Download as pdf or txt
Download as pdf or txt
You are on page 1of 37

Site Wet Utilities 17.

IFC Design Report –C December 2022


SEVEN - ABHA
17.0. Site Wet Utilities

17.1 Introduction
This section presents the IFC design for the Abha Entertainment Complex project's wet utility network networks. Section outline is as follows:

17.1 Introduction
17.2 Codes, Regulation, and Design Standards
17.3 Water Supply Networks
17.4 Fire Fighting Networks
17.5 Sewage Network
17.6 Irrigation Network
17.7 Storm Water Drainage System

17.2 Codes, Regulations, and Design Standards

Wet Utilities Networks/Systems shall be designed according to the following codes:

NWC National Water Company


MEWA Ministry of Environment, Water, and Agriculture
MOMRA Ministry of Municipal and Rural Affairs
SASO Saudi Arabian Standards Organization.
ASTM American Society for Testing and Materials
ACI American Concrete Institute
NFPA National Fire Protection Association
SIO Saudi Irrigation Organization

IFC Design Report


SEVEN - ABHA
17.3 Potable Water Site Network
17.3.1 Introduction:
This section presents the design philosophy, criteria, and hydraulic results summary for the proposed potable water site network of Abha
Entertainment Complex.

17.3.2 General Potable Water System Description:

This document covers the potable water network scope of work for Abha site, as shown in Figure 17.3.1.
This figure describes the extent of the scope and extended scope of the project.
Google image is attached as background indicating the interfaces with the existing road in west and north location of Abha site.
The existing Ø300 DI water line which is the main source for the potable will supply to the potable tank.
The existing Ø300 mm DI line is shown in Figure 17.3.1 and the proposed tapping point is also shown from the existing Ø300 mm DI line.
The proposed tie-in potable transmission size is Ø110 mm HDPE, PN-16, PE- 100 pipe is confirmed by NWC.

A potable water source is a potable water tank located on the basement floor. To supply the potable water to the distribution network, water will
be pumped from the potable water tank which is by building/plumbing (MEP) scope.

Figure 17.3.2 presents the general layout for the potable water site network for Abha.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.3 Potable Water Site Network – Cont.

Figure (17.3.1) : Location of Abha Plot and Scope Limits

IFC Design Report


SEVEN - ABHA
17.3 Potable Water Site Network – Cont.

Figure (17.3.2) : General Layout for the Potable Water Network for Abha

IFC Design Report


SEVEN - ABHA
17.3 Potable Water Site Network – Cont.
17.3.3 Potable Water Demand:
Potable water demand is estimated based on the number of visitors and employees for different land use categories and staff/employees according
to MEWA water consumption rates per capita consumption per day.
The average day demand and peak day demand are provided in the below table also, the proposed diameter sizing calculation is also provided in
the table meeting MEWA requirements.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.3 Potable Water Site Network – Cont.
17.3.4 Design Criteria:
• Network Type
Water mains are configured in segmented grids and loops and are located within the established right-of- way or utility easement. Looping of
distribution mains is done, avoiding as many locations with dead ends as possible.
• Pressure
The network is designed to ensure a minimum pressure of 1.5 bar at the highest point within the network and a maximum pressure of 4.0 bar at
the lowest point within the network as per MEWA requirements.
• Velocity
A minimum velocity of 0.2 m/s and a maximum velocity of 2.0 m/sec is adopted in the distribution network as per MEWA.
• Pipe Size and Material
 Materials of construction shall conform to SASO, AWWA, and ASTM Standards.
 All pipes material is HDPE PN (16), PE-100.
• Cover
Minimum pipe cover is 1.0 meter below final ground level as per MEWA.
• Pipe Gradients
Minimum design gradient to allow for the movement of air-to-air valves shall be 1 in 1000 in the direction of flow and 2 in 1000 in the adverse
direction.
• Pipe Hydraulics
The Hazen-Williams Formula is used in the analysis of pressure pipe systems. The formula is as follows:
Q = K. C. A. R0.63 .S0.54
Where:
Q = Discharge in the section (m3/s, cfs)
C = Hazen-William’s roughness coefficient (unitless), C=130 is adopted
A = Flow area (m2, ft.2)
R = Hydraulic radius (m, ft.)
S = Friction slope (m/m, ft./ft.)
k = Constant (0.85 for SI units, 1.32 for US units).
• Pipe Head loss
Maximum acceptable head loss in pipes shall be 20m/km

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.3 Potable Water Site Network – Cont.

• Valves
 On main loops sufficient valves are placed to close the network during maintenance, repair, replacement, or additions. to allow flexibility of
operation, a direct buried gate valves are installed on the main.
 Electromagnetic Flow meter will be provided in chamber.
 Flow control valve will be provided in chamber.

17.3.5 Hydraulic Results Summary:


 The total flow required at tie-in with NWC 300 DI main is 5.44 and 3.62 l/sec @ peak and average day demand scenarios.
 The minimum pressure required at tie-in point with NWC 300 DI main is 2 Bar approx. The limit of pressure should be maintained in potable
water network in between 1.5 to 4 bar as per MEWA requirements which is already complied.
 The velocity in both average day and peak day scenario are complying to MEWA requirements of 0.2 to 2 m/sec.

