NESMA AL AQABA

CITY COMPANY LTD.

Document Submittal Form


Document
Contractor:. NESMA & PARTNERS CO. LTD. 5K-4800000622-NAP-CIV-MST-000014
submittal no.

Contract no:. 4800000622 Date 22-June-2023

Project Name:. 5K CONSTRUCTION VILLAGE AT GOA NORTH

Rev
Document no. Type Description Action required
no.
Approval Comments
Method 5K – Method Statement for
5K-4800000622-NAP-CIV-MST-000014 02
Statement Painting Application Works Other
Information

************************

Contractor authorized signatory


Name Richard Nehme Date 22-June-2023

Signature

Comments Box.

Contractor May Proceed for Site Implementation

Reviewed by NAP QA/QC Rep.


Exception as noted revise
No exception taken Revise and resubmit
Status code and resubmit for record
Rejected Review not required Issued for Construction

Engineer’s name Nicomedes Falguisana Date 22-June-2023

Signature

Classification | Company General Use


NESMA AL AQABA CITY COMPANY L

Document Submittal Form


Contractor:. NESMA & PARTNERS CO. LTD. Document submittal
5K-4800000622-NAP-CIV-MST-000014
no.

Contract no:. 4800000622 Date 22-June-2023

Project Name:. 5K CONSTRUCTION VILLAGE AT GOA NORTH

Reviewed by Project Monitor


Name Date

Signature

Reviewed by DBFOM Co
Name Date

Signature

EPM (Optional)
Name Date

Signature

Neom (Optional)
Name Date

Signature

Classification | Company General Use


6/22/23, 11:24 Acon

4800000621 NESMA Document Control (CV Goa … Final (WF-000090) 5K-4800000621-NAP-CIV-MST-0000… 17/05/2023
NAD COMPANY LIMITED WORKFLOW TRANSMITTAL NAD-WTRAN-001386

Nesma Al Aqaba City Company


NAD Company Limited
Limited Po.Box 20799
Jeddah
JEDDAH
Jeddah
Saudi Arabia
Makkah 23212 Saudi Arabia

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal NAD-WTRAN-001386 NAD-WTRAN-001386

Final (WF-000090) 5K-4800000621-NAP-CIV-MST-000014- 5K - Method statement


for Painting Application Works

From Mr 4800000621 NESMA Document Control (CV Goa North - NAD Company Limited

To
(4) Mr Muhammad Arqam - Dorsch Group (+3 more...)

Cc Mr Waleed Helmy - Nesma & Partners (+2 more...)


(3)

Sent Wednesday, 17 May 2023 1:38:01 PM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

Revision
File Document No Revision Title Status
Date

5K-4800000621-NAP-CIV- 5K - Method statement for Painting Revise & Re-


01 02/01/2023
MST-000014 Application Works Submit

MESSAGE

Workflow Review History

The attached documents have completed the "5K-4800000621-NAP-CIV-MST-000014- 5K - Method statement for Painting Application Works"

workflow with the following results :

This transmittal was automatically generated.

Doc No Step Participant Review Outcome Comments

The Signatures page must


5K-4800000621-NAP-CIV- 4 Document Control Incorporate Comments -
NAD have Reference NO,
MST-000014 DC (CV Goa North Proceed
Project Name, etc

https://ksa1.aconex.com/hub/ 1
6/22/23, 11:24 Acon

Dorsch Discipline
M Arqam Verified
Engineer (DC on CC)

SAJ Discipline Engineer M Barajaa Verified

SAJ Consolidation Step M Barajaa Verified

The signatures page must

have reference page,


4 Document Control (CV
NAD DC 2nd Review Revise & Re-submit project name, etc. Pls
Goa North
submit with the correct
contract number

NOTES

https://ksa1.aconex.com/hub/ 2
Classification | Company General Use

5,000 Construction Village at GOA North


Method Statement for Painting Application Works

Revision Status

Comment
Revision Date By
METHOD Issued to Consultant

01 For Approval

STATEMENT FOR
02-Jan-2023

PAINTING APPLICATION WORKS

PROJECT NO. 4800000622

5,000 Construction Village at GoA


North
5,000 Construction Village at GOA North
Method Statement for Painting Application Works

DOCUMENT APPROVAL SHEET


PROJECT :5,000 Construction Village at GOA North
DOCUMENT Number :5K-4800000622-NAP-CIV-MST-000014
DOCUMENT Revision :01
CLIENT :NESMA AL AQABA CITY COMPANY LTD.

