DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS SITE PREPARATION

Qty Unit Rate CI c

SITE PREPARATION
NOTE: All Quantities in this Section are
Provisional
Preliminary site work

Location of underground services; The contractor


should refer to the site works section of this BQ in
conjunction with the Civil Engineering drawings
a when pricing this item ITEM 0.00 0.00

Excavating alongside existing underground


services; The contractor should examine the Site
Works Section of this BQ and the Civil Engineers
drawings to ascertain the location of existing
services and allow here for excavating along side or
b over these ITEM 0.00 0.00
Site filling
Local rock to raise levels to average +9.5' msl - rate
includes supply, delivery, water & compaction
c Cayman rock (to be completed by others) 0 CF 0.00 0.00
Imported 6" thick crusher run layer compacted to
95% of max dry density
compacted to 95% AASHTO T-180 density, below
d roads 3615 CF 0.00 0.00
e below pavements 71 CF 0.00 0.00
f below hardscape 8565 CF 0.00 0.00

Page 1
To Summary CI 0.00

Page 2
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS CONCRETE PATHS

Qty Unit Rate CI c

CONCRETE PATHS
a Pavements/Sidewalks

3000 PSI reinforced in-situ concrete filled into


formwork and packed and vibrated around
reinforement
Slab on grade, 4 1/2" thick including edge
b thickenings, laid to falls and cross falls and floated 53 CF 0.00 0.00

Damp proof membrance, 6 mil polyethylene moisture


barrier with 6" end and side laps dresses against
crushed stone, footings, edge slabs and the like
c Below concrete pavements 141 SF 0.00 0.00
Formwork

Formwork and supports including 1/4" chamfer to


exposed corners, release agent and making good
exposed faces of concrete after removal to
d Edges of slabs not exceeding 12" thick 87 LF 0.00 0.00
Reinforcement
Fabric
10 x 10 GA, 6"x 6" WW road mesh, including all
e end and side laps 141 SF 0.00 0.00

High yield steel deformed bar reinforcement; rates to


include laps, bends, hooks,tying wire and spacers as
general reinforcement
f #4 bars 9 LBS 0.00 0.00
Joints
Provide3/16" x 1 -1/4" min. tooled control joints at
g 10'-0" o/c max 40 LF 0.00 0.00
Worked finishes
h Broom finish ito in situ concrete 141 SF 0.00 0.00

Page 3
To Summary CI 0.00

Page 4
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS ROADS

Qty Unit Rate CI c

ROADS
Coated macadam and asphalt
Asphaltic pavement per NRA requirements
2" min. compacted thickness, over compacted lime
a rock (measured separately) 7229 SF 0.00 0.00
Line markings
b Allow for disabled marking 1 NR 0.00 0.00
c Directional arrows 5 NR 0.00 0.00
d Disabled hatching 123 SF 0.00 0.00
Curbs

4000 PSI cast in place straight and curved concrete


curbs as per dimensioned diagram detail 5 of drawing
e C500 698 LF 0.00 0.00
Accessories
Wheel stops

5" x 5" x 6'-0" long hardwood parking blocks


secured in parking space by 3 #2 rebar 6'-0" wide
wheel stops fixed to grasscrete surfaces see
f dimensioned detail 13 of drawing L-1 13 NR 0.00 0.00

Page 5
To Summary CI 0.00

Page 6
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS RETAINING WALLS

Qty Unit Rate CI c

RETAINING WALLS
Note: Seawall and retaining boundary walls and
stairs have already been installed without finishes
Seawall finishes

Allow for elastomeric acrylic finish (EIFS) and base


coat primer as per manufacturer's instructions, to the
a inside face of wall approximately 2' high 985 SF 0.00 0.00
Retaining boundary wall finishes

Allow for elastomeric acrylic finish (EIFS) and 1/2"


sand cement render to the inside face of wall
b approximately 2' high 611 SF 0.00 0.00

Page 7
To Summary CI 0.00

Page 8
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS DRAINAGE BELOW GROUND

