Professional Documents
Culture Documents
Site Procedures Manual Final
Site Procedures Manual Final
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
1
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
INDEX
Page No.
INTRODUCTION 3
SITE ORGANISATION 9
LABOUR MANAGEMENT 12
MATERIAL CONTROL 20
STEEL EQUIPMENT 41
REPORTING 47
PROJECT SUSPENSION 53
2
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
INTRODUCTION
3
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
1. GENERAL
1.1 Introduction
This manual is to be used as a guide in the execution of projects. On large sites it is
probable that many of the duties described will be delegated but the ultimate
responsibility for ensuring that these duties are carried out will remain with the Site
Agent.
Words purporting any one gender shall include the other and words purporting singular
shall include the plural and vice versa.
The Site Agent is not allowed to speak to the media. Any approach from the media must
be referred to the Contracts Director at Head office or in the Director’s absence to the
Managing Director. If the Site Agent feels that any feature of his site is worthy of media
coverage, he should refer this to his Contracts Director. Any resulting publicity will be
arranged from Head Office.
4
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
2.1 Planning
2.1.1 Contract Programme
Purpose:-
To anticipate and plan for eventualities and avoid short term panic and crisis
management.
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
Responsibility:-
Produced by:-
Format:-
Approval:-
To be agreed internally with the Contract Director and then with the
Client’s Representatives for compliance with contract requirements and
mutual acceptance.
Distribution:-
Reporting:-
6
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
Updating:-
Purpose
Include Masimba Construction work content and critical path for the next
four week period
Indicate labour requirements to meet targets
Comply with main programme
Indicate key interfaces between work elements
Information should be extracted from the approved master programme
Primary use – to ensure correct labour requirements are on site, plant and
material.
Responsibility:-
Produced by:-
Format:-
7
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
Updating:-
Weekly
Purpose:-
To plan in detail the following week’s work and share with the relevant personnel
the targets for the week
Responsibility:-
Produced by:-
Implementation:-
The weekly programme of work for the following week will be completed
and issued to the relevant parties before close of work every Friday.
Acceptance of the programme must be confirmed by all relevant parties.
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
SITE ORGANISATION
9
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
1. SITE ORGANISATION
1.1 Objective
This procedure exists to ensure that there is accountability on the construction sites and
works are conducted in line with the Company’s strategy.
1.2 Responsibility
It is the responsibility of Site Agent on site to ensure that these procedures are adhered
to.
The Site Agent is directly responsible to his Contract Director for the complete operation
of the site.
10
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
11
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
LABOUR MANAGEMENT
12
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
2. LABOUR MANAGEMENT
2.1 Objective
To ensure that labour is managed in a cost effective manner and according to the governing
labour laws of the Republic of Zimbabwe.
2.2 Responsibility
It is the responsibility of Site Agent to ensure that this procedure is adhered to.
The HR Department will be responsible for the coordination of site labour requirements and
movements.
Coordination of labour involves issues of contract issuance and termination thereof.
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
Employee personnel files will be kept at Head office. These files are to contain information
such as the employees’ contract, personal details, disciplinary record and safety issues.
14
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
In instances where it’s inevitable to work overtime prior to authorization, Site Agent should
adequately document the reasons thereof and such instances should be kept at a minimum.
The Overtime Request Form is completed in duplicate and distributed as follows
First copy to Wages department
Second copy , File on site
2.11 Timekeeping
Site Agent to ensure that a record is kept of hours worked.
It is the responsibility of the Foreman that the company pays for actual time worked.
Foreman must patrol the site at intervals during the day to check on the presence of
workers.
Detailed below are the minimum procedures to be adopted to ensure that time is accurately
recorded
15
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
Site is prohibited to advance any loans to employees; applications for loans are to be
submitted to HR Department for approval and disbursed by the Finance Department.
