Professional Documents
Culture Documents
BOILER DP Transmitter Water Level
BOILER DP Transmitter Water Level
Table of contents
1 Description
The water level control is a modulating system at this type of boiler. The system is
illustrated in Figure 1. For measuring and control of the water level, the boiler is
equipped with a dp water level transmitter unit, which includes external reference
and variable legs, and a dp-transmitter. The continuous 4-20 mA output signal from
the dp-transmitter is processed in the control system, which provides level
alarms/shut downs and control of the regulating feed water valve.
Feed water
valves
Reference leg
Variable leg
Boiler
Valve Control
manifold system
(panel)
dp-transmitter
Figure 1 dp_0_mod.cdr
1 General
The dp water level transmitter unit controls and supervises the water level in the
boiler. The complete unit is installed in a vertical position and connected to the
boiler sockets, provided for this purpose, by means of shut-off valves (see Figure 1).
The dp water level transmitter unit includes reference leg, variable leg, transmitter
connection valves mounted on a manifold, and a differential pressure transmitter.
The differential pressure transmitter converts the detected water level into an
analogue signal (4-20 mA) which is transmitted to the control system. The signal
can also be used for remote level indication in the engine control room.
Filling plug
Reference leg
Drain valve
Boiler
Filling plug
Variable leg
Drain valve
Valve manifold
Connection
valves
Equalising valve
dp-transmitter
Figure 1 dpunit.cdr
The differential pressure transmitter is installed with the process connections upward
to prevent trapping of air. The pipes are mounted with continuous fall (at least 5°)
from the boiler connections to the transmitter also to prevent trapping of air.
The reference impulse leg (upper connection point) is connected to the high pressure
connection (+), and the variable impulse leg (lower connection point) to the low
pressure connection (-).
Note: The dp water level transmitter unit or any part of it must not be
insulated to ensure the correct function.
2 Commissioning
Before the boiler is pressurised and started for the first time some initial
commissioning procedures can be performed with regard to the valves of the dp
water level transmitter unit. The shut-off valves, transmitter connection valves, and
equalising valve should be operated in the following sequence during the initial
commissioning:
Step A: Initial setting; all valves of the dp water level transmitter unit closed (see
Figure 1).
Step C: Unscrew the filling plugs for the reference leg and variable leg. Fill the legs
with feed water.
Step D: Open the transmitter connection valve and venting facility on the reference
leg side of the transmitter.
Step E: Close the venting facility on the reference leg side of the transmitter when
no more air escapes.
Step F: Open the venting facility on the variable leg side of the transmitter.
Step G: Close the transmitter connection valve on the reference leg side of the
transmitter when no more air escapes.
Step H: Open the transmitter connection valve on the variable leg side of the
transmitter.
Step I: Close the venting facility on the variable leg side of the transmitter when no
more air escapes.
Step J: Close the transmitter connection valve on the variable leg side of the
transmitter.
Step L: Refill the legs with feed water and screw on the filling plugs for the
reference leg and variable leg.
Step B: Use the "M" key to select modes on the differential pressure transmitter.
When a mode is selected, the keys ↑ and ↓ are used to change the mode
value.
Step C: Set the values in mode 4 (electrical damping), 9 (output in error situation),
10 (pushbuttons functions), 11 (characteristic), 13 (value displayed), and 14
(engineering units). In mode 14 select e.g. "mm H2O" as engineering units.
Step E: Use the ↑ or ↓ key to set the start of scale in the selected engineering unit. If
mm H2O is selected as engineering units, then set the start of scale to the
calculated value in mm H2O (differential pressure at 4 mA).
Step F: Press both the ↑ and ↓ keys simultaneously for about 2 seconds, and the
start of scale is set to zero (in the selected engineering unit).
Step H: Use the ↑ or ↓ key to set the full scale in the selected engineering unit. If
mm H2O is selected as engineering units, then set the full scale to the
calculated value in mm H2O (differential pressure at 20 mA).
Step I: Press both the ↑ and ↓ keys simultaneously for about 2 seconds, and the full
scale is set to the upper limit (in the selected engineering unit).
Step J: Mount the protective cover of the differential pressure transmitter again.