DOCUMENT TYPE: METHOD STATEMENT FOR PAINTING APLLICATION WORKS


S/N DESCRIPTION NAME DESIGNATION SIGN

Nazeerkhan
Site Engineer-Civil
1 Prepared by Ahamed Jalaludeen

2 Reviewed by Mouhamad Khoder Construction Manager

Nicomedes
3 Checked by QA/QC Manager
Falguisana

4 Approved by Richard Nehme Project Manager

5 Risk Assessment by Mohammed Jameel Site HSE Manager


Classification | Company General Use

5,000 Construction Village at GOA North


Method Statement for Painting Application Works

Name Designation CONTACT


Mobile e-mail
Nazeerkhan Site Engineer 053 018 3135 nazeerkhan.jalaludeen@nesmapartners.com
Ahamed Jalaludeen
050 477 0925 samer.zantout@nesmapartners.com
Samer Zantout Site Manager - Civil
053 358 9968 nicomedes.f@nesmapartners.com
Nicomedes Falguisana QA/QC Manager
055 897 7416 richard.nehme@nesmapartners.com
Richard Nehme Project Manager
055 428 5369 jameel.mohammad@nesmapartners.com
Mohammed Jameel Site HSE Manager
5,000 Construction Village at GOA North
Method Statement for Painting Application Works

INDEX

1. GENERAL

2. SCOPE/OBJECTIVE/PURPOSE

3. REFERENCES

4. DEFINITIONS AND INTERPRETATION

5. RESPONSIBILITIES

6. TOOLING AND EQUIPMENTS

7. PAINTING APPLICATION PROCEDURES

8. SAFETY PRECAUTIONS

9. ATTACHMENT

➢ Risk Assessment
5,000 Construction Village at GOA North
Method Statement for Painting Application

1. GENERAL

The method statement for PAINTING APPLICATION WORK in 5000 Construction village at GoA North
controlled by NESMA, according to the specifications as well as consultant’s/client instructions.

2. SCOPE

This method statement provides the guidance to be followed to be for all hand. Painting application
works activities within the project area, ensuring full compliance all relevant drawings and
International Codes related to Painting Application works.

3. REFERENCES

3.1 Approved Shop Drawings & IFC Drawing


3.2 5,000 Construction Village at GoA Project Quality Plan.
3.3 5,000 Construction Village at GoA Safety Plan.
3.4 Material Data Submittal.
3.5 PAINTING APPLICATION WORKS ITP.

4. DEFINITIONS AND INTERPRETATION

In this Method Statement (as hereinafter defined) the following words and expressions shall have
the meanings hereby assigned to them.

➢ The Client’ means NESMA AL AQABA CITY COMPANY LTD and its legal successors.

➢ The Consultant or the Engineer means the firm or company named by the Client to act as
‘Consultant’ for the design and supervision of construction, who is NESMA AL AQABA CITY
COMPANY LTD, including its representatives, successors and permitted assigns.

➢ The Contractor’ means NESMA has been nominated by the Client and the legal successors to
execute the work.

➢ The Subcontractor’ means any company who will execute a particular part of the work under
control and supervision of the Main Contractors.
5,000 Construction Village at GOA North
Method Statement for Painting Application

5. RESPONSIBILITIES

5.1 Project Manager:


NESMA Project Manager has the responsibility for ensuring that the works are performed and shall report
directly to the Contracts Manager. He will attend all weekly site meetings.
5.2 Construction Manager:
NESMA Construction Manager has the overall responsibility for ensuring that NESMA complies with all
the requirements of this Method Statement / Quality Control Procedure. Construction Manager will
nominate a Senior Site Engineer to supervise and coordinate all the activities of NESMA on site.
5.3 Site Engineers:
NESMA Site Engineers nominated by NESMA’s Construction Manager has the responsibility to supervise
and coordinate all the site activities of NESMA.

NESMA Site Engineers have the responsibility to ensure that the work is fully coordinated with other on a
day to day basis. NESMA Site Engineer have the responsibilities for organizing and supervising the
transportation of the materials to in co-ordination with the other departments to ensure that the hoists,
cranes and the platforms are efficiently allocated and utilized. NESMA Site Engineers will also ensure that
approved and agreed safety practices and procedures are fully implemented.

5.4 QA / QC Manager:

NESMA QA/QC Manager will check/Involve a strict internal quality control and inspection to ensure that
the work is executed fully in accordance with the requirements of the contract specifications and
drawings.