For more details regarding the hydraulic results of the potable water system, please refer to Potable Water Site Network Hydraulic Report.
DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00001-C

17.3.6 Conclusions:
Based on the results from the model considering tank node with specified demand load, pipe size of 110 mm outer dia. HDPE PE-100 and PN-16 is
adequate to deliver the required quantity of water at needed pressure. Pressure at tank node is noted 28 psi adequate to fill the tank in the
basement.
The potable demand and pressure are shared with NWC to confirm for tapping point from 300 mm DI main.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.4 Fire Water Site Network
17.4.1 Introduction:
This section presents the design philosophy, criteria, and hydraulic results summary for the proposed Firefighting site network of Abha
Entertainment Complex.

17.4.2 General Fire System Description:


This document covers the fire water network scope of work for Abha site, as shown in Figure 17.4.1.
This figure describes the extent of the scope and extended scope of the project.
Google image is attached as background indicating the interfaces with the existing road in west and north location of Abha site.
The existing Ø300 DI water line which is the main source for potable and fire water network will supply both potable and fire tanks.
The existing Ø300 mm DI line is shown in Figure 17.4.1 and the proposed tapping point is also shown from the existing Ø300 mm DI line.
The proposed tie-in potable transmission size is Ø110 mm HDPE, PN-16, PE- 100 pipe is confirmed by NWC.

Fire water source is a fire tank located in basement floor and fire water will be pumped from the fire
tank by fire pump set to supply site firefighting network.

Figure 17.4.2 presents the general layout for the firefighting site network for Abha.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.4 Fire Water Site Network – Cont.

Figure (17.4.1) : Location of Abha Plot and Scope Limits

IFC Design Report


SEVEN - ABHA
17.4 Fire Water Site Network – Cont.

C FIGURE 17.4.2 UPDATED


Figure (17.4.2) : General Layout For Firefighting Site Network for Abha
IFC Design Report
SEVEN - ABHA
17.4 Fire Water Site Network – Cont.
17.4.3 Fire Water Demand:
During fire event, it is assumed that 2 Fire hydrants will work to cover the fire area and each fire hydrant can handle 750 gpm (2839 l/min), so total
fire demand needed in this fire event is 1500 gpm (5678 l/min) as per Appendix B of SBC-801. The two hydrants which are on comparatively
farthest location & high elevation are selected for the fire flow nodes as per MEWA. Residual pressure of 20 psi (1.4bar) is required at the farthest
hydrant during fire flow as per Appendix B of SBC-801. There are 2 fire flow scenarios included for analysis as per Client comments at 100% DD and
life safety requirements in addition to one mentioned above scenario. Scenario-1:1 Fire Flow hydrant with 1500 US GPM @ 1.4 bars
Scenario-2:2 Fire Flow hydrants each 750 US GPM @ 1.4 bars

17.4.4 Design Criteria:

• Network Type
Water mains are configured in segmented grids and loops and are located within the established right of- way or utility easement. Looping of
distribution mains is done, avoiding as many locations with dead ends as possible.
• Fire Hydrant
 Average spacing between fire hydrants is 120 m in line with Fire Life Safety Report and SBC 801.
 Each fire hydrant is designed to handle 47.3 l/s (750gpm).
 Control valve shall be installed in each hydrant connection along with bollard. Hydrants will be installed along with valve in chamber with a
protection bollard as per NWC standards details included in fire drawings.
• Pressure
The network is designed that a minimum pressure of 1.4 bars is ensured at all fire hydrants during fire events as per Appendix B of SBC-801.
• Velocity
The velocity in pipes shall be in accordance with pipe manufacturer recommendations.
• Pipe Size and Material
 Materials of construction shall conform to NWC, MEWA, AWWA, and ASTM Standards.
 All pipes material is HDPE PN (20), PE-100 and SDR-9. These shall be provided in accordance with NFPA 20, section 4.7.7)
 For mains that supply fire hydrants, pipe size shall not be less than 6 in. (150 mm) nominal size. According to NFPA24.
 The connection from the hydrant to the main shall not be less than 6 in. (150) (nominal), According to NFPA24.
 However, the fire main shall be adequate to deliver the required fire flow at the desired pressure so the main size can be increased as
needed.
• Cover
Minimum pipe cover is 1.0 meter below final ground level as per MEWA/NWC.
IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.4 Fire Water Site Network – Cont.
• Pipe Hydraulics
The Hazen-Williams Formula is used in the analysis of pressure pipe systems. The formula is as follows:
Q = K. C. A. R0.63 .S0.54
Where:
Q = Discharge in the section (m3/s, cfs)
C = Hazen-William’s roughness coefficient (unitless), C=130 is adopted
A = Flow area (m2, ft.2)
R = Hydraulic radius (m, ft.)
S = Friction slope (m/m, ft./ft.)
k = Constant (0.85 for SI units, 1.32 for US units).

• Thrust Blocks
Thrust blocks are not required as per NFPA 24, section 10.6.