16
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
d) Once all the entries have been made in the Petty Cash account and unclaimed wages
book, payments of unclaimed wages must be made from Petty cash. The Petty cash
voucher must indicate the following information:-
Name and employee number
Amount to be paid
Wages for which period
e) The appropriate entry in the duplicate copy remaining in the unclaimed wages book should
be paid ex-petty cash and date paid.
f) Unclaimed wages must not be kept “over a week-end” or “for a couple of days” in
anticipation that employees will appear to claim them. They must be dealt with in the
manner described above that is immediately after a pay-out.
17
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
3.1 Objective
Site Petty Cash is to be utilized to procure miscellaneous items on site and should not be
substituted as an alternative source of procuring materials for site use.
As a guideline you are only authorized to procure a maximum of 5 items per category of
material per month through petty cash or less than USD100.
The Petty Cash must be used exclusively for the company’s benefit; loans and advances for
site employees from Petty Cash may be made only in exceptional circumstances and as
authorized.
3.2 Responsibility
The Site Agent to ensure that petty cash is utilized according to company laid down
procedures. Any shortfalls should be immediately notified to Head office.
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
Vouchers and receipts should be certified by the Site Agent on signing the weekly cash
return. The expense vouchers to be authorized first before disbursement of cash.
Cash balances should be correct every week-end and check again on the opening Monday.
Receipts Payments
Date Receipt Amount Date Receipt Amount
23.04.2001 Bal, B/fd. 100.00 24.04.2001 Pay Offs 205.00
25.04.2001 Ex-bank 2000.00 25.04.2001 w/s 234 1540.00
25.04.2201 Unclaimed wages w/s 235 134.00
23 A Sand w/e By cash on hand 521.00
24.04.01 300.00
2400.00 2400.00
The above signatures will confirm that all supporting documents are correct and the return
can be posted to Head Office.
Petty Cash must at all times be kept in the safe in a metal cash box to which the Site Agent
holds the keys. Where safes are not provided, the Site Agent must make other adequate
arrangements for the safe custody of the cash. Under no circumstances should it be the
practice for the Site Petty Cash to be kept on an employee’s person.
19
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
MATERIAL CONTROL
20
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
4. MATERIAL CONTROL
4.1 General
All temporary and permanent materials required for the carrying out of works are to be
sourced through the Buying department, which will allocate a designated contract buyer for
the project.
Schedules should be forwarded to the Contract Buyer. At the start of the contract the Site
Agent should provide the Buyer with a delivery programme for all the built-in-items.
Based on the Buying Schedule the Contract Buyer identifies items that require longer lead
times and advises Site Agent to place requisitions ahead of time.
4.3 Requisitions
21
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
Telephoned requisitions to the Buyer are only permitted in cases of emergency and must be
followed up by a requisition form clearly marked “Confirmation of telephone requisition”.
Requisitions can also be sent through e-mail to speed up the procurement process.
Pay particular attention to the following points:-
a) Send your requisition to the Buyer by the fastest possible means.
b) Clearly mark requisition concerning P.C. items with the words “P.C. Items”.
c) Drawings or sketches must be attached separately so that they can be forwarded direct
to the merchant with the buying order and do not have to be copied from the requisition.
d) Wherever possible, give the Buyer adequate notice (10 days) to arrange for purchase at
the most advantageous price before delivery date.
Bulk orders should be monitored closely and overrun on deliveries will necessitate
explanation to the Managing Director.
The Buying Schedule to be updated with the following information and to be presented to
Head Office (Planning Department) on a weekly basis so that we manage the risk of stock
outs and excessive purchases:-
Orders placed
Materials delivered
Materials still to be delivered
22
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
4.5.1 General Rules for the use of the M.R. Form- Manual System
Forms must be used consecutively, and under no circumstances may a book be
used for more than one current contract.
Entries must be made daily, and the original and duplicate copies sent immediately
to Head Office.
Cancelled forms must not be destroyed, but instead should also be sent to Head
Office.
They must be dated the day on which the materials arrive on Site.
They should be filled in as follows:-
1. Quantity.
2. Unit. Kgs.; Metres; Cubic Metres; No.; etc.
3. Complete Description. This entails copying what appears on the suppliers
Delivery Note but this can be abbreviated as long as it is quite clear what has
been received.