5.5 QC Inspector:
NESMA QC Inspector will be responsible for all the quality control procedures. QC Engineer has
responsibility for ensuring full compliance with the prescribed QC requirements including the submission
of inspection requests. NESMA QC Inspectors will operate inspection regime to ensure that the work is
executed fully in accordance with the requirements of the contract specifications and drawings prior to
inspection requests being submitted to the Consultant to minimize the need for re-inspections.
5.6 Safety Manager:
NESMA Safety Manager has the responsibility for ensuring that NESMA staff are complying with the
requirements of the approved safety plan and procedures, including carrying out routine safety audits and
toolbox meetings, submitting of the necessary equipment test certificates, routine checks of the
equipment’s and getting the approval before the commencement for using and participating to the
regular safety meetings.
5,000 Construction Village at GOA North
Method Statement for Painting Application

5.7 Surveyor:
NESMA Surveyor under the direction of the nominated Site Engineer has the responsibility to establish the
main reference and levels to check the same at regular intervals.
5.8 Supervisors / Foreman:
NESMA Supervisors have the direct overall responsibility for the supervision of their allocated area
including the direct supervision of the fixers and labors involved and the strict implementation of safety
rules and procedures.

6. TOOLING AND EQUIPMENTS

6.1 Hand tools (Different sizes of Brushes and Painting rollers)

6.2 Sand Papers, masking tape, Sealants and caulking tools.

6.3 Grinder and Electrical sanding machine.

6.4 Air compressors and Electrical airless paint sprayers.

6.5 Ladders and scaffolding.

6.6 Paddle mixture.

6.7 Ventilation fan with flexible round air duct.

7. PAINTING APPLICATION PROCEDURES

7.1 Notification to start activity.

7.1.1 Prior to start Painting application notification to be submit to Client/PMC as information.

7.2 Surface Preparation

7.2.1 Prior to starting paint application on Blockwork, Plastered Concrete surface & Gypsum board
surface. The substrate shall be carefully checked and the surface shall be clean, dry, smooth & free from
any oil, grease, protruding nail or sharp edges, correct plumpness, alignment and level within
acceptable tolerance.

7.2.2 Any honey combing, small cracks shall be repaired using approved material and
masonry joints shall be flushed. All adjacent area shall be covered by plastic and masking
tape.
5,000 Construction Village at GOA North
Method Statement for Painting Application

7.2.3 Expansion and contraction joint shall be clear and mark off prior to painting work. The
surface of concrete should be dry before painting applications.
7.2.4 All substrates to coated with painting application have any projections, mortar spatter or
uneven surfaces shall be leveled by grinding or scraping.
7.2.5 wood surfaces shall be cleaned of all dirt, dust, grease, oil and other foreign
materials. Any high resign areas subject to bleeding through the paint coating shall be
sealed with sealer/stain killer before painting.
7.2.6 Dry wall Gypsum board shall tape and floated and have one coat of texture paint shall
have applied with a stippling roller to give a fine sand finish prior to painting acrylic latex wall
paint.

7.3 PAINTING APPLICATION ON PREPARED SURFACE


7.3.1 All coats of paint shall be applied to dry prepared surfaces before any contamination can occur.

7.3.2Paints shall have mixed and thinned in strict accordance and as per manufacturers
recommendations. Weather conditions shall be considered application shall not be applied if it
foggy, wet and dusty.
7.3.3 Moisture contents of the surface within the limit recommended by paint
manufacturer prior to start application. Atmospheric relative humidity shall be less than 85%
during surface preparation for coating.
7.3.4 After application of primer, Surface preparation of succeeding coat. Succeeding coat may
be applied by brush, roller or spraying equipment’s. Keep all brushes, roller and spraying
equipment clean and free from contaminants.
7.3.5 Visually inspect each coat for defects and uniform appearance. All coats shall be inspected
prior for application of succeeding coats. Additional coats shall be applied until color and
textured to be match.
7.3.6 All coats shall be exact the same as per approved mock up sample provided by the
Painting subcontractor.
7.3.7 All painting shall be free from tears run, blister, thin patches ragged edges or peel effect.
7.3.8 All relevant painting work ensure the work is carried out in conformance with project
specification and approved ITP and submit for inspection on all stages of work.
5,000 Construction Village at GOA North
Method Statement for Painting Application

8. SAFETY PRECAUTIONS

8.1 All regulation and safety precaution which stated clearly in the approved hazard
identification plan will be mandatory required to achieve, implement and followed which
include approved project HSE plan.

