Professional Documents
Culture Documents
Vol 4 Specifications 010823
Vol 4 Specifications 010823
Project Nº P161777
RFB No.:MZ-AIAS-331803-CW-RFB
CONTENTS:
VOLUME 4 OF 6: WORKS REQUIREMENTS - SPECIFICATIONS
BIDDING PROCEDURES, CONDITIONS OF CONTRACT AND CONTRACTOR FORMS (UNDER
VOLUME 1)
SCOPE OF WORKS (UNDER VOLUME 2)
BILL OF QUANTITIES (UNDER VOLUME 3)
SPECIFICATIONS
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (UNDER VOLUME 5)
DRAWINGS (UNDER VOLUME 6)
August 2023
i
TABLE OF CONTENTS
i
4.8. Mounting of Starters ................................................................................................. 126
4.9. Earthing .................................................................................................................... 126
4.10. Local Equipotential Bonding .................................................................................... 127
4.11. Lightning Protection ................................................................................................. 128
4.12. Testing ...................................................................................................................... 129
4.13. Underground Ductwork ............................................................................................ 129
4.14. Lighting .................................................................................................................... 129
4.15. Ultrasonic sensor and Grid - Installation and Commissioning ................................. 131
4.16. Wire and Cable ......................................................................................................... 131
4.17. Cable Trenches ......................................................................................................... 134
4.18. Local Devices ........................................................................................................... 135
4.19. Switchboards, Sub-panels and Sub-main Distribution Boards ................................. 137
4.20. Mains Decoupling Relay .......................................................................................... 142
4.21. Programmable Control Relay ................................................................................... 142
4.22. 24V DC Power Supply Unit ..................................................................................... 143
4.23. Data Logger .............................................................................................................. 144
4.24. Axial Fans................................................................................................................. 144
4.25. Power Factor Compensation ..................................................................................... 144
4.26. Electric Direct Heating ............................................................................................. 145
4.27. Multi-turn Actuators for OPEN-CLOSE Duty ......................................................... 145
4.28. Lighting .................................................................................................................... 145
5. GENERAL REQUIREMENTS FOR INSTRUMENTATION, CONTROL AND
AUTOMATION....................................................................................................... 149
5.1. Instrumentation ......................................................................................................... 149
5.2. Control Systems........................................................................................................ 149
5.3. Automation System .................................................................................................. 149
5.4. Testing of Instrumentation, Control and Automation Installations........................... 151
6. PARTICULAR SPECIFICATIONS FOR WORKS IN TETE ................................. 153
6.1. Background .............................................................................................................. 153
6.2. Location of the Works.............................................................................................. 154
6.3. Right of Access to the Site ....................................................................................... 154
6.4. Contractor's Designs ................................................................................................. 154
6.5. Submittals................................................................................................................. 155
6.6. Particular Specifications: Electrical Installation ....................................................... 157
6.7. Particular Specifications: Mechanical installations ................................................... 161
6.8. Particular Specifications: Operational Technology and SCADA ............................ 173
7. ENVIRONMENTAL AND SOCIAL (ES) REQUIREMENTS............................... 184
7.1. Environmental and Social Policy (Statement) .......................................................... 184
7.2. ES Minimum Requirements ..................................................................................... 185
7.3. Payment for ES Requirements .................................................................................. 185
i
LIST OF FIGURES
Figure 1. 1: Project area, sewer network, pumping stations, and WWTP - Right Bank ........................ 7
Figure 1. 2: Priority Areas of Sewerage Network, Condominium Sewer, and WWTP in the right bank
...............................................................................................................Error! Bookmark not defined.
LIST OF TABLES
Table 6. 1: Lengths of the Proposed Sewers per Phase – Right Bank ............................................... 153
Table 6. 2: Lengths of the Proposed Sewers per Phase – Left Bank.................................................. 153
Table 6. 1: Technical specification for the submersible pumps of PS01 at the Right
Bank…………169
_Toc112412329
i
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
1.1.2 Scope
The scope of works shall include, all general works preparatory to the construction of the works and
materials and work of any kind necessary for the due and satisfactory construction, completion and
maintenance of the works to the intent and meaning the specifications and instructions that may be
issued by the Engineer from time to time, during construction works, whether specifically mentioned
or not in the clauses of this specifications.
The scope of works is defined in the detailed design report of the project and presented in the Volume
2 – Scope of Works of the presented bid documents.
The project implementation area was defined based on the short-term measures proposed up to 2030
(Phase 1) in the detailed design, and are planned to be carried out on the left and right banks of the
Zambezi River. The main components of the project are summarized in the following table.
5
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Left Bank Right Bank
Conventional Sewerage System: Conventional Sewerage System:
• No action required • Rehabilitation of 2.23 km collectors
• Construction of 14.14 km collectors
• Construction of 1.80Km of Pressure main.
• Project Manholes: 427
o Newly construction 187 manholes
o Rehabilitation of 85 manholes
o To be reused 155 existing manholes
• Construction 2,682 house connections
• Improvement of 100 house connections
• Construction of 1 pumping station
Construction of 1.8 km of pressure
mainConstruction of a WWTP (composed by
headworks, 2 anaerobic ponds, 2 facultative and 2
maturation ponds).
Condominial System: Condominial System:
• Construction of 5.25 km of collectors • Construction of 2.6 km of collectors
• Construction 400 house connections • Construction 200 house connections
• Construction of 278 inspection boxes • Construction of 400 inspection boxes
• Construction of 1,350m of gravity
main
• Construction of WWTP (composed
of ABRAF principle)
Storm Water: Storm Water:
• No actions required • Rehabilitation of 2 km of existing collectors
• Replacement of 3.8 km of existing collectors
• New construction and connection of 279 gutters.
• Disconnection of 102 sewerage illegal
connections, 20 bypass lines on the equal number
of manholes, and 6 sewer from stormwater
outfall chambers/manholes at discharge points.
• Cleaning and reshaping of 2.5 km of earth
channel at Nhartanda valley before the WWTP.
• Reshaping and lining of 6.13km of existing open
channel after the WWTP.
6
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Figure 1. 1: Project area, sewer network, pumping stations, and WWTP - Right Bank
1.1.3 Definitions
1.1.3.1 General
Acceptable/ Approved (Approval) - Acceptable to/ approved (Approval) by the Employer (or by the
Engineer, if so authorised by the Employer);
Agreed - Agreed in any form of written documentation agreed amongst and made available to other
Party(-ies);
As Detailed - As detailed in the drawings;
Authorised/ Ordered/ Rejected - Authorised/ ordered/ rejected by the Employer (or by the
Engineer, if so authorised by the Employer);
Indicated - Indicated in or reasonably to be inferred from the Contract, or indicated in writing by the
Engineer;
Instructed/ Directed/ Permitted - Instructed/ directed/ permitted by the Engineer;
Satisfactory - Capable of fulfilling or having fulfilled the intended function;
7
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
1.1.3.2 Tolerances
Deviation - The difference between the actual (i.e. measured) size or position and the specified size or
position
Permissible Deviation - The specified limit(s) of deviation
Tolerance - The range within which a size or position must lie
8
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
1.2.4 Units’ Abbreviations
Symbol Description
% Percent
< smaller/ less than
> larger/ more than
° degree(s)
°C degree(s) Celsius
Symbol Description
ASTM American Society for Testing and Materials
ASHRAE American Society of Heating, Refrigerating and Air-
Conditioning Engineers ASME American Society of Mechanical Engineers
AWWA American Water Works
Association ICC International Code
Council
PMI Project Management Institute
DIN Deutsche Industrie Norm (German Standard)
EN European Norm
ISO International Standards Organization
BSI British Standards Institution
IEC International Electrotechnical Commission
ANSI American National Standards Institute
SABS South African Bureau of Standards
SATCC Southern Africa Transport and Communication
Commission g/cm³ gram(s) per cubic centimetre
° degree(s)
°C degree(s) Celsius
C- ESMP Contractor’s Environment and Social Management Plan
g/m² gram(s) per square metre
h hour(s)
cm centimetre(s)
d day(s)
kg kilogram(s)
kg/mm² kilograms per
square millimetre km kilometre(s)
kN kilonewton(s)
kPa kilopascal(s)
kW kilowatt(s)
l litre(s)
l/s litre(s) per second
m metre(s), running metre
m/s metre(s) per second
m² square metre(s)
m³ cubic metre(s)
m³/d cubic metre(s) per day
m³/h cubic metre(s) per hour
m³/s cubic metre(s) per second
masl metre(s) above sea level
Symbol Description
mBar Millibar
mg/l milligram(s) per litre
mm millimetre(s)
MPa Megapascal(s)
mWc metre(s) water column
h.p. Horse power
N Newton(s)
9
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
N/mm² Newton(s) per square millimetre
s second(s)
Ton tonne (mass) i.e. 1 000 kg
µg/l microgram(s) per litre
Ppm parts per million
OD Outer (external) Diameter
dia./Ø Diameter
T Temperature
TWL Top Water Level
DN Nominal Diameter
ID Internal Diameter
SN Nominal Stiffness
PN Nominal Pressure
PPc Corrugated Polypropylene
GRP Glass Fiber Reinforced Plastic
DCI Ductile Cast Iron
PVC Polyvinyl Chloride
PC Prestressed Concrete
HDPE High-Density Polyethylene
AC Asbestos Cement
10
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
11
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
12
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
1.9.2 Site Drainage
The Contractor shall keep the construction sites of the Works well drained until it is substantially
complete and shall ensure that, as far as it is practicable, all Works are carried out in the dry. The
Contractor shall, for this purpose, provide, operate and maintain sufficient pumping equipment, well
points, pipes and other equipment and shall construct, operate and maintain all temporary coffer-dams,
sumps, ditches, drains and other temporary works as may be necessary for the removal of water from
the Works while construction is in progress. Any costs resulting in site drainage shall be considered in
the unit prices. Any damage resulting from site drainage shall be on Contractor’s own cost.
13
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
welding or cutting metals.
14
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
plans of action to be taken if any of these incidents occur. The Contractor shall ensure that his
employees are aware of and adhere to the prescribed procedures and shall display, in prominent
positions, posters describing these procedures and the associated plans of action, including emergency
telephone contact details.
The Contractor shall agree emergency procedures with the relevant emergency services and carry out
emergency drills in accordance with statutory requirements and when recommended by the emergency
services.
The Contractor shall immediately notify the Employer, via the Engineer, if any Covid-19 infections and
serious or fatal accidents occurs on the Site which results in any injury to any person, whether directly
concerned with the Contract or a third party. Such notification may initially be verbal and shall be
followed by a written report within 24 hours of the accident. The Contractor shall, in a similar manner,
report any accident that occurs off the Site in connection with any activity forming part of the Contract
to the Employer, via the Engineer.
1.9.8 Signboards
Signboards shall be placed and repositioned up to once each by the Contractor as instructed by the
Engineer. They shall be in English and Portuguese language and contain information about the project,
the project funder and the Employer plus the names of the Engineer, the Contractor. The signboards’
dimensions are shown in the Drawings. They shall be of durable construction capable of withstanding
the effects of the climate until the end of the Defects Notification Period.
Besides these signboards, the Contractor shall not, except with the agreement of the Engineer, exhibit
or permit to be exhibited on the Site any other form of advertisement.
15
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
16
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Within the Contractor facilities, the Contractor shall ensure that a GRM is accessible to all workers and
that information of the Workers GRM is adequately disposed so that all workers can have access to the
GRM. The Contractor shall as well ensure that a code of conduct is visibly displayed in multiple
locations on the Contractor’s Site facilities.
The Contractor shall provide 01 car to the employer and/or the Engineer during the project
implementation period.
17
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Section of the Works, all items shall be completed, all required documents submitted and all trash,
debris, unused building materials and temporary facilities as well as construction equipment shall have
been removed from the Site.
The Contractor shall adequately furnish the office with the following:
Each office module:
• 3 desks for the offices.
• 3 swivel office arm chairs.
• 6 office chairs.
• 2 lockable filing cabinets, one of them of big size with doors.
18
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
• 1 plan chest.
• Drawing material and office consumables.
• Printer, scanner, copier and internet.
19
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
by the service representative of the vehicle should be handed over to the Employer.
Vehicles Requirements
Table 1.2 – Specification for the Double cab 4x4 Vehicle
20
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
INTERIOR • Front seating for driver plus one passenger, 8-way power-adjustable
driver and front-passenger seats with head rests, bucket seats with
lumbar support and map pockets.
• Inertia seat belts for driver and front-passenger.
• Rear seats with head rests and fitted with seat belts
for three passengers.
• Front and rear passenger hand braces.
• Seating capacity for double cabin vehicle shall be 5 including
driver and 1 passenger in front.
• Automatic headlamps (Ambient lighting).
• Satellite Navigation, AM/FM/MP3/CD 4.2” – 6.1” color display,
auxiliary input jack, USB port and Bluetooth voice control with at
least 4 Speakers and 2 tweeters.
• Air conditioning – dual-zone electronic automatic temperature
control (DEATC) non CFC.
• Heater/demister or defroster.
• Interior mirror-Auto-dimming rear view.
• Sun visors on Driver and Front passenger with mirror on Front
passenger side only.
• Automatic Windows – power front and rear with one – touch down
• Lockable fuel tank lid with facility for local and remote opening
• Illuminated and lockable stowage bin.
• Rear of cab fitted with Ventilation Windows.
• Fire extinguisher inclusive.
• Body technical manual (Workshop Manual) in English and
Portuguese.
• Center Console – Cooled.
• Floor mats front and rear with Make or Model Logo.
• Power points – 12-volt auxiliary in front in rear of center console
• Steering wheel-Leather-wrapped with mounted audio and Bluetooth
controls.
• External temperature display.
• Cruise Control.
• Bottle holders – doors.
• Under rear seat storage tray.
21
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
22
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
KEYS • Three sets of keys, separated, with each set fitted on spring
washer with metal / plastic lag showing key numbers.
Model and type The model should be in current production and is common on the
Mozambican market.
23
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Engine Diesel fueled Engine with water cooling system engine suitable for hot
climate.
Engine capacity Not to exceed 3000 cc.
Cylinders 4 in line.
Air/Fuel supply The vehicle can either be normal aspirated or turbo- charged.
Power (Kw) The vehicle to have minimum peak power output of 85 Kw.
Transmission type 5 forward speeds with manual shift mechanism.
Drive wheels The vehicle to be fitted with none permanent four-wheel drive facility.
Front brakes Discs.
Read brakes Drum.
Fuel tank capacity Minimum tank capacity must be 80 liters.
Keys • Three sets of keys, separated, with each set fitted on spring
washer with metal / plastic lag showing key numbers.
Miscellaneous / • Full tropical specifications
Equipment • With vinyl upholstery.
• Fitted with FM & Shortwave radio & CD, with at least 2
Speakers.
• Manufactures approved Jack and toolkit.
• Manufactures approved antitheft / hijack device.
• Emergency first aid kit.
• Two reflector red warning triangles.
• Owner’s manual.
• 2 spare parts catalogues (English).
• One full size spare wheel and tire secured by lockable device.
• Loading Bed Liner.
• Front grill guard (Nudge Bar).
• Rear black cover for load area.
LIGHTING • Two adjustable headlights with high and low beams.
• Two parking lights.
• Two stop and tail light combination.
• Reverse lights.
• Indicators (amber).
• Interior overhead light.
• Instrument panel light.
• Reflectors.
Power steering Power assisted power steering to be fitted on the vehicle.
24
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Two photographic equipment (digital camera with at least 15 Megapixels and a 20x optical
zoom lens) will be made available for the duration of the Contract for the sole use of the
Engineer and Employer representative when requested.
The Contractor shall, when required by Employer or Engineer, supply labour and necessary
measuring aids such as levelling instruments, theodolite for assisting the Engineer in various
tasks such as measuring, levelling and setting out.
25
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
26
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
supplies, communication facilities and other services and facilities required for the undertaking of the
Works.
Along with all pertinent documents that shall be posted in information panels available and visible to
the workers and visitors (e.g., ES and health and safety policies and general rules; list of subcontractors
in the site at a given moment), a detailed updated organization chart of the contractor at the site must
be present at all times.
27
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
payments, and covers activities such as but not limited to: Coordination and adjustment site possession,
coordination and adjustment of time schedules, working space, manpower, timing, traffic regulation;
attending of coordination meetings called in by the Employer or as might be necessary for optimum
coordination of activities.
28
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
29
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
30
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
31
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
It is emphasized that a collection of standard pamphlets of general nature unaccompanied by drawings
and descriptions referring to the actual as-built or as-installed situation will not be acceptable. In
particular, information supplied by Sub-Contractors and manufacturers employed by the Contractor
shall be prepared to form a comprehensive manual. Cross-references of descriptive texts, drawings and
spare part lists must be included and shall be related to the ABD described above.
The Contractor shall deliver to the Engineer loose leaf copies of draft operation and maintenance
manuals for the Works and the auxiliary Plant in reasonable time before issue of the taking over
certificate. The manuals shall be divided into several volumes (e.g. function, operation, maintenance,
and overhaul) and shall fully and clearly set out the Contractor's own recommendations and instructions
for the satisfactory operation, maintenance and overhaul of the Works and equipment as far as part of
this Contract.
The text or accompanying diagrams shall in addition show the electrical wiring, handling and erection
instructions. Draft manuals shall, during the testing and commissioning of the Works, be carefully
checked by the Contractor, updated and modified to ensure that they are fully descriptive and applicable
to the final layout of the Works.
The finally agreed manuals shall be securely bound in A4 sized loose leaf binders, clearly titled, index
linked and cross referenced. If prepared on computer, standard PC word processor software such as
Word for Windows shall be used, and a copy of the data file for each volume, on CD or USB Flash
Drive, shall be supplied in order to facilitate updating and searching for information. No section of the
Works will be taken over by the Engineer as completed unless this requirement has been met.
If during the defect notification period, the Contractor or the Engineer has found that the manual
requires modification or enlargement as a result of subsequent operational and maintenance experience
in the Works, the Contractor shall provide such modification for each relevant manual.
For the systems, these shall include depending on its specifics:
• Detailed procedures for operation, repair and maintenance
• Listing required daily, weekly, monthly, yearly or other regular maintenance procedures,
including for e.g. bar screens, sluice gates, movable weirs, stop logs, ultrasonic level meter, solar
power system.
• Complete overhaul, dismantling and reassembly, testing and re-commissioning
• Recommendations for pipe repair material
• Detailed descriptions of how to make house connections on the supplied pipe material
• Description on how to adjust the level of street caps, in case e.g. the surface/ road level will be
changed
• Guidelines for protection of Works and equipment
• Maintenance of protective coating
• Health and safety and environmental and social management measurements for operation
• For any equipment installed, the manual shall also include:
• Checklists for daily, weekly, yearly maintenance procedures
• Maintenance and service time schedules
• Systematic failure and troubleshooting procedures
• Easy understandable procedures for change of weir parts, repair works and re start-up
• Clear and visually supported installation schemes of the equipment
• Lists of supplies for repair and maintenance material
• Health and safety and environmental and social management measures for operation
• Outline of training conducted for operating personnel (Training Manual)
The operating instructions shall be harmonized between the electrical and mechanical systems and
contain the function of the electric equipment as well as the process itself, which is controlled with it.
The instructions shall clearly specify the function of each device and how it has to be operated. All
signals and indicated values shall be explained; necessary instructions shall be added.
The Contractor shall in preparing these documents cooperate with the Engineer. However, the
32
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Contractor shall present their own format at first.
Within 21 days after receipt of the subsequently to be delivered as-built documentation, the Engineer
shall return to the Contractor 1 copy of each document showing any amendments required by the
Engineer. Within 21 days after receipt of the amended documents, the Contractor shall issue the
amended documents.
The Taking-Over Certificate will not be issued before receipt of the final as-built documents. Any delay
in issuing the Take-Over Certificate caused by late submission of the as-built documents by the
Contractor will be classified as a delay caused by the Contractor and the corresponding penalties will
be applicable.
33
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
1.13.9 Summary of Contractor’s Documents
The schedule below gives a summary of the documents that shall be submitted by the Contractor in
accordance with the Contract. The schedule is not exhaustive, but provides an overview of Contractor’s
submittals. If not specifically mentioned, all documents shall be submitted in Original (if applicable,
e.g. Securities, Insurance policies), two hard copies as well as soft copies, either in editable (e.g. -.doc,
-.xls) or noneditable version or both.