4. Supplier. This will show either the supplier’s name or in the case of receipts on
D/C Advice Notes that the Yard or another contract is the supplier.
23
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
5. Transporter. This column is for truck registration number, the names of the
person who delivered the goods to the site
6. Delivery Note Numbers. As this is the only means the office has of distinguishing
between deliveries of identical quantity this is very important.
7. Amount. This is the value of the delivery if known.
8. Cost Code Numbers. This column should bear the cost code to which the cost is
to be allocated and should conform to the cost code shown on the requisition and
order.
9. Order Number
All supporting Delivery Notes and Dockets must be attached to the original M.R.
Form in the same order as the entries on the form.
Short deliveries should be clearly endorsed on the Supplier’s delivery note and only
the actual quantity received is recorded on the MR. R Form.
All Materials received on site should be checked for quality and quantity
Only one MR Form per supplier is to be used.
The M.R. form when complete should bear the signature of the Site Clerk/ Storeman
and the Site Agent.
Dispatch M.R. forms to Accounts Department on a weekly basis to ensure that we
maintain our credit terms with the suppliers.
All fields on the M.R Form are mandatory and to be completed in full.
These procedures are to be adopted when receiving goods through the procurement
module. Follow the procedures as detailed below:-
24
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
(i) Ensure that you have the order for the aggregates and compare to the delivery
notes.
(ii) Check the capacity of the Trucks delivering sand and stone to the contract both
at the commencement of the contract and periodically thereafter.
25
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
(iii) Maintain a register of the vehicle registration number and capacity of all vehicles
delivering to the contract.
(iv) Check the materials as they are off-loaded, and sign the Delivery Note, retaining
the original for the M.R. Form. The Delivery Note should be endorsed with the
date/time of delivery and vehicle registration number.
(v) If there are any discrepancies in quantity they must be pointed out to the Driver
immediately, and all copies of the Delivery Note endorsed accordingly.
Materials on site can be issued from the stores to the following locations and hence different
procedures will need to be identified. These have been documented below.
Works
Defective materials returned to supplier
Issued to another project
Generally we use the Debit Credit Advice Note (DCA) to account for the movement of
materials and is completed in quadruplicate and distributed as follows:-
First and second copy should be attached and sent to the recipient
Blue copy is sent to Finance
Fast copy
The recipient must acknowledge receipt of the goods by signing on the tear off slip
on the first site copy and the site copy is sent to the originator of the DCA
The tear off slip is attached to the MR Form and send to accounts
Accounts will match the tear off slip with the blue copy and process the transaction.
26
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
27
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
3. Physically check at least ONCE A WEEK that the stocks on hand agree with the book
balance.
4. Take precautions for the protection of your cement stocks against rain.
5. DO NOT …..
Sell, lend or give cement to any person for use other than on your contract. Only in
exceptional cases and on the authority of the Contracts Director may cement be sold to
clients or outside firms or persons. Such sales must be covered by a DCA Note priced by
the Engineer or Quantity Surveyor and all four copies of the Delivery Note signed by the
recipient. The Accounts copy must be sent immediately to Accounts Department for
processing.
28
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
29
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
30
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
5.1 General
At tender stage the Managing Director, Contracts Director and the Plant Manager will decide
on major items of plant to be used on the project and tentative programme dates. On award
of the project, they will review this plan with the Site Agent and a list of major plant together
with the required dates will be issued to the Plant Manager.
The Site Agent is responsible for the care and use of plant and vehicles on their sites and
must ensure that abuse by overloading, maltreatment and lack of site maintenance is
avoided. Site Agents must also enforce the instruction that private use of plant and vehicles
is prohibited.
Reference to plant items will also include transport, unless specified otherwise.
The hire out rates will be communicated to the Site Agent and Quantity Surveyor at
commencement of the project and these should be kept confidential.
Particular attention is drawn to Section 5.5 on the maintenance and use of plant.
Depending on the size and quantity of Plant items on site, a mechanic and auto electrician
should be resident on site. They will assist in maintaining the service record of the plant
items on site. The personnel should be consulted on all technical matters.