Table 1
t1 = not existing
Differential pressure
between connections:
Height between
525 x 0.9922 =
connections, e.g.:
525 mm
521 mm H2O (at 4 mA)
Water level
o
t3 = 170 C at 7 barg,
204oC at 16 barg
o 3
t2 = 40 C, density: 992.2 kg/m t1 = not existing
Water level
Differential pressure
between connections
(at 7 barg):
525 x (0.9922 - 0.8970) =
Height between
50.0 mm H2O (at 20 mA) connections, e.g.:
525 mm
Differential pressure
between connections
(at 16 barg):
525 x (0.9922 - 0.8596) =
69.6 mm H2O (at 20 mA)
o
t3 = 170 C at 7 barg,
3
density 897.0 kg/m
o
204 C at 16 barg,
3
density 859.6 kg/m
Figure 2 dpunit_cali1.cdr
minimum indicated "Too low water level" on the control system not is lower than
the actual "Too low water level" mark. Because of the density difference in the
boiler water at different working pressures/temperatures the indicated water levels
will not be identical. This means that the differential pressure transmitter should be
calibrated when the boiler plant operates in high pressure mode.
When the boiler operates at normal working pressure carry out the following work
steps (please also see the specific instruction for the differential pressure
transmitter):
Step A: Unscrew the screws that hold the protective cover of the differential
pressure transmitter for access to the push buttons.
Step B: Use the "M" key to select modes on the differential pressure transmitter.
When a mode is selected, the keys ↑ and ↓ are used to change the mode
value.
Step C: Set the values in mode 4 (electrical damping), 9 (output in error situation),
10 (pushbuttons functions), 11 (characteristic), 13 (value displayed), and 14
(engineering units). In mode 14 select "mA" as engineering units.
Step D: Ensure that the boiler cannot be filled with feed water by closing the feed
water valves or stopping the feed water pumps.
Step E: Slowly decrease the water level in the boiler until the lower connection
point is reached (socket centre line of the variable leg). The water level can
be decreased by means of the blow down valves.
Step F: The upper and lower connection points will normally be beyond the visual
indication area of the water level gauges. It is therefore impossible to see
when the water level is at these points. However, the rising/falling rate of
the water level can be controlled, by throttling the feed water valves/blow
down valves. By clocking the rate it can be calculated when the water level
has reached the connection points.
Step H: Set the output current corresponding to the start of scale using the ↑ and ↓
keys. Or set the output current to 4 mA by pressing the ↑ and ↓ keys
simultaneously for about 2 seconds.
Step I: Slowly increase the water level in the boiler until the upper connection point
is reached (socket centre line of the reference leg). The water level can be
increased by means of the feed water pumps.
Step J: When the water level is increased operate the burner so that the boiler
pressure is kept at normal working pressure.
Step L: Set the output current corresponding to the full scale using the ↑ and ↓
keys. Or set the output current to 20 mA by pressing the ↑ and ↓ keys
simultaneously for about 2 seconds.
Step M: Mount the protective cover of the differential pressure transmitter again.
During final commissioning a function test of the dp water level transmitter unit
must be performed before the boiler plant is put into normal operation. The purpose
of the function test is to check that the output signals from the differential pressure
transmitter are correct. Furthermore, it should be checked that the connected
alarms/shut downs and control functions are operational. The boiler should be
operated at normal working pressure during the test to provide for correct
indications. When the boiler is at normal water level and the burner is in operation,
carry out the following work steps:
Step A: Slowly increase the water level in the boiler by forcing operation of the feed
water pump until the water level has risen to the "High water level" level.
The control system should indicate an alarm, (if provided).
Note: Note that shut downs, alarms, and cut out functions can be delayed via
timers in the control system.
Step B: Increase the water level somewhat until the "Too high water level" mark is
reached. The burner should stop, and a shut down should be indicated on
the control system, (if provided).
Step C: Increase the water level somewhat until the upper connection point is
reached (socket centre line of the reference leg). Check that the output
signal from the differential pressure transmitter is at 20 mA or the full scale
value in the selected engineering units.
Step D: The upper and lower connection points will normally be beyond the visual
indication area of the water level gauges. It is therefore impossible to see
when the water level is at these points. However, the rising/falling rate of
the water level can be controlled, by throttling the feed water valves/blow
down valves. By clocking the rate it can be calculated when the water level
has reached the connection points.
Step E: Ensure that the boiler cannot be filled with feed water by closing the feed
water valves or stopping the feed water pumps.