Qty Unit Rate CI c

DRAINAGE BELOW GROUND


NOTE: REFER TO DRAWINGS C501 AND P1-00
Storm water drain systems

Catch basins and sanitary deep well, including all


excavation and earthworks, complete with NEENAH
R-3339-A heavy duty cast iron inlet frame and grate
and 8" dia. min. bore hole, cement slurry, 4"" PVC
well casing, bentonite seal, 4"" PVC coupling, well
drilled 80 feet min. below ground level and cased with
PVC pipe to 70 feet min. below ground level
(assumed)
a CB SAN - 4'-4" x 4'-4" x 24"min deep 1 NR 0.00 0.00

Catch basins and deep well, including all excavation


and earthworks, complete with USF 5105/6148 frame
and grate and 8"" dia. well drilled 100 feet below
ground level and cased with PVC pipe to 30 feet
below ground level as per dimensioned diagram detail
1A of drawing C/501
b CB1 - 4'-4" x 4'-4" x 24"min deep 4 NR 0.00 0.00

Ditto; but with NEENAH R-3339-A heavy duty cast


iron inlet frame and grate as per dimensioned diagram
detail 1B of drawing C/501, "
c CB2 - 4'-4" x 4'-4" x 24"min deep 3 NR 0.00 0.00

"Deep well including 4"" PVC cap, 2"" grout ring, 8""
dia min. bore hole, cement slurry, 4"" PVC well
casing, bentonite seal, 4"" PVC coupling as per
dimensioned diagram detail 2 of drawing C/501"
d Sanitary deep well 4 NR 0.00 0.00

Allow for drain runs including pipework, fittings,


connections, all excavation and earthworks, bedding
materials and backfill as specified
3" dia PVC storm water collector from downspouts
e in trenches 499 LF 0.00 0.00
f 4" dia PVC storm water pipe in trenches 186 LF 0.00 0.00

Rain collection clean-out, 6" PVC cleanout with


removable screw cap connected to 6" dia gutter
works PVC pipe adapter or similar approved
g Rain collection clean-out 21 NR 0.00 0.00
Testing and commissioning
h Test and commission the full service installation ITEM 0.00 0.00

Page 9
To Summary CI 0.00

Page 10
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKSFOUL DRAINAGE AND TREATMENT FACILITIES

Qty Unit Rate CI c

FOUL DRAINAGE AND TREATMENT FACILITIES


NOTE: REFER TO APEC'S CIVIL ENGINEERING
DRAWING C501
Foul water drainage installations

Supply and install 1000 gallon septic tank and all


connections to incoming services as per dimensioned
a diagram detail 7 of drawing C/501 3 NR 0.00 0.00

Allow for drain runs including pipework, fittings,


connections, all excavation and earthworks, bedding
materials and backfill as specified
Sanitary drainage pipe runs from buildings to septic
b tanks ITEM 0.00 0.00

Page 11
To Summary CI 0.00

Page 12
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS SITE PLUMBING INSTALLATION

Qty Unit Rate CI c

SITE PLUMBING INSTALLATION


Mains water

Mains water supply to new buildings including all


excavation and earthworks, piping, fittings,
connections, valves, meters, etc.; allow builders work
in connection with this item.
a External water supply and distribution ITEM 0.00 0.00
Washout
Allow for the full supply of the water main washout
system
b Water main washout ITEM 0.00 0.00
Gate valve
Allow for the full supply and installation of the gate
c valve ITEM 0.00 0.00
Sundries
Sundries including support brackets, thrust blocks;
identification stripes
d Generally ITEM 0.00 0.00
Testing
e Allow for testing the whole of the works in this section ITEM 0.00 0.00
Builders work

Allow for forming openings, holes, chases, mortices,


etc. for conduit and the like for the whole of the
services installation through or in concrete slabs
or/and walls; including making good the structure and
f all finishes ITEM 0.00 0.00
Plumbing trenching
Allow here for all plumbing trenching and backfilling
g as detailed on the drawings ITEM 0.00 0.00

Page 13
To Summary CI 0.00

Page 14
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS SITE ELECTRICAL INSTALLATION