From time to time during the course of the contract the Site Agent must review his plant
holdings on site and inform the Plant Manager of any changes to the plant requirements
No plant or transport may be hired to outside sources without the prior authority of the Plant
& Transport Manager and Contract Directors.
31
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
5.2 Requisitions
PLANT
1. Plant is obtained by requisition on the standard requisition form addressed to the Plant &
Transport Manager.
2. Telephonic requisitions should be made to the Plant & Transport Manager only as an
exception and must immediately be followed up by a requisition form clearly marked
“confirmation of telephone requisition”.
3. The requisition form must state clearly:-
(a) The contract name
(b) The items of plant required.
(c) The date on which it is required.
(d) The estimated time for which it is required.
(e) The Site Agent’s signature as authority for the requisition.
4. Plant items should be requested at least a month in advance so as to:-
(a) Ensure that the right plant is available when it is needed.
(b) Avoid delays in the work programme.
(c) Keep hire charges to a minimum.
5. Make sure that your requisition gets to the Plant & Transport Manager by the most certain
and fastest possible means, and check up in good time to be sure that it has been received.
6. Plant should not be hired from an outside supplier, unless approved in writing by the
Finance Manager and/or Contract Director.
VEHICLES
1. Company vehicles will be:-
(i) Allocated to the site by the Plant & Transport Manager in consultation with the
Contracts Director at the commencement of a Contract. Delivery of Plant and
Equipment to and from sites is to be arranged with the Plant & Transport
Manager.
32
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
2. Non-Company
(a) Site Agents on sites outside the Harare area have authority to hire transport for delivery
of materials to site. This is done through the normal procurement process.
(b) Cartage Contractors should preferably be engaged on a “per load” basis.
(c) Transport may be hired on a “time” basis only with the prior consent of the Plant &
Transport Manager and Contract Director and if such consent is given, the
order/requisition procedure in (a) above will apply.
All plant and vehicles are under the direct control of the Plant & Transport Manager, whose
decision on their utilization, allocation, maintenance and repair is final. Their movement is
controlled in the following manner.
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
(f) Attach the white copy of the DCA to the MR form and file accordingly.
1. To the Yard
(a) If site transport is not suitable or not available make arrangements for the transport of
the plant with the Plant & Transport Manager.
(b) Make out a DCA Note clearly stating the following:
contract name
Description of plant item
Plant number
Indicate the corresponding DCA # to which the site received the asset on.
34
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
(c) Make the necessary entry on the daily MR Form regarding the condition of the Plant.
(d) Send the driver with the white copy of the DCA to the Plant and Transport Manager.
(e) The receipt portion of the DCA Note will be returned from the Yard and should be filed
and attached to the MR file copy
2. To other Sites
(a) Plant may not be transferred to another site without the consent of the Plant and
Transport Manager.
(b) For transport arrangements see paragraph “Receipt – 2(b)” above.
(c) Make out a DCA Note clearly stating the following
Contract name from which it is being dispatched and the contract name of the
receiving site
Description of the plant item
Plant number
Quantity
(d) Send the white copy of the DCA Note to the receiving site and the yellow copy to the
yard.
(e) Make the appropriate entry in the daily MR Form.
(f) Site Clerk to follow up tear off slip (DCA) from receiving site and match with file copy.
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
5.4.1 Plant
1. Hire charges will be levied from the day the plant leaves the Yard until the day it leaves the
site.
2. If an item of plant is no longer required or has broken down the Plant & Transport Manager
must be notified immediately. If this is not done the full daily hire rate will continue to be
charged.
3. In special cases and only with the prior agreement of the Plant & Transport Manager, plant
which is not required for a definite period may be kept on site free of charge. This depends
on the requirements of other contracts and on the availability and cost of transport.