C As-Built Documents
D1 Monthly reports and Sub-Clauses 1.13.4 and 1.11.5 28th day of each report
record photographs month
D2 Records of Contractor’s GC 6.10 Monthly
Personnel & Equipment
34
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Item Document Description/ Reference Timing
D3 Test certificates and numerous within the Specifications In accordance with Work
reports programme
35
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
and HSP implementation of the Contractor at any time during the Contract, in which case an audit report
shall be completed not later than 3 weeks after the performance of the audit.
If the Engineer establishes, by means of such an audit or in the course of performing his obligations
under the Contract, that the Contractor or his Sub-Contractors or suppliers are not complying with any
aspect of the QAP or procedure, (s)he shall notify the Contractor of such non-compliance, with a copy
to the Employer.
The Contractor shall, on receipt of such a notification, take immediate action to achieve compliance and
shall, within a period of 10 working days from the date of receiving the notification, respond to it in
writing indicating what corrective actions have been taken by him and what measures have been
implemented by him to prevent the recurrence of such a non-compliance.
1.14.3 Certificates
Where certificates are required by the Specifications or relevant Reference Standards, the original and
one copy of each such certificate shall be submitted to the Engineer by the Contractor. Certificates shall
be clearly identified by serial or reference number and shall include information required by the relevant
Reference Standard or Specification clause.
36
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
37
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
38
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
dust is likely to be created and shall dampen stored materials during dry and windy weather.
Stockpiles of materials shall be sited in sheltered areas or within hoarding, away from sensitive areas.
Stockpiles of friable material shall be covered with clean tarpaulins, with application of sprayed water
during dry and windy weather. Stockpiles of material or debris shall be dampened prior to their
movement, except where this is contrary to the Specification.
All trucks transporting soil or other potentially dust producing materials through populated areas shall
be covered with clean tarpaulins in good condition. The tarpaulins shall be properly secured and extend
at least 300 mm over the edges of the side and tail boards.
Construction vehicles and machinery shall be kept in good working order and engines turned off when
not in use. Appropriate measures shall be taken to limit exhaust emissions from construction vehicles,
machinery and plant, and the Contractor shall include details of such proposed measures in the EPP.
1.15.6 Noise
The Contractor shall take effective measures to minimize noise when planning and executing of the
Works (Noise quality standards can be found in the World Bank Group General Environmental, Health
and Safety Guidelines of April 2007).
The Contractor shall use plant and equipment conforming to national or international standards and
directives on noise and vibration emissions and shall include details of measures for abating noise at
source in the EPP and shall maintain all plant and silencing equipment in good condition so as to
minimize the amount of noise emission created by his activities.
39
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
to be approved by the Engineer. The Contractor recruits for this purpose an ISO 45001, OHSAS
18001:2007, NEBOSH or similar certified Health & Safety Specialist.
The Contractor shall be responsible for the safe implementation of the Works. He shall ensure that all
operations are carried out safely and that any person made responsible for the safe conduct of any part
of the operations carries out his duties in a proper manner.
Where any part of the Works is not covered by the Contractor’s Safety Policy, or includes a high-risk
activity, the Contractor shall, before commencing work on that part of the Works or activity, submit to
the Engineer a safe system of working statement. He shall immediately submit to the Engineer any
subsequent additions to, or amendments of, this statement. No work covered by any safe system of
working statement shall be commenced unless the Engineer has indicated that (s)he has no objection to
the methods proposed.
The Contractor shall provide all necessary qualified medical staff, ambulance, toilet (urinal or toilet
plus a washbasin) and other facilities for the welfare of his employees at Site. The facilities shall be to
at least the standard required by law, local regulations or agreements between Trade Unions and
Employer’s, and shall not be less than the more stringent between OSHA regulations, ANSI and BS
standards and HSE recommendations. A high standard of hygiene and cleanliness shall be maintained
at all times.
40
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
The HSP shall document how the Contractor will ensure that:
• The implementation of Health and Safety procedures is properly managed and recorded
• Adequate attention is given to site safety including:
• Preparation of safe working procedures for all construction, operation and maintenance
activities
• Promoting cleanliness and care of the components of the Works
• Reporting of accidents and hazards
• Promoting safe practice in pumping stations, water treatment works, water reservoirs and
towers, pipeline construction, etc.
• The Safety file is maintained and updated
The HSP shall be sufficiently detailed that there can be no ambiguity in its interpretation at a later date.
The HSP shall be subject to the approval of the Engineer, who will not allow any work on site to proceed
until such time as it has been fully and formally approved. Approval of the HSP shall not relieve the
Contractor of any of his responsibilities with regard to safety.
1.16.6 Electricity
The Contractor shall ensure that any person having access to the locations on Site where open or only
partly protected power supply cables and contacts are present, is safeguarded against accidental contact
with electricity. The Contractor shall also ensure that any person working with or near to electrical
equipment and plant is properly trained, skilled and equipped to avoid any accidental contact with
electricity.
The Contractor shall inform the local electricity company about any work which might affect their
power supply network and he shall implement any measures prescribed by the company for the
undertaking of such work.
41
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
or articles will be accepted, and all work of assembly and construction shall be done in a proper and
workmanlike manner.
When obtaining quotations for materials intended for delivery to the Site and incorporation into the
Works under any portion of these Specifications, the Contractor shall provide the manufacturer or
supplier with all information necessary for achieving compliance with this clause and he shall, in every
case, quote this clause in full to each manufacturer or supplier.
Manufacturer’s Certificate of Compliance. For off-the-shelf labelled stock products of standard
manufacture which have a record of satisfactory performance in similar work over a period of not less
than two years, the Contractor shall obtain notarized statements from the manufacturers or suppliers
certifying that the products conform to the Specifications.
42
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
will be ready for testing or inspection at the supplier’s premises or at a laboratory agreed with the
Engineer. Unless the Engineer attends at the appointed place and time, the test may proceed in his
absence. The Contractor shall, in all cases, submit the test results to the Engineer within seven days
after the test, respectively in due time after test completion.
43
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
• Where applicable, operation and maintenance manuals, as part of the As-Built documents, for
the Section of the Works to be handed-over to the Engineer.
44
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
2.2 Earthworks
2.2.1 General
Earthworks under this Chapter include excavation, trench sheeting and piling, and backfilling for
45
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
embankments, pipe trenches, structures (e.g. chambers, pipes, pipe supports), foundations of buildings,
and reinforced concrete structures. The BS 6031 Code of practice for earthworks shall be followed.
Everything contained in the Specification with regard to the implementation of the excavations, disposal
of excavated material, etc. shall equally apply to the various types or classes of excavated material
unless otherwise stated. The Contractor shall prepare the working area in such a manner that the Works
may be constructed without any danger or hindrance to persons or property.
The Contractor shall ensure that he is in possession of all required permits, local and national, prior to
commencing any Works. In addition, and well in advance of the commencement of the work, the
Contractor shall obtain permission for the undertaking of the work from all land or property owners
who may be affected by the Works, incl. permission for temporary access to the affected land or
property wherever this is necessary for the Works to be carried out.
Where pipelines pass through bush or fields, the Contractor shall clear a strip centred on the pipeline
centreline along the route of the pipeline. All trees, bushes, shrubs, logs, stumps, roots, weeds, rubbish
and other organic material within the strip shall be removed by the Contractor, who shall permit the
owners or occupiers of the affected land to utilize this material or who shall otherwise arrange for its
disposal in an environmentally acceptable manner. However, the Contractor shall obtain the approval
of the owners, responsible Authorities or occupiers of the designated strip before removing any large
trees i.e. trees with a circumference exceeding 500 mm measured 1 m above original ground level, and
shall endeavor not to remove any such trees unless this is unavoidable. Furthermore, in protected bush
areas, the Contractor shall also obtain the approval of the responsible Authorities before removing
smaller trees in the designated strip and shall do only such clearing as is essential for the undertaking
of the work.
The Contractor shall also permit the owners of fruit bearing trees and crops growing within the strip to
harvest the fruit or crops before he commences clearing of the strip and, if this is not practicable, he
shall record in writing and the quantities and condition of the trees and crops concerned and take
photographs before any work is done by him in the strip. The Contractor shall submit this information
to the Engineer for possible use in determining any compensation that may become due to the owners.
Failure by the Contractor to compile such records, complete with photographs, will result in the
Contractor being held liable for compensation of claims submitted by the owners, particularly if these
claims cannot reasonably be evaluated by the Employer or Engineer due to the lack of the relevant
records or photographs.
The Contractor shall search for and expose all buried pipes, cables or structures inside the cleared
working area. In this regard, the Contractor is to note that buried pipes, cables or structures other than
those of being informed by the relevant Authorities, as a follow up of Contractors inquiry, may be
encountered within the working area. The details and positions of all buried pipes, cables or structures
encountered during the Works shall be recorded by the Contractor and shall be shown on the as-built
drawings. In cases of occurrence of damage or necessity of removal or relocate the buried pipes, cables
or structures.
The Contractor shall protect all survey points. If any survey point has to be removed, the Contractor
shall re- instate that survey point after the work has been completed.
The Contractor shall strip/ remove the humus/ topsoil before commencing any excavations and shall
carefully store the same within the working area so that it can be used for re-instatement of the working
area after the Works are finished. Topsoil which is incorrectly removed or which becomes contaminated
due to carelessness on the part of the Contractor shall be replaced by the Contractor at no additional
cost to the Employer.
2.2.2 Standards
The Contractor shall carry out Works described in this Specification in accordance with the appropriate
EN and DIN Standards. These include but are not limited to the following:
• DIN 4124 Excavation and Trenches - Slopes, Planking and Strutting breadths of Working Spaces
46
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
47
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
2.2.4 General and Foundation Excavation
2.2.4.1.1 General
Everything contained in this Chapter with regard to the implementation of excavations, disposal of
excavated material, etc. shall apply to all types of material, unless otherwise stated.
All excavations shall be carried out to the lines and limits shown on the excavation plans and other
drawings, or as defined in the Specification. The said lines and limits may be amended by the Engineer
to suit the materials and other conditions encountered during actual excavation and field inspection.
When excavating in any material other than rock for formation levels under any structure, the last 150
mm of excavation shall be taken out not more than 12 hours before the placing of foundations or fill.
The material in the bottom of excavations in “common” material shall be moistened and thoroughly
compacted before final trimming and shall, together with “excavations in “rock”, be trimmed to the
required lines and levels before placing of concrete of fill.
The Contractor shall well and effectively support the sides and ends of all trenches and excavations
wherever necessary with strong, close timbering so as to prevent any collapse of the sides or ends into
the trenches or excavations. If, despite such precautions, or by reason of their neglect, any portions of
the sides or ends of any trenches or excavations shall collapse, the Contractor shall at his own expense
excavate and remove all the ground thereby disturbed both inside and outside the limits of the trench or
excavation.
Should the Contractor exceed in depth or extend the excavation or be ordered to take out extra
excavation for the reasons given above, no payment will be made for such extra excavation and he shall,
if ordered by the Engineer and at the Contractor's expense, make the sides or bottoms of the excavation
good with well rammed fill or in such class of concrete as may be ordered by the Engineer.
Before commencing any pipe laying, building or backfilling, all shattered and loose material shall be
removed by hand and the excavation trimmed as necessary to ensure that the work sits on a sound and
clean foundation or abuts tightly against sound ground.
48
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
been laid, or the initial restoration or maintenance of surfaces, the Engineer may order the Contractor
to stop all trench excavation until the outstanding work has been carried out at no extra costs.
49
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
2.2.6.2 In rock
All solid rock, boulders and large stones which protrude into the excavations for structures shall be
excavated using appropriate techniques and the resultant voids shall be refilled with material agreed
with the Engineer which has been moistened and thoroughly compacted.
2.2.7 Backfilling
2.2.7.1 General
Backfill shall generally be laid and compacted in maximum 300 mm thick so as to resemble as close as
possible the surrounding existing naturally consolidated soil state. If the Engineer deems this not
suitable material, the Contractor will be instructed whether the backfill is required to be imported or
selected.
Backfill material:
• Backfill material shall be evenly graded and not include constituents exceeding 75 mm or any
50
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
clay or organic material
• Grading curve shall be 0/ 63 according to DIN 4226
• Excavated material can be used for main backfilling if the quality achieves the required grade
and if the fixed compaction grade can be achieved
• Backfill material shall consist of sand, gravel, crushed stones or equivalent material
• Backfill material shall be compactable to the required value, thus it shall consist of different
sizes of grains Compaction:
• The compaction shall be done by mechanical rollers, compactors, vibrators or other adequate
machinery and such that provide a dry density not less than 95% of the maximum dry density
• Heavy compaction equipment is not to be used with less than 300 mm cover above the crown
of the pipe
• Backfill shall be by distributing and compacting it in horizontal layers with a uniform thickness
and thickness of non-compacted material not exceeding 300 mm
• Trench backfilling shall commence as soon as possible after pipe laying to give the pipe
protection against damage from objects possibly falling into the trench
• The backfill compaction shall conform to the requirements placed upon it by the type of existing
construction (unpaved, road or the like) above the pipeline which shall be reinstated
All backfill material, either as excavated material or from an agreed quarry, shall be released for
application by the Engineer. It will be the responsibility of the Contractor to locate the sources of
backfill material (quarry). The Contractor shall inform the Engineer about the location and will provide
samples of the materials he proposes to use. It is not permitted to take any backfill material from areas
where the stability of slopes is endangered or where problems of infiltration may arise. On completion
of excavation from the backfill material source, the Contractor will restore the area to a satisfactory
state from the point of view of environment and aesthetic conditions, following the requirements of the
relevant authority.
The Contractor shall check carefully the moisture content of backfill material before and during
compacting, so that it is within the limits of values specified, in accordance with the material and method
of compacting.
During backfilling, the Contractor shall undertake the necessary tests to guarantee the required
parameters. If a sample does not reach the minimum specification requirement, the material placed in
the permanent works shall either be further compacted or removed completely and replaced on no
additional costs.
Backfilling shall take place immediately after placing of the pipeline in order to avoid temperature
differences and/ or pipe buoyancy effects. Covering shall generally take place within 12 hours if the air
temperature is above 30°C or within 24 hours if the air temperature is below 30°C.
During backfill the material shall be wetted if need be to optimum moisture content and compacted to
95% Proctor.
Normally, joints of pressure mains will be left exposed during testing of pipelines. However, the
Engineer may at any time order the Contractor to proceed with the complete backfilling of the trench
before testing, where the pipeline is laid in the right-of-way of a road, in built-up areas and wherever
for any other reason the pipe trench cannot be left open until after testing. In such cases it is
recommended that the positions of all joints are clearly marked by the Contractor outside of the trench
so that they can easily be located for the purpose of repair if and when required.
Any deficiency in the quantity of material for backfilling the trenches shall be supplied by the
Contractor. The Contractor shall make good any settlement of the trench backfills occurring after
backfilling and until the expiry of the DNP.
51
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
there is not sufficient soft material specific for backfilling the Contractor shall transport suitable
material from other parts of the work or from borrow pits. The material shall be similar or better as that
for selected excavated material unless otherwise instructed by the Engineer. If required, the Contractor
shall submit the way leave bills on site showing that the material is according to Specification.
The same installation parameters as for selected excavated material shall apply.
2.2.7.3 Structures
Before beginning backfilling around structures, all foreign material, including water, shall be removed
from the space to be backfilled and the area to be backfilled shall be inspected and agreed with the
Engineer.
No backfill shall be placed around or on a structure until the concrete has attained sufficient strength.
The concrete strength shall be determined by tests on representative cubes or cylinders cured under
conditions similar to those prevailing at the Site.
Backfill shall be placed in uniform layers and brought up evenly on opposite sides of structures so as to
minimize unbalanced loading of the structures. The Contractor shall inform the Engineer of the
sequence of backfilling which he proposes to follow around each structure.
Backfill around and over structures shall be placed in horizontal layers of thicknesses which suit the
type of compaction equipment being used, but in no case shall the lifts be more 200 mm thick after
compaction. Each layer shall be evenly spread and moisture-conditioned to the optimum moisture
content (OMC) ± 3 percent, as determined using the Proctor method, and then compacted to at least the
densities specified below.
The backfill shall be laid partially humid and evenly across the entire surface either manually or
mechanically. During the laying the material shall be wetted evenly across the surface and compacted.
Compaction of the material shall be done in back & forth motions in both X and Y directions with
overlapping of the previous compacted areas so as to reach a minimum of 95% Proctor.
Unless otherwise instructed by the Engineer, all backfill for objects or pipe ancillaries (e.g. valve
chambers and the like, thrust blocks and buried valves) along the line shall be of the same type as per
the requirement for trench backfilling. The backfill shall be wetted to optimum moisture content and be
compacted however in maximum 15 cm layers to minimum 95% Proctor.
If required, and in case of imported material, the Contractor shall submit for each case the loading way
leave bill to the Engineer, attesting that the imported material matches the requirements.
2.2.7.4 Tests
The compaction, as specified hereunder, will be checked by a “Penetration Test (DPH)” to ensure a
minimum 95% Modified Proctor. The Engineer will decide, on which spot the penetration test shall be
performed. The tests shall be performed only in the presence of the Engineer. For each test a written
protocol shall be compiled by the Contractor. In the event one test fails / the compaction does not reach
the required quality, the Contractor shall perform an additional test at his own costs.
In the event the compaction does not reach the required quality the backfill shall be removed and
replaced by the Contractor. The section where the backfill shall be re-excavated will be defined by the
Engineer.
Further tests may be carried out during backfilling as directed by the Engineer, including tests on the
grading of the material using sieves on site, or physical testing of the soil to check the organic and/ or
clay content.
Dynamic plate loading test of each layer shall be done. A drop penetration test with the 10 kg weight
according to DIN 4094 shall be executed after the last layer of the backfill material is compacted on the
same place where the dynamic plate loading test is executed.
52
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
2.2.7.5 Rejection
Fill or backfill material shall be immediately rejected if the fill or backfill material, whether selected or
imported:
• Is saturated with water beyond its optimum moisture content prior to placement or is brought to
site in such a condition that results in excessive and unnecessary additional transportation costs
and thereby CO2 emissions.
• Contains swelling clay or a disproportionate amount of clay substances, humus, vegetation,
roots, and organic material or is contaminated with pollutants.
• For bedding material: It does not comply with bedding specifications.
The Engineer will order the Contractor the above situations to be rectified at his own costs, if they
occur.
For steeper sections or long slope sections the bedding material must be protected with sandbags barriers
in the trench in order to avoid the erosion of the bedding material. Distances of those sandbags depends
53
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
on the slope, however not longer than 50 m. Those sandbags are to be placed at no extra costs.
Material:
• Excavated soil shall not be used for embedment unless instructed otherwise by the Engineer
• Embedment material shall not contain any organic material or any other material which can lead
to any damage of the pipes or fittings
• Sand, sand/ gravel mix or crushed stone fines (all non-cohesive granular material) are allowed
to be used and is further required to be free draining
• Particle size of round material shall not exceed 16 mm unless the pipeline supplier recommends
a smaller size; content of particles between 8 and 16 mm shall not exceed 10 %
• Particle size of crushed stone fines shall not exceed 11 mm unless the pipeline supplier
recommends a smaller size
• Embedment material shall be compactable to the required value, thus it shall consist of different
sizes of grains
• Compaction:
• Pipe surrounding bedding and later trench backfilling shall commence as soon as possible after
pipe laying to give the pipe protection against damage from objects possibly falling into the
trench
• Heavy compaction equipment not to be used with less than 300 mm cover above the crown of
the pipe
• Lower backfill can be compacted with heavy equipment
• Hollows, which occur after removal of trench wall supports, shall be filled and compacted.
The compaction will be checked by in-situ density testing undertaken by an agreed testing laboratory.
The Engineer will determine when and where density tests shall be performed but the Contractor will
be responsible for arranging for the tests to be carried out. The tests shall be performed only in the
presence of the Engineer. A written report on each test shall be submitted to the Engineer by the
Contractor. If a test indicates that the compaction has not been done to the required standard, the
Contractor shall, at his cost, arrange for a second test to be done adjacent to the first test position. If this
second test confirms that the material has not been compacted to the required standard, the backfill shall
54
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
be removed by the Contractor to the extent directed by the Engineer and replaced by the Contractor at
his cost.
55
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
equipment in an approved manner to a sufficient depth to provide satisfactory bonding.
If the compacted surface of any layer is judged to be too wet for proper placing and compaction of the
next layer of material due to rainfall or over-wetting, it shall be removed or be worked with scarified or
other suitable equipment in a manner to reduce the moisture content to the permissible amount and, if
necessary, the layer shall be recompacted before the next layer of material is placed. The removed
material may be reused, provided the moisture content is reduced to the acceptable amount.