Qty Unit Rate CI c

SITE ELECTRICAL INSTALLATION


Mains incoming supply

Allow for the full installation of the incoming mains


supply Including all necessary excavation and
a earthworks, conduit and fittings. ITEM 0.00 0.00
Sub-mains
b Generally ITEM 0.00 0.00
Final circuits and auxillary installations
c Power installations ITEM 0.00 0.00
d Telephone and data installation ITEM 0.00 0.00
e General equipment ITEM 0.00 0.00
Control gear
Including switchgear, distribution gear, contractors,
f starters, switchboards etc. ITEM 0.00 0.00
Accessories

Utility pole base including all excavation and


earthworks, concrete works, metal work and final
surface finishes Including all pendants, all lighting,
g lighting switches, socket outlets etc. ITEM 0.00 0.00
Lightning conductor
h Generally ITEM 0.00 0.00
External lighting

Complete installation in accordance with the


electrical drawings; including all conduits, trenching
and backfilling, light fittings and installation as per
Landscape Lighting Plan - PL-4 Options 1-3

Provide price for all 3 options and carry in to the


pricing column the lowest cost option - A detailed
breakdown of the entire bid will be required should
the contractor be successful based on the option
selected by the Employer
Option 1 - Beachside Lighting CI$
Option 2 - Kicher Lighting CI$
Option 3 - AQ Lighting CI$
i Lowest Cost Option ITEM 0.00 0.00
Testing and commissioning
j Allow for testing the whole of the works in this section ITEM 0.00 0.00

Page 15
To Collection CI 0.00

Page 16
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS SITE ELECTRICAL INSTALLATION

Qty Unit Rate CI c

SITE ELECTRICAL INSTALLATION continued ...


Temporary installations

Allow for applying for and installing a temporary


supply for the construction works including provided a
a temp fixing meter etc. ITEM 0.00 0.00
Sundries

Including supports, brackets, fixings, anchors,


insulation blocks, identification dicks, label plates,
charts and colour coding, tools and spares,
documents including drawings, operating instructions
b and maintenance manuals ITEM 0.00 0.00
Builders work

Allow for forming openings, holes, chases, mortices,


etc. for conduit and the like for the whole of the
services installation through or in concrete slabs
or/and walls; including making good the structure and
c all finishes ITEM 0.00 0.00
Electrical & Mechanical trenching
Allow here for all electrical and mechanical trenching
and backfilling as detailed on the drawings

Page 17
To Collection CI 0.00

Page 18
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS SITE ELECTRICAL INSTALLATION

Qty Unit Rate CI c

Collection

Total from Page 8 CI 0.00

Total from Page 9 CI 0.00

Page 19
To Summary CI 0.00

Page 20
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS CABANAS

Qty Unit Rate CI c

CABANAS

Not withstanding the principles of the 'New Rules


of Measurement NRM 2' the contractor is required
to price the entire installation. Refer to Drawings
S-400 and L-2
NOTE: CABANA FLOOR FINISHES ARE INCLUDED
IN THE LANDSCAPING SECTION
Cabana 1
Foundation

Allow here for strip footings - generally including


foundation block - no height specified including
formwork, reinforcement, as detailed on Apecs
a structural drawing S-400 ITEM 0.00 0.00
Floor slab

Allow here for 5" RC slab 4000 psi vibrated


including formwork, reinforcement and sundries, as
b detailed on Apecs structural drawing S-400 ITEM 0.00 0.00
Frame and Roof
Timber posts, roof trusses, and rafters including all
c marine grade stainless steel hardware ITEM 0.00 0.00
Coconut leaf roof including all sundries and
d hardware ITEM 0.00 0.00
Cabana 2
Foundation

Allow here for strip footings - generally including


foundation block - no height specified including
formwork, reinforcement, as detailed on Apecs
e structural drawing S-400 ITEM 0.00 0.00
Floor slab

Allow here for 8" RC slab 4000 psi vibrated


including formwork, reinforcement and sundries, as
f detailed on Apecs structural drawing S-400 ITEM 0.00 0.00
Frame and Roof
g Cayman stone column bases ITEM 0.00 0.00
Timber posts, roof trusses, and rafters including all
h marine grade stainless steel hardware ITEM 0.00 0.00
Coconut leaf roof including all sundries and
i hardware ITEM 0.00 0.00

Page 21
To Collection CI 0.00

Page 22
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS CABANAS

Qty Unit Rate CI c

CABANAS continued ...