Step F: Decrease the water level in the boiler by means of the blow down valves
until the water level has fallen to the " Low water level " level. The control
system should indicate an alarm.
Step G: Decrease the water level somewhat until the "Too low water level" mark is
reached. The burner should stop, and a shut down should be indicated on
the control system.
Step H: Decrease the water level somewhat until the lower connection point is
reached (socket centre line of the variable leg). Check that the output signal
Step I: After completion of the function test open the feed water valves or start the
feed water pumps.
Attention: Both shut-off valves between the boiler and impulse legs must
always be fully open and the reference leg must be totally filled with
water during normal operation of the boiler.
To ensure a safe and reliable operation of the boiler plant check the dp water level
transmitter unit whenever an opportunity occurs by comparing the water level
indicated by the control system with the level indicated in the water level gauges.
A great difference in the water levels may indicate blocked connections to the
differential pressure transmitter. Therefore it is recommended to blow-through the
impulse legs and connection pipes frequently. The blow-through procedures can be
performed, e.g. in connection with stopping the boiler plant, in order to get rid of
dissolved particles that could settle during the stop periods. In case of prolonged
standstill the dp water level transmitter unit should be checked for the correct
function before the boiler plant is restarted.
3.1.1 Blow-through procedure of the impulse legs
The blow-through procedure should be performed as describe below when the boiler
plant is in operation and in steady load condition. The procedure should be carried
out at least once each month. When the blow-through procedure is carried out, it is
very important that the water level in the boiler is carefully and continuously
supervised by the ship engineering personnel. The feed water control valve must be
operated manually, if necessary.
Step A: Isolate the differential pressure transmitter by closing the two transmitter
connection valves in the manifold. The equalising valve must remain closed
during the blow-through procedure and normal operation.
Step B: Slowly open the drain valves of the impulse legs, and allow the legs to
blow-through for a few seconds.
Step D: Close the drain valves again when the reference leg is completely
depressurised.
Step E: Unscrew the filling plug of the reference leg and fill the leg with feed water.
Step F: Screw on the filling plug and slowly open the shut-off valve for the
reference leg.
Step H: After performing the blow-through check that the dp water level transmitter
unit and feed water control valve are fully operational.
In case of contaminated boiler water, e.g. sludge, mud, etc., the blow-through
procedure of the impulse legs must be done more often.
3.1.2 Blow-through procedure of the connection pipes
The blow-through procedure should be performed as describe below when the boiler
plant is stopped, but still pressurised. The procedure should be carried out at least
once each year.
Step A: Open the venting facilities located on the valve manifold for the impulse
legs. The transmitter connection valves must remain open and the
equalising valve closed during the blow-through procedure.
Step B: Close the venting facilities on the valve manifold when only clean water
escapes.
Step E: Close the drain valve again when the reference leg is completely
depressurised.
Step F: Unscrew the filling plug of the reference leg and fill the leg with feed water.
Step G: Screw on the filling plug and slowly open the shut-off valve for the
reference leg.
In case of contaminated boiler water, e.g. sludge, mud, etc., the blow-through
procedure of the connection pipes must be done more often.
3.1.3 Function test of the dp water level transmitter unit
During normal operation of the boiler plant a function test of dp water level
transmitter unit should be carried out at least once each month. The purpose of the
function test is to check that the connected alarms/shut downs and control functions
are operational. The boiler should be operated at normal working pressure during the
test to provide for correct indications. When the boiler is at normal water level and
the burner is in operation, carry out the following work steps:
Step A: Slowly increase the water level in the boiler by forcing operation of the feed
water pump until the water level has risen to the "High water level" level.
The control system should indicate an alarm, (if provided).
Note: Note that shut downs, alarms, and cut out functions can be delayed via
timers in the control system.
Step B: Increase the water level somewhat until the "Too high water level" mark is
reached. The burner should stop, and a shut down should be indicated on
the control system, (if provided).
Step C: Ensure that the boiler cannot be filled with feed water by closing the feed
water valves or stopping the feed water pumps.
Step D: Decrease the water level in the boiler by means of the blow down valves
until the water level has fallen to the "Low water level" level. The control
system should indicate an alarm.
Step E: Decrease the water level somewhat until the "Too low water level" mark is
reached. The burner should stop, and a shut down should be indicated on
the control system.
Step F: After completion of the function test open the feed water valves or start the
feed water pumps.