4. Hire charges are fixed by Management from time to time as they are based on capital cost,
running costs and maintenance and repairs which have a tendency frequently to vary
upwards
5. Each month the site will receive two copies of the Monthly Plant Hire Charges Schedule
which will show the charges raised by the Plant & Transport Manager for the plant used on
the site during the month. One copy is for the contract records; the other copy is for return
to the Plant and Transport Manager with any queries noted on it and with the signature of
the Site Agent, within two days of receipt of charges schedule.
5.4.2 Vehicles
1. Company-Owned
(a) Yard Based
As these vehicles are used mainly for transporting plant and materials to site they are
charged on “time away from Yard” basis. This rate includes driver, fuel and oil. Charges
are raised through an invoice approved by the Plant and Transport Manager.
The rate levied to site will be based on a monthly rate and as such it’s critical for Site to
communicate any major breakdowns. The monthly rate is exclusive of driver, fuel and oil
costs and these are charged separately through a DCA note.
36
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
5.5 MAINTENANCE
5.5.1 General
A large proportion of the Company’s capital is tied up in Company owned plant and vehicles
and the annual profits are directly affected by the way they are treated on site.
Both the cost of repairing plant and vehicles which have been mistreated and the drain on
capital caused by its shortened life directly affect the amount of work that the Company can
undertake, the rates that can be applied to tenders and therefore the employment of all site
personnel.
For these reasons it follows that plant and vehicles must be maintained properly and the
instructions detailed in this section must be strictly adhered to.
MAITENANCE PROCEDURES
(a) Centralized Scheduled Maintenance/Service Control.
(b) Application of Plant and Vehicle Maintenance/Service.
(c) Breakdowns
(d) Accidents
(e) Maintenance/ Service Record Forms.
(f) Ordering of Spares.
(g) Repairs by Local Garages.
37
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
(c) Breakdowns
All breakdowns or similar problems are to be referred to the Plant and Transport
Manager who will either carry out repairs directly or place orders necessary for a
third party to carry out the repairs.
(d) Accidents
38
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
The Risk and Security Manager and the Plant and Transport Manager are to be
jointly informed immediately by telephone of all accidents and an accident report
should be submitted within 48 hours of such accident. Plant Department will handle
all insurance queries.
39
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
5. Loose tools are acquired by purchase through the Buying Office or from Second Hand
Trading Store at the Company Yard. Site Agents should, before a contract starts and from
time to time during a contract visit the Second Hand Trading Store to ascertain what loose
tools are available.
6. At the end of a contract all loose tools must be returned to Second Hand Trading Store at
the Company Yard and credit will be passed to the contract for the value agreed between
the Yard Manager and the Site Agent.
7. Site Agents must not allow employees to appropriate loose tools for their own use during
and after a contract.
8. Repairs to mechanical loose tools will be done by the Site Service Mechanic or by the Yard
Manager and in every instance a requisition must be made out. Cost of repairs will be a
charged to the Site.
9. Adequate facilities should be provided to safeguard artisans’ own tool boxes left on site
overnight.
10. Prior to completion of a contract, a stock-take of all Company owned loose tools will be
undertaken and a variance analysis be submitted to the Finance Manager.
40
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
STEEL EQUIPMENT
41
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
6.1 GENERAL
“Steel Equipment” is a term given by the Company to certain specific items of scaffolding –
shuttering etc.
42
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
Steel Equipment may either be hired from the Yard, or, in exceptional circumstances, hired from
outside suppliers through the Yard manager.
Care should be taken in the treatment of Steel Equipment on Site and when awaiting use,
should be stacked neatly. Sites will be charged for any damage caused to Steel Equipment
through gross negligence.
Consumable items of Steel Equipment, i.e. Ferrule Cones will not be hired to the site, but
charged in full to contract costs as a consumable loose tool.
6.2 REQUISITION
1. Steel Equipment requisitions on the standard requisition form must be for Steel Equipment
only and should be addressed to the Yard manager.
3. Steel Equipment may only be hired through the Yard manager and may not be hired by sites
direct from suppliers.
4. Scaffolding decking and propos may, on occasion, be supplied, erected and dismantled on
site by a sub-contractor on a lump sum basis. If this service is required the Contracts
Manager/Director will make the necessary arrangements in consultation with the Yard
Manager and progress payments must be made by the use of sub-contract certificate, and
in accordance with the Company’s agreement with the Sub-contractor.