In general, the filling shall be executed and maintained approximately in horizontal layer.
Each compacted layer shall be sloped adequately towards the upstream of downstream side of the
embankment to facilitate draining.
The requirement as specified by the Engineer after field test shall be met by the most efficient type of
equipment, thickness of layers, number of passes of compaction equipment and suitable material or
mixture of different materials.
Placement of impervious material will not be permitted when in the judgment of the Engineer a proper
placing due to weather conditions e.g. heavy rainfall, cannot be expected.
56
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
with the following criteria:
• Having a permeability value (hydraulic conductivity) ≤ 10-9 m/s;
• At least have 20% of fine particles (with clay dimensions and thin silt)
• Having a plasticity index (PI) that shall be in between 10 ≤ IP ≤30;
• It must be free of stones larger than 25 mm;
During compaction, clods should be mechanically broken down to the smallest possible size by
compacting equipment, namely, sheepsfoot rollers.
2.2.11 Protection
The work under this subsection shall include slope protection for anaerobic ponds construction.
Where shown on the anaerobic ponds drawings, the slopes of embankments, shall be protected against
water or other action with concrete slabs.
57
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
• Once the adequacy of the interim reinstatement has been demonstrated, after agreement of the
Engineer, the Contractor shall carry out the permanent reinstatement
58
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
works until in the opinion of the Engineer, any concrete or other works therein are sufficiently set. The
Contractor’s rates are deemed to cover compliance with this requirement.
The Contractor shall construct any sumps or temporary drains that the Engineer may deem necessary
and shall be responsible for the removal and disposal of all water entering the excavations from
whatever source and shall deal with and dispose of such water in a manner approved by the Engineer
so as to ensure that excavations are kept dry.
The Contractor shall provide all plant, labour and materials required for such work and all costs incurred
shall be deemed to be included in his rates for excavation.
59
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
The Contractor shall perform as many tests as are necessary to ensure that the Works conform to the
requirements of the Contract. The number of tests shall be at least one test per 100 m³ of fill and per
day or two tests per structure, whichever is the greater.
The following DIN and British Standards will be applicable for tests on earthworks:
• DIN 18121: Moisture Test
• DIN 18122: Consistency Test
• DIN 18123: Grading Tests
• DIN 18124: Density Test (solid volume without voids)
• DIN 18125: Density Test for Soils (including voids)
• DIN 18127: Proctor Test
• DIN 18134: Loading Test
2.3 Pipelaying
2.3.1 General
Pipe laying shall be carried out according to internationally accepted standards and in accordance with
the laws of Mozambique.
60
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
shall they be walked on by workers wearing boots with leather or metallic soles.
The implements, tools and facilities used by the Contractor shall be entirely suitable for the safe and
efficient implementation of the Works and shall be subject to the approval of the Engineer. All pipes
shall be carefully lowered into the trench in a manner that will prevent damage to them. Any damage
to protective linings and/ or coatings from any cause whatsoever shall be repaired by the Contractor at
his own expense and strictly in accordance with the manufacturers’ instructions.
Under no circumstance shall pipes be dropped or dumped into the trench or on to other pipes already in
the trench, and no pipe shall be rolled into position for lowering into the trench unless such rolling is
done on timber planking and controlled with ropes or other approved tackle.
2.4 Testing
2.4.1 Water supply line pressure testing
All HDPE piping (pipe-lines with visco-elastic behaviour) shall be pressure testing as per Standard
61
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Specification EN 805: 2000 - Water supply – requirements for systems and components outside
buildings.
The section shall be tested to the pressure ordered by the Engineer. The Engineer shall take the pipeline
levels along the test section into consideration when determining the test pressure. The test pressure
shall not exceed the maximum field pressure recommended by the pipe manufacturer or the nominal
working pressure of the pipe plus 50%, whichever is the lesser, at any point along the test section.
Each section to be tested shall have been backfilled except at the joints, which shall be left open for
inspection, unless agreed with the Engineer otherwise. All anchor blocks on each line to be tested shall
have been cast at least seven days before testing.
All valves shall be operated and examined and a specifically shall be made operation tests of valves for
proper functioning. Particular care shall be taken that valves on each section to be tested are properly
closed.
Before testing any pipeline, the Contractor shall ensure that it is anchored adequately and that thrusts
from bends, branch outlets or from the pipeline ends are transmitted to solid ground or to a suitable
temporary anchorage. Open ends shall be stopped with plugs, caps or blank flanges properly jointed.
The Contractor shall provide all labour, testing equipment, interconnecting pipework or water tankers,
jointing material, end caps, blank flanges, etc. required and shall fill the pipes with water and
subsequently empty them after test. Water drained from the pipes shall be discharged in a way that does
not damage the Works or any other property or facilities, or cause inconvenience or a nuisance to the
Employer or other parties.
The Contractor shall notify the Engineer at least 3 working days beforehand of his intention to test a
section of pipeline. The test shall be made in the presence of the Engineer.
Should a line fail to pass any of the acceptance test, the Contractor shall, at his expense, determine the
source of the failure, make any necessary repairs, and retest the segment of piping in question at no cost
to the Employer.
All leakages shall be located and repaired by the Contractor. If leaks cannot be repaired while the line
is full, the water shall be drained and the necessary repairs made. The test procedure shall be repeated
until all leaks have been located and repaired.
On completion of each piping, the Contractor shall compile the data into a report, which shall be
submitted to the Engineer.
62
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
does not damage the Works or any other property or facilities, or cause inconvenience or a nuisance to
the Employer or other parties.
The Contractor shall notify the Engineer at least 3 working days beforehand of his intention to test a
section of pipeline. The test shall be made in the presence of the Engineer.
Should a line or manhole fail to pass any of the acceptance test, the Contractor shall, at his expense,
determine the source of the failure, make any necessary repairs, and retest the segment of piping or
manhole in question at no cost to the Employer.
All leakages shall be located and repaired by the Contractor. The test procedure shall be repeated until
all leaks have been located and repaired.
On completion of each pipeline, the Contractor shall compile the data into a report, which shall be
submitted to the Engineer.
All new sewers must be inspected by Closed Circuit Television (CCTV) survey in a period of 30 days
from its complete installation with backfilled trench. The CCTV survey shall include profile verification
with laser light- line, measuring any deformation of the pipeline.
Acceptance of pipes shall be subject to approval of the Engineer based on its review of CCTV survey
reports. Appreciation of these reports shall also result in repairing or replacement of surveyed pipes
whenever quality requirements are not met, at the sole expense of the Contractor. In advance of the
CCTV survey, it is the Contractor’s responsibility to ensure that sewers are suitably cleansed.
For any inspected pipeline, the CCTV report shall evidence the evaluation of all surveyed pipes,
including: an inspection DVD with all relevant footage; a photo report of anomalies; a slope report; a
deformation assessment of the pipes; report of other occurrences.
Pipe defects, dips, back fall and poor jointing highlighted by these surveys will need to be repaired.
Pipes with deformation in excess of 1.0% must be replaced.
2.5 Concrete
2.5.1 Standards
Concrete shall, except where otherwise specified, comply with the relevant provisions of
• ISO 6935-2: Steel for the reinforcement of concrete — Part 2: Ribbed bars
• ISO 10144: Steels for the reinforcement and prestressing of concrete — Certification scheme
for steel bars and wires
• ISO 12696: Cathodic protection of steel in concrete
• ISO 13270: Steel fibres for concrete — Definitions and specifications
• ISO 14654: Epoxy-coated steel for the reinforcement of concrete
• ISO 14656: Epoxy powder and sealing material for the coating of steel for the reinforcement of
concrete
• ISO 15630-1: Steel for the reinforcement and prestressing of concrete — Test methods — Part
1: Reinforcing bars, rods and wire
• ISO 12439: Mixing water for concrete
• ISO 16204: Durability — Service life design of concrete structures
• ISO 19595: Natural aggregates for concrete
• ISO 19596: Admixtures for concrete
• ISO 22965-1: Concrete — Part 1: Methods of specifying and guidance for the specifier
• ISO 22965-2: Concrete — Part 2: Specification of constituent materials, production of concrete
and compliance of concrete
• ISO 22966: Execution of concrete structures
• EN 10080: Steel for the reinforcement of concrete - Weldable reinforcing steel - General
• EN 197-1: Cement. Composition, specifications and conformity criteria for common cements
• EN 14216: Cement. Composition, specifications and conformity criteria for very low heat
63
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
special cements
• EN 14647: Calcium aluminate cement. Composition, specifications and conformity criteria
• EN 15743: Supersulfated cement. Composition, specifications and conformity criteria
• EN 12620: Aggregates for concrete
• EN 13055: Lightweight aggregates
• EN 13139: Aggregates for mortar
• EN 450: Fly ash for concrete. Definition, specifications and conformity criteria
• CEN/TR 15840: Evaluation of conformity of fly ash for concrete - Guidelines for the application
of EN 450- 2
• EN 15167-1: Ground granulated blast furnace slag for use in concrete, mortar and grout Part 1:
Definitions, specifications and conformity criteria
• EN 15167-2: Ground granulated blast furnace slag for use in concrete, mortar and grout Part 2:
Conformity evaluation
• EN 13263-1: Silica fume for concrete Part 1: Definitions, requirements and conformity criteria
• EN 13263-2: Silica fume for concrete Part 2: Conformity evaluation
• EN 934: Admixtures for concrete, mortar and grout
• EN 1008: Mixing water for concrete. Specification for sampling, testing and assessing the
suitability of water, including water recovered from processes in the concrete industry, as
mixing water for concrete
• EN 14889- 1: Fibres for concrete – Part 1: Steel fibres - Definitions, specifications and
conformity
• EN 14889- 2: Fibres for concrete – Part 2: Polymer fibres - Definitions, specifications and
conformity
• EN 206: Concrete. Specification, performance, production and conformity
• EN 1504-2: Products and systems for the protection and repair of concrete structures.
Definitions, requirements, quality control and evaluation of conformity. Surface protection
systems for concrete
• EN 1504-9: Products and systems for the protection and repair of concrete structures.
Definitions, requirements, quality control and evaluation of conformity. General principles for
use of products and systems
• EN 1504-10: Products and systems for the protection and repair of concrete structures.
Definitions, requirements, quality control and evaluation of conformity. Site application of
products and systems and quality control of the works
• EN 13670: Execution of concrete structures
• EN 12811-1: Temporary works equipment. Scaffolds. Performance requirements and general
design
• EN 12811-2: Temporary works equipment. Information on materials
• EN 12812: Falsework. Performance requirements and general design
• EN 13377: Prefabricated timber formwork beams. Requirements, classification and assessment
• EN 14487- 1: Sprayed concrete. Definitions, specifications and conform
• EN 14487- 2: Sprayed concrete. Execution
• DIN 1164: Cement
• DIN 1045-1: Concrete - specification, properties, production and conformity - Design
• DIN 1045-2: Concrete - specification, properties, production and conformity - Application rules
• DIN 1045-3: Concrete - specification, properties, production and conformity - Execution of
structures
• DIN 1045-4: Concrete - specification, properties, production and conformity - Execution of pre-
fabricated structures
• DIN 1048: Quality tests of concrete
• DIN 1084: Quality control of concrete
• DIN 4226: Concrete aggregates
• DIN 488: Reinforcing steel
64
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
65
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
EC2/ EN 206.
A C20/25
B
32 mm S3/100-150
C30/37 mm
C W/C ≤ 0.55
OPC
D 64 mm
C12/15 S2/50-90 mm
E 32 mm
The two numbers in the terminology according to EC2/ EN 206 respectively represent the characteristic
28-day strength values of 150 mm diameter x 300 mm high test cylinders and of test cubes with 150
mm edge lengths when prepared and tested in accordance with ISO 4012 e.g. test cylinders and cubes
made from C20/25 concrete shall respectively have characteristic strength values of 20 and 25 MPa at
28 days.
The Contractor shall arrange for trial mixes to be made for each class of concrete using the same type
of equipment and the same concrete ingredients as he intends to use for the Works and shall arrange for
specimens to be made from these mixes and tested in an approved laboratory for compliance with the
strength and other requirements specified above. The Contractor shall give the Engineer 24 hours’
notice of his intention to initiate the trial mix exercise described above so as to enable the Engineer to
witness the making of the trial mixes. He shall also arrange for the specimens that are prepared to be
tested and for the results to be submitted to the Engineer in the form of a report which contains a
recommendation for the mix that is to be used for each class of concrete. The recommended mixes shall
be used for all concrete produced for the Works.
The trial mix procedure described above shall be repeated every time the Contractor wishes to change
any of the concrete ingredients or the agreed batching plant/ place of manufacture.
2.5.5 Cement
2.5.5.1 Standards
The cement used in the Works shall be ordinary Portland cement (OPC) complying with EN 196 or an
equivalent Standard unless the concrete will be coming into contact with aggressive water. Cement for
concrete that will be coming into contact with aggressive water shall comply with the classification
“increased sulphate resistant” according to EN 197. Samples of cement shall be supplied, when
requested by the Engineer, both from the Contractor's store on Site and from the place of manufacture.
66
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
2.5.6 Additives
All additives shall be in liquid form. Additives shall not contain chloride.
If additives are specified or permitted, the concrete batching plant shall be equipped to automatically
and accurately dispense the additives into the mix.
Additives which produce the following effects may be specified:
• Shrinkage reducers for certain sealing grout or mortars (such additive shall be free of
iron)
• Water reducing plasticisers to provide satisfactory workability within the water-cement
ratio specified
• Air entraining admixtures to improve workability and imperviousness
The cement content of a mix shall not be reduced below the specified minimum content whether or not
additives are used.
Before the Contractor uses any additive, he shall determine:
• the compatibility of proposed additive with the other concrete ingredients
• its influence on the proportion of water for comparable consistencies
• the mechanical strength of the concrete obtained
• the optimum proportion of additive for the mix
The Contractor shall submit his findings to the Engineer and shall only use the additive once it has been
agreed with the Engineer.
2.5.7 Water
The water used for making and curing concrete shall be at the time of use be free from polluting matter
in any quantity. The Contractor shall arrange for the water which he proposes to use to be tested in an
approved laboratory and shall submit the records of any such tests to the Engineer before placing any
concrete in the Works.
67
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
crushed stone, or other suitable materials for use with the cement specified. It shall be free from clay,
shells, organic material or other deleterious substances and shall be furnished from agreed sources.
The Contractor shall arrange for all aggregates to be tested and shall provide such facilities as may be
necessary for procuring representative test samples. The tests shall include chemical analyses designed
to detect the presence of constituents which could adversely affect the concrete quality or longevity. If
any aggregate does not comply with specified grading, the Contractor shall correct the grading with no
extra cost for the Employer.
Aggregates shall be stored on concrete floors in order to avoid contamination. The different fractions
of the aggregates shall be stored separately and mixing of the different fractions shall be prevented by
means of partition walls or other approved methods.
All aggregates shall be washed with clean fresh water at no extra cost to the Employer if this is necessary
for them to comply with the Specifications.
68
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
before entering the mixer. The moisture contents of the aggregates shall be determined and the mixing
water content shall be adjusted correspondingly.
The Contractor shall provide standard test weights at least equivalent to the maximum working load
used on the most heavily loaded scale and other auxiliary equipment required for checking the
satisfactory operation of each scale or other measuring device. Tests shall be made by the Contractor at
least once a week or at intervals to be determined by the Engineer and shall be carried out in his
presence. For the purpose of carrying out these tests, there shall be easy access for personnel to the
weigh hoppers. The Contractor shall furnish the Engineer with copies of the complete results of all
check tests and shall make any adjustments, repairs or replacements necessary to ensure satisfactory
performance.
The nominal drum or pan capacity of the mixer shall not be exceeded. The turning speed and the mixing
time shall be as recommended by the manufacturer, but in addition, when water is the last ingredient to
be added, mixing shall continue for at least one minute after all the water has been added to the drum
or pan. The blades of pan mixers shall be maintained within the tolerances specified by the manufacturer
of the mixer and the blades shall be replaced when it is no longer possible to maintain the tolerances by
adjustment. Mixers shall be fitted with an automatic recorder registering the number of batches
discharged.
The water to be added to the mix shall be reduced by the amount of free water contained in the coarse
and fine aggregates. This amount shall be determined by the Contractor by a method agreed by the
Engineer immediately before mixing begins each day and thereafter at least once per hour during
concreting and for each delivery of aggregates during concreting. When the correct quantity of water,
determined as set out in the Specification, has been added to the mix, no further water shall be added,
either during mixing or subsequently.
After mixing for the required time, each batch shall be discharged completely from the mixer before
any materials for the succeeding batch are introduced. Mixers which have been out of use for more than
30 minutes shall be thoroughly cleaned before any fresh concrete is mixed and thereafter the first batch
of concrete through the mixers shall contain only half the normal quantity of coarse aggregate. This
batch shall be mixed for one minute longer than the time applicable to a normal batch. Mixers shall be
cleaned out before changing to another type of cement.
Concrete for structural purposes shall not be mixed by hand. Where non-structural concrete is required,
hand mixing may be carried out subject to the agreement of the Engineer. The mixing shall be done on
a hard impermeable surface. The materials shall be turned over not less than three times dry, water shall
then be sprayed on and the materials again turned over not less than three times in a wet condition and
worked together until a mixture of uniform consistency is obtained. For hand mixed concrete the
specified quantities of cement shall be increased by 10% and not more than 0.5 cubic meter shall be
mixed at one time. During windy weather efficient precautions shall be taken to prevent cement from
being blown away during the process of gauging and mixing.
69
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
2.5.11 Placing Concrete
2.5.11.1 Consent for placing
Concrete shall not be placed in any part of the Works until the Engineer’s consent has been given in
writing, and the Contractor shall give the Engineer at least 1 full working day’s notice of his intention
to place concrete. No concrete shall be placed before agreement from the Engineer is sought
respectively given. The release shall cover amongst others associated formwork, installation of parts to
be embedded, preparation of surfaces etc. Concrete shall be placed only in the presence of the Engineer,
unless permission is obtained by the Contractor for placing concrete in his absence.
If concrete placing is not commenced within 24 hours of the Engineer’s consent the Contractor shall
again request consent as specified above.
2.5.11.3 Chutes
In general, transportation of concrete by the use of chutes will not be permitted unless approved by the
Engineer. The chute shall have a section with round corners and shall have a proper fixed slope so as to
allow the concrete to flow satisfactorily and without segregation. The lower end of chute shall be
provided with a drop chute not less than 0.6m in height to avoid segregation of falling concrete. The
height of drop shall not exceed 1.5m. Chutes shall be protected from direct sunlight, wind and rain.
70
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
from the pipe line or any other part.
Air boosters shall not be used except in conditions where the outlet of the pipe is completely embedded
at least 2 metres in fresh concrete.
71
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
or is likely to be prolonged, the Contractor shall immediately take the necessary action to form a
construction joint so as to eliminate as far as possible feather edges and sloping top surfaces and shall
thoroughly compact the concrete already placed in accordance with Clause 406. All work on the
concrete shall be completed while it is still plastic and it shall not thereafter be disturbed until it is hard
enough to resist damage. Plant and materials to comply with this requirement shall be readily available
at all times during concrete placing.
Before concreting is resumed after such an interruption the Contractor shall cut out and remove all
damaged or uncompacted concrete, feather edges or any other undesirable features and shall leave a
clean sound surface against which the fresh concrete may be placed.
If it becomes possible to resume concrete placing without contravening the Specification and the
Engineer consents to a resumption, the new concrete shall be thoroughly worked in and compacted
against the existing concrete so as to eliminate any cold joints.
72
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
No concrete shall be placed when the ambient temperature is less than 5°C. When ambient temperatures
are high, measures shall be taken by the Contractor to maintain the temperature of freshly mixed
concrete below 32°C, failing which concreting shall be stopped until the ambient temperature has
dropped to a level at which the temperature of the freshly mixed concrete can be kept below 32°C
without any measures being taken to cool down the ingredients.
73
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
The curing process shall commence as soon as the concrete is hard enough to resist damage from the
process, and in the case of large areas or continuous pours, shall commence on the completed section
of the pour before the rest of the pour is finished.
Details of the Contractor’s proposals for curing concrete shall be submitted to the Engineer before the
placing of concrete commences in the Works. Formed surfaces may be cured by retaining the formwork
in place for the required curing period.
If the use of the foregoing methods is inappropriate, surfaces which will not have further concrete
bonded to them and which are not to receive an application of a finish may be cured by the application
of a curing compound having an efficiency index of at least 90 percent. Curing compounds shall contain
a fugitive dye to enable the extent of the spread to be seen easily.
