
1st Stage Flow
30680.16 x KW 1
=
2nd Stage
30680.16 x KW 2
Flow =
Pump Cost
D.
Capitalized
Pn = C =
Po(1+r)n
Po = C/(1+r)n
Where,
Po = Initial Capitalized Investment
C = Amount needed after 10 years to purchase the second stage Pumping set
r = Rate of Compound Interest = 10% per year
n = no. of
years = 10
Po = C/ 2.594
E. Energy charges capitalized
CC = CR {(1-
(1+r)-n)/n}
For values r = 10% and n = 10 years
CC = 7.606 CR
Therefore,
CC 1st Stage = 7.606 CR 1st Stage
CC 2nd Stage = 7.606 CR 2nd Stage
Present Energy Charges (CP) for 2nd stage capitalized value i.e. for CC 2nd stage
CP = CC 2nd Stage/2.594
75.000 73.99
Total of Capitalized cost for 20 years
74.000
73.000
71.70
72.000 70.91
71.000
69.51
70.000
69.000 68.23
68.000
67.000
66.000
65.000
100 150 200 250 300
Dia of Pipe in mm
A. Design Data:
1 Water Requirement:
Population Year Water Demand
A) Initial 756.00 KLD
B) Intermediate 756.00 KLD
C) Ultimate 756.00 KLD
CALCULATIONS:
1st 15 years 2nd 15 years
Discharge at starting of period Qs1 756 KLD Qs2 756 KLD
Discharge at ending of 10 yrs Qe1 756 KLD Qe2 756 KLD
Average discharge Qav1 756 KLD Qav2 756 KLD
Average pumping hours
T1 14.00 hrs T2 14 hrs
during period
V = 143.534 CR r0.6575S0.5525
h = [L(Q / CR)1.81]/994.62D4.81
in which,
V = velocity of flow in m/s.
CR = pipe roughness coefficient, ( 1 for smooth pipes; < 1 for rough pipes);
r = hydraulic radius in m;
s = friction slope;
D = internal diameter of pipe in m;
h = friction head loss in m;
L = length of pipe in m; and
Q = flow in pipe in m3 / s
Roughnes
Dia of Hydraulic Head
1 st stage Dia of pipe s Total
S.No. pipe Gradient Loss per Velocity (m/s)
Flow (cum/s) (m) Coefficien Losses (m)
(mm) (m) 1000m
t (CR)
1 0.015 100 0.1 0.03 1 32.44 1.91 9.732
2 0.015 150 0.15 0.04 1 4.614 0.85 1.385
3 0.015 200 0.2 0.05 1 1.157 0.48 0.348
4 0.015 250 0.25 0.06 1 0.396 0.31 0.119
5 0.015 300 0.3 0.08 1 0.165 0.21 0.050
Roughnes
Dia of Hydraulic Head
2 st stage Dia of pipe s Total
S.No. pipe Gradient Loss per Velocity (m/s)
Flow (cum/s) (m) Coefficien Losses (m)
(mm) (m) 1000m
t (CR)
1 0.015 100 0.1 0.03 1 32.440 1.91 9.732
2 0.015 150 0.15 0.04 1 4.614 0.85 1.385
3 0.015 200 0.2 0.05 1 1.157 0.48 0.348
4 0.015 250 0.25 0.06 1 0.396 0.31 0.119
5 0.015 300 0.3 0.08 1 0.165 0.21 0.050
Kilowatts & cost of pump sets required for different pipe diameter and pipe cost
1st stage flow 2st stage flow Total
Cost of
Diameter of cost of
S.No. Class of pipe Pumping Total Pumping pipe per
Pipe KW pipe Rs.
Total Losses (H1) cost Rs. Losses KW required cost Rs. unit m
required Lacs
Lacs (H2) Lacs
1 100 DI K9 73.705 21.678 3.252 73.705 21.678 3.252 1,191.41 3.574
2 150 DI K9 64.524 18.978 2.847 64.524 18.978 2.847 1,728.48 5.185
3 200 DI K9 63.383 18.642 2.796 63.383 18.642 2.796 2,332.32 6.997
4 250 DI K9 63.131 18.568 2.785 63.131 18.568 2.785 3,103.50 9.311
5 300 DI K9 63.055 18.546 2.782 63.055 18.546 2.782 3,877.60 11.633
C. Annual Cost in Rs. Of electrical energy @ Rs.6.00 per unit (KWT hours of pumping x average days per year x 6.00)
1st Stage Flow
30680.16 x KW 1
=
2nd Stage
30680.16 x KW 2
Flow =
Pump Cost
D.
