Deznisipator Design

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 44

ASEAN-German Mini Hydro Project (AGMHP)

Gravel & Sand Traps /


Desilting Basins

Consulting and Engineering 41 Slide 41


ASEAN-German Mini Hydro Project (AGMHP)

Purpose & function


• The purpose of desilting structures is to trap and eliminate
sand and silt from the diverted water.
• If heavy sand and silt-laden water is admitted to the turbine,
hard particles may cause damage to runners, seals and
bearings. Silt might also settle in the water conveyance
system and obstruct flow.
• The traditional method of excluding sand and silt is to
reduce the velocity of the flowing water - in a specifically
designed basin - to such an extent that the particles of a
certain size settle out at the bottom of the structure from
where they can be flushed back to the river (gravity
sluicing).

Consulting and Engineering 42 Slide 42


ASEAN-German Mini Hydro Project (AGMHP)

Gravel trap and sand trap


• A gravel trap and / or sand trap is NOT required when
tapping springs that never flood.
• If the source stream carries heavy bed load during floods, a
gravel trap shall be provided just after the intake orifice.
• In all cases, except for low-head installations with
netH < 10m, a sand trap is required. Recommended:
– 90% of grains > 0.2mm for heads of up to 100m
– 98% of grains > 0.2 mm for heads above 100m
• The bed of the sand trap has to have a trough-like shape in
order to facilitate sediment flushing. A sill at the end of the
sandtrap shall prevent the sand from being washed into to
the headrace canal / pipe. A flushing device in the form of
timber stop logs, steel slide gate or cylindrical bottom outlet
cum spillway shall be provided.
Consulting and Engineering 43 Slide 43
ASEAN-German Mini Hydro Project (AGMHP)

Design principles
Desilting basin must be a longish structure, i.e. about eight
times longer than wide. If the basin is too wide, water will
tend to meander through the basin and areas of high velocity
or even reverse flow will occur and settling of particles is
limited.

In the “ideal desilting basin”


a particle entering water
surface at beginning of
settling basin (point X)
should reach the end
of the basin (point Y) if
it is to be settled.

Consulting and Engineering 44 Slide 44


ASEAN-German Mini Hydro Project (AGMHP)

Basic principles
 L = length of settling zone
 B = width of settling zone
 y = mean water depth or hydraulic depth
 t = time for particle to travel L (s)
 vp = horizontal velocity
 w = fall velocity (from Shield’s graph)
 Q = discharge

Consulting and Engineering 45 Slide 45


ASEAN-German Mini Hydro Project (AGMHP)

Design computation
1. The travelling time of a particle through the basin is
tx = L/v
2. The settling time of the same particle is
ty = H/w
where w is the fall velocity of the particle
3. If the particle is to reach the bottom of the basin at
point C, the two times tx and ty must be equal:
L/v = H/w

Consulting and Engineering 46 Slide 46


ASEAN-German Mini Hydro Project (AGMHP)

Design computation (cont.)

 4. The basin should be not more than 8 times


longer than wide. Considering this, the above
formulas and the equation of continuity, we
receive the following equation:

8Q
L>
w
The fall velocity w can be obtained from Shield’s
graph (following slide)

Consulting and Engineering 47 Slide 47


ASEAN-German Mini Hydro Project (AGMHP)

Shield’s Graph
Fall velocity of quartz spheres in still water

Consulting and Engineering 48 Slide 48


ASEAN-German Mini Hydro Project (AGMHP)

Design computation (cont.)

 5. According to Vischer and Huber, 1982, the


critical water velocity can be estimated using
the following formula:

v = 0.44 × d

Accordingly, to settle particles with a size of


max 0.2mm, the critical velocity is 0.2 m/s

Consulting and Engineering 49 Slide 49


ASEAN-German Mini Hydro Project (AGMHP)

Design computation (cont.)