• Valves
 On main loops sufficient valves are provided to close the network during maintenance, repair, replacement, or additions. to allow flexibility of
operation, a gate valves are installed on the main and on the branch.
 Air release valves are not required as per NFPA recommendations.
 Drain valves are proposed at the lowest points in the network, Final location of valves to be exactly determined on site according to site
conditions.

17.4.5 Hydraulic Results Summary:


• Scenario-1
 The results of the fire flow scenario-1 are presented in the Appendix-A.
 The minimum pressure required from the pump for the scenario-1 is 45 psi with one fire hydrant with flow of 1500 US GPM.
• Scenario-2
 The results of the fire flow scenario-2 are presented in the Appendix-B. All nodes are satisfying all constraints of pressure, flow, and velocity.
Hydraulic results indicate minimum requirements met during fire event of 2 hydrants flowing with 750 US GPM @ 1.4 bar which meet with
NFPA 24 (section C.4.1.3) and SBC 801 Appendix-B requirements.
 The minimum pressure required from the pump for scenario-2 is 42 psi with two Fire hydrants each with a flow of 750 US GPM.
For more details regarding the flow analysis and hydraulic results of the firefighting system, please refer to Fire Water Site Network Hydraulic
Report. DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00004-C.
IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.5 Sewage Network
17.5.1 Introduction:
This section describes the design philosophy, criteria, and hydraulic calculation used for the proposed sanitary sewer network of the Abha site.

17.5.2 Sewage Network Scope Split:


The sewage of Abha Entertainment Complex will be managed by both plumbing and site sewage network. The interface will be
1 m outside the building between the plumbing tie-in with site sewage network. The sewage generated inside the building’s boundary will be
collected by plumbing and diverted towards the west site in the proposed gravity pipes and site sewer manholes.

17.5.3 Sewer Interface:


National Water Company (NWC) has provided two tie-in points for connection to the proposed sewerage network for the Abha site, as shown in
Figure-17.5.1. The consultant has submitted a proposal for approval of sewer tie-in 2. NWC confirmed via letter no: 1443/5156/82893 dated : April
20, 2022, that the sanitary sewer network should be tied in with the existing manhole on Ø 400 mm existing trunk sewer, as shown in Figure-
17.5.1.

17.5.4 Design Criteria:


The following Design Criteria will be used for the design of the wastewater collection system:

17.5.4.1 Codes and Standards

The design of the sanitary sewer network will be prepared by the following codes and any other standard(s) required from the Authorities/Client or
local standards.
1. NWC – National Water Company
2. MEWA – Ministry of Environment, Water and Agriculture
3. ASTM -American Society for Testing and Materials
4. SASO - Saudi Arabian Standards Organization
5. ACI-American Concrete Institute

17.5.4.2 Software Modelling


SewerGEMS Connect Edition Update 3 is being used to design the new sanitary sewer network, including sizes of the pipe, the invert levels of the
manhole, Q/Qf, and d/S ratios, and velocity in pipes.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.5 Sewage Network – Cont.
17.5.4.3 Quantity of Flow
85 percent of water consumption shall be used for calculating the wastewater flows in accordance with MEWA Section-2-9.

17.5.4.4 Peak Factor


A peak factor (Pf) is a multiplier used to account for the variation inflow during the day. This factor will vary depending on the nature of the
development. The peak factor will depend on the upstream population and several other factors such as distance travelled and pipe size. Several
methods and formulas are available to calculate peak factors, and the Babbitt formula is used to calculate Abha Peak Sewage Flow.

Where:
Pf = Peak Factor
P = Population of the catchment

The Babbitt formula is not suitable for low populations. Therefore, the upper limit for peak factor shall be taken as Pf = 6 for populations up to and
including 500. The minimum value of the peak factor is usually 2.5-3.0.

17.5.4.5 Hydraulic Analysis


The hydraulic design of the sewer network will be based on uniform flow conditions using Manning’s equation to determine the velocity in sewer
pipes as follows:

1
V = 𝑅𝑅2/3 𝑆𝑆 1/2
𝑛𝑛

Where:

V is the mean velocity of flow (m/s)


n is the Manning’s roughness coefficient for pipes
R is the hydraulic radius (m)
S is the slope of the energy grade line or channel bed slope (m/m)

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.5 Sewage Network – Cont.
17.5.4.6 Depth of Cover to Sewers
All sewers will be designed to have a minimum cover of 1.2 m below both existing and final ground level. Where the cover is less than 1.0m,
concrete encasement will be provided.

17.5.4.7 Design Depth of Flow


Sewers will be designed to flow 75% full under peak flow conditions.

17.5.4.8 Hydraulic Analysis


Approximately 10% of Average Daily Flow is considered for groundwater infiltration and leakage.

17.5.4.9 Velocity Requirements


The minimum pipe velocity (self-cleaning) is 0.6 m/s for gravity pipes, and the maximum velocity for circular pipes shall not exceed 3 m/s in
reducing the risk of scour in the system.