Capitalized
Pn = C =
Po(1+r)n
Po = C/(1+r)n
Where,
Po = Initial Capitalized Investment
C = Amount needed after 10 years to purchase the second stage Pumping set
r = Rate of Compound Interest = 10% per year
n = no. of
years = 10
Po = C/ 2.594
E. Energy charges capitalized
CC = CR {(1-
(1+r)-n)/n}
For values r = 10% and n = 10 years
CC = 7.606 CR
Therefore,
CC 1st Stage = 7.606 CR 1st Stage
CC 2nd Stage = 7.606 CR 2nd Stage
Present Energy Charges (CP) for 2nd stage capitalized value i.e. for CC 2nd stage
CP = CC 2nd Stage/2.594
114.000
Total of Capitalized cost for 20 years
111.25
112.000
110.000
108.000
106.000 103.75
104.000 101.54
102.000 99.59
99.45
100.000
98.000
96.000
94.000
92.000
100 150 200 250 300
Dia of Pipe in mm
A. Design Data:
1 Water Requirement:
Population Year Water Demand
A) Initial 1008.00 KLD
B) Intermediate 1008.00 KLD
C) Ultimate 1008.00 KLD
CALCULATIONS:
1st 15 years 2nd 15 years
Discharge at starting of period Qs1 1008 KLD Qs2 1008 KLD
Discharge at ending of 10 yrs Qe1 1008 KLD Qe2 1008 KLD
Average discharge Qav1 1008 KLD Qav2 1008 KLD
Average pumping hours
T1 14.00 hrs T2 14 hrs
during period
V = 143.534 CR r0.6575S0.5525
h = [L(Q / CR)1.81]/994.62D4.81
in which,
V = velocity of flow in m/s.
CR = pipe roughness coefficient, ( 1 for smooth pipes; < 1 for rough pipes);
r = hydraulic radius in m;
s = friction slope;
D = internal diameter of pipe in m;
h = friction head loss in m;
L = length of pipe in m; and
3
Q = flow in pipe in m / s
Roughnes
Dia of Hydraulic Head
1 st stage Dia of pipe s Total
S.No. pipe Gradient Loss per Velocity (m/s)
Flow (cum/s) (m) Coefficien Losses (m)
(mm) (m) 1000m
t (CR)
1 0.02 100 0.1 0.03 1 54.60 2.55 191.107
2 0.02 150 0.15 0.04 1 7.767 1.13 27.185
3 0.02 200 0.2 0.05 1 1.947 0.64 6.815
4 0.02 250 0.25 0.06 1 0.666 0.41 2.331
5 0.02 300 0.3 0.08 1 0.277 0.28 0.970
Roughnes
Dia of Hydraulic Head
2 st stage Dia of pipe s Total
S.No. pipe Gradient Loss per Velocity (m/s)
Flow (cum/s) (m) Coefficien Losses (m)
(mm) (m) 1000m
t (CR)
1 0.02 100 0.1 0.03 1 54.602 2.55 191.107
2 0.02 150 0.15 0.04 1 7.767 1.13 27.185
3 0.02 200 0.2 0.05 1 1.947 0.64 6.815
4 0.02 250 0.25 0.06 1 0.666 0.41 2.331
5 0.02 300 0.3 0.08 1 0.277 0.28 0.970
Kilowatts & cost of pump sets required for different pipe diameter and pipe cost
1st stage flow 2st stage flow Total
Cost of
Diameter of cost of
S.No. Class of pipe Pumping Total Pumping pipe per
Pipe KW pipe Rs.
Total Losses (H1) cost Rs. Losses KW required cost Rs. unit m
required Lacs
Lacs (H2) Lacs
1 100 DI K9 271.218 106.360 15.954 271.218 106.360 15.954 1,191.41 41.699
2 150 DI K9 90.904 35.648 5.347 90.904 35.648 5.347 1,728.48 60.497
3 200 DI K9 68.497 26.861 4.029 68.497 26.861 4.029 2,332.32 81.631
4 250 DI K9 63.564 24.927 3.739 63.564 24.927 3.739 3,103.50 108.623
5 300 DI K9 62.067 24.340 3.651 62.067 24.340 3.651 3,877.60 135.716
C. Annual Cost in Rs. Of electrical energy @ Rs.6.00 per unit (KWT hours of pumping x average days per year x 6.00)
1st Stage Flow
30680.16 x KW 1
=
2nd Stage
30680.16 x KW 2
Flow =
Pump Cost
D.
Capitalized
Pn = C =
Po(1+r)n
Po = C/(1+r)n
Where,
Po = Initial Capitalized Investment
C = Amount needed after 10 years to purchase the second stage Pumping set
r = Rate of Compound Interest = 10% per year
n = no. of
years = 10
Po = C/ 2.594
E. Energy charges capitalized
CC = CR {(1-
(1+r)-n)/n}
For values r = 10% and n = 10 years
CC = 7.606 CR
Therefore,
CC 1st Stage = 7.606 CR 1st Stage
CC 2nd Stage = 7.606 CR 2nd Stage
Present Energy Charges (CP) for 2nd stage capitalized value i.e. for CC 2nd stage
CP = CC 2nd Stage/2.594
570.00
600.000
Total of Capitalized cost for 20 years
500.000
400.000
300.000 256.61
237.56 232.44
215.05
200.000
100.000
0.000
100 150 200 250 300
Dia of Pipe in mm