 6. Velikanov proposed a number of correction factors so that the
formula presented (4.) is modified as follows:
2 2 2
Q λ v(H − 0.2)
L=
B w 7.51 w H
with L = length of the sediment trap in m
B = width of the sediment trap in m (estimated from 4.)
Q = design flow in m3/s
w = fall velocity of sediment particle in m/s (Shield)
λ = 1.55 (coefficient that accounts for the amount of
settled particles to those
transported)
v = average velocity through desilting basin in m/s
(see 5.)
H = depth of basin in m (without storage depth)
Consulting and Engineering 50 Slide 50
ASEAN-German Mini Hydro Project (AGMHP)

Design computation (cont.)

 7. The effective depth H becomes (using the equation of


continuity):

Q
H=
v B

0.12
H= = 1.0m
0.2 * 0.6

Consulting and Engineering 51 Slide 51


ASEAN-German Mini Hydro Project (AGMHP)

Sections of a Sand Trap

 Typical Cross Section



 Typical Longitudinal
Section ↓

Consulting and Engineering 52 Slide 52


ASEAN-German Mini Hydro Project (AGMHP)

Terminology of a typical intake with sand trap

Side spillway
Masonry weir
Flushing gate
Sluice gate

Intake orifice
Gravel trap
Intake gate Coarse rack
Sand trap Headrace

Consulting and Engineering 53 Slide 53


ASEAN-German Mini Hydro Project (AGMHP)

Terminology of a typical intake with sand trap

Side Spillway

Flushing Gate

Intake Gate

Intake Channel
Trash Rack
Sand trap
Headrace Pipe
Consulting and Engineering 54 Slide 54
ASEAN-German Mini Hydro Project (AGMHP)

Typical layout

Consulting and Engineering 55 Slide 55


ASEAN-German Mini Hydro Project (AGMHP)

Typical design of a small sand trap

Consulting and Engineering 56 Slide 56


ASEAN-German Mini Hydro Project (AGMHP)

Typical arrangement of settling basin after a Tyrolean intake

Consulting and Engineering 57 Slide 57


ASEAN-German Mini Hydro Project (AGMHP)

Desilting basin with two parallel chambers

Consulting and Engineering 58 Slide 58


ASEAN-German Mini Hydro Project (AGMHP)

Requirement for sediment storage

Consulting and Engineering 59 Slide 59


ASEAN-German Mini Hydro Project (AGMHP)

Operation
• Make sure that water levels in sediment trap are as
required. If water levels are lower, flow velocities increase
and sediment cannot settle.
• Watch sediment accumulation. When predefined level of
sediment is reached, sediment trap needs to be flushed by
opening sluice gate. If sediment trap is not flushed,
sediment particles enter power canal and may damage
turbine.
• During flushing, less or no water flows to power house,
flushing should therefore be intense and rapid. Flushing
procedure depends on design
• Make sure that sediment flushed from the sediment trap is
moving far enough and does not block sluice gate
Consulting and Engineering 60 Slide 60
ASEAN-German Mini Hydro Project (AGMHP)

Operation during floods

• During low flows, no sediment and only small silt


concentrations occur. Possibly, sediment traps need
flushing at rare intervals.
• During the rainy season and floods, more sediment is
transported, check sediment traps more frequently if
flushing is required.

Consulting and Engineering 61 Slide 61


ASEAN-German Mini Hydro Project (AGMHP)

Monitoring and maintenance


• Check if sediment trap works during high sediment
concentrations, take water samples after sediment trap
and watch if particles larger than 0,2 mm are removed
efficiently. Allowed size and concentration depends on
turbine and is provided by manufacturer
• If flushing does not remove all sediments, remove
sediments manually
• Often 2 parallel basins are provided. The designer must
clarify how sediment trap should be operated at
low/high flows and for flushing.
• Check structure and gates similarly like weir or dam

Consulting and Engineering 62 Slide 62


ASEAN-German Mini Hydro Project (AGMHP)

Headrace
Channels
and
Structures

Consulting and Engineering 63 Slide 63


ASEAN-German Mini Hydro Project (AGMHP)