Curing compound is used on surfaces exposed to the atmosphere shall contain sufficient finely divided
flake aluminum in suspension to produce a complete coverage of the surface with a metallic finish when
applied at the rate recommended by the manufacturer.
Curing compounds shall become stable and impervious to the evaporation of water from the concrete
surface within 60 minutes of application. The material shall not react chemically with the concrete
surfaces for at least the first four days of the curing period.
If instructed by the Engineer, the Contractor shall, in addition to the curing provisions set out above
provide a suitable form of shading to prevent the direct rays of the sun reaching the concrete surfaces
for at least the first four days of the curing period.
Exposed concrete surfaces shall be closely covered with impermeable sheeting, properly secured to
prevent its removal by wind and the development of air spaces beneath it. Joints in the sheeting shall
be lapped by at least 300mm.
If for some reason it is not possible to use impermeable sheeting, the Contractor shall keep the exposed
surfaces continuously wet by means of a water spray or by covering with a water absorbent material
which is kept wet, unless this method conflicts with requirements.
Water used for curing shall be of the same quality as that used for concrete mixing.
The Contractor shall limit the development of temperature differentials in concrete after placing by any
means appropriate to the circumstances including the following:
• Limiting concrete temperatures at placing;
• Use of low heat cement, subject to the agreement of the Engineer;
• Insulation of exposed concrete surface by insulating blankets. Such blankets shall have an
insulation value at least equivalent to 50mm of dry mineral wool;
• Leaving formwork in place during the curing period. Steel forms shall be suitably insulated on
the outside;
• Preventing rapid dissipation of heat from surfaces by shielding from wind;
• Avoiding the use of water sprays when such use would cause rapid cooling of the surface.
74
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
shall maintain in good working order all plant and equipment required for this purpose.
In the event that conditions become such that even with the use of the equipment the requirements
cannot be met, concrete placing shall immediately cease until such time as the requirements can again
be met.
During hot weather the Contractor shall take all measures necessary to ensure that the temperature of
concrete at the time of placing in the Works does not exceed 30 degrees centigrade and that the concrete
does not lose any moisture during transporting and placing.
Such measures may include but are not necessarily limited to the following: i) shielding aggregates
from direct sunshine; ii) use of a mist water spray on aggregates; iii) sun shields on mixing plants and
transporting equipment; iv) cooling the mixing water. If ice is used for this purpose it should preferably
be in flake form. Lump ice shall not be allowed to enter the tank supplying the mixer drum; and v)
covering skips closely with polythene sheet so that the latter is in contact with the concrete.
Areas in which concrete is to be placed shall be shielded from direct sunshine and rock or concrete
surfaces shall be thoroughly wetted to reduce absorption of water from the concrete placed on or against
them.
After concrete in any part of an area has been placed, the selected curing process shall be commenced
as soon as possible. If any interval occurs between completion of placing and start of curing, the
concrete shall be closely covered during the interval with polythene sheet to prevent loss of moisture.
75
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
2.5.16.2 Compliance with Specified Requirements
The concrete shall be deemed to comply with the specified strength requirements if:
• the average strength determined for the 3 cubes in each set that are tested at 28 days
exceeds the characteristic strength for the grade of concrete in question i.e. exceeds 25 MPa
for Class A (C20/25) concrete; and
• each of the 28-day test results exceeds 85% of the specified characteristic strength i.e.
exceeds 21.3 MPa for Class A (C20/25) concrete.
2.5.18 Tolerances
Unless otherwise shown in the Drawings, the tolerances shown in the following table shall be applicable
to concrete structures (Note: For buried construction, the tolerances shall be twice those shown).
76
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Variation from plumb, from the specified batter, or from the curved surfaces of in 3 m 12 mm
all structures, including piers, buttresses, arch sections, vertical joint grooves,
in 6 m 20 mm
and visible arises.
Variation from the level or from the grades indicated for slabs, beams, soffits, in 3 m 6 mm
horizontal joint grooves and visible arises.
in 6 m 12 mm
Variation in the thickness of slabs, walls, arch sections, and similar members Minus 6mm
77
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
with water.
2.6 Formwork
2.6.1 General
Formwork means the surface against which concrete is placed to form a face, together with all the
immediate supports to retain it in position while concrete is placed. Falsework means the structural
elements supporting both the formwork and the concrete until the concrete becomes self-supporting. A
formed face is one which has been cast against formwork. An exposed face is one which will remain
visible when construction has been completed.
The Contractor shall be responsible for the design and construction of the formwork and shall supply
and fix all formwork required for the placing of concrete together with its attendant scaffolding,
timbering, shoring, strutting, etc.
Depending on the required surface finish, the Contractor will be permitted to use timber boards,
plywood, steel plate or timber for the construction of formwork. Where timber is used, the formwork
surfaces coming in contact with wet concrete shall be made of properly seasoned timber.
All formwork shall be correctly aligned and securely braced so as to be able to withstand, without
displacement or deflection, the movement of men, materials and plant and the pressure of wet concrete
whilst it is being poured and vibrated.
The formwork shall be constructed in such a manner that leakage of concrete is prevented.
All exposed concrete shall have the external angles chamfered 25mm x 25mm by means of moulding
strips fixed to the formwork.
Ferrules and wire ties shall not be used for the temporary connection of the opposite sides of formwork
for concrete walls and members of water retaining or conveying structures. The use of such connection
methods in other structures will be subject to the Engineer’s agreement. Wherever ferrule and wire
78
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
connections are permitted, the ends of the ferrules or ties shall, after removal of the forms, be cut back
at least 15mm from the face of the concrete and covered with 1:2 cement: sand mortar containing a
shrinkage-reducing additive. The hole formed by the cutting process shall be thoroughly cleaned and
wetted before filing. The mortar shall be of damp, but not fluid consistency. The patch shall be properly
trowelled smooth to match the surrounding concrete surfaces and shall be thoroughly cured by keeping
it moist for at least three days. After the patch has hardened, the patch and the adjacent concrete shall
be ground smooth. The rates for concrete will be deemed to cover the costs of all these operations.
Embedded metal rods shall be used for the temporary connection of the opposite sides of formwork for
concrete walls and members of water retaining or conveying structures. Such rods shall, after removal
of the forms, be cut back at least 25 mm and 40 mm respectively below the formed surfaces of dry and
wet concrete faces. Embedded fasteners on the ends of such rods shall be such that their removal will
leave holes of regular shape. The holes left in the concrete surfaces by the removal of fasteners on
holding rods shall be filled and finished off in the manner described above.
Where necessary, parallel sided or tapered pockets for the casting-in of holding-down bolts, brackets
for pipes, ladders or other fittings, etc. shall be formed in the concrete using polystyrene formers or
wooden boxes fabricated in such a manner that they can be completely withdrawn or broken up and
removed after the concrete has set. The rates for concrete will be deemed to cover all costs associated
with the forming and grouting up of such pockets.
2.6.2 Construction
Before construction begins, the Contractor shall submit to the Engineer, drawings showing details of
the proposed formwork and falsework.
Formwork and falsework shall be so constructed that they will support the loads imposed on them by
the fresh concrete together with additional stresses imposed by vibrating equipment and by construction
traffic, so that after the concrete has hardened the formed faces shall be in the positions shown on the
drawings within the tolerances set out in ISO, EN, DIN and/or BSI standards.
Ground supports shall be properly founded on footings designed to prevent settlement. Joints in
formwork for exposed faces shall, unless otherwise specified, be evenly spaced and horizontal or
vertical and shall be continuous or form a regular pattern. All joints in formwork including formwork
for construction joints shall be tight against the escape of cement, water and fines. Where reinforcement
projects through formwork, the form shall fit closely round the bars.
Formwork shall be so designed that it may be easily removed from the work without damage to the
faces of the concrete. It shall also incorporate provisions for making minor adjustments in position if
required, to ensure the correct location of concrete faces. Due allowance shall be made in the position
of all formwork for movement and settlement under the weight of fresh concrete.
Where overhangs in formwork occur, means shall be provided to permit the escape of air and to ensure
that the space is filled completely with fully compacted concrete.
Formwork shall be provided for concrete surfaces at slopes of 30 degrees to the horizontal or steeper.
Surfaces at slopes less than 20 degrees may be formed by screeding. Surfaces at slopes between 20
degrees and 30 degrees shall generally be formed unless the Contractor can demonstrate to the
satisfaction of the Engineer that such slopes can be screeded with the use of special screed boards to
hold the concrete in place during vibration.
Horizontal or inclined formwork to the upper surface of concrete shall be adequately secured against
uplift due to the pressure of fresh concrete. Formwork to voids within the body of the concrete shall
also be tied down or otherwise secured against floating.
The internal and external angles on concrete surfaces shall be formed with fillets and chamfers of the
sizes shown on the drawings unless otherwise instructed by the Engineer.
Supports for formwork for non-water retaining structures may be bolted to previously placed concrete
provided the type of bolt used is acceptable to the Engineer. If metal ties through the concrete are used
79
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
in conjunction with bolts, the metal left in shall not be closer than 50mm to the face of the concrete.
Supports for formwork for water retaining structures may be bolted to previously placed concrete
provided the type of bolts and positions of fixing are acceptable to the Engineer. After concreting the
Contractor shall remove all support bolts and seal all holes with well rammed cement/sand mortar
containing approved waterproofing cement additive. Metal ties which would be left in the concrete shall
not be permitted.
Formwork shall not be re-used after it has suffered damage which in the opinion of the Engineer is
sufficient to impair the finished surfaces of the concrete.
Where circumstances prevent easy access within the form for cleaning and inspection, temporary
openings for this purpose shall be provided through the formwork.
Shear keys shall be provided in all construction joints of the size and shape indicated on the drawings.
Where precast concrete elements are specified for use as permanent formwork, or proposed by the
Contractor and agreed by the Engineer, they shall comply with the requirements of the Specification.
Such elements shall be set true to line and level within the tolerances prescribed for the appropriate
class of finish in Clause 506 and fixed so that they cannot move when concrete is placed against them.
2.6.3 Preparation
Before any reinforcement is placed into position within formwork, the latter shall be thoroughly cleaned
and then dressed with a release agent. The agent shall be either a suitable oil incorporating a wetting
agent, an emulsion of water suspended in oil or a low viscosity oil containing chemical agents. The
Contractor shall not use an emulsion of oil suspended in water nor any release agent which causes
staining or discoloration of the concrete, air holes on the concrete surface, or retards the set of the
concrete.
In order to avoid colour difference on adjacent concrete surfaces, only one type of release agent shall
be used in any one section of the works.
In cases where it is necessary to fix reinforcement before placing formwork, all surface preparation of
formwork shall be carried out before it is placed into position. The Contractor shall not allow
reinforcement or prestressing tendons to be contaminated with formwork release agent.
Before placing concrete all dirt, construction debris and other foreign matter shall be removed
completely from within the placing area.
Before concrete placing commences, all wedges and other adjusting devices shall be secured against
movement during concrete placing and the Contractor shall maintain a watch on the formwork during
placing to ensure that no movement occurs.
2.6.4 Removal
Forms shall not be removed until the strength of the concrete is such that form removal will not result
in perceptible cracking, spalling or breaking of surfaces, or other damage to the concrete. Any concrete
so damaged shall be repaired in accordance with this Specification at the Contractor’s expense.
In no case shall forms to soffits be struck until test cubes from the actual concrete concerned have
yielded the targeted 7-days strengths. As a guide, and subject to the foregoing the following minimum
removal times are recommended for forms (*) Cement according to EN 197):
80
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Table 2.3 – Standards for formwork Removal
Cement Type by Formwork for Sides Formwork for Soffits of Props of Beams,
Strength of Wall, Beams, Pillars Slabs and Beams Frames and Slabs
Formwork shall be carefully removed without shock or disturbance to the concrete. No formwork shall
be removed until the concrete has gained sufficient strength to withstand safely any stresses to which it
may thereby be subjected.
The minimum periods which shall elapse between completion of placing concrete and removal of forms
are given in the Table below and apply to ambient temperatures higher than 10 degrees centigrade. At
lower temperatures or if cement other than ordinary Portland are involved, the Engineer may instruct
that longer periods be used. Alternatively, formwork may be removed when the concrete has attained
the strength set out in the Table below, provided that the attained strength is determined by making test
cubes and curing them under the same conditions as the concrete to which they refer.
Compliance with these requirements shall not relieve the Contractor of his obligation to delay removal
of formwork until the removal can be completed without damage to the concrete.
81
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
to prevent any slumping at the face. The mortar shall be mixed in the same proportions as the fine
aggregate and cement in the surrounding concrete and with the same materials and shall be finished
flush with the face of the concrete.
82
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
After stripping of the formwork, all projections shall be removed, irregularities repaired and the surface
rubbed or treated as necessary to form a smooth finish of uniform texture, appearance and colour.
Surface irregularities shall not exceed 2 mm for abrupt irregularities or 6 mm for gradual irregularities.
Abrupt irregularities will not be permitted at construction joints.
2.7 Reinforcement
2.7.1 General
Bar reinforcement shall be of mild steel and shall comply with the relevant DIN and EN Standards.
Only ribbed bars with a yield point of 590 N/mm² and an ultimate tensile strength of 620 N/mm² or
higher and mesh consisting of such ribbed bars shall be used in the Works.
Steel reinforcement shall be stored clear of the ground and supported to prevent distortion. Bars which
have become distorted shall not be straightened or re-bent for incorporation into the Works. The
reinforcement shall, at the time of incorporation into the Works, be clean and free from damage and
loose rust.
The Contractor shall ascertain for himself from the information given in the Drawings and in the
Specification the precise requirements of steel reinforcement to be obtained for the Works. Where
necessary, the Contractor shall prepare working reinforcement drawings and bending schedules. In
preparing such drawings and schedules, the Contractor shall allow for lapping of the bars in accordance
with standard practice and shall avoid unnecessary lapping of bars or excessive lap lengths.
The Contractor shall ensure that the reinforcement is rigidly fixed so that it remains in the position
shown on the drawings during placing of the concrete. Welding of the reinforcement is designated as
being weldable in accordance with EN10080. Spacers, either PVC or metallic, shall be subject to release
for application by the Engineer.
83
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
The Contractor shall not place concrete around reinforcement until the Engineer has inspected the
reinforcement and has given his consent for concrete placing.
84
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Before concrete is placed in any section of the Works which includes reinforcement, the reinforcement
shall be completely clean and free from all contamination including concrete which may have been
deposited on it from previous operations.
The Engineer’s approval for concrete placing is to be sought in writing for each pour, leaving adequate
time to inspect and rectify any defects noted in the formwork, falsework, reinforcement, scaffolding,
concreting arrangements, etc.
2.8 Geotextiles
The geotextiles to be applied in the work must be submitted to the Engineer’s approval, accompanied
by certificates of origin and technical data sheet, as well as works in which it has been applied with
identical functions. They must be of the type and characteristics indicated in the Project, depending on
the work conditions. When used as geotextile for separation and filtration and drainage, they will be
non-woven and punctured (said, in slang, needled).
The material shall be not rotatable, insensitive to acids or bases and unassailable by microorganisms or
insects and shall have the minimum characteristics stipulated for each use. The material shall also have
a homogeneous texture and thickness, without defects, and shall be protected during storage from
sunlight, mineral salts, dust, rain or ice.
If transport, storage or handling has been impaired, the first turns of the defective geotextile roller must
be eliminated. The application of geotextile should be at least 0.30m overlapped.
On-site storage of the geotextile rollers shall be carried out by the Contractor at an appropriate location
and the protective covering shall only be removed from the factory at the beginning of the installation.
Special care should be taken to avoid prolonged direct exposure of the geotextile to the action of
sunlight, dust, clay soils, or other factors that may affect its quality.
Regardless of the size that has to be done for each particular case, it is recommended that the minimum
and maximum characteristics of landfill geotextiles be as follows:
• Ultimate tensile strength (EN ISO 10319), minimum 15kN/m
• Creep rupture (EN ISO 10319), minimum 40%
• Puncture resistance (EN ISO 12236) 1,5 kN
• Permittivity (prEN 12040), minimum 0,2 s-1
• Porometry (O90), maximum 150 m
• Materials to be applied to geotextile with separation function at the bottom of the landfill shall
be free of debris, organic matter or any other harmful substances, and shall meet the following
minimum characteristics:
• Maximum dimension 200 mm
• The percentage of material passing the ASTM (No.200) sieve 15%
• Liquid limit 25%
• Plasticity index 6%
• Sand equivalent 20%
The material to be applied over geotextiles for the purpose of forming a draining layer under landfills
for the drainage of waters resulting from the consolidation process of very compressible alluvial
formations shall be of uniform quality, free from organic matter or other harmful substances and shall
comply with: following minimum characteristics:
a) Sand
• Nominal size granulometry 0,06 / 6 mm
• The percentage of material passing the ASTM (No.200) sieve 6%
• Sand equivalent 70%
• Rocky Material
• Maximum dimension 200 mm
85
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Exterior 1 1 5
Interior 1 1 6
Smooth finish 1 4 8
86
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
All masonry work shall be carried up in a uniform manner with no portion being more than one metre
above an adjacent portion at any time. Walls are to be set raking where one length of wall is to be
bonded with another adjoining wall at a later stage, with the raking portion being wetted thoroughly
before work is recommenced.
Horizontal joints shall be neatly pointed around as the work proceeds.
Vertical joints shall not exceed one course in height and shall be staggered. All headers shall be bonded
lengthwise through solid walls and no bats shall be used except where required as closers.
2.10 Metalwork
2.10.1 General
Before commencing fabrication of metal work, the Contractor shall verify all conditions affecting the
work and obtain accurate dimensions and arrangements of all existing or newly built supports.
Welding of galvanized steel work shall not be permitted. Instead, it shall be assembled using bolts and
nuts.
The permissible design stresses for materials, bolts, rivets, etc. shall be as given in DIN 18800. The
permissible design stresses for welds shall be as given in DIN 4100.
Rolled structural steel sections shall be mild steel, conforming to DIN 17100. The dimensions,
tolerances and properties of the structural sections shall conform to DIN 18201, DIN 18203 and DIN
18800. Where prefabricated proprietary designs are used, the Standards to which they are manufactured
87
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
shall be at least equivalent to the foregoing.
For structural steel work assemblies, steel bolts, nuts and washers shall be high strength friction grip
bolts conforming to DIN 6914 up to DIN 6916 or black bolts including nuts and washers conforming
to DIN 7989 and DIN 7990.
All welding consumables (electrodes, wire, filler rods, flux, shielding gas and the like) shall comply
with the requirements of the appropriate DIN Standard and with the requirements of the appropriate
welding procedure.
All metal work shall be erected and installed to the lines and positions shown on the Drawings and shall
be well anchored to the concrete foundations or structures.
Unless the grouting in of anchor bolts in previously prepared recesses is agreed, anchor bolts and metal
parts to be embedded in concrete shall be placed in position before casting of the concrete and shall be
held firmly and accurately in place while the concrete is being placed.
Cast iron fittings such as chamber covers, spindle casings and step shall be of standard manufacture.
All other metal work such as pipe supports, holder bats, pipe anchor clamps, etc. shall be fabricated by
the Contractor.
Bolt holes shall be made by drilling only, and shall be accurately positioned so that bolts can be easily
inserted. Unless otherwise shown on the Drawings, bolts shall protrude from nuts not less than two
threads.
88
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Refer also to the “General Mechanical Requirements”
Ladders 1, 3 and 4
Step irons 2
Hand railing 3
During installation, each item of metalwork shall be temporarily supported and braced as necessary to
resist all forces which are likely to be applied to it during installation, fixing and building in. Any bolted
connections required as part of the installation shall be fitted and tightened before fixing bolts are
tightened or pockets are grouted. The nuts of grouted or resin fixed bolts shall not be tightened until the
grout has fully cured.
89
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
90
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
rings shall be manufactured from synthetic rubber. Flanged joint gaskets shall be of the inside bolt circle
type, unless specified otherwise.
3.1.4.1 General
All metalwork that is to be painted shall be cleaned down to the bare metal and given a complete
treatment of surface preparation, priming coats and finishing coats to give a durable, protective system
consistent with the conditions which the metalwork will experience on Site. Surface preparation and at
least one priming coat shall be applied at the manufacturer’s premises.
All paints and materials shall be agreed with the Engineer and shall be used in accordance with the
manufacturers’ instructions. Undercoats shall be of distinctive tints and finishing colours shall be as
directed by the Employer.