8.2 All personnel involved will use appropriate PPE as required such as safety helmet, glasses, coverall

shoes, gloves, ear plugs etc. Rubber gloves, white disposable coverall & gumboots to be
provided for those handling worker & workers involved in concrete activity.

8.3 The workers will have made aware of the safety requirements related to this activity through
daily STA meeting.

8.4 All required work permits will be acquired and kept available at respective work site
hanged clearly in plastic folders.

8.5 NESMA will inspect all equipment prior to use.

8.6 Safety will be as per approved project HSE plan requirements.

8.7 Supervisory personnel or other qualified staff must always be present at the work site while
any work is in progress.

8.8 All accident, incident, first aid cases and near misses shall be reported immediately to
NESMA HSE management.

8.10 All barriers will be inspected daily by task supervisor to ensure they are in good state of
repair. The supervisor shall repair all defects immediately.

8.11 NESMA shall maintain the approved project HSE plan at the worksite.

9. Attachments

➢ 9.1 – Risk Assessment


Classification | Company General

RISK

RA # RA-NEOM-5KCV-009 PROJECT 5K Construction Village


TASK Plastering Works
DATE 02 January 2023 ☒ New □ Revised Revision Date

☒ Cold Work □ Hot Work □ Excavation □ Confined Space □ Work at Height


1.0 Permit(s) Required:
□ LOTO Permit □ Night Work □ Radiography □ Lifting Permit □ Road Closure Permit
☒ Hard Hat ☒ Fluorescent Reflective Vest □ Rain Suit □ Cut resistant gloves
☒ Clear Safety Glasses ☒ Dust Mask □ Disposable Coverall □ Leather Gloves
☒ Dark Safety Glasses □ Cartridge Respirator Mask □ Fire resistant coverall ☒ Rubber Gloves
2.0 PPE Required: ☒ Coverall □ Air supplied respirator □ Chemical Goggles □ Nitrile gloves
☒ Cotton Gloves □ SCBA □ Cutting Goggles □ Elect Insulated gloves
☒ Safety Shoes □ Ear Plugs □ Face Shield □ Welding Aprons
□ Dielectric footwear □ Earmuffs □ Welding Hood □ Welding Leggings
Special Tools and □ Gas Badge □ Anemometer □ Lifeline □ Fire Extinguisher
3.0 Equipment □ Dosimeter □ Lux Meter □ Retrieval Line □ Ventilation Fans
Required: □ Multi-Gas Monitor ☒ Noise Meter □ Full body Harness □ Lighting
Foreman / Supervisors to secure work permit before commencing activity and conduct brief safety talk
(E.g. toolbox meeting, topics shall include heat stress awareness).
Additional Wear mandatory PPE’s (hard hats, safety glass, coverall, safety shoes, visibility vest)
4.0
Instructions Ensure availability of sufficient hydration and rest shade area.
Maintain adequate supervision.
Dangerous occurrence, near miss and other’s related incident shall be reported accordingly.

Page 1| NP/NEOM/OSH/PRO/05/
Classification | Company General

RISK

Basic Risk Calculation


Fire Risk Rating = Likelihood (L) X Severity (S)

5 5 10 15 20 25

4 4 8 12 16 20
Severi

3 3 6 9 12 15

2 2 4 6 8 10

1 1 2 3 4 5

1 2 3 4 5

Likelihood

R Unacceptable risk, Plan out or add additional controls

O Acceptable only if no other method viable and with high level control in place

Y Acceptable with suitable control measures

G Acceptable, no further action required

Page 2| NP/NEOM/OSH/PRO/05/
Classification | Company General

RISK
Calculation of Risk
A method is shown below for calculating the Risk, given the estimate Likelihood of occurrence (L), Severity (S).
Risk Factor (RF) = Likelihood (L) X Severity (S)
Where:
a - L = Likelihood of fire occurrence i.e. probability of the event occurring because of the risk is measured on the likelihood of happening. (1, 2, 3, 4,
5) b - S = The Severity (Outcome) are ranked on a scale from catastrophe to minor interruption. (1, 2, 3, 4, 5)
Residual Risk RR = is the amount of risk associated with an activity remaining after risks have been reduced by control measures.

