Professional Documents
Culture Documents
Design Report
Design Report
17.1 Introduction
This section presents the IFC design for the Abha Entertainment Complex project's wet utility network networks. Section outline is as follows:
17.1 Introduction
17.2 Codes, Regulation, and Design Standards
17.3 Water Supply Networks
17.4 Fire Fighting Networks
17.5 Sewage Network
17.6 Irrigation Network
17.7 Storm Water Drainage System
This document covers the potable water network scope of work for Abha site, as shown in Figure 17.3.1.
This figure describes the extent of the scope and extended scope of the project.
Google image is attached as background indicating the interfaces with the existing road in west and north location of Abha site.
The existing Ø300 DI water line which is the main source for the potable will supply to the potable tank.
The existing Ø300 mm DI line is shown in Figure 17.3.1 and the proposed tapping point is also shown from the existing Ø300 mm DI line.
The proposed tie-in potable transmission size is Ø110 mm HDPE, PN-16, PE- 100 pipe is confirmed by NWC.
A potable water source is a potable water tank located on the basement floor. To supply the potable water to the distribution network, water will
be pumped from the potable water tank which is by building/plumbing (MEP) scope.
Figure 17.3.2 presents the general layout for the potable water site network for Abha.
Figure (17.3.2) : General Layout for the Potable Water Network for Abha
• Valves
On main loops sufficient valves are placed to close the network during maintenance, repair, replacement, or additions. to allow flexibility of
operation, a direct buried gate valves are installed on the main.
Electromagnetic Flow meter will be provided in chamber.
Flow control valve will be provided in chamber.
For more details regarding the hydraulic results of the potable water system, please refer to Potable Water Site Network Hydraulic Report.
DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00001-C
17.3.6 Conclusions:
Based on the results from the model considering tank node with specified demand load, pipe size of 110 mm outer dia. HDPE PE-100 and PN-16 is
adequate to deliver the required quantity of water at needed pressure. Pressure at tank node is noted 28 psi adequate to fill the tank in the
basement.
The potable demand and pressure are shared with NWC to confirm for tapping point from 300 mm DI main.
Fire water source is a fire tank located in basement floor and fire water will be pumped from the fire
tank by fire pump set to supply site firefighting network.
Figure 17.4.2 presents the general layout for the firefighting site network for Abha.
• Network Type
Water mains are configured in segmented grids and loops and are located within the established right of- way or utility easement. Looping of
distribution mains is done, avoiding as many locations with dead ends as possible.
• Fire Hydrant
Average spacing between fire hydrants is 120 m in line with Fire Life Safety Report and SBC 801.
Each fire hydrant is designed to handle 47.3 l/s (750gpm).
Control valve shall be installed in each hydrant connection along with bollard. Hydrants will be installed along with valve in chamber with a
protection bollard as per NWC standards details included in fire drawings.
• Pressure
The network is designed that a minimum pressure of 1.4 bars is ensured at all fire hydrants during fire events as per Appendix B of SBC-801.
• Velocity
The velocity in pipes shall be in accordance with pipe manufacturer recommendations.
• Pipe Size and Material
Materials of construction shall conform to NWC, MEWA, AWWA, and ASTM Standards.
All pipes material is HDPE PN (20), PE-100 and SDR-9. These shall be provided in accordance with NFPA 20, section 4.7.7)
For mains that supply fire hydrants, pipe size shall not be less than 6 in. (150 mm) nominal size. According to NFPA24.
The connection from the hydrant to the main shall not be less than 6 in. (150) (nominal), According to NFPA24.
However, the fire main shall be adequate to deliver the required fire flow at the desired pressure so the main size can be increased as
needed.
• Cover
Minimum pipe cover is 1.0 meter below final ground level as per MEWA/NWC.
IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.4 Fire Water Site Network – Cont.
• Pipe Hydraulics
The Hazen-Williams Formula is used in the analysis of pressure pipe systems. The formula is as follows:
Q = K. C. A. R0.63 .S0.54
Where:
Q = Discharge in the section (m3/s, cfs)
C = Hazen-William’s roughness coefficient (unitless), C=130 is adopted
A = Flow area (m2, ft.2)
R = Hydraulic radius (m, ft.)
S = Friction slope (m/m, ft./ft.)
k = Constant (0.85 for SI units, 1.32 for US units).
• Thrust Blocks
Thrust blocks are not required as per NFPA 24, section 10.6.
• Valves
On main loops sufficient valves are provided to close the network during maintenance, repair, replacement, or additions. to allow flexibility of
operation, a gate valves are installed on the main and on the branch.
Air release valves are not required as per NFPA recommendations.
Drain valves are proposed at the lowest points in the network, Final location of valves to be exactly determined on site according to site
conditions.
The design of the sanitary sewer network will be prepared by the following codes and any other standard(s) required from the Authorities/Client or
local standards.
1. NWC – National Water Company
2. MEWA – Ministry of Environment, Water and Agriculture
3. ASTM -American Society for Testing and Materials
4. SASO - Saudi Arabian Standards Organization
5. ACI-American Concrete Institute
Where:
Pf = Peak Factor
P = Population of the catchment
The Babbitt formula is not suitable for low populations. Therefore, the upper limit for peak factor shall be taken as Pf = 6 for populations up to and
including 500. The minimum value of the peak factor is usually 2.5-3.0.