General
• The headrace conveys the water from the intake /
desilting basin to the forebay. A headrace can have any
length from zero (if penstock starts at desilting basin) to
several kilometers.
• The most cost effective headrace is an open channel
because these can be constructed with low gradients
(longitudinal slopes) but large cross-sections and hence
introduce low head losses to the scheme.
• Earth channels are the lowest cost options. However,
problems associated with unlined open channels are:
high maintenance requirements, water losses,
landslides triggered by seepage water from unlined
canal, requires stable and relatively flat cross slopes.
Consulting and Engineering 64 Slide 64
ASEAN-German Mini Hydro Project (AGMHP)

Headrace

• If open channel headrace is not possible (e.g.


crossings, unstable or steep ground) pipelines should
be used.
• For both, open channel and pipeline, the flow velocity
should be such that gravel and sediments can be
carried to the sediment trap or forebay to be flushed
from there.
• Also excessive velocity should be avoided because it
may cause erosion of canal walls.

Consulting and Engineering 65 Slide 65


ASEAN-German Mini Hydro Project (AGMHP)

Allowable flow velocities

Consulting and Engineering 66 Slide 66


ASEAN-German Mini Hydro Project (AGMHP)

Sedimentation velocities

Consulting and Engineering 67 Slide 67


ASEAN-German Mini Hydro Project (AGMHP)

Lining Types
Type of lining Remarks
Stone masonry lining low cost solution if stones and
(trapezoidal section or inexpensive labor is available
flume type)
Concrete lining (plain thickness of lining 50 to 100 mm,
concrete, non-reinforced) common problems with joints and
poor subsoil (embankment situations)
Ferro-cement lining requires skilled workers
Buried membrane linings side slopes of canals must be flat to
(PE, PVC or butyl liners) place membranes => canal requires
large space
pre-fabricated canal only for small flow rates
sections (sheet metal,
concrete, etc.)
Consulting and Engineering 68 Slide 68
ASEAN-German Mini Hydro Project (AGMHP)

Lined Channels

Consulting and Engineering 69 Slide 69


ASEAN-German Mini Hydro Project (AGMHP)

Design principles
• Leakage from an unlined headrace canal shall not exceed 5
l/s per 100m of canal length. In steep terrain or landslide
prone areas, headrace pipes shall be used.
• Plastic pipes must be buried. Steel or cast iron pipes
forming a pipe bridge are to be used to cross gullies or
landslide areas.
• In long headrace canals and/
or steep terrain, canal over-
flow spillways into existing
gullies shall be provided.
• Provision shall be made to
release trapped air along
pipelines.

Consulting and Engineering 70 Slide 70


ASEAN-German Mini Hydro Project (AGMHP)

Design and analysis:


Free surface flow

Consulting and Engineering 71 Slide 71


ASEAN-German Mini Hydro Project (AGMHP)

Geometry of channels
The best geometry would be a semi-circle because the
circular (for pipe flow) and the semi-circular shapes (for free
surface flow) give the largest area with the smallest wetted
perimeter (where friction retards the flow). (However, the semi-
circle is seldom chosen in practice because excavation to a
circular shape is difficult.)
Trapezoidal sections are common for earth channels; for small
design discharges (Q<500l/s), the
trapezoidal form should be as
close as possible to the semi-
circle. For larger flows somewhat
wider but shallower channels
must be chosen to avoid deep
excavation.
Consulting and Engineering 72 Slide 72
ASEAN-German Mini Hydro Project (AGMHP)

Manning-Strickler formula

v = K s × R2 3 I
Where v = mean velocity [m/s]
Ks = roughness coefficient according
to Strickler [m1/3s-1]
R = hydraulic radius = A/p [m]
Where A = the cross-sectional area [m2]
p = wetted perimeter [m]
I = slope of water surface
= slope of canal or river bed for
uniform flow = Is [m/m]

Consulting and Engineering 73 Slide 73


ASEAN-German Mini Hydro Project (AGMHP)