Page 3| NP/NEOM/OSH/PRO/05/
Classification | Company General

RISK
Risk Residual Risk Responsible
SN Activity Hazard Hazard effect Control Measures
L S RF L S RF Party
1 Secure night Working Failure on implementing Secure necessary permit from authorized permit
work permit without valid the control measure issuer.
work permit indicated on the work Comply the requirement listed in the permit prior Supervisor/
permit 3 3 9 1 3 3
to start of any work. Foreman
Plan the work as far as practicable to limit the need
for night working

2 Pre-task briefing Lack of Miscommunication and Communicate with all workers of all the condition
and inspection knowledge to lack of knowledge of work permit.
the activity and regarding the hazard on Supervisor/
3 3 9 Conduct Pre-task safety instructions prior to start 1 3 3
poor the activity Foreman
of any work, ensure that everyone understand its
communication task.

3 Mobilization of Driving without Road traffic accident, All drivers must have a valid SAG license before
materials, license, reckless sticking personnel, fix driving any vehicle.
intended driving, using un facilities and others Drivers and passengers shall wear seatbelts while
plastering works inspected vehicles travelling
vehicle
Drivers shall obey the traffic flow and traffic
signages Equipment In-
Vehicles must be inspected by the driver on daily charge/ Site
3 4 12 1 4 4
basis, in good condition, and checklist maintained. Supervisor/
Do not use vehicle that fails in daily inspection Foreman

Preventive maintenance must be conducted on


regular basis, and the records shall be maintained.
The driver must not use any kind of distraction
while driving (Mobile phone, Headset, Eating,
Drinking, etc.).

Page 4| NP/NEOM/OSH/PRO/05/
Classification | Company General

RISK
Risk Residual Risk Responsible
SN Activity Hazard Hazard effect Control Measures
L S RF L S RF Party
Movement of Striking of Personnel, All drivers and operators to follow the site rules and
personnel on Vehicle or Equipment by must attend Defensive driver, MEPI, Safe dump
nearby Movement of machinery truck training.
equipment and All plant and equipment must be inspected by
vehicles on the Nesma assigned equipment inspector and
working area provided with an inspection sticker.
No objects in the cabs blocking driver’s views.
All plant and equipment to have reverse alarms and
flashing amber lights, mirrors and windows clear.
MEPI trained supervision to be in place.
Drivers and operators must stay in cabs unless
parked in a safe area where there is no MEPI Construction
related danger. Manager/ H&S
Daily pre-use inspections shall be carried out by Personnel/ Site
3 5 15 1 3 3
the operator and recorded on a daily inspection Engineer/
checklist. Supervisor/
Foreman
Persons are prohibited in the area when plant &
equipment is moving. Watchman shall assign to
ensure that personnel shall be at least 3 meters
away from moving vehicle, equipment.
A nominated MEPI trained flagman /Ticket
collector wearing full PPE will stay and be protected
in a safe zone by hard barriers to avoid any contact
with the moving equipment.
Adequate lighting will be provided.
Exclusion zones demarking the work area will have
barricades MEPI bilingual /pictorial warning signs
and hazard warning lights in place.

Page 5| NP/NEOM/OSH/PRO/05/
Classification | Company General

RISK
Risk Residual Risk Responsible
SN Activity Hazard Hazard effect Control Measures
L S RF L S RF Party
Personal/Private vehicle shall not be allowed to
enter on working area to minimize the number
vehicle unless it was used to deliver small
materials. Assigned parking for light and heavy
vehicle shall properly stablished at site.

4 Commencing Heavy and Body/Back Pain, Physical All worker involved to the activity shall undergo
Plastering works awkward size of Injury “Manual Lifting and Material Handling Training”
materials and other related training.
(Cement) Avoid extreme range of motion and twisting their
body when lifting.
Minimize reach and distance the load is carried. Supervisor/
3 2 6 1 2 2
Foreman
Avoid lifting loads above shoulder height.
Keep objects as close to the body as possible.
Keep assistance when performing manual material
handling tasks that may be beyond one’s physical
capabilities.

Cement dust, Inhalation of dust particles Employees shall be informed of the health risks
and dust associated with airborne dust and the control
emission on the measures in place to protect them thru toolbox
area meeting or proper training
Damp the area where the manual breaking takes
place to minimized the dust emission
Supervisor/
3 4 12 The number of workers exposed to dust and the 1 3 3
Foreman
length of their exposure are kept as low as
possible and rotate those involved in the task and
provide short and frequent breaks.
RPE (Respiratory Protective Equipment) shall be
worn, and employees are trained in its correct
fitting and use. Wear RPE where dust levels cannot

Page 6| NP/NEOM/OSH/PRO/05/
Classification | Company General

RISK
Risk Residual Risk Responsible
SN Activity Hazard Hazard effect Control Measures
L S RF L S RF Party
be lowered but make sure it fits properly and is the
right type: a N95 disposable mask and CE marked.