17.5.4.10 Gradient of Sewers


The minimum gradient for a section of sewer will generally be the gradient necessary to satisfy the minimum velocity requirements. Where the
velocity is less than 0.6 m/sec, routine flushing of the sewer will be recommended.

17.5.4.11 Pipe Size and Material


• The minimum size of the sewer pipe will be 200 mm in diameter.
• uPVC Class-4 material will be used for pipes smaller than or equal to 250 mm.
• GRP manhole will be used for pipe size greater than or equal to Ø200 mm.

17.5.4.12 Manholes
Manhole structures should provide safe access to the sewers for maintenance and operations, cause a minimum of interference to the hydraulics
of the sewer and have adequate strength and durability. Manholes will be provided for the cleansing purpose at the head of each gravity sewer, at
changes in direction or gradient, at changes in pipe size, at the intersection of sewers, and at the end of sewer lines that will be extended at a later
stage. The spacing between manholes along straight runs will otherwise be as follows:
Pipe Diameter (mm) Maximum Spacing Between Manholes (m)
If 200 < ∅ ≤ 600 100
If 700 < ∅ ≤ 1000 150
If ∅ >1000 300
IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.5 Sewage Network – Cont.

Figure (17.5.1) : Existing Sewer Manhole Tie-ins from NWC


IFC Design Report
SEVEN - ABHA
17.5 Sewage Network – Cont.
17.5.5 Sewage Flow Estimation
Sewage flow is estimated based on the number of visitors for different land use categories and staff/employees according to MEWA water
consumption rates per capita consumption per day. The summary of the sewage flow estimation is shown in table below:

Infiltration (10%
MAXIMUM MAXIMUM CATEGORY Average Sewage (85%) of Total Average Peak Sewage Peak Sewage
CATEGORY ACCORDING PCWD of Average Peak
LAND USE NUMBER OF PCWD (L/C/D) NUMBER OF ACCORDING TO Water Average Water Sewage Flow) Flow Flow
TO MEWA (L/C/D) Sewage Flow) Factor
VISITORS STAFF MEWA Demand (L/d) Demand (L/d) (L/d) (L/d) (L/s)
(L/d)

BLACK BOX Entertainment & Leisure 1200 60 22 Office/Employee 80 2.794


73760 62696 6269.6 68966 3.5 241380
BOWLING Entertainment & Leisure 375 60 10 Office/Employee 80 0.883
23300 19805 1980.5 21786 3.5 76249
CINEMA Theatre 996 60 50 Office/Employee 80 2.415
63760 54196 5419.6 59616 3.5 208655
EDUTAINMENT Entertainment & Leisure 331 60 9 Office/Employee 80 0.779
20580 17493 1749.3 19242 3.5 67348
GO KART Entertainment & Leisure 60 60 8 Office/Employee 80 0.161
4240 3604 360.4 3964 3.5 13875
GOLF Entertainment & Leisure 145 60 5 Office/Employee 80 0.345
9100 7735 773.5 8509 3.5 29780
PRE-TEEN EDU Entertainment & Leisure 100 60 15 Office/Employee 80 0.273
7200 6120 612 6732 3.5 23562
RETAIL/F&B Commercial & Retail 459 95 147 Office/Employee 100 2.208
58305 49559.25 4955.925 54515 3.5 190803
SEVEN FEC Entertainment & Leisure 346 60 40 Office/Employee 80 0.908
23960 20366 2036.6 22403 3.5 78409
WELLNESS Gym 79 100 11 Office/Employee 100 0.341
9000 7650 765 8415 3.5 29453
TOTAL 4,091 317 293,205 249,224 24,922 274,147 959,513 11.105

Restaurant Average Usage


(per meal) 30% of the Restaurant (per meal) 1322 15 19,836 16,861 1,686 18,547 3.5 64,913 0.751
total occupant load

TOTAL 313,041 266,085 26,608 292,693 1,024,427 11.857

PCWD = Per Capita Water Demand


L/C/D = Litre per capita per day
85 percent of water consumption shall be used for calculating the wastewater flows in
accordance with MEWA Section-2-9.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.5 Sewage Network – Cont.
17.5.6 Proposed System Description
The proposed sanitary sewer network includes manholes and building plumbing connections to the main pipes under gravity flow. All the proposed
building tie-ins are located on the project's west side. The generated sewage flow from the building tie-ins has been collected in the main sewers
connected through manholes. After collecting sewage from the building, the main sewer in the road is ultimately discharged into the existing
manhole on Ø 400 mm existing trunk sewer. A sewer pipe of Ø200 mm is proposed for the overall layout plan for the proposed Abha sanitary
sewer network as shown in Figure 17.5.2.

17.5.7 Hydraulic Analysis Results


SewerGEMS Connect Edition Update 3 is being used for the analysis of proposed sewer network. Sewage loading is distributed on the nearest
building manholes to determine the sizing for pipes. All parameters are considered for the sanitary networks is following MEWA and NWC
Standards. For more details regarding hydraulic calculations identifying various parameters for the slope, diameter, velocity, design flows, ground
levels, invert levels, and carrying capacities, please refer to the proposed sanitary sewer calculations via DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-
WE-DEC-00002-C.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.5 Sewage Network – Cont.