1
V = 𝑅𝑅2/3 𝑆𝑆 1/2
𝑛𝑛
Where:
17.5.4.12 Manholes
Manhole structures should provide safe access to the sewers for maintenance and operations, cause a minimum of interference to the hydraulics
of the sewer and have adequate strength and durability. Manholes will be provided for the cleansing purpose at the head of each gravity sewer, at
changes in direction or gradient, at changes in pipe size, at the intersection of sewers, and at the end of sewer lines that will be extended at a later
stage. The spacing between manholes along straight runs will otherwise be as follows:
Pipe Diameter (mm) Maximum Spacing Between Manholes (m)
If 200 < ∅ ≤ 600 100
If 700 < ∅ ≤ 1000 150
If ∅ >1000 300
IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.5 Sewage Network – Cont.
Infiltration (10%
MAXIMUM MAXIMUM CATEGORY Average Sewage (85%) of Total Average Peak Sewage Peak Sewage
CATEGORY ACCORDING PCWD of Average Peak
LAND USE NUMBER OF PCWD (L/C/D) NUMBER OF ACCORDING TO Water Average Water Sewage Flow) Flow Flow
TO MEWA (L/C/D) Sewage Flow) Factor
VISITORS STAFF MEWA Demand (L/d) Demand (L/d) (L/d) (L/d) (L/s)
(L/d)
Ø 200 mm
Ø 200 mm
There are two irrigation water sources which are considered for the Abha site as follows:
1.0 Water Tanker for irrigation
2.0 Grey Water Treatment Plant which has a capacity of 160-180 m3/day.
The calculation for size and other hydraulic parameters are covered in the following sections for option 2. Tapping point from the Irrigation pump
station is shown in Figure-17.6.2.
17.6.4.2 Pressure
The network is designed to ensure a recommended pressure of 3.0 bar at each Solenoid Valve and recommended pressure of 4.0 bar at each
tapping point from pump station /plumbing/building tie-in.
Equipment for tertiary networks like drip tubing, bubblers, and sprinklers are recommended to be designed in the range of 0.7 to 4 bar as
recommended by Irrigation equipment’s Manufacturer.
Q = K. C. A. R0.63.S0.54
Where:
Q = Discharge in the section (m3/s, CFS)
C = Hazen-Williams roughness coefficient (unitless), C=130 is adopted
A = Flow area (m2, ft.2)
R = Hydraulic radius (m, ft.)
S = Friction slope (m/m, ft./ft.)
k = Constant (0.85 for SI units, 1.32 for US units).
17.6.4.10 Valves
On main loops, sufficient valves are placed to close the network during maintenance, repair, replacement, or additions to allow flexibility of
operation, and direct buried gate valves are installed on the main.
Rain CAD, a hydraulic analysis, and design software is used for the hydraulic modelling against different scenarios to see the effects of changed
conditions in relevant models. The Irrigation water network is modelled based on the assumption that all plants will not be irrigated in same time.
Detail design contractor shall design irrigation system to be irrigated by time zones using efficient control system. Based on the results from the
model considering the worst scenario for the farthest solenoid valves node with specified demand load, pipe size of 110 mm outer dia. HDPE PE-
100 and PN-16 is adequate to deliver the required quantity of water at needed pressure as shown in Figure 17.6.4 . Pressure at tapping point is
required 4 bar to feed all solenoid valves for the calculated flows based on landscape planting. Please refer to the proposed sanitary sewer
calculations via DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00005-C.
N.B. Storm water disposal point at the existing culvert is pending for approval from Amana and will be confirmed after getting approval of the
Hydrology study report.
As per our discussions with SEVEN, roads and areas surrounding the complex shall be part of our study and the storm water collection shall be
outside the complex not towards the complex and existing roads in the west will be further developed by Amana as a part of their future
development program.
The external flow into the project area is calculated as 2.17 m3/s @ 100 years return period. Also, the existing floodplain’s level ranges from around
2 cm to 1.66 meters with an average depth of 36 cm throughout the project area. Additionally, the velocity of the flow across the project area
ranges from 0.01 m/s to 2.73 m/s with an average velocity of 0.85 m/s.
Figure 17.7.1 below shows the proposed stormwater drainage system of Abha Entertainment Complex.
For more details regarding the proposed storm water drainage system, please refer to the PROPOSED STORM WATER SYSTEM IFC HYDRAULIC
REPORT (REV.A) DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00003-C.
IFC Design Report
SEVEN - ABHA 17 OCTOBER,
2021
17.7 Proposed Storm Water Drainage System – Cont.
Figure (17.7.1) : Proposed Storm Water Drainage System of Abha Entertainment Complex
IFC Design Report
SEVEN - ABHA
C FIGURE 17.7.1 UPDATED
17.7 Proposed Storm Water Drainage System – Cont.
17.7.5 Rainfall Intensity:
The Rainfall Intensity was obtained from Station A112 Intensity Duration Frequency (IDF) Curves which were presented in Hydrology & Flood
Mitigation Study REV.08 prepared by M/s ACES dated 26.07.2022 and Figure 17.7.2 shows the considered Intensity Duration Frequency (IDF) Curves.
Based on the above results, the maximum gutter depth @ 100 years is 6.5 cm which is below the curb height (15 cm), so the maximum
gutter depth is acceptable
For more details regarding the proposed storm water drainage system, please refer to the PROPOSED STORM WATER SYSTEM
HYDRAULIC REPORT (REV.A) DOCUMENT NO. 6ABHA09-ABHA-FC-DAE-WE-DEC-00003-C.