Skin and eye Skin and eye irritation, Rubber gloves and clear safety glass shall be worn
contact of grout allergic reaction, burn by workers.
mixture Disposable coverall (Tyvek Suit) shall be use by
workers involved to grouting works
Any burn / injury shall be treated by the nurse Supervisor/
4 3 12 1 3 3
provided full time at site. Foreman
MSDS shall be available at site and in the clinic to
be used in case of emergency.
Eyewash shall be available at site to be used in case
of emergency.

Excessive noise Noise-induced hearing loss, Conduct noise monitoring


from mixer noise stress Signages related to noise shall be posted on the site Supervisor/
3 3 9 1 3 3
Earing protection shall be use on are where the Foreman
noise level reached above 85 dB

Damage/ Use of Hand Injury All hand tools should be inspected daily prior to
improper hand start work and damaged hand tools shall be Supervisor/
3 3 9 1 3 3
tools replaced or repaired by concerned technicians Foreman
immediately.

Health Hazard Cold Stress, hypothermia Thermal clothes or warm jacket shall be used on
(Exposure to frostbite/trench food and areas with low/cold temperature. Engineer/
excessive cold other long-term health 3 4 12 1 3 3 Supervisor/
Proper supervisor shall be provided to the activity Foreman
temperature) effects.

Protruding Punctured by protruding All used protruding rebars shall be covered by rebar Supervisor/
3 3 9 1 3 3
rebars rebars caps. Foreman

Page 7| NP/NEOM/OSH/PRO/05/
Classification | Company General

RISK
Risk Residual Risk Responsible
SN Activity Hazard Hazard effect Control Measures
L S RF L S RF Party
Chemical spills Soil contamination Ensure that all equipment is inspected and free
(oil, diesel,) to from leaks and in good condition prior starting
ground from work.
equipment/ Remove any equipment leaking or showing any
vehicle, damage in the hoses, pipes or tanks (oil, diesel)
Grout spill to immediately from site.
the ground Provide proper cover to the ground to avoid Supervisor/
3 3 9 2 2 4
contamination of soil from grout spillage Foreman
Spill kit available and used by trained personnel
when spills are identified.
All contaminated material found among the
excavated soil shall be removed, assessed and
stored as Hazardous waste or non-hazardous
waste in the designated areas for disposal.

Emissions of Air pollution, contribute to Ensure that all equipment are inspected not
black smoke climate change emitting any black smoke and in good condition
from prior starting work. Supervisor/
equipment/ 3 3 9 2 2 4
Any plant/equipment emitting black smoke shall Foreman
vehicle involved be stopped and checked/repaired before continue
to the activity to use or removed from site if not repairable.

Working for Mental and body Night shifts


long period of exhaustion, fatigue and At least 2 days off shall be given to worker before
time, irregular stress night shift works. Project
shifts Manager/
3 3 9 Avoid keeping workers on permanent night shifts. 1 3 3
(day/night), Construction
poor social Rest periods Manager
consideration
Allow minimum of 12 hours between shifts and
avoid ‘quick return’ of 8 hours if possible. (Rest

Page 8| NP/NEOM/OSH/PRO/05/
Classification | Company General

RISK
Risk Residual Risk Responsible
SN Activity Hazard Hazard effect Control Measures
L S RF L S RF Party
period between shifts should permit sufficient time
for commuting, meals and sleep.)
Plan some weekends off, advisably at least every 3
weeks.
Social considerations
Consider travelling time of workforce.
Provision of recreational facilities on camps for
workers and employees

5 Housekeeping Scattered Slips, trips and fall Ensure proper access such as ladder for up & down
materials to truck.
Proper housekeeping should be kept. Supervisor/
3 3 9 1 3 3
Access free from obstructions. Foreman
Access marked properly and all areas barricaded.
Proper material arrangement shall be maintained

Prepared By Reviewed By Approved By


Name Ahmed Alhabili Mohammed Jameel Richard Nehme
Position Safety Supervisor Site HSE Manager Project Manager
Date 02 January 2023 02 January 2023 02 January 2023
Signature

Page 9| NP/NEOM/OSH/PRO/05/