Professional Documents
Culture Documents
Attach-5 ITP For Static Equipement
Attach-5 ITP For Static Equipement
CO., LTD
INSPECTION AND TEST PLAN 1 of 10 Rev.0
For Bidding
0 For Approval
Inspection Class
Standard or code Inspection
No. Items Name Acceptance criteria Frequency Record Remarks
executed method Owner/ WUHUA Subcontr
PMC N actor
1 Construction Preparation
Actual
Foundation acceptance and Meet design and standard EQ-001 Record of Re-measurement for
1.3 Design drawing measurement at Before installation Foundation H H P
Handover requirement
site
2 Equipment Installation
Visual &
2.4 Grouting Design drawing Meet drawing requirement After installation N/A W W P
checking
Installation of the Equipment Steel ruler, Tape, EQ-010 Record of Tray Installation
2.5 Design drawing Meet drawing requirement Each Equipment EQ-011 Record of Equipment Filling
W W P
Internal model plate
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD 2 of 3
ITP for Static Equipment Installation
Inspection Class
Standard or code Inspection
No. Items Name Acceptance criteria Frequency Record Remarks
executed method Owner/ WUHUA Subcontr
PMC N actor
Cleaning and Closing of the Visual & EQ-049 Manhole closed checking
2.6 Work Procedure Before close. H W P
Equipment checking Record
"H"—Hold point
"W"—Witness point
remark
"R"—Review Point
"S"—Surveillance
"P"—Performer
MUST NOT BE COPIED, TRANSMITTED TO OTHERS OR USED WITHOUT PERMISSION OF WUHUAN ENGINEERING CO. LTD 3 of 3
Talcher Fertilizers Limited WUHUAN Job. No.
WUHUAN
Coal Gasification Plant, Talcher
ENGINEERING
CO.,LTD. Confirmation of Measurement device at site 1 of 1 Rev. 0
1
2
3
Project:
Record of Re-measurement for
EQ-001 Unit:
Foundation
Section:
Item
Equipment Name
No.
Distance allow deviation ±10mm Elevation allowable deviation ±20mm
Design Actual Design Actual
Item Deviation Item Deviation
Value Value Value Value
Project:
Record of Case-open Check of
EQ-006 Unit:
Equipment
Section:
Name of
Tag No.
Equipment
Inspection of Equipment:
Handover Record of Documents and Special Tools delivered together with Equipment:
Project:
Installation Record of Vertical
EQ-008 Unit:
Equipment
Section:
h represents the distance between the two measured points. (Unit: mm)
Plumb
Plumb
Conclusion
Project:
Installation Record of Horizontal
EQ-009 Unit:
Equipment
Section:
(Unit: mm)
C
Elevation
D
B-C
Axial levelness
D-E
B-D
Radial Levelness
C-E
L OD
Conclusion
Project
EQ-010 R e c o r d o f Tr a y I n s t a l l a t i o n Unit
Section
Name of
Tag No Type
Equipment
1
2
3
4
5
6
Tab.EQ-010
WUHUAN
Project
Section
Name of Type and
Tag No
Equipment Specification
Sectional
Fillings description Specification of Fillings Filling Height (m) Remark
SN
Tab.EQ-011
WUHUAN
Project
Quality Control Table For Assembling
EQ-012 Unit
Sectioned Column
Section
Specification Material
Design pressure
Design temp.
(MPa)
Medium Standard for execution
Assembling inspection
Non-destructive testing
Heat-treatment of weld
Medium
Pressure
Pressure(MPa):
test
Duration(Min)
Note
Tab.EQ-012
WUHUAN
Project
Record of Field Assembly and
EQ-013 Unit
Welding of Equipment
Section
Name of Type and
Tag No
Equipment Specification
Joint No.
Bae metals
Filler metals
Welding Process
WPS/PQR
Welder’s ID
Nominal (Max-Min)
0-180° 45-225° 90-270° 135-315°
I.D. Out of roundness
0°
90°
Note: The sketch map of welding aperture, distribution of welder and section classification of non-damaging inspection.
Tab.EQ-013
WUHUAN
Project
Record of Machinery
EQ-019 Unit
Installation
Section
Elevation Deviation
Longitudinal
Deviation in Central
line position
Transversal
Verticality Deviation
Longitudinal
Levelness Deviation
Transversal
Conclusion:
Tab.EQ-019
WUHUAN
Project
Record of Machinery
EQ-020 Dismantling Inspection and Unit
Re-assembly
Section
Name of
Tag No
Equipment
Actual Measured
Allowable Measured Values
Value When
Positions Measured and Content of Inspection Value During Dismantling
Re-assembling
(mm) and Inspection (mm)
(mm)
Remark:
Conclusion:
Tab.EQ-020
WUHUAN
Project
Construction Quality Inspection
EQ-027 Unit
Record of Industrial Boiler
Section
Material of Boiler
Construction
Wall Bricklaying
Appearance of Fire-proofing
Concrete
Appearance of Adiabatic
Concrete
Liner-sticking of Fire-proofing
Fiber
Remark:
Tab.EQ-027
WUHUAN
Project
Installation Inspection Record
EQ-028 Unit
of Industrial Boiler
Section
Sub-Construction
Inspector
Item of Inspection Result of Inspection Inspection
Sub-Construction Owner / PMC
Date
Inspection on Equipment,
Components and Materials
Re-measurement of
Foundation Construction
Installation of Steel-work of
Boiler
Installation of Burners
Pressure Test
Remark:
Tab.EQ-028
WUHUAN
Project
Section
Drying Date From (Y) (M) (D) (H) to (Y) (M) (D) (H), Total (D)
Drying Method
°C
Remark: The thin solid line is the
controlling line,
while the thick solid line is the
actual line.
0
Time( )
Conclusion:
Tab.EQ-029
WUHUAN
Report No Location
Course No Tank No
Record:
Conclusion:
Tab.EQ-049