Cabana 3
Foundation

Allow here for strip footings - generally including


foundation block - no height specified including
formwork, reinforcement, as detailed on Apecs
a structural drawing S-400 ITEM 0.00 0.00
Floor slab

Allow here for 5" RC slab 4000 psi vibrated


including formwork, reinforcement and sundries, as
b detailed on Apecs structural drawing S-400 ITEM 0.00 0.00
Roof and Frame
c Bamboo wall including all sundries ITEM 0.00 0.00
Solid hardwood entry door including all brass
d hardware and fastners ITEM 0.00 0.00
Timber posts, roof trusses, and rafters including all
e marine grade stainless steel hardware ITEM 0.00 0.00
Coconut leaf roof including all sundries and
f hardware ITEM 0.00 0.00

Page 23
To Collection CI 0.00

Page 24
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS CABANAS

Qty Unit Rate CI c

Collection

Total from Page 11 CI 0.00

Total from Page 12 CI 0.00

Page 25
To Summary CI 0.00

Page 26
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS LANDSCAPING

Qty Unit Rate CI c

LANDSCAPING
NOTE: REFER TO LANDSCAPE DRAWINGS L1-L3,
PL1-PL-7
Hardscape

Note: All hardscape finishes laid to 6" crusher run


(measured in 'site preparation') unless otherwise
noted
Ground level Trex composite decking - standard
colour and finish

Allow for foundation, frame, decking, and marine


grade stainless steel hardware including bracing
members and sundry timber required to complete
installation as per dimensioned detail 4 on drawing
a C502 2147 SF 0.00 0.00
b Supply and install 6" sand fill below decks 2147 SF 0.00 0.00
Cayman stone paving

Laid and jointed in approved thinset


mortar, all joints filled with matching grout,
contractor to allow for labour, adhesive and grout
including all labours, cutting, edge trims etc
c Around cabana A2 182 SF 0.00 0.00
d Pathway between building E and cabana 3 102 SF 0.00 0.00
e Off building C deck 7 SF 0.00 0.00
Stone pavers

Laid and jointed in approved thinset


mortar, all joints filled with matching grout,
contractor to allow for labour, adhesive and grout
including all labours, cutting, edge trims etc
f To outside of buildings A&B leading to Cabana 106 SF 0.00 0.00
Concrete Pavers

Laid and jointed in approved thinset


mortar, all joints filled with matching grout,
contractor to allow for labour, adhesive and grout
including all labours, cutting, edge trims etc
g To outside of building F 97 SF 0.00 0.00
Grasscrete parking surfaces
Supply and install - laid to manufacturers
h instructions 2418 SF 0.00 0.00
3" Crusher run pathways
i Supply and install 432 SF 0.00 0.00

Page 27
To Collection CI 0.00

Page 28
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS LANDSCAPING

Qty Unit Rate CI c

NOTE: REFER TO LANDSCAPE DRAWINGS L1-L3,


PL1-PL-7 continued ...

Note: All hardscape finishes laid to 6" crusher run


(measured in 'site preparation') unless otherwise
noted continued ...
Corten metal edging - See detail 3 of PL-6
Supply and install along crusher run path and along
a planters on buildings D & C decks 281 LF 0.00 0.00
3" Gravel
b Supply and install 172 SF 0.00 0.00
3" Sand
c Supply and install 19 SF 0.00 0.00
Stamped Concrete finished slabs
Applied to front patio floors of buildings A-D and
pathway between cabanas

Allow for 5" thick reinforced concrete engineered


insitu slab; 4000 psi; waterproof membrane
d formwork, and reinforcement 618 SF 0.00 0.00
Broom finish lounge area concrete slab