Roughness coefficient according to Strickler


Roughness Coefficient (Ks)[m1/3s-1]
for different channel types (selection)
Earth Canals
- smooth, straight, uniform sections, no vegetation 40 - 60
- in rock, relatively smooth and uniform 30 - 40
- in rock but coarse with irregularities 20 - 30
- smooth, straight in fine soils and some vegetation 30 - 35
Concrete Canals
- with smooth cement finish (smoothed surface) 65 - 90
- with normal timber formwork 60 - 75
Stone Masonry Canals
- well-pointed stone masonry using river stones 50 - 60
- plastered masonry canals 65 - 90

Consulting and Engineering 74 Slide 74


ASEAN-German Mini Hydro Project (AGMHP)

Example
Example Qd = 300 l/s = 0.3 m3/s
Stone masonry channel vrec = 1.0 m/s
Selected A = Q/v = 0.3/1.0 = 0.3 m2
width b = height h =0.30.5 = 0.55 m
pointed stone masonry Ks = 50 m1/3s-1
R = A/p=0.3/(3x0.55)
=0.18m
23 v 2 1.0 2
v = Ks × R I → I= ( 23
) → I = ( 23
) = 0.0039
Ks × R 50 × 0.18

0.0039 m/m = 3.9 mm/m or 3.9 0/000

Consulting and Engineering 75 Slide 75


ASEAN-German Mini Hydro Project (AGMHP)

Design graphs

Consulting and Engineering 76 Slide 76


ASEAN-German Mini Hydro Project (AGMHP)

Example for a channel with I=0.0012

Consulting and Engineering 77 Slide 77


ASEAN-German Mini Hydro Project (AGMHP)

Design details
A pipe bridge over a gully with a A coarse trash rack to prevent
side spillway large debris from entering a
siphon

Consulting and Engineering 78 Slide 78


ASEAN-German Mini Hydro Project (AGMHP)

Failure mechanisms

There are two types of failure mechanisms:


1. Failure of hydraulic performance
2. Structural failure
• due to seepage flow in earth channels, especially
under rapid drawdown conditions
• due to seepage flow and erosion under concrete
channels (poor drainage)
• due to uplift pressure under concrete channels,
especially when channel is empty and during high
flood water levels

Consulting and Engineering 79 Slide 79


ASEAN-German Mini Hydro Project (AGMHP)

Failure mechanisms
Structural failure due to seepage flow in earth channels,
especially under rapid drawdown conditions
Rapid drawdown is a critical loading case for earth channels
and should be avoided unless channel is designed for this
condition

Consulting and Engineering 80 Slide 80


ASEAN-German Mini Hydro Project (AGMHP)

Failure mechanisms
• Structural failure due to seepage flow and erosion under
concrete channels (poor drainage)
• Provide and maintain proper drainage

Consulting and Engineering 81 Slide 81


ASEAN-German Mini Hydro Project (AGMHP)

Failure mechanisms
Structural failure due to uplift pressure under concrete
channels, especially when channel is empty and during high
flood water levels
Avoid under all circumstances, fill canal

River flooding

River at normal flow

Consulting and Engineering 82 Slide 82


ASEAN-German Mini Hydro Project (AGMHP)

Operation and maintenance

In order to reduce friction losses and maintain the


conveyance capacity, there should be no obstacles or
sediment depositions in the headrace. Obstacles can be
objects in the headrace but also growth of vegetation. If the
flow velocities are too small, e.g after long periods of low
flows, or following floods, there can be sediment
depositions which must be flushed or removed manually.
Excessive vegetation in earth channels must be removed.
Both, obstacles or sediment depositions can reduce flow
velocities and increase water levels which can cause spill
over the channel side walls.

Consulting and Engineering 83 Slide 83


ASEAN-German Mini Hydro Project (AGMHP)

Monitoring and maintenance


• Check channel regularly for leaks, watch especially for
increasing leakage
• Watch stability of earth channels (erosion, slope stability)
and structural integrity of concrete channels (cracks, leaks)
• Make sure drainage during ditches function properly to
avoid seepage flow underneath channel
• Check regularly for erosion under concrete channel if it is
located within flooding river
• Remove sediment deposits

Drainage ditch
Consulting and Engineering 84 Slide 84

You might also like