In no case shall paint be applied during rainy or misty weather or to surfaces upon which there is
moisture condensation. At least 24 hours shall elapse between the application of successive coats unless
otherwise specified by the manufacturer. All surfaces of steelwork or iron work to be painted shall be
well rubbed down and wire- brushed to ensure that they are free from rust or scale.
Paintwork of more than one coat shall not consist of any two coats of the same colour. The colours of
the coats of paint shall be determined in consultation with the Engineer.
The paintwork must be free of drips, runs and blisters. Any areas of damaged paintwork, once
discovered, shall be de-rusted immediately with sharp scrapers and brushes, and directly thereafter re-
touched with the same paint as present on the surrounding surfaces.
Freshly painted components must not be moved or transported before the drying times recommended
by the paint supplier have elapsed. The transportation of wholly or partially painted components must
be arranged in such a way that the chances of the paint work being damaged are as limited as possible.
Components of the installation that are to be purchased from third parties shall be preserved with a paint
system similar to the system to be employed by the Contractor under his own control.
Components to be cast into concrete shall be preserved - prior to their being cast in - by means of the
galvanisation or metallization of all their surfaces that will be external to the concrete or internal to the
concrete up to a depth of approx. 100 mm; surfaces internal to concrete must never be painted.
Components that must remain uncovered in order to function properly shall be either carefully smeared
with water-repellent, acid-free grease or, if necessary, coated with preservation lacquer. All plain steel
fasteners, bolts, nuts, washers etc. that are to be employed in humid atmospheres should be hot-dip
galvanised.
The coating thickness referred to in the specifications apply to dried paint. Total coating thickness
includes any metallizing layers applied. The following coating specifications may, subject to the
Engineer’s agreement, be changed to equal alternatives according to coating supplier’s
recommendations.
3.1.4.2 Specifications
Cleaning
Before cleaning begins, steel components should be brought as far as possible into their final forms.
Steel components that would otherwise be rendered inaccessible (and therefore incapable of being
cleaned) as a result of welding operations shall be first cleaned, directly thereafter welded, and as soon
91
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
as possible preserved. The number and dimensions of spaces that will be inaccessible after the
completion of components should be reduced to a minimum by appropriate design. Cleaning of steel
components shall incorporate thorough stripping-off of grease, good drying and subsequent thorough
de-rusting and abrasive-blast or pickle cleaning; accompanied with hot-dip galvanising. Blast-cleaning
shall be carried out with steel shot of maximum grain diameter 0.7 mm, or a mixture of similarly-sized
steel shot and chopped steel wire in equal proportions, or an inert medium.
After cleaning, all free surface slag and scale shall be chipped off, the rough surfaces shall be abraded,
and then the components shall once again be thoroughly cleaned. Cast-iron components shall be
thoroughly de-rusted and blast-cleaned until bright.
3.1.4.3 Application
All prime coatings and finish-paint shall be applied by brush or airless spray or a combination of these
methods, as recommended by the coating manufacturer.
Paint erroneously applied to items that are not to be painted shall be removed at the Contractor's
expense, leaving the surface clean, unstained and undamaged.
To the maximum extent practical, the coats shall be applied as a continuous film of uniform thickness
and free of pores. Overspray, skips, runs, sags and drips shall be kept to a minimum. The different coats
shall not be of the same colour.
Each coat of paint shall be allowed to harden before the next is applied. For epoxy paint the hardening
time before the next coat will normally be 12 - 14 hours. Suppliers' recommendations regarding
92
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
hardening time of epoxy paints must be followed.
Particular attention must be paid to applying the full film thickness at edges.
3.1.4.4 Materials
All paint materials shall be first quality products manufactured for the exposures involved. The different
system materials shall be as follows:
System A
Primer Ferrous metal, un-primed:
• coat zinc chromate primer
• coats alkyd enamel semi-gloss
• Ferrous metal, shop primed
• Touch up with zinc chromate primer
• 1 coat alkyd enamel semi-gloss Galvanized and non-ferrous surfaces:
• 1 coat vinyl butyral etch primer
• 1 coat alkyd zinc phosphate primer
• 1 coat alkyd zinc phosphate primer
Intermediate 1 coat 2-component micaceous iron oxide epoxy Finish 1 coat 2-component aliphatic
polyurethane finish
System B
Primer Ferrous metal, un-primed:
• 1 coat zinc chromate primer
• 2 coats alkyd enamel semi-gloss Ferrous metal, shop primed
• Touch up with zinc chromate primer
• 1 coat alkyd enamel semi-gloss Galvanized and non-ferrous surfaces:
• 1 coat vinyl butyral etch primer
• 1 coat alkyd zinc phosphate primer Intermediate 1 coat alkyd enamel gloss Finish 1 coat
alkyd enamel gloss
System C
Primer 1 coat 2-component high solids coal tar epoxy Finish 2 coats 2-component high solids coal
tar epoxy Service Condition System A
Metals subject to corrosive chemical moisture, atmosphere, or condensation shall be prepared and
coated in accordance with the following requirements:
• Surface Preparation: all bare metal surfaces shall be field sandblasted. Weld surface, edges, and
sharp corners shall be ground to a curve and all weld splatter removed and all welds neutralized
with thinner. All surfaces shall be dry before applying any paints or coatings
• Coating System: use material specified for System A. Coatings shall be applied by airless spray
but by brush for small areas. Prime coat shall have a minimum thickness of 50 microns. An
intermediate coat shall have a minimum thickness of 100 microns, and finish coat shall have a
minimum thickness of 100 microns. The total system shall have a minimum dry film thickness
of 250 microns
• Time between Coatings: a minimum of 12 hours’ time is required before additional coats may
be applied to the prime coats, two hours for the intermediate coat, and two hours for the finish
coat
93
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Miscellaneous Coatings
• Hydrants, indicator posts, traffic posts, guard rails and ladders, shall be in safety colour, or equal
applied using specified coating System "B"
• All surfaces shall be dry before applying any paints or coatings
3.1.5 Erection
3.1.5.1 Erection of Pipes
Care shall be taken during the erection of pipework, either during erection or during service. The
Contractor shall use end caps or plugs to prevent the entrance of dirt, water and other foreign matter
into pipes or fittings. Plates, plugs or caps may not be attached to the pipes by means of welding or any
other method, which will damage the pipe ends. The caps or plugs shall be installed after finishing daily
work or whenever work is interrupted for other than very short duration.
Joints shall be made strictly in accordance with the manufacturers’ instructions. The Contractor shall
make use of the technical advisory services offered by manufacturers for instructing pipe jointers in the
method of assembling joints. Where manufacturers recommend the use of special jointing methods, the
Contractor shall use these methods for the assembly of all joints to pipes.
Before making any joint all jointing surfaces shall be thoroughly cleaned and dried and maintained in
such condition until the joints have been completely made or assembled, using joint lubricant if
recommended by the pipe manufacturer. Notwithstanding the flexibility provided in the pipe joints,
pipes must be securely positioned to prevent avoidable movements during and after making the joint.
94
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
The gap between the end of the spigot and the shoulder of the socket of flexibly jointed pipes shall be
as recommended by the manufacturer. All pipes shall be accurately marked prior to laying ensuring that
the correct gap is left in the joint.
All nuts and bolts used in jointing buried flanged pipes shall be of stainless steel SS316. The flanges or
flanged joints shall be correctly positioned and the component parts including any insertion gasket
cleaned and dried. Insertion gaskets shall be fitted smoothly to the flange without folds or wrinkles. The
flange faces and boltholes shall be brought fairly together and the joints shall be made gradually and
evenly by tightening bolts in diametrically opposed positions. Only standard-length spanners shall be
used to tighten the bolts. The protective coating, if any, of the flange shall be made good when the joint
has been completed.
95
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Materials
Attention shall be paid to obtaining a good working environment such as selection of low smoke
developing consumables, etc.
The weld filler metal selected shall give a weld metal matching the base metal properties as closely as
possible. The yield strength of consumables shall neither overmatch the base material yield strength by
more than one level in EN 499, nor shall under-matching be allowed.
Welding Processes
Acceptable welding processes are:
• Shielded Metal Arc Welding (Stick) SMAW
• Gas Tungsten Arc Welding (TIG) GTAW
• Gas Metal Arc Welding (MIG/MAG) GMAW
• Flux Cored Arc Welding FCAW
Processes may be used in combination if the same combination and sequence of processes have been
qualified by the welding procedure qualification test.
Welding Preparation
The material grades, wall thicknesses and pressure ratings of welded items shall conform to the
requirements laid down in the applicable drawings and specifications.
Each pipe or component shall be visually inspected to ensure that it has not sustained any visually
determinable damage.
All requirements for welding preparation contained in the qualified welding procedure specification
96
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
shall be strictly adhered to.
Welding
Welding shall be suspended by the Contractor when prevailing weather conditions will impair the
quality of the work, e.g. airborne moisture, blowing sand, high winds or thunderstorms.
Stray arcing outside the weld groove is not permitted. Should stray arcing outside this area occur, this
shall be brought to the attention of the Engineer who may require any such damaged section to be
repaired or cut out at the Contractor's expense.
Earth connections for the welding shall always be positioned in the centre of the joint during root and
cap-bead laying. They shall be mechanically or magnetically connected to the pipe.
Each pass shall be completed around the whole circumference before the next pass is started. The
position of start/ stop on subsequent passes shall not be identical.
Upon completion of the cap bead, the weld and the pipe surface shall be cleaned of weld spatter and
other deposits, and shall then be wrapped with a dry waterproof insulating mat to ensure a slow cooling
of the weld zone and to give protection against rain.
Welding Inspection
Examination may be performed according to this specification and the following codes and standards:
• Radiographic examination according to ISO 1106, Part 3, Recommended. Practice for
Radiographic Examination of Fusion Welded Joints in Steel Pipes of up to 50 mm Wall
Thickness.
• Ultrasonic examination according to ASME Boiler and Pressure Vessel Code Section V, Non-
destructive Examination, Article 5, Ultrasonic Examination Methods for Materials and
Fabrication.
• Magnetic particle examination according to ASME Boiler and Pressure Vessel Code, Section
V, Non- destructive Examination, Article 7, Magnetic Particle Examination.
• Liquid penetrant examination according to ISO 3452, Non-destructive Testing, Penetrant
Inspection, General Principles.
• Visual examination according to ASME Boiler and Pressure Vessel Code, Section V, Non-
destructive Examination, Article 9, Visual Examination.
• Hardness measurement according to ASTM El 10, Standard Test Method for Indentation
Hardness of Metallic Materials by Portable Hardness Testers.
The Contractor shall engage a qualified independent inspection company which shall perform, evaluate
97
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
and document all welding inspection.
All non-destructive examination shall be performed according to a written procedure. The procedure
shall conform to the requirement of the adequate method standard and this specification. Procedures
shall be submitted to and agreed with the Engineer.
3.2 Pipework
All pipes must be approved by relevant Authorities for wastewater and water application.
3.2.1.2 Standards
EN 13476 - Plastics piping systems for non-pressure underground drainage and sewerage - Structured-
wall piping systems of unplasticized polyvinyl chloride (PVC-U), polypropylene (PP) and polyethylene
(PE).
98
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
wastewater.
GRP pipes and fittings covered by this specification will be classified according to their nominal
diameter (DN), nominal pressure (PN) and their nominal stiffness (SN), coupling type, service type and
installation type.
The nominal pressure (PN) shall be corresponding to the maximum working pressure of the piping at
steady state, including no fluid circulation, without regard to overpressures due to water hammer.
Maximum pressure must be ≤1.4 times nominal pressure (PN), so maximum pressure will be working
pressure plus water hammer overpressure.
The safety coefficient in the calculation of PN shall not be less than 4 for overhead or buried
installations. Higher safety coefficients may be defined for specific project conditions.
Additionally, prior to contracting, parameters of initial specific circumferential stiffness, initial flexural
strength, longitudinal tensile strength and circumferential tensile strength shall be agreed upon in
accordance with the manufacturer's standard parameters or in their implementation.
The piping to be supplied shall be of nominal diameter, nominal pressure and design as specified in the
detailed design documents. In the event of a contradiction between this specification and the detail
design report and drawings to put for bid, these shall prevail.
3.2.2.3 Materials
The materials (resin and fibre) used in the manufacture of GRP pipes shall be certified, by the
manufacturer in such a way that their use allows obtaining a final product that exceeds the certification
tests by an accredited laboratory.
The glass fibre to be used should be of type E, consisting essentially of silica, aluminium and calcium
oxides (calcium aluminosilicate glass) or silicon, aluminium and boron (alumino-borosilicate glass).
The resins to be used in the manufacture will be certified, presenting the respective certificates upon
pipe delivery.
In order to reinforce the laminate and make it more rigid, silicon sand aggregates or other materials may
be used. These aggregates must comply with the supply specification in order to be correctly recognized
and to avoid impurities with unspecified dust or colourants. The loads shall be located in a single core
layer of the tube, with the aggregate particles not exceeding 1 mm.
The use of additives in the resin (for viscosity control or others) should not prejudice the product
characteristics or prevent the visual inspection of the final product.
The use of accelerators, catalysts and inhibitors for the complete polymerization of structural member
components shall be in full compliance with the resin supplier's recommendations.
99
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
3.2.2.4 Constructive Prescriptions
Pipes:
The pipes will be manufactured according to “Automatic Helical Filament Winding” or “Automatic
Cross Filament Winding” processes with continuous glass filaments impregnated with polyester resin,
with or without inert fillers, and possible application of additives for specific resin properties.
The pipes will have their wall consisting of 3 layers, namely:
The inner liner shall be made of isophthalic thermostable resin (for non-aggressive fluids) without
aggregates and with glass and/or synthetic reinforcements. It is not allowed to manufacture liners
entirely with resin.
Structural layer shall be made of glass reinforcement and thermostable orthophthalic resin, possibly
with aggregates. The glass reinforcements will be either continuous or cut wire. The use of aggregates
is only permissible when jointly using cut glass fibre reinforcements.
The structural layer is the only layer that can include aggregates in its composition.
The outer layer shall be formed of a thermostable resin without aggregates or fillers with glass
reinforcements or synthetic filaments, capable of withstanding external aggression and the expected
aggressiveness of the external environment.
When there is a risk of corrosive fluids and/or high temperatures, or the risk of using chemical additive
mixtures, vinylester-type or equivalent high strength resins should be used in the inner layer as well as
the remaining layers. This resin should be studied as a function of fluid properties and design conditions.
The resin used in the structural layer must have a bending temperature of at least 70 ° C.
In the manufacture of pipes, the resin should be cured by supplying internal and external heat, and heat
derived from the exothermic reaction of the resin's own polymerization process will not be accepted as
the only means of cure.
The cure level of the resin shall be such that the amount of residual styrene in the laminate shall not
exceed 0,02% by weight as per the test as defined in ISO DIS 4901.
As a routine control of manufacture, Barcol hardness testing shall be performed in accordance with
ASTM D 2583; the minimum hardness value shall not be less than 35.
The inner and outer surfaces shall be free of irregularities that may affect the ability of piping
components to meet functionality requirements. The ends of the pipes should be perpendicular to their
longitudinal axis.
Fittings:
GRP fittings supplied by the manufacturer must be made by Chemical Rolling Certified personnel.
According to German Guide DVS 2220 and BS EN 13.121-3
The fitting diameter series shall be the same as the diameter series of the straight pipe length (s) to be
connected to the piping system.
The nominal pressure rating of the fitting shall not be less than the straight length (s) of the pipe to be
connected to the piping system.
For a given material, fitting of the same wall thickness and construction as a pipe of the same diameter
will have a stiffness equal to or greater than that of the pipe due to its own geometry.
Fittings shall be designed and manufactured in accordance with the appropriate sizing rules for the
purpose of achieving operation equal to or greater than the GRP pipe of the same pressure and stiffness
class. If the need is identified, the elements should be supported using anchored or recessed blocks.
100
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Connections:
Joints shall be classified as flexible or rigid as capable of withstanding axial or non-axial stresses.
Flexible joints include “bell and spigot” joints, with a leaktightness double-ring elastomer, and
mechanical joints with metal joints with rubber seals, suitable for use with plastic materials.
Rigid joints include flanged joints, butt joints (with resin welds, fleeces and fibre fabrics) and “bell and
spigot” joints with retaining ring pouches.
Marking:
All pipes and fittings shall be factory marked in a legibly way without cracking or other breakages with
the following data:
• Reference standard;
• Nominal diameter size (DN) and diameter series;
• Nominal pressure (PN);
• Nominal stiffness (SN);
• Manufacturer Identification;
• Date and code of manufacture;
• Angle and special parts (curves, leads or inserts);
• Nominal sizes DN1 and DN2 for reduction elements;
• Applicable flange standard (if any);
• Joint type and resistance to axial stress (if applicable);
• Standard Quality Mark (if exist). Reception Conditions
The allowable dimensional tolerances shall be in accordance with the values given above.
3.2.2.5 Tests
All pipes and fittings will have factory tests made to test pieces, according to previously agreed
methodology, with destructive tests that will include:
• Internal pressure tightness test (acc EN 1229 and/or EN 1796 standards);
• Proof of Nominal Stiffness and Circumferential Flexural Strength (acc EN 1228; any cracks and
tears acc EN 1796);
• Percentage of Glass and Resin of the product (acc EN 637);
• Circumferential tensile strength (acc EN 1394 method C);
• Long Longitudinal Tensile Strength (acc EN 1393 method A);
• Water Absorption Test (acc EN ISO 62);
Certificates of conformity to EN 10204: 2004, shall be issued at least until EN 10204 - 2.2.
3.2.2.6 Standards
The manufacture’s Quality must be certified to ISO 9000 or equivalent.
The materials will also comply with the following standards or equivalents:
• BS EN 14364 / EN 14364 plumbing systems in plastics for disposal and sanitation with or
without pressure.
• Glass fibre reinforced thermosetting plastics (GRP) made from unsaturated polyester resin (UP);
• ENV 1046 Piping and conduction system in plastic materials. Water conduction or sanitation
systems outside building structures. Best practices for overhead or buried installations;
• ISO 10467 Plumbing systems made of plastic for evacuation and sanitation with or without
pressure. Glass fibre reinforced thermosetting plastics (GRP) made from unsaturated polyester
resin (UP);
101
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
3.2.3.2 Pipes
Ductile cast iron pipes shall be thickness conform EN 598.
The pipes shall be standard length socket and spigot pipes or double-flanged pipes, as scheduled.
3.2.3.3 Fittings
Ductile cast iron fittings shall be in accordance with EN 598 and shall be manufactured with spigot,
socket or flanged ends as scheduled.
102
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
3.2.3.8 Shop Testing and Inspection
Each pipe and fitting shall be inspected and checked at the factory for external appearance, shape,
dimensions and mass. All pipes and fittings shall be sound and free from surface defects.
The following tests shall be carried out at the factory:
Hydrostatic Test
Each pipe shall be tested to the hydrostatic test-pressure specified in EN 598. The hydrostatic pressure
test shall be performed prior to coating or lining of the pipes.
3.2.3.9 Marking
Each pipe shall, at the least, be marked with its nominal size, thickness and length.
Each fitting shall, at the least, be marked with its nominal size. In addition, each bend shall be marked
with its bend angle.
The marks may be cast on, painted on or cold-stamped and they shall be applied in such a way that they
do not affect the mechanical quality of the pipework nor the water tightness of the joints.
103
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
comply with European standard:
• EN 12201: Plastics piping systems for water supply, and for drainage and sewerage under
pressure - Polyethylene (PE)
• High density polyethylene pipes for drainage and underground pressure sewage shall comply
with European standard:
• EN 13244: Plastics piping systems for buried and above-ground pressure systems for water for
general purposes, drainage and sewerage. Polyethylene (PE)
Pipes must be resistant against UV- radiation and frost.
For diameters of 110, 125, 160, 200, 250, 315mm, HDPE - PE 100 SDR17 tubes (σ = 8.0 MPa) shall
be used. The joining of HDPE pipes DN 110, and between them and fittings shall be by butt welding
For diameters of 32, 40 50, 63, 75 and 90 mm diameters, HDPE - PE 80 SDR 11 (σ = 6.3 MPa), shall
be used.
The HDPE DN 90 pipes jointing and between them and the fittings shall be with electrofusion fittings
It will be issued a CE certificate of conformity by the manufacturer which will have certification
accordingly with the EN ISO 9001 quality system or equivalent.
104
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
The PP-R pipes and fittings to be implemented must be covered by civil liability insurance of a
minimum of 10 years, in accordance with EEC Directives 85/374.