Ø 200 mm
Ø 200 mm

EXISTING TIE-IN MANHOLE


Figure (17.5.2) : Proposed Sanitary Sewer Network of Abha Entertainment Complex ON ∅400 MM EXISTING SEWER PIPE
E= 250377.729
N= 2017873.653
IFC Design Report
SEVEN - ABHA FIGURE 17.5.2 UPDATED C
17.6 Irrigation Network
17.6.1 Introduction:
This section describes the design philosophy, criteria, and hydraulic calculation used for the proposed irrigation network of the Abha site.

17.6.2 Standards & Regulations


The design of irrigation water networks is carried out in line with the guidelines and codes of practice developed by international
agencies/societies and adopted in Saudi norms:

A. Ministry of Environment, Water, and Agriculture (MEWA)


B. National Water Company (NWC)
C. Saudi Irrigation Organization (SIO)
D. Amana Municipality
E. National Fire Protection Association (NFPA)
F. Saudi Building Code (SBC)
G. Saudi Arabian Standards Organization (SASO).
H. American Water Works Association (AWWA).
I. American Society of Testing and Materials (ASTM).
J. British and European Standards and Codes of Practice (BS-EN).

17.6.3 General System Description


The irrigation water network scope of work for the Abha site and building tertiary network, is shown in Figure-17.6.1. This figure describes the
extent of the scope and extended scope of the project. Google image is attached as background indicating the interfaces with the existing road in
west and north location of Abha site.

There are two irrigation water sources which are considered for the Abha site as follows:
1.0 Water Tanker for irrigation
2.0 Grey Water Treatment Plant which has a capacity of 160-180 m3/day.
The calculation for size and other hydraulic parameters are covered in the following sections for option 2. Tapping point from the Irrigation pump
station is shown in Figure-17.6.2.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.6 Irrigation Network – Cont.
17.6.3 General System Description – Cont.
Irrigation water source is a grey water treatment plant (water from wash basins and kitchen) on the basement floor in option-2. To supply the
irrigation water to the main irrigation distribution network, water will be pumped from the irrigation tank using a booster pump.

Figure (17.6.1) : Location of Abha Plot and Scope Limits


IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.6 Irrigation Network – Cont.

Figure (17.6.2) : Location of Abha Plot and Plumbing Network


IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.6 Irrigation Network – Cont.
17.6.4 Design Criteria:
The following Design Criteria will be used for the design of the wastewater collection system:

17.6.4.1 Network Type


Irrigation mains are configured and located within the established right-of-way or utility easement. Looping of distribution mains is not feasible as
east side is having no landscape so dead end cannot be avoided.

17.6.4.2 Pressure
The network is designed to ensure a recommended pressure of 3.0 bar at each Solenoid Valve and recommended pressure of 4.0 bar at each
tapping point from pump station /plumbing/building tie-in.
Equipment for tertiary networks like drip tubing, bubblers, and sprinklers are recommended to be designed in the range of 0.7 to 4 bar as
recommended by Irrigation equipment’s Manufacturer.

17.6.4.3 Pipe Velocity


A minimum velocity of 0.2 m/s and a maximum velocity of 2.0 m/sec is adopted in the distribution network as per MEWA for Irrigation.
Tertiary irrigation pipes shall be designed using the recommended velocity of 1.5-2.0 m/sec per most irrigation vendors.

17.6.4.4 Pipe Size and Material


• Materials of construction shall conform to SASO, AWWA, and ASTM Standards.
• All pipe material is HDPE, PN-16, PE-100 for the main and HDPE, PN-10, and PE-100 for the tertiary network.

17.6.4.5 Pipe Cover


The minimum pipe cover is 1.0 meters below the final ground level as per MEWA for the main irrigation pipe, and for tertiary, it should be 300 mm
to 600 mm from the finished grade level.

17.6.4.6 Pipe Gradients


The minimum design gradient to allow for the movement of air-to-air valves shall be 1 in 1000 in the direction of flow and 2 in 1000 in the adverse
direction.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.6 Irrigation Network – Cont.
17.6.4.7 Pipe Hydraulics
The Hazen-Williams Formula is used in the analysis of pressure pipe systems. The formula is as follows:

Q = K. C. A. R0.63.S0.54
Where:
Q = Discharge in the section (m3/s, CFS)
C = Hazen-Williams roughness coefficient (unitless), C=130 is adopted
A = Flow area (m2, ft.2)
R = Hydraulic radius (m, ft.)
S = Friction slope (m/m, ft./ft.)
k = Constant (0.85 for SI units, 1.32 for US units).

17.6.4.8 Thrust Blocks


Thrust blocks to be installed at:
• Tees
• Tapers (change in diameter)
• Blank flange (end cap)
Thrust blocks to be tested on a test pressure of 1.5 x working pressure

17.6.4.9 Pipe Head loss


Maximum acceptable head loss in pipes shall be 20m/km

17.6.4.10 Valves
On main loops, sufficient valves are placed to close the network during maintenance, repair, replacement, or additions to allow flexibility of
operation, and direct buried gate valves are installed on the main.