Allow for 5" thick reinforced concrete engineered


insitu slab; 4000 psi; waterproof membrane,
e formwork, reinforcement and broom finish 820 SF 0.00 0.00
Softscape

Allow for supply and installation of planting and


landscaping. Approximate area 6,629 sq.ft. See
Landscape drawings
f 6" top soil 6629 SF 0.00 0.00
g Grass area 6629 SF 0.00 0.00
h Trees - see Itemized Plant List ITEM 0.00 0.00
i Plants and Shrubs - see Itemized Plant List ITEM 0.00 0.00
Irrigation
Allow for the supply and installation of irrigation
j systems as per zones in PL-7 drawings ITEM 0.00 0.00
Site fittings
k 10' x 10' Garbage skiff ITEM 0.00 0.00
3' high bamboo planter boxes - allow the PC Sum of
l CI$500 each for supply 4 NR 0.00 0.00

Page 29
To Collection CI 0.00

Page 30
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS LANDSCAPING

Qty Unit Rate CI c

NOTE: REFER TO LANDSCAPE DRAWINGS L1-L3,


PL1-PL-7 continued ...
Site fittings continued ...
Benches
2' x 5' bench - allow the PC Sum of CI$500 each for
a supply 3 NR 0.00 0.00
2' x 10' bench - allow the PC Sum of CI$900 each
b for supply 1 NR 0.00 0.00
Fiberglass equipment vault

Supply and installation of fibreglass equipment vault


as per dimensioned diagram detail 9 of drawing
C/500 - Allow for foundation, backfill, and all
c hardware ITEM 0.00 0.00

Page 31
To Collection CI 0.00

Page 32
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS LANDSCAPING

Qty Unit Rate CI c

Collection

Total from Page 14 CI 0.00

Total from Page 15 CI 0.00

Total from Page 16 CI 0.00

Page 33
To Summary CI 0.00

Page 34
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS PROVISIONAL SUMS

Qty Unit Rate CI c

PROVISIONAL SUMS
a GARBAGE ENCLOSURE & GATES

Allow a Provisional Sum of CI$13,000 for supply


and installation of CMU Garbage enclousure to
secure 10x10 garbabe skiff with pair of gates
including frame, all hardware and final surface
b finishes SUM 13000.00 13,000.00
SWIMMING POOL

Allow a Provisional Sum of CI$55,000 for the supply


and installation of swimming pool, excavation and
earthworks, water, related equipment and finishes.
c Approximate size 400 sq.ft. SUM 55000.00 55,000.00
FITTINGS AND FURNISHINGS

Allow a Provisional Sum of CI$7,500 for the supply


and installation of development signage and
d direction boards SUM 7500.00 7,500.00
FIRE HYDRANT AND FIRE WELLS

Allow a Provisional Sum of CI$10,000 for the supply


and installation of a fire hydrant and fire well
e system SUM 10000.00 10,000.00
CONTINGENCY SUM
Allow a Provisional Sum of CI$50,000 for Project
f Contingency Sum SUM 50000.00 50,000.00

Page 35
To Summary CI 135,500.00

Page 36
DREAM BIG DIVE RESORT - EXTERNAL WORKS & SITE WORKS

Qty Unit Rate CI c

Summary

SITE PREPARATION Page 1 CI 0.00

CONCRETE PATHS Page 2 CI 0.00

ROADS Page 3 CI 0.00

RETAINING WALLS Page 4 CI 0.00

DRAINAGE BELOW GROUND Page 5 CI 0.00

FOUL DRAINAGE AND TREATMENT ... Page 6 CI 0.00

SITE PLUMBING INSTALLATION Page 7 CI 0.00

SITE ELECTRICAL INSTALLATION Page 10 CI 0.00

CABANAS Page 13 CI 0.00

LANDSCAPING Page 17 CI 0.00

PROVISIONAL SUMS Page 18 CI 135,500.00

Page 37
Total for Bill CI 135,500.00