16 6 2.7 10.6
20 6 304 13.2
25 6 4.2 16.6
32 6 5.4 21.2
40 6 6.7 26.6
50 6 8.4 33.2
3.2.6.3 Marking
As an example, the manufacturer must mark on the tube the identification data between which:
• Manufacturer name.
• Diameter and thickness.
• DIN 8077/78.
• SKZ A 214.
• ATG 98/2061.
• Pressure class PN20 – 20 °C.
• NSF 61.
3.2.6.4 Installation
The installation of the pipes must comply with EN 806 - 1/ 2/ 3/ 4/ 5/ 6.
It is recommended for thermofusion connection to use a proper Polyfuser with a temperature in the
matrices of 260 °C produced in accordance with the DVS2207 standard. The pipes will be cut
perpendicular to its central line and will be cleaned before starting the thermofusion. The heating and
assembly times should be respected, depending on the diameter of the pipe, as indicated in the supplier's
technical catalogue. Small alignment corrections may only be made immediately after insertion of the
pipe into the fitting.
It is recommended for electrofusion to use a proper welder. The pipes will be cut perpendicular to its
central line and they'll be perfectly cleaned before electrofusion starts. The installation instructions
given in the supplier's technical catalogue must be followed.
105
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Never heat the tube with a free flame.
Protect the tube at low temperatures from violent blows or shocks in the transport phase. In building
sites the pipes should be stored in a clean and protected place. Do not mount damaged pipes.
Do not expose the pipes to direct UV rays. For outdoor installations follow the manufacturer's
recommendations. Follow the manufacturer's provisions with regard to linear thermal expansion and
fixing/support systems.
The installations shall be tested as required by European standard EN806-4.
3.2.7.2 Materials
Gas pipe shall be made in Galvanized steel (GI) or Polyvinyl chloride (PVC). GI is most commonly
used for gas pipe. GI pipes are certified as European Conformity Standards (CE).
GI pipes shall be installed inside biogas plant and buildings because they have high strength, good
impact resistance as well as resistance to chemical corrosion.
3.2.7.3 Standards
Standards for gas pipe shall follow the ISO and European norm (EN) standards as follows:
• BS EN 10255:2004: Manufacture standard for GI pipes
• ISO 17484-1:2014 Plastics piping systems — Multilayer pipe systems for indoor gas
installations with a maximum operating pressure up to and including 5 bar (500 kPa) — Part 1:
Specifications for systems
• ISO 17484-2:2009 Multilayer pipe systems for indoor gas installations — Part 2: Code of
practice
• ISO/TR 19480:2005 Polyethylene pipes and fittings for the supply of gaseous fuels or water —
Training and assessment of fusion operators
• ISO 23555-1:2022 Gas pressure safety and control devices for use in gas transmission,
distribution and installations for inlet pressures up to and including 10 MPa — Part 1: General
requirements
• ISO 23555-2:2022 Gas pressure safety and control devices for use in gas transmission,
distribution and installations for inlet pressures up to and including 10 MPa — Part 2: Gas
pressure regulator
• ISO/CD 23555-3 Gas pressure safety and control devices for use in gas transmission,
distribution and installations for inlet pressures up to and including 10 MPa — Part 3: Safety
shut-off devices
• ISO 4437-2: Plastics piping systems for the supply of gaseous fuels – Polyethylene – Part 2:
Pipes.
3.2.7.4 Classification
GI pipes are categorized into light, medium and heavy as follows:
• Light (Class A) - Marked in yellow color for identification.
• Medium (Class B) - Marked in blue color for identification.
106
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
3.3.2 Electricity
In the screen supply shall be include an electrical panel with all controllers, protection and sensors
which are necessary for the well-functioning of the equipment. It will also include the water level
measurement in order to activate the automatic cleaning and in alternative the adjustable timer.
The motor shall be asynchronous, three-phased, with rotor in short circuit, velocity 1 500 r.p.m.
The supply voltage shall be 3x400 V, 50 Hz. It shall be installed a torque limiter to protect the motor in
case of overload.
The protection shall IP 56, insulation class F, storm protection. Shall possess a fan attached directly to
the electrical motor shaft.
107
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
3.3.3 Trials
It will be issued a CE certificate of conformity by the manufacturer which will have certification
accordingly with the EN ISO 9001 quality system or equivalent.
It will be issued CE certificate of conformity with the EN 10204 standard, at least until EN 10204 or
equivalent.
3.4 Gates
The gates shall be rising spindle type sluice gates, consisting of frame, gate door, spindle, lifting set,
stem, sealing rubbers, anchor bolts, etc.
Frame shall be of stainless-steel and designed to withstand the required maximum hydraulic head. All
contact surfaces on the frame shall be machined to set stainless steel facing to be fixed to the frame with
flat head bolts or equivalent material. The stainless steel sheet shall conform to 1.4301 (EN 10088-3)
or equivalent. The wedge plate shall be made of stainless steel conforming to 1.4301 (EN 10088-3) or
equivalent and shall be tightly fastened with flat head bolts of equivalent material.
The door shall be of stainless steel according to 1.4301 (EN 10088-3), heavy duty and one-piece
construction with integrally cast horizontal and vertical ribs of sufficient cross. sectional area to
withstand the required maximum hydraulic head. The door shall be fitted with brass sheet conforming
to CuZn40 (EN 1652) or equivalent by flat head bolts of equivalent material and machined and scraped
to provide a good contact with the frame.
The Spindle shall be designed to withstand the thrust forces during the open and close operation of the
gates, and to withstand the specified hydraulic heads. The spindle shall be preferably of one piece
construction to facilitate the installation and maintenance, and shall be of stainless steel conforming to
1.4301 (EN 10088-3) or equivalent.
108
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
with a protection index non inferior to IP 65 and with total protection of the “display” panel
against UV rays.
• The flow indicator shall allow, at least, the instantaneous flow and accumulated flow readings;
• The transmitter shall have an analogic signal output of 0/4-20 mA;
• For the alarm signaling, it shall exist 2 contact inverters potential free;
It will be issued CE certificate of conformity by the manufacturer that will possess the certification
accordingly with the EN ISO 9001 quality systems or equivalent.
The ultrasonic flow meter will comply with the following specific standards or equivalents.
• IEC 60695-2-11 - Electrical material;
• IEC 60811 - Electrical material;
• IEC 60950 - Electrical material;
• IEC 61000-4-2/3/4/5 e IEC 61000-3-2/4 - Electrical material;
• IEC 61000-4-2, IEC 61000-4-3, IEC 61000-4-4, IEC 61000-4-5, IEC 61000-4-6, IEC 61000-4-
8, IEC 61000-
• 4-11e IEC 61000-4-12 - Electromagnetic compatibility;
• EN 50178 – Electronic equipment.
109
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
The solids discharge upstream or downstream directly into a reception box, as indicated in the Project
parts.
This vertical screen is operated by a strap or cable driven by one gearmotor.
The cleaning system shall be automatic, with the gravity closing debris removal tank and the strap in
polyester or cable in stainless steel.
110
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Underground warning tapes (UWT) shall be laid above the top of the pipe embedment material. UWT
shall be brown coloured polyethylene underground marker tapes with a printed warning message for
marking the underground buried sewer pipes.
• Material – Linear low density polyethylene.
• Warning text: “Caution: Sewer Pipe Below” in English language.
• Soil tolerance from pH 2.5 to pH 11.0 inclusive.
• Dimensions: 150mm x 0.05mm (or thicker).
111
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.2.2.4 EMC-Directive
All electrical devices and installations to be provided must comply with the Electromagnetic
Compatibility (EMC) Directive.
The technical instructions of ARENE - AUTORIDADE REGULADORA DE ENERGIA (Energy
Regulatory Authority) and EDM - ELECTRICIDADE DE MOZAMBIQUE (Electricity of
Mozambique) shall be considered. Special attention shall be paid to the connections to the public local
ESCOM distribution grid. Selection of material and devices as well as the dimensioning and
construction of the grid connections shall correspond to the instructions of the local power supply utility
as well as to relevant IEC/EN standards and instructions given by manufacturers. All relevant
installations shall be clarified in co- operation with the power utility; their written authorization shall
be obtained before devices are procured, delivered and before construction works starts.
If appropriate technical instructions of the power utilities are not available or not sufficient to reach the
specified requirements concerning quality, function, safety, reliability, compatibility and Employer’s
requirements, electrical equipment and installations shall comply with the Harmonized European
Standards (IEC/EN) and not least with DIN VDE (German Industrial Standard), if IEC/EN is not
appropriate or not sufficient. The devices must be marked accordingly.
Regulations and instructions of the relevant power utility for putting devices and plants in operation
shall be observed. If not specified differently, the Contractor is in general responsible for relevant
applications and permissions.
116
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.2.6 Protective Measures
Type of System shall be to IEC 60364-1 latest version (e.g. TN, TT or IT).
Selection of appropriate protection against shock currents shall be to IEC 60364-4-41 latest version. It
includes protection against direct and indirect contact. The protective device must automatically
disconnect the faulty part of the installation. At no point of the installation may there be a touch voltage
or an effective duration larger than permitted to IEC 60364-4-41.
117
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.2.11 Wiring
4.2.11.1 Minimum Cross-Section
The minimum cross-section for single-core and multi-core copper conductors inside control-panels is
1,5 mm².
Degree of protection
The minimum degree of protection shall apply:
• for contact elements and lamp sockets: IP 20
• for switches, push button and key-operated actuators and indicator lights: IP 65
• Red: Danger or Alarm; Warning of potential danger or a situation which requires immediate
action
• Yellow: Caution; Change or impending change of conditions
• Green: Safety; Indication of a safe situation or authorization to protect, clear way
• Blue: Specific meaning assigned according to the need in the case considered
• White: No specific meaning assigned
Control Transformer
IEC 60204 requires the use of a control transformer on machines or separate parts of the electrical
system with more than five electro-magnetic coils. It must be connected downstream of the main switch
to allow for its isolation, and preferably between two phase conductors. The incoming supply cables to
the primary terminals of the control transformer must be protected against short circuits. On the
secondary side, a short circuit protective device is required in the non-earthed conductor.
Preferred secondary voltages are 24V, 48V, 110V, 220V at 50 Hz. Before using low voltages, it must
be checked whether fault-free operation is possible.
The control transformer must be adequately rated to keep the voltage drop within permissible limits
even under adverse conditions.
In non-earthed control circuits an insulation monitor must be fitted to indicate earth faults and to initiate
disconnection. In earthed systems, the auxiliary circuits must be earthed on one side and one side of the
coils must be directly connected to the earthed conductor.
Earth faults must neither lead to unintentional starting of the machine, nor prevent it from stopping. In
order to avoid this risk, auxiliary circuits have to be earthed on one side and one side of the coils must
be connected directly to the earthed conductor.
In non-earthed control circuits, an insulation monitor must be fitted to indicate earth faults or initiate
disconnection.
119
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.3.2 Motor Protective Circuit Breakers
Inherently short-circuit-proof switches capable of coping with the highest prospective fault levels at the
point of installation without the need for back-up protection shall be selected. The setting devices shall
fully meet the requirements of the connected device.
4.3.4 Contactors
Contactors shall be selected whose entire range provides consistently reliable operation in the event of
voltage drops – consistency down to 80% of the nominal voltage should be aimed for - and whose
contact system will not assume an indeterminate position, either on closing or opening, in such
conditions. The contactors shall be 3 pole, 380V AC, 50Hz, and a control coil of 240V AC or 380V AC
for a 3 Phase, and 2 Pole for a single phase system.
In the course of selection and detail design of the electrical and mechanical system the Contactor shall
consider that it is probable that the voltage stability will - at least for some time - leave much to the
desired in many applications, as a result of long power lines, small local generators or under
dimensioned respectively overloaded transformer substations. Moreover, regular and long lasting power
failures and voltage fluctuations shall be considered.
120
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.3.7 Enclosures
In buildings with difficult environmental conditions, such as dust, drip water, splashed water, humidity
and unusual high or low temperatures totally insulated enclosures with transparent covers shall be
selected. Consider special conditions in chemical environment.
In all other rooms’ enclosures according to the following specifications shall be supplied:
Heavy-duty indoor enclosure, capable of withstanding the most severe conditions to be expected, such
as dust, drip water, splash water, constant humidity and low temperatures. The enclosure complies with
IEC/EN 60439. It is made either from steel sheet with anti-corrosion protection and polyester-epoxy
coating inside and out or alternatively it can be made for small enclosures of self-extinguishing halogen
free polycarbonate. Degree of protection is IP 54 or higher. The degree of protection against mechanical
impacts as per EN 50102 is IK10.
Installations inside the enclosure shall provide protection in accordance to IP 32 or higher. Protection
class 2. Wall fixing shall be made by adjustable wall fixing lugs. The enclosure is equipped with one
gland plate with gasket, mounted on the bottom side only. All cables lead into the enclosure through
metric cable glands only, exactly dimensioned for the connected cable. Degree of protection of all
glands is IP 55 or higher. Each gland contains one cable only. A reserve of at least four tight glands for
later installation shall be installed. The rigid door is reversible and opens 120°. The thickness of the
cover/ door allows the installation of indicating lights, push buttons, instruments, etc. Doors shall be
equipped with a lock.
Earthing is provided by welded studs in the enclosure and on the door. The enclosure shall be equipped
with one mounting plate made from galvanized steel or insulating material for free installation of
devices. All equipment to be installed inside the enclosure shall be mounted on mounting rails to EN
60715. The enclosure shall be directly fixed to the wall using fixing straps.
Cables and devices inside the enclosure, such as fuses and terminals shall be marked accordingly. Single
line diagrams shall correspond to this marking.
4.4.2 Supports
Wall mounted equipment, where shown on tile wall, or other walls inadequate to support the equipment,
shall be mounted on a mounting frame manufactured of angle iron or channel supports, which shall be
capable to support the equipment independent of the wall type. Outlet boxes shall be adapted to their
respective locations and fastened to a rigid support independent of conduit.
4.4.5.2 Nameplates
Nameplates in English language shall be provided for all pieces of electrical equipment including panel-
boards, motor control centres, terminal cabinets, disconnect switches, motor starters, contactors, push
button stations, junction boxes and pull boxes.
Nameplates shall be laminated rigid plastic on interior items and stainless steel in exterior items with ≥
5 mm high engraved letters. Nameplates shall be fastened to equipment in a conspicuous location.
Warning signs shall be provided on all removable equipment covers through which access may be
gained to live parts. Signs shall show electrical "lighting" symbol and the words "Danger - High
Voltage" in the specified languages; in white engraving on red background.
Buried cables and conduits shall be identified by cover plates with appropriate markings.
4.6.2.2 Screening
Screening reduces emitted interference (noise immunity of neighbouring systems and devices against
external influences). Cables laid between the frequency inverter and the motor must be screened, but
the screen must not be considered a replacement for the PE cable. Power cables shall be equipped in
principle with a PE-wire. The screen must be connected to earth (PES) at both ends with a large-area
connection. Do not connect the screen with pigtails. Interruptions in the screen, such as terminals,
contactors, chokes, etc., must have a low impedance and be bridged with a large contact area. To do
this, sever the screen near the module and establish a large-area contact with earth potential (PES, screen
terminal). Free, unscreened cables must not be longer than about 100 mm.
124
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.6.2.3 Filtering Measures
Radio interference filters and line filters shall be supplied and installed according to requirements and
acc. to instructions of manufacturer of the frequency inverter. The filters shall protect against conducted
high- frequency interference and shall reduce the frequency inverter’s high-frequency interference,
which is transmitted through or emitted from the mains cable, and which must be limited to a minimum
level (emitted interference).
Filters may produce leakage currents which, in the event of a fault (such as phase failure or load
unbalance), can be much larger than the rated values. To prevent dangerous voltages, the filters must
be earthed according to instructions of manufacturer. As the leakage currents are high-frequency
interference sources, the earthing connections and cables must have a low resistance and large contact
surfaces.
For leakage currents above 3,5 mA, one of the following must be fulfilled according to EN 60335:
• the protective conductor must have a cross-section greater than 10 mm2
• the protective conductor must be open-circuit monitored, or
• an additional conductor must be fitted
125
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.9 Earthing
4.9.1 General
Equipment requiring earthing by relevant Standards (IEC, IEE Electrical Code, EN, local Standards)
and regulations of Local Electricity Utility shall be earthed accordingly and included in the Work
regardless of whether it has been shown on drawings or called for in these Specifications.
Installations shall be made in accordance with Type of System being installed (e.g. TN-C-S). New
buildings and constructions shall be equipped with a foundation earthing. Galvanized flat or round iron
including suitable accessories in accordance with present-day installation standard shall be used for
installation in the foundation. In foundations the earthing iron shall be connected to the reinforcement
in a regular distance of at least 2 meters. Connection flags and local equipotential bonding bars shall be
provided wherever switchboards, sub-panels, enclosures, machines, motors or other installations
requiring grounding and/ or local equipotential bonding with electric installations are being installed.
PE-conductors shall be of green- yellow colour coding only and directly grounded.
In principle 10 mm round steel conductor with zinc coating = 50 µm mean value or 30x3,5 mm steel
tape with zinc coating = 70 µm mean value shall be supplied and installed.
The earth resistance shall not be higher than 10 Ohm. Great importance is attached to accurate execution
of works so that the installation permanently withstands the environmental stress and that reliable
protection and system function is guaranteed. All connections between parts of the earthing system must
be low resistive, with a maximal value of 0.2 Ohms. The total earth resistance and the low resistivity of
the connections must be measured and documented in the earthing protocol.
126
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Arrange earthing system in such a way that under normal operating conditions no injurious amount of
current will flow in any earthing conductor. Single phase loads shall be connected so that there is least
possible unbalance of three phase supply.
Earth lead-ins shall be corrosion protected. The protective coating shall be of bitumen or shrink sleeve.
The protection shall reach for a minimum of 0.3 m above and below the earth point.
Deep driven earth rods shall be made of hot-galvanized steel; they shall be joined together using spigot
and hole. Minimum earth rod length shall be 1500 mm; minimum rod diameter shall be 25 mm. Use
impact tips and driving heads for driving down into hard soils and with the cable clamp.
Connections of components/ conductors made of different materials such as steel or aluminium with
copper require additional measures against corrosion. Use bimetallic connectors or isolating clamps or
inlays made of double metal (copper-plated aluminium sheets or sleeves) according to requirements.
Intermediate lead layers are not permissible.
When bushings for water-proof and press-water-proof duct of walls are being installed, the connections
shall either be welded or clamp connections shall be protected by bitumen coating respectively bitumen
taping.
Principal external lighting protection Arrangement of down conductors in mesh interception net
128
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Installation dimensions
4.12 Testing
At completion of installation, tests shall be conducted under consideration of relevant Standards. All
tests in general shall include polarity, phasing, continuity, earth loop resistance, voltage tests and empty
conduit tests.
Megger lighting and power circuits and if resistance to earth is less than 5.0 mega ohm such circuit shall
be considered defective and shall be replaced.
4.14 Lighting
4.14.1 General
The lighting system shall be designed and installed to comply at least to the following criteria:
• Minimal illumination intensity must be adequate for the particular use of the area, as e.g.:
• 200 lx in large machine halls, storage rooms, etc.
• 300 lx in operation rooms
• 500 lx in control rooms, offices, etc.
• The luminous colour shall adequate for the particular use of the area. For standard working
applications 4000 K or higher shall be used.
Fittings housing, frame or canopy shall provide a suitable cover for the fixture opening. Fittings shall
be installed at mounting heights.
Fittings located on the exterior of the building shall be installed with non-ferrous metal screws finished
to match the fittings.
Fittings and/ or fitting outlet boxes shall be provided with hangers to adequately support the complete
weight of the fitting.
129
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Flush mounted recessed fittings shall be suitable for the type of false ceilings used, and shall be installed
so as to completely eliminate leakage within the fitting and between the fitting and adjacent finished
surface.
Pendant fittings within the same room or area shall be installed plumb and at a uniform height from the
finished floor. Adjustment of height shall be made during installation. Fittings shall bear the
manufacturer's name. Lighting fittings employing tungsten filament lamps and having metal back plates
shall not be fixed direct to boxes of thermo plastic material. Only metal boxes shall be used in such
situations. Heat resistant type lamp holders shall be used with flexible cords and enclosed type lighting
fittings regardless of the lamp cap position, i.e. cap-up or cap down.
Lamp holders incorporated in weatherproof fittings shall be porcelain or brass. Fittings installed
externally shall be weatherproof and insect proof in general and shall conform to the specific IP ratings
mentioned in the particular cases.
Fittings installed in damp locations shall be totally enclosed and shall prevent the ingress of moisture.