17.6.11 Solenoid Valve


Solenoid valves with a pressure of 20 to 200 psi and flow rate of 0.25 to 200 gpm shall be used. Solenoid shall be used for irrigation zone control.
Valve sizing criteria will be as recommended by the manufacturers. A suitable solenoid valve size shall be used to eliminate the friction loss through
the valve. The friction loss for the estimated flow should be less than 10% of the pressure available at the mainline.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.6 Irrigation Network – Cont.
17.6.4.12 Solenoid Valve
Filters shall be 1”, 1.5” and 2” large capacity with a maximum pressure of 116 psi.
17.6.4.13 Emitters
7 and 5 GPH flow emitters in combination of (4+1) shall be used for trees and rings of 3 drip emitters with 2 GPH shall be used for shrubs and
ground covers. Spray head and bubblers are avoided in design to minimize the wastage of irrigation water.
17.6.4.14 Irrigation Controller and Central Control
Irrigation control cables will be connected to the remote terminal unit (RTU) inside the irrigation booster pump station or individual irrigation
controller. Each individual RTU or irrigation controller facility will be programmed to provide the water requirement of different plant species in two
cycles per day or as recommended by Aseer Municipality. The main irrigation controller will be connected through GSM/ GPRS system to the Aseer
Municipality building. The input power to the RTU or irrigation controller shall be from an electrical panel located nearby. The irrigation controller
should be sourced from an approved manufacturer or vendor for compatibility of the entire irrigation system. The irrigation controller can also
control the solenoid valve as a standalone unit.
17.6.4.15 Decoder
Two-Wire Decoders system will be used to control the solenoid valve operations for each irrigation zone. Multi-station decoders will be used to
control solenoid valves grouped or near each other. Decoder in the latest smart solenoid valves is built in with decoder ion the same valve box for
smart communication with the controller.
17.6.4.16 Control Cables
As recommended by the irrigation vendor, a control cable (12 or 14 AWG or approved equal) shall be used to connect each solenoid valve to RTU or
irrigation controller. Control cables shall be installed in 32mm PVC pipe/HDPE sleeves and pull boxes shall be provided for future maintenance.
17.6.4.17 Drip Line
On-surface XFD or approved equal dripline will be used for a flow range of 3.5 l/h to 4.5 l/h, and tubing available to irrigate ground cover, shrubs,
and dense plantings. The drip lines shall be capable of handling pressure in the limits of 0.58 bar to 4.1 bar. The diameter of these tubes should be
16.1 mm outer and 13.6 mm inner or as per approved irrigation vendor.
17.6.4.18 Quick Coupling
Quick coupling valves will be installed near pavements for easy identification and access for each stub out used.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.6 Irrigation Network – Cont.
17.6.5 Irrigation Water Demand
Irrigation water demand is estimated based on the net area of the landscaping and planting pattern. The total irrigation demand for the Abha is
shown in table below. The proposed diameter sizing calculation is also provided in the table meeting MOMRA requirements.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.6 Irrigation Network – Cont.
17.6.6 Proposed System Description
The irrigation water is supplied to irrigation tank through booster pump and then to the main distribution irrigation network at site and some green
pockets in the complex corridors and on parking slab of the basement. The interfaces between mechanical/plumbing and wet unities are shown in
Figure-17.6.2. This irrigation water will be distributed both within the complex landscape areas and outside the complex in the north. The tie in
from plumbing is shown as one tapping point of 110 mm diameter HDPE pipe which will be feeding two irrigation lines outside the complex.
There are various interfaces between the main and secondary within the complex for Irrigation as shown in the Figure-17.6.2 above.
The irrigation tank is filled from the grey water treatment plant. This report will describe and check the following requirements:

• Required flow for trees, shrubs, ground covers, etc.


• Minimum flow required at tie-in point
• Minimum pressure required at tie-in point
• Minimum pressure calculated
• Pipes head losses
• Pipes velocity
• Pipes diameters
• Junctions pressure

17.6.6 Hydraulic Results Summary:

Rain CAD, a hydraulic analysis, and design software is used for the hydraulic modelling against different scenarios to see the effects of changed
conditions in relevant models. The Irrigation water network is modelled based on the assumption that all plants will not be irrigated in same time.
Detail design contractor shall design irrigation system to be irrigated by time zones using efficient control system. Based on the results from the
model considering the worst scenario for the farthest solenoid valves node with specified demand load, pipe size of 110 mm outer dia. HDPE PE-
100 and PN-16 is adequate to deliver the required quantity of water at needed pressure as shown in Figure 17.6.4 . Pressure at tapping point is
required 4 bar to feed all solenoid valves for the calculated flows based on landscape planting. Please refer to the proposed sanitary sewer
calculations via DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00005-C.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.6 Irrigation Network – Cont.

Figure (17.6.3) : General Layout for Irrigation Network For Abha


IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
C FIGURE 17.6.3 UPDATED
17.6 Irrigation Network – Cont.