5. If there is a scaffolding sub-contractor on site and the site holds stocks of Company owned
Steel Equipment it is doubly important that a close watch be kept to prevent its removal by
the Sub-contractor.
6.2 CONTROL
43
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
1. Steel Equipment stock cards are issued with every site’s establishment stationery kit, but if
missing should be obtained from the Yard Manager.
2. These cards must be kept up-to-date on site by recording all Steel Equipment received and
dispatched in the following manner:-
RECEIPTS
(a) When the Steel Equipment arrives on site the Site Clerk will receive with it the
white copy of a Debit/Credit Advice Note on which there will be a description of
the items and the numbers issued.
(b) Check the equipment received and compare to original requisition, complete the
receipt “tear-off” portion of the DCA Note and return it to the Yard manager or the
site from which it has come from.
(c) Any variances between requisition and actual quantity should be immediately
followed up with a memo to the Yard Manager requesting details of when the
shortfall will be delivered to site.
(d) Enter the DCA Note number and the number of items received in the appropriate
columns of the Steel Equipment stock card (annexure 13)
(e) All receipt entries should be indicated in blue ink
(f) File the white copy of the DCA Note.
(g) Make the necessary entry on the MR Form.
ISSUES
Returns to Yard/Site
(a) Make out DCA Note with the description and number of items being returned.
(b) Send the white copy of the DCA Note to the Yard/Site with the Steel Equipment.
(c) Make the appropriate entry in the Stock card capturing the DCA number and the
number of items returned.
(d) All entries should be marked in red ink.
(e) The yellow copy of the DCA Note should be sent to the Yard Steel Equipment
Clerk.
44
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
(c) Send the white copy of the DCA Note to the site to which the Steel Equipment is
being transferred and the yellow copy to the Yard Steel Equipment Clerk.
(d) Site Clerk to follow up with the receiving Site Clerk for the DCA tear off slip within
a week of transferring the equipment.
3. Sub Yards
In certain areas where a number of contracts are operating, sub-yards are established to
which Steel Equipment may be returned. In such instances the same procedure as outlined
above must be followed. Yard Clerks in these sub-yards will send the yellow copies of DCA
Note issues and the white copies of DCA Note receipts to the Yard Steel Equipment Clerk,
who will maintain the master records.
This procedures provides a guideline on how to resolve disputes between the Site and
Yard regarding Steel Equipment
If the Steel Equipment received from the Yard is in an unacceptable condition, the
receiving site should immediately prepare a DCA returning to Yard indicating nature of
problem. The cost of such transportation shall be for the account of the Yard Manager
If receiving site notes discrepancies between information/ description of details and
quantities, the Site Agent is required to inform the Yard Manager and/or Site Agent of
dispatching site in writing detailing the nature of discrepancies noted and such
correspondence should be done within 24 hours and copied to the Finance Manager.
6.3 CHARGES
1. Steel Equipment is charged to sites at hire rates which are established from time to time as
a percentage of the capital cost of the equipment if it is Company owned. If it is hired from
an external supplier, the site will be charged the hire rate paid to the external supplier.
2. Charges for Steel Equipment are raised every month from the Yard records, of the Steel
Equipment on site on the last day of the month. Hence the importance of sending the yellow
copy of the DCA Note to the Steel Equipment Clerk at the Yard.
45
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
3. This is prepared in the form of a Steel Equipment Hire Schedule (annexure 14) two copies
of which are sent to each site. One copy is for site records; the second copy must be signed
by the Site Agent and returned to the Yard manager with any queries clearly noted on it.
4. The signed form should be attached to a MR form and sent to Head Office for processing.
5. Site clerks should check the monthly return against the Site Stock Card to ensure that the
correct charge has been made prior to signature by the Site Agent
6.4 STOCKTAKING
2. Each site will receive two copies of a standard stock sheet listing all the items of Steel
Equipment used by the Company and Site Agents are responsible for ensuring that the
stock count is accurately conducted and the stock sheet completed with the number of items
on site.