Fluorescent fittings shall contain all associated control gear within the fitting. All metal fittings or metal
parts of fittings shall be effectively earthed. Fittings installed in positions subject to vibration shall be
of the antivibration type.
Recessed fittings shall be constructed so as to fit into tile suspended false ceilings, tile fixed to ceilings
or other suspended false ceilings or plastered ceilings without distorting either the fitting or the ceiling
and including all necessary labour for cutting and making good.
Fittings with hinged diffuser doors shall be provided with spring clips or other retaining devices to
prevent the diffuser from moving and the diffuser shall remain hanging, during relamping and
maintenance.
4.14.4 Lamps
4.14.4.1 General
In general LV halogen lamps shall have individual or groups, step down transformers of dimmable or
non- dimmable and magnetic type as shown on the drawings. The step down transformers shall conform
to relevant IEC Standards and marked in protective enclosures. Lamps shall be furnished and installed
in all lighting fittings furnished under this contract. Lamps used for temporary lighting service shall not
be used in the final lamping of fittings.
130
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.14.4.2 Fluorescent Tubes
Lamps shall be of type, wattage and colour rendering index as herein specified unless otherwise
indicated on drawings. All fluorescent lighting luminaires shall be provided with capacitors to give P.F.
in excess of 0.9 lagging. Capacitors shall comply with relevant IEC Standards.
4.16.8 H07V-U (Ye), H07V-R (Ym) (PVC Insulated Single Core Wire)
According to DIN VDE 0281-3
Construction: Solid or stranded copper bar conductor. Core insulation made of PVC.
Application: For indoor fixed installations in dry locations in switchboards and distributors, installed in
surface mounted or embedded conduits or directly on suitable insulated objects. Temperature range for
fixed installation: -5°C till +70°C. Nominal voltage 450/ 750 V.
134
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.18.2 Raceways
Cable trays and ladders shall be of heavy duty galvanized steel or heavy duty GRC complete with
fittings, accessories and supports. They shall be of “lay-in” type. Trays will be manufactured with a
longitudinal T welded safety edge along the top edges. The tray shall be manufactured from steel wires,
welded together and bent into a final U-shape. Straight sections shall be provided in at least 3000 mm
length. The cable tray shall be electroplated with at least 12 microns of zinc. The cable tray internal
depth shall be 50 mm +/- 10 mm.
Trays made of steel wires shall be made with a minimum wire diameter of 4.5 mm for widths from 50
to 200 mm and 5 mm from 300 to 450 mm. Trays shall be constructed with a mesh configuration not
wider than 50 mm x 100 mm. All tray fittings (bends, risers, tees, crosses, reducers, etc.) shall be
constructed on- site using side action bolt croppers and fastened using 25 mm and 30 mm counter
clamps with bolts and nuts, all surfaces shall be treated as noted above.
Trays will be coupled together using either fast spring couplers or counter clamp with bolt and nut
combination with supporting fishplate if necessary, all surfaces shall be treated as noted above.
Trays shall be supported at 6-foot intervals by either trapeze, wall, floor or pendant mounting methods.
All welds will be manufactured to a tensile strength of 700 kg per weld.
Metal separator shall be installed on the trays between power and control/telecommunication cables.
4.18.3 Conduits
Conduits shall be rigid heavy wall type, of high impact PVC. Minimum internal diameter shall be 20
mm. Provide draw wires in all empty conduits.
4.18.6 Sockets
Nominal data: 16 A/ 250 V AC, IP55.
Socket types acc. to the national standards, or to DIN VDE (Schuko type). Single or twin type as shown
on drawings. Protection against electric shock to IEC 536: Finger and back-of-hand proof. Type of
protection: IP X1
CEE 16A, 32A or 64A/400V AC, 5 pins, IP44, colour red. Socket types acc. to the national standards,
or to DIN VDE (CEE type). Protection against electric shock to IEC 536: Finger and back-of-hand
proof. Type of protection: IP X1
13 A, 250 V AC twin socket (MK, T & J, or CrabTree Types) Socket types acc. to the national standards,
or to DIN VDE (CEE type). Protection against electric shock to IEC 536: Finger and back-of-hand
proof. Type of protection: IP X1
Cover plates for weatherproof outlets and devices shall be die cast aluminium with stainless steel
fastenings of equivalent non-corrosive materials, with spring-loaded covers where applicable.
4.18.8 Disconnects
Disconnect switches shall be kW-rated, quick-make, quick-break, with handle interlocked so that switch
door cannot be opened unless switch is in de-energized position. Switches shall be heavy duty, having
visible blade constructions and silver plated current carrying parts. Rating and number of poles shall
acc. to requirements. Provision shall be made for padlocking switch to "OFF" position. Where no rating
is shown, they shall be sized as per manufacturer's recommendations for the load of the circuit. All
enclosures shall be dust-tight and corrosion-resistant, rated for site conditions.
137
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Protective coating of frame and add- ■ Priming colour
on pieces ■ Powder coating
Colour RAL according to specifications; otherwise RAL 7035
Protection class I
Protection against direct contact Protection of all live parts against direct contact by insulation
Inside measurements According to requirements incl. 20% reserve space per panel
Mounting options for built-in devices 35 mm standard size fixing bar
Depot for drawings One depot per panel door for drawings DIN A 4
Four pieces per panel; only required for transport and installation
Eye-bolts at site
Separate cable ducts and routing of energy, control and extra low-
Cable and wire routing voltage cables
Panel lighting One fluorescent lamp per panel; controlled by door positioning
switch
138
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
■ Material: E-CU; size according to requirements
■ Shock hazard protection
■ Rated-short-time current (1s) up to 50 kA
■ Rated peak withstand current (1s) up to 150 kA
Bus bar ■ Rated-short-time current of distribution bus-bar (1s) up to 30 kA
■ 3 or 5-conductor system (TN-C-S-Type of System)
■ Bus bar shroud in accordance with VBG4
■ Protection against direct contact
■ Type-tested to IEC 60 439-1, EN 60 439-1
4.19.5 Meter
4.19.5.1 General
kWh-and kVArh-meters shall be supplied and installed according to the following specification, if not
specified differently by the responsible Local Electricity Utility.
141
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.19.8 Miniature Circuit Breaker
The miniature circuit breaker shall comply with the following minimum requirements:
• Characteristics: B or C acc. to requirements
• Standard: IEC/EN 60 898
• Protection against electric shock to IEC/EN 61140. Finger and back-of-hand proof
• Degree of protection (terminals): IP 20
• Switching capacity to IEC/EN 60 898: 10 kA
• Nominal voltage of single phase MCB: 230 V AC
• Nominal voltage of three phase MCB: 230/400 V AC
• Integral password protection for circuit configuration and relay value pre-sets
• Current flow display for circuit configuration testing
• Selection option from at least the following languages: English, German, French
• Integrated timing relays, including delay functions
• Integrated up- and down- counter relays
• Integrated timers
• Integrated analogue value comparators
• Separate or integrated LCD-display
• At least 16 auxiliary relays
• Integrated interface for network connection with other relays of same type
• Integrated interface for connection to a PC
• Degree of protection ≥IP 20
• Accuracy of timing relays +/- 1%
• Resolution in range “seconds”: 10 ms
• Resolution of analogue and digital signals: 0.1V
• Bit-resolution: 10
• Accuracy of actual value: +/- 2%
143
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.28 Lighting
4.28.1 Indoor Lighting
4.28.1.1 Twin-lamp moisture-proof diff. Luminary
For all indoor and outdoor applications without exposure to chemicals luminaries acc. to the following
specification shall be selected.
• Moisture-proof diffuser luminary
145
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
• Iluminant: LED tube, e.g. one or two tubes approx. 20 W/ 4,000 lm/ 6,000 K
• LED lamps must provide sufficient lumen for the particular application. The LED illuminant
must be replaceable by illuminants of the same connection type. LED fittings/lamps, with a non-
replaceable lamp, need a particular approval of the Consultant prior to installation.
• Optionally: fluorescent tube (e.g. 2 x 22 W or 1 x 22 W)
• Duo circuit
• Type of protection IP 65
• For T26, low-loss conventional ballast
• Housing made of unbreakable polycarbonate
• One-piece diffuser made of polycarbonate with internal prismatic structure
• Reflector made of galvanised sheet steel, painted in white
• Through-wiring using standard cable shall be possible
• 5-pole push-in terminal
• Installed on ceiling, wall or trunking. Can also be suspended on chain using chain suspension
brackets.
For applications involving exposure to chemicals as well as moisture luminaries acc. to the following
specification shall be selected.
• Moisture-proof diffuser luminaire LED tube, e.g. one or two tubes approx. 20 W/ 4,000 lm/
6,000 K, optionally fluorescent tube 2 x 22W or 1x22W
• Duo circuit
• For T26, low-loss conventional ballast
• Rugged diffuser in conjunction with stainless steel catches shall be used
• Type of protection IP 65
• Housing made of halogen-free glass-fibre reinforced polyester
• Non-ageing polyurethane foam seal
• Diffuser made of either PMMA or PC with internal prismatic structure
• Installed directly on ceiling or mounting track
• Can be installed on trunking
• Luminary consists of roll-formed reflector made of galvanised sheet steel, painted in white, can
be hinged
• Reflector made of white glass-fibre reinforced polyester
• 5-pole push-in terminal
• Heat stability with PM 650°C, with PC 850°C
147
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
4.28.2.4 LED Lamps
High efficiency floodlight LED elements, e.g. 200 W/ 20,000 lm/ 6,000 K
148
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
5.3.3 Communications
5.3.3.1 General
The Contractor shall supply install and commission all necessary communications equipment and
software to for data transmission between the facilities and the Central SCADA System, as specified in
the Particular Specifications.
152
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Sewer Network:
The construction of the sewer network will be phased and explained in the following Table 6.1 and 6.2.
The total length of the sewer network proposed for the right bank for 2030 amounts to about 22 km, of
which about 9 km are main collectors, about 13 km secondary sewers, 130 m Effluent Sewer. For the
left bank, the total length of the proposed sewer network is only for 2030 with about 2.3 km.
Table 6.1: Lengths of the Proposed Sewers per Phase – Right Bank
Right Bank
Conventional Sewer
DN (mm) Length (km)
150 0.61
200 10.69
250 0.35
300 1.18
350 1.24
400 0.05
Sub-total 14.14
Condominium Sewer
150 2.59
Sub-total 2.59
Source: HYDROPLAN
Table 6.2: Lengths of the Proposed Sewers per Phase – Left Bank
Left bank
Condominium Sewer
DN (mm) Length (km)
150 4.48
250 0.73
Sub-total 5.22
Total 21.95
153
Condominium Sewer
DN (mm) Length (km)
150 1.9
Construction of Tete WWTP and Sewerage200 0.63 - Specifications
Network: Volume
Sub Total 2.5
__________________________________________________________________________________
Total Right Bank 24.5
Left Bank
Condominium Sewer
DN (mm) Length (km)
150 2.9
200 2.3
Total Left Bank 5.2
Total 29.7
Source: HYDROPLAN
Pump stations
One pumping station is installed in the right bank area. The design of pumping stations was followed
the guidelines of Decree with a minimum diameter of 200 mm sewer pipe and a minimum slope of
0.3%.
6.5 Submittals
6.5.1 Inclusions
This includes submittal procedures for:
• Schedule of Values
• Construction Schedules
• Shop Drawings, Product Data, and Samples
• Operations and Maintenance Data
• Manufacturer's Certificates
• Construction Photographs
• Project Record Documents
• Design Mixes
• Video Tapes or DVD’s
• And all other submittals the owner deems necessary.
6.5.2 Procedures
A. Scheduling and Handling
1. Schedule submittals well in advance of the need for the material or equipment for construction. Allow
time to make delivery of material or equipment after submittal is approved.
2. Develop a submittal schedule that allows sufficient time for initial review, correction, resubmission
and final review of all submittals. The Owner Representative will review and return submittals to the
Contractor as expeditiously as possible but the amount of time required for review will vary
depending on the complexity and quantity of data submitted. In no case will a submittal schedule be
acceptable which allows less than 30 days for initial review by the Owner Representative. This time
for review shall in no way be justification for delays or additional compensation to the Contractor.
3. The Owner Representative’s review of submittals covers only general conformity to the Drawings,
Specifications and dimensions which affect the layout. The Contractor is responsible for quantity
determination. No quantities will be verified by the Owner Representative. The Contractor is
responsible for any errors, omissions or deviations from the Contract requirements; review of
submittals in no way relieves the Contractor from his obligation to furnish required items according
to the Drawings and Specifications.
4. Submit 3 copies of documents unless otherwise specified in the following paragraphs or in the
Specifications.
5. Revise and resubmit submittals as required. Identify all changes made since previous submittal.
6. The Contractor shall assume the risk for material or equipment which is fabricated or delivered prior
to approval. No material or equipment shall be incorporated into the Work or included in periodic
progress payments until approval has been obtained in the specified manner.
C. Contractor's Certification
1. Each submittal shall contain a statement or stamp signed and dated by the Contractor, certifying that
the items have been reviewed in detail and are correct and in accordance with Contract Documents,
except as noted by any requested variance.
B. Product Data:
1. Submit product data for review as required in Specification sections.
2. Contractor's Certification shall be placed on each data item submitted.
3. Mark each copy to identify applicable products, models, options to be used in this Project.
Supplement manufacturers' standard data to provide information unique to this Project, where
required by the Specifications.
4. For products specified only by reference standard, give manufacturers, trade name, model or
catalogue designation and applicable reference standard.
5. For products proposed as alternates to "approved" products provide all information required to
demonstrate the proposed products meet the level of quality and performance criteria of the
"approved product".
C. Samples
156
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
1. Submit samples for review as required by the Specifications.
2. Contractor's Certification shall be placed on each sample or a firmly attached sheet of paper.
3. Submit the number of samples specified in Specifications; one of which will be retained by the
Owner’s Representative.
4. Reviewed samples which may be used in the Work are identified in Specifications.
159
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
6.6.4.1 Power Distribution Switchboard
The power distribution switchboard shall comply with the following minimum requirements:
• Voltage: 230/ 400 VAC, 3 phases, 50Hz, TN-C-S earthing system
• Connection point for the incoming LV power cable from the transformer station or, if applicable,
from the PV system (the automatic switching over device is part of the PV system, providing
full-automatic switching under load between the supplier power supply from the transformer
station (public grid) and the PV system)
• Main circuit breaker: for short circuit and thermal overload protection, adjustable tripping
values, capacity as required
• Metering station: if required, including a suitable current transformer metering and display of:
kW, kWh, kVA, kVAh Display of currents I1/ I2/ I3
• Grid feeding monitoring relay
• Protection functions at least: over voltage, under voltage, over frequency, under frequency
• Display of: V (U1/U2/U3, U1-2/U2-3/U3-1), Hz
• LV busbar, 3 phases, 230/400V, 50Hz
• Overvoltage/Surge arresters, connected to the busbar
• Fuse disconnectors or circuit breakers in the feeders for the other switchboards. Fuse
disconnectors must be of A type, allowing a safe replacement of the fuse cartridges without
tools. The ratings of these switching devices must be selected in such a way that the protection
to the upstream equipment is acc. to IEC, and selective tripping of them related to the further
upstream switching devices is ensured.
• Waste Containers
• Air Blowers
• Grit Pump to Grit classifier
• Grit Pump and Pipework
• Sludge Drying bed inlet pipework
• Any pipework not included in any above item
• Borehole pumps
• Faecal Acceptance Station
• Gas motors
6.7.2 Pumps
Pumping stations for the Tete in the period of 2030 include 01 lifting pumping station (PS01) installed
in the right bank area . The lifting pump was selected as submersible pumps.
6.7.2.1.2 Products
Manufacturer:
As indicated provide non-clog pumps as manufactured by Flygt, ABS, GRUNDFOS or approved equal.
Each pump shall be furnished with a sufficient length of 13-2-1 hypalon jacketed type SPC cable to
extend from the pump to the junction box or control panel outside of the pump containment structure.
Each pump used in a submersible application shall be supplied with 316 stainless steel chain of adequate
strength, and length, to permit lifting and lowering the pump without wet well entry.
Pump Characteristics:
The pumps shall meet all of the design and performance requirements as outlined on the detailed
engineering design report or Bill of Quantities.
Pump Design:
The pump(s) shall be capable of handling raw unscreened sewage. The pump discharge piping shall
include either a connection elbow permanently installed in the wet well along with the discharge piping
or a threaded pipe connection on grinder units, 1.5 Hp and smaller. If a permanent elbow is used in a
submersible application, the pump(s) shall be automatically connected to the discharge connection
elbow when lowered in place, and shall be easily removed for inspection or service. Sealing of the
pumping unit to the discharge connection elbow shall be accomplished by a simple linear downward
motion of the pump. Using either type of connection system, there shall be no need for personnel to
enter the lift station wet well.
A sliding guide bracket shall be an integral part of the pump unit. The entire weight of the pumping unit
shall be guided by no less than two stainless steel guide bars or rails. When using a permanent elbow,
the pump shall be laterally supported by the guide bars (rails) and pressed tightly against the discharge
connection elbow, with metal-to-metal contact. All mating surfaces where watertight sealing is required
shall be machined and fitted with nitrile rubber Orings. Fitting shall be such that sealing is accomplished
by metal to metal contact between machined surfaces, resulting in controlled compression of nitrile
rubber O-rings without the requirement of a specific torque limit to affect this. No secondary sealing
compounds, rectangular gaskets, elliptical "O"-rings, grease or other devices shall be used. No portion
of the pump shall bear directly on the floor of the sump. The pump, with its appurtenances and cable,
shall be capable of continuous submergence underwater without loss of watertight integrity to a depth
of 60 feet. Submersible grinder pumps (where specified) may have the pump casing resting on the floor
via mounting legs and may use an O-ring sealing arrangement.
163
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Pump Construction:
Major pump components shall be of grey cast iron, Class 30, with smooth surfaces devoid of blow holes
and other irregularities. Where watertight sealing is required, O-rings made of nitrile rubber shall be
used. All exposed nuts and bolts shall be of stainless steel 316. All surfaces coming into contact with
sewage, other than stainless steel, shall be protected by an approved sewage resistant coating. Pump
exterior shall be sprayed with zinc primer and a high solids epoxy finish.
Cable Entry:
The cable entry seal design shall preclude specific torque requirements to insure a watertight and
submersible seal. The cable entry shall consist of dual cylindrical elastomer grommets, flanked by
washers, all having a close tolerance fit against the cable outside diameter and the entry inside diameter.
The grommets shall be compressed by the cable entry unit, thus providing a strain relief function. The
assembly shall provide ease of changing the cable when necessary using the same entry seal. The cable
entry junction chamber and motor shall be sealed from each other, which shall isolate the stator housing
from foreign material gaining access through the pump top. Epoxies, silicones, or other secondary
sealing systems shall not be considered acceptable.
Pump Motors:
Pump Motor 10 horsepower and below. Cooling characteristics suitable to permit continuous operation
in totally submerged, partially submerged, or non-submerged conditions without overheating. The
pump motor shall be a NEMA B design, induction type with a squirrel cage rotor, shell type design,
housed in an air filled, watertight chamber. The stator windings shall be insulated with moisture resistant
Class H insulation rated for 180°C (356°F). The stator shall be insulated by the trickle impregnation
method using Class H monomer-free polyester resin resulting in a winding fill factor of at least 95%.
The motor shall be inverter duty rated in accordance with NEMA MG1, Part 31. The stator shall be
heat-shrink fitted into the cast iron stator housing. The use of multiple step dip and bake-type stator
insulation process is not acceptable. The use of bolts, pins or other fastening devices requiring
penetration of the stator housing is not acceptable. The motor shall be designed for continuous duty
handling pumped media of 40°C (104°F) and capable of no less than 15 evenly spaced starts per hour.
The rotor bars and short circuit rings shall be made of cast aluminium. Thermal switches set to open at
125°C (260°F) shall be embedded in the stator end coils to monitor the temperature of each phase
winding. These thermal switches shall be used in conjunction with and supplemental to external motor
overload protection and shall be connected to the control panel. The junction chamber containing the
terminal board shall be hermetically sealed from the motor by an elastomer compression seal.
Connection between the cable conductors and stator leads shall be made with threaded compression
type binding posts permanently affixed to a terminal board. The motor and the pump shall be produced
by the same manufacturer.
The pump shaft shall rotate on two bearings. Motor bearings shall be permanently grease lubricated.
The upper bearing shall be a single deep groove ball bearing. The lower bearing shall be a two row
angular contact bearing to compensate for axial thrust and radial forces. Single row lower bearings are
not acceptable.