Figure (17.6.4) : WORST CASE SCENARIO IRRIGATION NETWORK FOR ABHA


IFC Design Report
17 OCTOBER,
SEVEN - ABHA
C FIGURE 17.6.4 UPDATED 2021
17.7 Proposed Storm Water Drainage System
17.7.1 Introduction:
This section describes the criteria and philosophy considered for the design of the proposed Storm water drainage network of Abha Entertainment
Complex and presents a summary for the hydraulic results of the network.

17.7.2 Storm Water Drainage Scope Split:


The storm water of Abha Entertainment Complex will be managed by both plumbing/building drainage and site storm water. The interface will be
1 m outside the building between the plumbing drainage and site storm drainage.
The storm water inside the building’s boundary will be collected by plumbing/building drainage and will be diverted towards the roads all around
the site through gravity pipes and these pipes shall be connected with the proposed site storm water manholes or pipelines via y-connections.

17.7.3 Outfall/Disposal of Storm Water:


Existing perimeter roads are draining ultimately towards the west side and finally in an unlined channel with two cells box culvert.
The slopes of the project area show that the storm flow streamlines direction is towards Southwest where an existing culvert is located.
In February 2022, DAR survey team verified the location of this culvert and provided it’s required information like its size, bed level, and top levels
of it also, survey was conducted for the road up to the existing culvert location where our proposed system is placed.
The two cells box culvert width is 2 m and its height is 3 m.
The upstream and downstream bed levels of the culvert are 2079.048 and 2078.653, respectively.
This existing culvert is considered as Abha’s Complex storm water drainage system outfall.

N.B. Storm water disposal point at the existing culvert is pending for approval from Amana and will be confirmed after getting approval of the
Hydrology study report.

17.7.4 Storm Water Collection Strategy and Proposed System:


The proposed storm water system comprises:
• Approximate 1.5 km of main pipes with diameters from 300 up to 1400 mm.
• Approximate 120 m of gully pipes with diameters from 200 to 300 mm.

As per our discussions with SEVEN, roads and areas surrounding the complex shall be part of our study and the storm water collection shall be
outside the complex not towards the complex and existing roads in the west will be further developed by Amana as a part of their future
development program.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.7 Proposed Storm Water Drainage System – Cont.
• At the North Side:
Storm water is collected from the buildings and inside the complex by building/plumbing drainage.
Tie points are provided to divert the storm water to the proposed site storm water system.
Storm water in the access road will be collected via catch basins to be installed at the low points locations and adjacent to each other with certain
distance calculated by the SewerGEMS in order to achieve acceptable values of gutter depth and spread at the 100 years return period.
Storm water in the landscape areas above the access road will be surface drain towards North with respect to its natural slope.
• At the East and South Sides:
Storm water is collected from the buildings and inside the complex by building/plumbing drainage.
Tie points are provided to divert the storm water to the proposed site storm water system.
Storm water in the access road and fire truck route will be collected via catch basins to be installed at the low points locations and adjacent to each
other with certain distance calculated by the SewerGEMS in order to achieve acceptable values of gutter depth and spread at the 100 years return
period.
• At the West Side:
Storm water is collected from the buildings and inside the complex by building/plumbing drainage.
Tie points are provided to divert the storm water to the proposed site storm water system.
Roads department considered in their design for both access roads 1 and 2 that their slopes directions to be outside the complex towards north
and west, respectively so the storm water collection will be outside the complex not towards it.
All landscape areas along with the west side of the complex is draining its water outside the complex except the above-mentioned area.
External Storm Water Flow:
As per the Hydrology & Flood Mitigation Study REV.06 prepared by M/s ACES dated 26.07.2022, there are two external watersheds that flow into
the project area, denoted by W1 and W2. The external flows for W1 and W2 are shown in Table 1:

The external flow into the project area is calculated as 2.17 m3/s @ 100 years return period. Also, the existing floodplain’s level ranges from around
2 cm to 1.66 meters with an average depth of 36 cm throughout the project area. Additionally, the velocity of the flow across the project area
ranges from 0.01 m/s to 2.73 m/s with an average velocity of 0.85 m/s.
Figure 17.7.1 below shows the proposed stormwater drainage system of Abha Entertainment Complex.
For more details regarding the proposed storm water drainage system, please refer to the PROPOSED STORM WATER SYSTEM IFC HYDRAULIC
REPORT (REV.A) DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00003-C.
IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.7 Proposed Storm Water Drainage System – Cont.

Figure (17.7.1) : Proposed Storm Water Drainage System of Abha Entertainment Complex
IFC Design Report
SEVEN - ABHA
C FIGURE 17.7.1 UPDATED
17.7 Proposed Storm Water Drainage System – Cont.
17.7.5 Rainfall Intensity:

The Rainfall Intensity was obtained from Station A112 Intensity Duration Frequency (IDF) Curves which were presented in Hydrology & Flood
Mitigation Study REV.08 prepared by M/s ACES dated 26.07.2022 and Figure 17.7.2 shows the considered Intensity Duration Frequency (IDF) Curves.