3. One completed copy of the stock sheet must be signed by the Site Agent and returned to
the Yard Manager within the agreed timeframes.
4. Taking stock of Steel Equipment is not easy and it should be planned in advance to ensure
that adequate time is set aside for it and sufficient personnel made available. Ensuring that
Steel Equipment stock cards are kept up-to-date will materially assist in the stock count.
5. Care must be taken that scrap panels purchased from the yard and used as a base for
storing aggregate are not included in the stock count and that scaffolding belonging to sub-
contractors is not counted.
46
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
REPORTING
47
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
7.1 GENERAL
The two important aspects on site costing are:-
(a) The daily control of major items in order to increase efficiency and productivity and therefore
ensure profits, i.e. labour and materials.
(b) The clerical aspect of ensuring an accurate financial monthly cost report.
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
the document number, date, description and amount of the cost excluding VAT
(where applicable), cost allocation.
b) Check if any previous understated/ accounts held back costs have been posted and
tick them off your previous month list.
c) Check if any previous over costed have been reversed and tick them off.
d) Check if previous month’s reallocations have been debited and credited correctly and
tick them off.
e) Thereafter the following lists are drawn up - Costs overstated; accounts held back;
misallocations; residual effects.
f) Any of the items above from previous months not taken care of must be carried
forward.
g) The under and overstate costs are effects for materials, labour and other agreed cost
transferred between contracts. Wages for days short and over the 25th of the month
must not be shown as contras but under or overstated costs.
Subcontractors
Accounts held back on subcontractors are when the company has claimed the value of the
works but no costs have been processed in ledger due to timing differences. Materials
Others
These are general costs such as rentals, fees, fuel, telephone, disbursement claims,
accommodation, electricity, etc.
49
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
OVERSTATED COSTS
These are costs that have been incorrectly processed to your site and amount
not correct.
A schedule to be prepared with reasons why site is rejecting the costs.
Section Description
1. Total certified per This is the total claimed form the client and this
Masimba valuation value to be reconciled to total revenue recorded
per cost sheet
2. Under /(over) claims Under claim is value that has been claimed due to
either differences in measurement dates of the
client and Masimba.
Under claims are not usually encouraged as we
have to ensure we claim everything that is due to
the company to manage cash flows.
Over claims are instances where we have
claimed for works to be carried out in the future.
These should also be kept at a minimum.
Included in over claims are materials on site, as
this is not yet revenue earned.
50
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
51
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
7.2.4 ALLOWABLES
This report is critical and is mandatory to be submitted with each monthly contract report,
exception to this should be approved by Finance Manager in writing.
It is essential to measure the works every month. If guesses are made they will only
complicate the issues when giving an accurate financial report. The allowables are
compiled using the certificates/ valuation quantities and careful note must be made of
the allocation of rate build ups, in that they must coincide with the cost allocations and
your requisitions (e.g. if you have used ready mixed concrete then your allowables must
be shown as such and not broken in plant sand, cement and stone. You should
compare banana to banana not kilometers or tones to cubic’s.
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
53
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
PROJECT SUSPENSION
8 GENERAL
Projects are suspended due to the occurrence of the following
Cash flow constraints by client.
On occurrence of accidents that would have caused loss of lives on site.
Included below are the procedures to be adopted when site is closed off before completion
of works.
The extent of us moving off site is primarily dependent on when we will move on site. If
closure of the site is less than 3 months then these procedures are not applicable. These
procedures are applicable when we are closing off site for more than 3 months.
54
Documents Type: Document Title: Effective Date: Revision No:
Financial System Site procedures 1 February 2013 0
Procedure
Document No: Prepared by: Finance Manager Approved by: Managing Director
MC 01 SP A Makamure A. Ilic
8.10.13 8.10.13
8.1 DOCUMENTATION
The Site Agent should receive a letter of instruction from Head Office signed off by the
Managing Director.
The instruction will state the duration of the suspension
55