The combined service factor (combined effect of voltage, frequency and specific gravity) shall be a
minimum of 1.15. The motor shall have a voltage tolerance of plus or minus 10%. The motor shall be
designed for operation up to 40°C (104°F) ambient and with a temperature rise not to exceed 80°C. A
performance chart shall be provided showing curves for torque, current, power factor, input/output kW
and efficiency. This chart shall also include data on starting and no-load characteristics.
The power cable shall be sized according to the NEC and ICEA standards and shall be of sufficient
length to reach the junction box without the need of any splices. The outer jacket of the cable shall be
oil resistant chlorinated polyethylene rubber. The
164
motor and cable shall be capable of continuous
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
submergence underwater without loss of watertight integrity to a depth of 65 feet or greater. The motor
horsepower shall be adequate so that the pump is no overloading throughout the entire pump
performance curve from shut- off through run-out. Securely affix in a conspicuous place on each pump
and motor a standard stainless steel nameplate showing the serial number and name of the manufacturer.
Also, show the capacity in gallons per minute at rated rpm and head in feet, impeller diameter,
horsepower, speed and electric current characteristics. Nameplates with distributing agents only are not
acceptable.
Each pump shall be provided with a lubricant chamber for the shaft sealing system. The lubricant
chamber shall be designed to prevent overfilling and to provide lubricant expansion capacity. The drain
and inspection plug, with positive anti-leak seal shall be easily accessible from the outside. The seal
system shall not rely upon the pumped media for lubrication. The motor shall be able to operate dry
without damage while pumping under load. Seal lubricant shall be FDA Approved, nontoxic.
Impellers:
Non-clog: The impellers shall be of grey cast iron, Class 35B, dynamically balanced, semi-open, multi-
vane, back-swept, non-clog design. The impeller vane leading edges shall be mechanically self-cleaned
upon each rotation as they pass across a spiral groove located on the volute suction which shall keep
them clear of debris, maintaining an unobstructed leading edge. The impeller(s) vanes shall have screw-
shaped leading edges that are hardened to Rc 45 and shall be capable of handling solids, fibrous
materials, heavy sludge and other matter found in waste water. The screw shape of the impeller inlet
shall provide an inducing effect for the handling of sludge and rag-laden wastewater. Impellers shall be
locked to the shaft and held by an impeller bolt. The pump volute shall be a single piece grey cast iron,
ASTM A-48, Class 35B, non-concentric design with smooth passages of sufficient size to pass any
solids that may enter the impeller. Minimum inlet and discharge size shall be as specified. The volute
shall have a replaceable volute insert ring containing spiral shaped, sharp-edged groove(s). The spiral
groove(s) shall provide the relief path and sharp edge(s) across which each impeller vane leading edge
shall cross during rotation so to remain unobstructed. The internal volute bottom shall provide effective
sealing between the multi-vane semi-open impeller and the volute. The insert ring shall be cast of
(ASTM A-48 Class 35B cast iron or ASTM A 532 (Alloy lll A), 25% chrome cast iron) A wear ring
system shall be installed to provide efficient sealing between the volute and impeller. The wear ring
shall consist of a stationary ring made of nitrile rubber moulded with a steel ring insert which is drive
fitted to the volute inlet and a rotating stainless steel ANSI 304 ring which is drive-fitted to the impeller
165
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
eye.
Electrical Controls:
Are to be provided as part of the process control with all connections, wiring and circuitry. See
specification sections specific to electrical and controls.
Access Hatch:
Were indicated on the plans provide an aluminium access hatch complete with frame, hinged access
doors with 316 stainless steel safety latch lockable hasp of size or dimensions shown on the plans and
as required to install or remove submersible pump. The access hatch assembly shall include stainless
steel springs for easy opening. This access hatch is to have 316 stainless steel tamper resistant nuts,
bolts and stainless steel anchors affixed to the frame for embedment in concrete top covers.
Each hatch shall include an internal fall-through prevention aluminium safety grate, OSHA orange
finish, with a minimum design capacity of 300 p.s.f. All mounting hardware shall be 316 stainless steel.
The safety grate shall be independent of the access hatch, the safety grate shall be hinged to swing up
and out of the way, leaving a clear access area as required to install or remove the submersible pump.
The safety grate shall be removable for maintenance purposes.
Process Control:
Provide a control panel complete with all mounting hardware, wiring, conduit, and components as
shown on the drawings and/or indicated below. Related component and electrical specifications are
found in Division 16 and/or indicated below.
• Control Panel
Provide a NEMA 4x stainless steel free standing enclosure with a minimum 4 inch mounting legs on
panel or as indicated on the drawings. The panel shall be affixed to corrosion resistant vertical mounting
supports, and shall have a minimum 36 inch mounting height. All Motor Control Panels shall be made
with external transformers for lighting and appurtenances.
• Controls
Provide all required relays, circuit breakers, motor starters, phase and surge protection, alarm horn and
light for a complete and operating system.
Transformers shall be mounted independently in NEMA 4x stainless steel enclosure.
6.7.2.1.3 Execution
Service:
A factory representative, as an advisor, shall be provided during the initial installation work; for the
inspection and checkout of the erected equipment; and during instruction for initial operation. These
166
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
services are to be for two (2) periods not exceeding five (5) days each.
Furnish the Owner with a written report from a service engineer employed by the manufacturer denoting
start-points and calibrations. Obtain Owner’s Representative's approval of final setting. Arrange for
manufacturer to have service personnel on 24-hour call.
Warranty:
The manufacturer shall warrant the units being supplied to the Owner against defects in workmanship
and material for a period of two (2) year from the date of final project acceptance, under normal use,
operation and service. The warranty shall be in printed form and apply to all similar units. (Contractor's
responsibility shall end after the one year warranty period they are required to provide).
Each manufacturer shall review the systems design in all matters relative to the proper operation of their
equipment, including piping, electrical, automatic controls, locations, and related items. With their shop
drawings, the manufacturer must submit a letter to the Owner’s Representative stating that the design
is satisfactory to the manufacturer and that the equipment will operate satisfactorily under the design
conditions. Further, the manufacturer must review the final installation at site and write a second letter
stating that the installation is satisfactory to the manufacturer and that the equipment will operate
satisfactorily under the installed conditions.
Pump Test:
The pump manufacturer shall perform the following inspections and tests on each pump before
shipment form factory.
• Impeller, motor rating and electrical connections shall first be checked for compliance to the
customer's purchase order.
• A motor and cable insulation test for moisture content or insulation defects shall be made.
• Prior to submergence, the pump shall be run dry to establish correct rotation and mechanical
integrity.
• The pump shall be run for 30 minutes, submerged a minimum of six (6) feet under water.
• After operational test submerged, the motor and cable insulation test are to be performed again.
• A written report stating the foregoing steps have been done shall be supplied with each pump at
the time of shipment.
• The pump cable end will then be fitted with a shrink fit rubber boot to protect it from moisture
or water seepage prior to electrical installation.
6.7.2.1.4 Standards
The following standards will be used as reference for the quality of the submersible pumps to supply in
the contract:
• Directive 2006/42/CE
• ISO 12100:2010
• ISO 5199:2002
• DIN 24299
• ISO 7005-2
• EN 1092-2
• DIN2501:1997
• ISO 8501:2006
• ISO 12944:2007
167
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Table 6. 3: Technical specification for the submersible pumps of PS01 at the Right Bank
Technical specification description
Product name SL1.80.150.90.4.52H.S.N.61G.A
Product type Submersible wastewater pumps
Liquid Liquid temperature range (10 - 40 °C)
Technical
Actual calculated flow 33 l/s
Maximum flow 63.9 l/s
Head of the pump 11.34 m
Maximum head 19 m
Type of impeller S-TUBE
Maximum particle size 80 mm
Rated speed 1785 rpm
Materials
Pump housing Cast iron (EN 1561 EN-GJL-250)
Impeller Cast iron (EN 5.1301 EN-GJL-250)
Motor Cast iron (EN 5.1301 EN-GJL-250)
Electrical data
Power input - P1 10.3 kW
Rated power - P2 9 kW
Mains frequency 60 Hz
Rated voltage [V] 3 x 380-480/660-690 V
Voltage tolerance +10/-10%
Starting current 209/96 %
Motor efficiency at full load 88 %
Number of poles 4
Built-in motor protection KLIXON
Length of power cable 10 m
Cable type S1BN8-F
Cable size 7G4+5X1.5ST
Installation
Range of ambient temperature -20 - 40 °C
Maximum operating pressure 6 bar
Flange standard DIN
Type of inlet connection DIN
Type of outlet connection DIN
Size of inlet connection DN 150
Size of outlet connection DN 150
Pressure rating PN 10
Maximum installation depth 20 m
Inst dry/wet SUBMERGED
Auto-coupling 97695489
Frame range 52
Controls
Moisture sensor with moisture sensors
Water-in-oil sensor
168
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Performance
Eta pump 43.1 %
Eta pump+motor 37.6 %
6.7.2.2.2 Installation
Before installation, inspect the pump for damage which may have occurred during shipment. Check as
follows:
• Inspect the pump for cracks, dents, damaged threads, and other obvious damage.
• Check for and tighten loose attaching hardware. Since gaskets tend to shrink after drying, check
for loose hardware at mating surfaces
• Check levels and lubricate as necessary.
• If the pump and power source have been stored for more than 12 months, some of the
components or lubricants may have exceeded their maximum shelf life. These must be inspected
or replaced to ensure maximum pump service.
If the maximum shelf life has been exceeded, or if anything appears to be abnormal the equipment
should be rejected. It is recommended that 18 inches (457 mm) of clearance be provided in front of the
back cover to permit removal of the cover and easy access to the pump interior. A minimum clearance
of 9 inches (229 mm) must be maintained to permit removal of the cover.
169
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
6.7.2.2.4 Suction lines
To avoid air pockets which could affect pump priming, the suction line must be as short and direct as
possible. When operation involves a suction lift, the line must always slope upward to the pump from
the source of the liquid being pumped; if the line slopes down to the pump at any point along the suction
run, air pockets will be created.
Suction lines should be the same size as the pump inlet. If reducers are used in suction lines, they should
be the eccentric type, and should be installed with the flat part of the reducers uppermost to avoid
creating air pockets. Valves are not normally used in suction lines, but if a valve is used, install it with
the stem horizontal to avoid air pockets.
If a strainer is furnished with the pump, be certain to use it; any spherical solids which pass through a
strainer furnished with the pump will also pass through the pump itself.
If a strainer is not furnished with the pump, but is installed by the pump user, make certain that the total
area of the openings in the strainer is at least three or four times the cross section of the suction line,
and that the openings will not permit passage of solids larger than the solids handling capability of the
pump.
The pump should be designed to handle up to a minimum of 2 1/2-inch (63,5 mm) diameter spherical
solids.
Since even a slight leak will affect priming, head, and capacity, especially when operating with a high
suction lift, all connections in the suction line should be sealed with pipe dope to ensure an air tight
seal. Follow the sealant manufacturer's recommendations when selecting and applying the pipe dope.
The pipe dope should be compatible with the liquid being pumped.
If a single suction line is installed in a sump, it should be positioned away from the wall of the sump at
a distance equal to 1 1/2 times the diameter of the suction line.
If there is a liquid flow from an open pipe into the sump, the flow should be kept away from the suction
inlet because the inflow will carry air down into the sump, and air entering the suction line will reduce
pump efficiency.
If it is necessary to position inflow close to the suction inlet, install a baffle between the inflow and the
suction inlet at a distance 1 1/2 times the diameter of the suction pipe. The baffle will allow entrained
air to escape from the liquid before it is drawn into the suction inlet.
If two suction lines are installed in a single sump, the flow paths may interact, reducing the efficiency
of one or both pumps. To avoid this, position the suction inlets so that they are separated by a distance
equal to at least 3 times the diameter of the suction pipe.
The depth of submergence of the suction line is critical to efficient pump operation. The shows
recommended minimum submergence vs. velocity recommendation of the supplier shall be respected.
6.7.2.2.6 Alignment
The alignment of the pump and its power source is critical for trouble-free mechanical operation. In
either a flexible coupling or V-belt driven system, the driver and pump must be mounted so that their
shafts are aligned with and parallel to each other. It is imperative that alignment be checked after the
pump and piping are installed, and before operation.
When mounted at the factory, driver and pump are aligned before shipment. Misalignment will occur
in transit and handling. Pumps must be checked and realigned before operation. Before checking
alignment, tighten the foundation bolts. The pump casing feet and/or pedestal feet, and the driver
mounting bolts should also be tightly secured.
When using couplings, the axis of the power source must be aligned to the axis of the pump shaft in
both the horizontal and vertical planes. Most couplings require a specific gap or clearance between the
driving and the driven shafts. Refer to the coupling manufacturer's service literature.
Align spider insert type couplings by using callipers to measure the dimensions on the circumference
of the outer ends of the coupling hub every 90º.The coupling is in alignment when the hub ends are the
same distance apart at all points Check parallel adjustment by laying a straightedge across both coupling
rims at the top, bottom, and side. When the straightedge rests evenly on both halves of the coupling, the
coupling is in horizontal parallel alignment. If the coupling is misaligned, use a feeler gauge between
the coupling and the straightedge to measure the amount of misalignment.
When using drive belts, the power source and the pump must be parallel. Use a straightedge along the
sides of the pulleys to ensure that the pulleys are properly aligned. In drive systems using two or more
belts, make certain that the belts are a matched set; unmatched sets will cause accelerated belt wear.
172
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
• All I&C equipment shall be new, of proven design, reputed make, and shall be suitable for
continuous operation. Unless otherwise specified, all instruments shall be tropicalized. The
outdoor equipment shall be designed to withstand tropical rain and temperature variation from
0 to + 500 C. Wherever necessary, space heaters, dust and waterproof cabinets shall be provided.
Instruments offered shall be complete with all the necessary mounting accessories. The control
equipment installed inside the control room should be designed to work at 350 C and the
instruments in sheltered place outside the control room at 500 C.
• Electronic instruments shall utilize solid state electronic components, integrated circuits,
microprocessors, etc., and shall be of proven design.
• For transmitting instruments, output signal shall be 4-20 mA DC linear having two wire system.
• Unless otherwise stated, overall accuracy of all measurement systems shall be ±1% of measured
value, and repeatability shall be ±0.5%.
• After a power failure, when power supply resumes, the instruments and associated equipment
shall start working automatically.
• The instruments shall be designed to permit maximum interchangeability of parts and ease of
access during inspection and maintenance.
• Unless otherwise stated, field mounted electrical and electronic instruments shall be
weatherproof to IP-65.
• The instruments shall be designed to work at extremes of the ambient conditions of temperature,
humidity, and chlorine contamination that may prevail. The instruments shall be given enough
protection against corrosion.
• Lockable enclosure shall be provided for the field mounted instruments wherever required.
• All field instruments, and cabinets / panel-mounted instruments shall have tag plates / name
plates permanently attached to them.
• The performance of all instruments shall be unaffected for the ±10% variation in power supply
voltage and ±5% variation in frequency simultaneously.
• All wetted parts of sensors shall be made out of non-corrosive material capable of working with
chlorine content of ppm.
• For all instruments (transmitting analogue signals) installed in the field (outside pump house),
surge protection devices (SPDs) shall be provided at both ends of the connecting cable for the
protection against static discharges / lightning and electromagnetic interference.
• Pressure transmitters shall be provided with two valve manifold and a test port, so that in situ
calibration can be carried out.
• Two wire transmitters shall be provided with on-line test terminals.
• The ranges of all instruments shall be suitable for the application in the process.
• Instruments of similar type shall be of same make for appropriate inventory of spares, ease of
maintenance and training.
• The imported equipment shall have establishment to provide after sales maintenance facilities.
175
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
Lift Pump Station sites
The pump station shall be provided with the following complete with all required
accessories:
• Each site should be fitted with a radio linking it to the main control room SCADA
• Telemetry panel shall be free standing and equipped with a local panel view (HMI min. 10”) of
suitable size.
• PLC with power supply and input / output modules
• Temperature, Vibration (DE & NDE side) and pressure transmitters for all the pumps.
• Pressure transmitters shall be installed on the suction and discharge of each pump.
• Multifunction meter (MFM) for each pump station with logging and trending capability.
• All the enclosures installed outdoor shall be of weather protection rating.
• The mounting accessories shall be GI.
6.8.4.2 Antennas
Antennas shall be supplied complete with mounting clamps and supports. All mounting materials shall
be stainless steel.
179
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
6.8.5.2 Scope of Work
The scope shall include the works as below;
• Design, supply, and delivery to site of a high strength tapered self-supporting tubular steel truss
radio mast.
• Design of a suitable mast and reinforced concrete foundation based on soil test results carried
out by the contractor. The Contractor’s designs shall be subjected to review and approval by the
Engineer. The contractor shall involve an approved structural Engineer experienced in similar
works.
• Excavation, removal of soil, staged backfilling and compaction with appropriate backfill
material. These works will be subjected to compaction test as per the structural Engineer’s
instruction.
• Provision of civil works for the tower foundation including all necessary foundation bolts and
accessories for the tower.
• Installation of a comprehensive Earthing kit to the tower (Lightning Spike and Down Conductor
70 mm sq black PVC) including an earth mat.
• Erection of the tower on the prepared suitable foundation including all accessories required for
the tower as per design.
• Supply and installation of two (2) dual LED navigation lights including a controller with day
and bypass switches complete with power cables.
• Supply and installation of internal climbing steps and caged ladder. The tower shall have suitable
spaced rest platform along the caged ladder (minimum 4 along the tower)
• Painting of the towers as per the CAO regulation and standard tower colour coding (red and
white).
• Provision of rigid cable ladder link between the tower and building communication equipment
room for communication cable support.
• Installation of a galvanized cable tray alongside the length of the tower for securing radio
antenna cables
• Training client technicians on basic rigging (fall rescue course). The training shall be classroom
based + practical and conducted by an accredited trainer.
• Supply and delivery of two (2) specialized rigging kits complete with helmets, harness and carry
bag and accessories required by rigger.
6.8.6 Specification for control systems and instrumentation, design of control room
6.8.6.1 Design of control room
The design criteria for the control room should adhere to ISO 11064-5:2008 which presents principles
and gives requirements and recommendations for displays, controls, and their interaction, in the design
of control-centre hardware and software
A number of current standards provide engineering principles for detailed design of control room
elements. The following standards shall be used under this contract:
• Workstation design –ISO 11064-4, ISO 9241-5
• Display design –EEMUA 201
• Alarm system design –EEMUA 191
• ISO 11064-4:2004
• ISO 9241-5:1999 • ISO 9241-5:1999.
• ISO 11064-1 Ergonomic design of control centres
• ISO 11064-5: 2008, Requirements and recommendations for displays and controls, and their
interaction, in the design of control-centre hardware and software
• ISO 9241-3: 1992, Ergonomic requirements for office work with visual display terminals
180
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
181
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
▪ Screen/ Monitoring hardware Specification
Individual standalone screens shall have the following specification:
• Diagonal Size32"
• Type Edge LED BLU
• Resolution1920*1080 (Full HD)
• Pixel Pitch(mm)0.360(H) x0.360(V)
• Active Display Area(mm)698.4(H) x 392.85(V)
• Brightness (Typ.)400 nit
• Contrast Ratio5000:1
• Viewing Angle(H/V)178/178
• Response Time(G-to-G)8ms(Typ.)
• Display Colors16.7M(True Display) 1.07B(Ditherd 10bit)
• Color Gamut72%
• Operation Hour16/7
• Haze2%
▪ Video wall
The contract should provide a video wall in addition to the individual 32 inch sized screen, the video
wall should provide the following;
• An overview of the total system – The “Eagle Eye view”
• Operators have personal data and Interactive processes at their desk
• The Videowall shows the whole process
Specification for the videowall (Preferred brands are LG & Samsung latest models)
• Diagonal Size 46"
• Type D-LED DID
• Resolution1920*1080 (Full HD)
• Pixel Pitch(mm)0.53025mm(H) * 0.53025mm(V)
• Active Display Area(mm)1018.08mm * 572.67mm
• Brightness (Typ.)500 nit
• Contrast Ratio4000:1
• Viewing Angle(H/V)178/178
• Response Time(G-to-G)8ms
• Display Colors8 bit - 16.7M
• Color Gamut72%
• Operation Hour24/7
• Haze25% (Outer Haze 23%)
• Quantity shall be 2 (two) video walls
183
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________
184
Construction of Tete WWTP and Sewerage Network: Volume 3 - Specifications
__________________________________________________________________________________