Figure (17.7.2) : Intensity Duration Frequency (IDF) Curves

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.7 Proposed Storm Water Drainage System – Cont.
17.7.6 Time of Concentration:
Time of concentration is used to select the rainfall intensity for a selected design storm. Kirpich formula is commonly used to estimate the time of
concentration as follows:
𝐿𝐿1.15
tc = 51.4 𝐻𝐻 0.38
Where:
Tc is the flow time of water from the furthest point in the catchments to the point of discharge, in minutes;
L is the horizontally projected length of flow in m
H is the difference in elevation, in m, between the furthest point of the catchments and the outlet.
The minimum design flow time of 10 minutes is a common practice.

17.7.7 Runoff Coefficient:


Combined Run-Off coefficient calculations were prepared based on the updated land use of the project area and these calculations are presented
in the below table.
Σ ( C1 X A1 + C2 X A2 + C3 X A3 + C4 X A4+ …..)
C=
ΣA
Where:
Cn = Run-off Factor Particular Surface
An = Area for Particular Surface
A= Total Area
C= Combined Coefficient of Run-off (C- Value)
RUN-OFF FACTOR FOR
CLASSIFICATION OF INDIVIDUAL AREA
INDIVIDUAL SURFACE (Cn x An) C
PARTICULAR SURFACES AREA (An) (ha) %
(Cn)
Loading Bay 0.80 0.03 0.4% 0.02
External walkway/circulation 0.75 0.15 2.2% 0.11
Roadworks 0.80 2.10 30.1% 1.68
Soft Landscaping 0.10 0.75 10.7% 0.07 0.70
Hard Landscaping 0.80 1.95 28.0% 1.56
Buildings 0.75 2.00 28.7% 1.50
Total 6.96 4.94

Combined Run-off factor (C- Value) = 0.70


IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.7 Proposed Storm Water Drainage System – Cont.
17.7.8 Hydraulic Design:
The hydraulic design of storm water drainage system will be based on uniform flow conditions using Manning’s equation to determine the velocity
in storm water pipes as follows:
1
V = 𝑅𝑅2/3 𝑆𝑆 1/2
𝑛𝑛
Where,
V is the mean velocity of flow, in m/s.
n, is the Manning’s roughness coefficient for pipes,
R, is the hydraulic radius in m; and
S is the slope of energy grade line, or channel bed slope, in m/m.

17.7.9 Design Criteria:


The following design criteria will be followed in the design of the storm water network:
• Minimum pipe depth of cover is 1.0 m to the crown of the storm water pipe. Concrete encasement shall be provided when minimum depth
cannot be satisfied.
• Pipe material shall be as follows:
 UPVC Class-4 for pipes smaller than or equal to 250 mm
 GRP for pipes equal or greater than 300 mm up to 900 mm
 RC for pipes greater than 900 mm
• GRP Manholes shall be installed in the system at all changes of direction, slope and diameter. In addition, manholes shall be installed on straight
reaches at distances not exceeding 90 m unless calculations show otherwise.
Maximum Spacing Between
Pipe Diameter (mm)
Manholes (m)
If 200 < ∅ ≤ 600 100
If 700 < ∅ ≤ 1000 150
If ∅ >1000 (box culvert section) 300

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021
17.7 Proposed Storm Water Drainage System – Cont.
• The minimum size of the storm main pipe shall be 300 mm or unless calculations show otherwise. However, the minimum size of pipe for gully
to gully pipe shall be 200mm.
• Manning formula will be used for the design of gravity pipes.
• Minimum pipe velocity (self-cleaning) is 0.6 m/s for gravity pipes and maximum velocity for circular pipes shall not exceed 3 m/s to reduce the
risk of scour in the system.
• Q/Qf =90% and d/D shall be maximum 75%.
• Intensity-Duration-Frequency Curves (IDF) was drawn on the basis of the rainfall intensity data for different return periods and the storm
network is designed at 10 years return period and checked against flooding at 100 years return period.

17.7.10 Hydraulic Results Summary:


- Maximum Spread and Gutter Depth:
- Minimum and Maximum Velocities:
 At 10 years return period
 At 10 years return period
Maximum Spread = 1.87 m
The Minimum velocity is 0.6 m/s and the maximum
Maximum Gutter Depth = 4.4 cm
velocity is 3.0 m/s which is recommended by
 At 100 years return period
NWC (Between 0.6 m/s and 3 m/s).
Maximum Spread = 2.46 m
Maximum Gutter Depth = 6.5 cm
- Maximum Q/Qf and d/D ratios:
 At 10 years return period
- Manholes / Catch basins which are not overflowing at 100 year
The maximum Q/Qf at P-7-9 = 77.5 % (Not exceeding 90%)
return period:
The maximum d/D at P-16 = 63.6 % (Not exceeding 75%)

Based on the above results, the maximum gutter depth @ 100 years is 6.5 cm which is below the curb height (15 cm), so the maximum
gutter depth is acceptable

For more details regarding the proposed storm water drainage system, please refer to the PROPOSED STORM WATER SYSTEM
HYDRAULIC REPORT (REV.A) DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00003-C.

IFC Design Report


SEVEN - ABHA 17 OCTOBER,
2021

You might also like