SUPER STRUCTURE
SLAB
Dead Load
Slab = 0.3 x 1.00 x 2.40 = 0.72 t/m
Asphalt = 0.05 x 1.00 x 2.20 = 0.11 t/m
Rain = 0.05 x 1.00 x 1.00 = 0.05 t/m
q1 = 0.88 t/m
Live Load
Track wide g = 50 cm
Impact factor
K = 1 + 20 = 1.363636
50 + L
1
SLAB
###
3.1
###
###
1.85 Bridge Span = 5.00 m
0.30
0.30 Span = 1.85 m
Concrete
K350 s bk = 115.5 kg/cm2
Steel U 32 sy = 1850 kg/cm2
n = 17.64
1.80
Bm = 6 ho + bo
= 1.80 + 1.80 = 3.60 m
Bm = 1/4 x L Used Bm = 1.85 m
= 1.25 m
Bm = 1.57 m
Dead Load
q1 = ( 0.30 x 1.85 + 1.80 x 0.00 ) 2.40 + 0.04
= 1.37 t/m
2
Dead Load
1.37
5.00
2
M- = - 1/24 x 1.37 x 5.0 = -1.429 tm
2
M+ = 1/8 x 1.37 x 5.0 = 4.29 tm
Live Load
8.26
1.514
5.00
2
M- = - 1/24 x 1.51 x 5.0 - 0.5 x ( 1/4 x 8.26 x 5.00 )
= -6.737 tm
2
M+ =( 1/8 x 1.51 x 5.0 + 1/4 x 8.26 x 5.00 ) x 5/6
= 12.542 tm
At span
M max = 16.829 tm
3
100
40
100
40 Length = 6.00 m
1 Concrete g = 2.40 t/m3
5 Masonry g = 2.20 t/m3
Soil g = 1.70 t/m3
50
6 2 f = 30 o
0
c = 1.75 t/m2
0 180
3
7
0
8
+
100
Elevasi
4
0 75 A
250
Dead Load
Soil Embankment
4
Active force
la = Tg 2 (45 - f/2}
= 0.333333
2.50
lp = 3
H1
###
H2
H3
H = H1 + H2 - H3 = 2.6208 ton
Mo = Mo1 + Mo2 - Mo3 = 2.5381944 tm
Live Load
q2 = 1.65 t/m
P1 = 9.00 ton
Impact factor
Impact factor
K = 1 + 20 = 1.363636
50 + L
K = 1.3636364
Distribution factor
D = 1.85 = 1
1.85
Track = 6.00 m
p1 = 4.90909 t/m
p2 = 26.7769 ton
Wind Load
5
W = 1.00 x 5.00 x 2.70 x 0.15 = 2.025 ton
MA = 2.025 x 2 = 4.05 tm
Earthquake force
G = 12.825 + 70.56 = 83.39 ton
Gp = 0.05 x 83.39
= 4.16925 ton
MA = 4.16925 x 2.50
= 10.423 tm
Friction force at bearing
F = k x Dl
= 0.18 x 12.83 = 2.3085 ton
MA = 2.3085 x 2.50 = 5.77125 tm
Load Combination
Combination I
= M + (H + K) + Fa + Ah : 100%
My = 0 tm
Combination II
= M + Ta + F + Ah + A + Sr + T: 125%
My = 3.24 tm
Combination III
= Com I + R + F + A + Sr + T : 140%
N = 48.63 ton
My = 2.892857 tm
Combination IV
= M + Ah + Gp + Ta :150%
N = 45.39 ton
Mo = Mx = 20.73 tm
My = 6.949 tm
6
Reinforcement
1.50
180
I
II 100
0.0 75
Section I
N = 50.76 ton
M = 2.54 tm
ht = 180 cm h = 175 cm
b = 2.50 m
Lk = 1.50 m
e1 = C1x C2 x Lk 2 x ht = 0.00
100 ht
e2 = 0.15 x ht = 0.27
e = Eo + E1 + E2 = 0.38
ea = E +0.5xht - 0.10 = 1.230911
Used
K 350 sb = 115.5 kg/cm2
U32 sa = 1850 kg/cm2
n = 17.64
Controle
sb = sa : nxf
= 1850 : 142.70147 = 12.96413 < 115.5 OK
Requirement of bars
A = wxbxh = 22.23225 cm2 f 22 - 15 A = 156 > 22.232
A' = A x d = 22.23225 cm2 f 22 - 15 A = 156 > 22.232
Amin = 0.25 % luas beton = 150 cm2 f 22 - 15 A = 156 > 150
Section II
-0.50
P = 20.41 t/m
Mmax = Px l2 = 5.102 tm
ht = 100 cm
d = 5 cm h = 95 cm
Controle
sb = sa : nxf
= 1850 : 142.70147 = 12.96413 < 115.5 OK
Requirement of bars
A = wxbxh = 22.23 cm2 f 22 - 15 A = 156 > 22.232
A1 = A = 22.23 cm2 f 22 - 15 A = 156 > 22.232
Amin = \ = 150 cm2 f 22 - 15 A = 196 > 150
7
APPROACH SLAB
Pavement
0.30 Pavement t1 = 0.3 m
0.30 gp = 2.20 t/m3
l2 Slab t2 = 0.3 m
l1 gc = 2.40 t/m3
l1 = 4.50 m
l2 = 3.15 m
Dead Load
Pavement qp = t1 x g p = 0.66 t/m
Slab qs = t2 x g c = 0.72 t/m
q = 1.38 t/m
T
Live Load T = 10 ton
2.75
1.2
Bending Moment
M1 = 1/8 x q x L2 = 1.711631 tm
M2 = 1/4 x P x Lo x ( L - 1/2 Lo) = 5.85 tm
Mt = 7.561631 tm
Reinforcement
f 15 - 100 As = 16.08 cm2
tc = n x M x (d - X)/Ii
8
PERHITUNGAN JUMLAH TIANG PANCANG
ABUTMENT
II I
0.96
0.50
1.68
1.68
1.68
0.5
S x2 = 4x ( 0.46 + -1.04 )
= 5.19
n = 6
m = 0 (pile inclination)
Tg f = 0.5773503
9
IV Eficiency daya dukung tiang dalam kelompok
s= 1.70
Data
D= 0.5
n 3 bh
m= 2 bh
q =arc tg D
s
q =arc tg 0.5
1.70
q =arc tg 0.29
q = 16.390
Eff h = 16.390 ( 3 - 1) 2+ ( 2- ) 3
1 -
90 2 x 3
= 7
1 - 0
6
=
1 - 0
= 0.78754
Formula Meyerhoff
Qa = 40 x Nb x Ap 0.2 x N x As
+
SF1 SF2
= 75.4 + 1.51
= 76.9 ton
10
PERHITUNGAN JUMLAH TIANG PANCANG
0.50
PIER
2.50
6.00
2.50
0.50
1.25 1.25
3.00
Combination I
N = 125.52 ton
M = tm
H = ton
2 2
S x2 = 4x ( 1.50 + -1.50 )
= 18.00
n = 3
m = 0 (pile inclination)
Tg f = 0.0296793
s= 1.68
Data
D= 0.6
n 3 bh
m= 1 bh
q =arc tg D
s
11
q =arc tg 0.6
1.68
q =arc tg 0.36
q = 19.654
Eff h = 19.654 ( 3 - 1) 1+ ( 1- ) 3
1 -
90 1 x 3
= 2
1 - 0
3
=
1 - 0
= 0.85442
12