isilah di kolom yg biru

Product PC-1501-001
Lead Time/weeks 2
Order Quantity 1,000
Saftey Stock 100
DTF/weeks 2
Beginning PAB 950

DTF WEEKLY PERIODS


1 2 3 4 5 6
Forecast 753 753 753 753 758 758
Forecast Net 7 -7 203 528 708 748
Order Requirements 746 760 550 225 50 10
Requirements Summary 746 760 753 753 758 758
MPS Scheduled Receipts 1000
Projected Available Balance 204 444 691 938 180 422
Net Requirements 0 0 309 62 0 578
MPS Planned Order Receipt 0 0 1,000 1,000 0 1,000
Planned Order Release 1,000 1,000 0 1,000 1,000 1,000
ATP 204 240 450 725 0 990
CUM ATP 444 894 1,619 1,619 2,609

1
PTF
7 8 9 10
758 759 761 761
753 759 761 761
5 0 0 0
758 759 761 761

664 905 144 383


336 95 0 617
1,000 1,000 0 1,000
0 1,000 1,000 1,000
995 1,000 0 1,000
3,604 4,604 4,604 5,604

2
Isilah di kolom yang biru

Product PC-1501-001
Lead Time/weeks 1
Order Quantity 30
Saftey Stock 0
DTF/weeks 2
Beginning PAB 20

DTF WEEKLY PERIODS


1 2 3 4 5 6
Forecast remining 1 6 1 15 24 25
Order Requirements 19 14 19 5 1 0
Requirements Summary
MPS Scheduled Receipts 30
Projected Available Balance
Net Requirements
MPS Planned Order Receipt
Planned Order Release

3
7
25
0