Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

PRELIMINARRY CONSTRUCTION PROGRAM OF WORKS - ISSUED FOR TENDER

ID Task Name Duration Start Finish


July 01 September 01 November 01 January 01 March 01
08/21 09/18 10/16 11/13 12/11 01/08 02/05 03/04 04/01
1 PRELIMINARY PROGRAMME 136 days Tue 23/10/03 Tue 24/04/09
2 SITE HANDOVER 1 day Tue 23/10/03 Tue 23/10/03
3 PRELIMINARIES AND GENERAL REQUIREMENTS 18 days Wed 23/10/04 Fri 23/10/27
4 Contactual Obligations / Documents 15 days Wed 23/10/04 Tue 23/10/24
5 Surety / Guarantees 14 days Wed 23/10/04 Mon 23/10/23
6 Contractor All Risk Policy 14 days Wed 23/10/04 Mon 23/10/23
7 Safety File / Works Programme 1 day Tue 23/10/24 Tue 23/10/24
8 Site Establishment 4 days Tue 23/10/24 Fri 23/10/27
9 Offices 1 day Tue 23/10/24 Tue 23/10/24
10 Equipments & Tools 3 days Wed 23/10/25 Fri 23/10/27
11 CLO Appointment & Labour Recruitment 1 day Tue 23/10/24 Tue 23/10/24
12 OHS Requirements 1 day Wed 23/10/25 Wed 23/10/25
13 CONTSRUCTION WORKS 119 days Thu 23/10/26 Tue 24/04/09
14 Mass Earthworks & Clearing 25 days Thu 23/10/26 Wed 23/11/29
15 Clearing & Grubbing 5 days Thu 23/10/26 Wed 23/11/01
16 Cut / Fills & Spoils 10 days Thu 23/10/26 Wed 23/11/08
17 Excavations 15 days Thu 23/11/09 Wed 23/11/29
18 Building Works 94 days Thu 23/11/30 Tue 24/04/09
19 Foundations 30 days Thu 23/11/30 Wed 24/01/10
20 Brick Works 40 days Tue 23/12/05 Mon 24/01/29
21 Waterproofing 3 days Tue 24/01/30 Thu 24/02/01
22 Roofing 15 days Fri 24/02/02 Thu 24/02/22
23 Plustering 10 days Fri 24/02/23 Thu 24/03/07
24 Plumbing 5 days Fri 24/03/08 Thu 24/03/14
25 Paint Works 14 days Fri 24/03/08 Wed 24/03/27
26 Tilling 10 days Wed 24/03/13 Tue 24/03/26
27 Extenal Works 10 days Wed 24/03/27 Tue 24/04/09
28 FINISHING OFF & COMPLETION 3 days Wed 24/03/27 Fri 24/03/29
29 Cleaning and Finishing Off 2 days Wed 24/03/27 Thu 24/03/28
30 Practical Completion 1 day Fri 24/03/29 Fri 24/03/29 03/29

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Summary Duration-only Progress
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only
PRELIMINARRY CONSTRUCTION PROGRAM OF WORKS - ISSUED FOR TENDER

ID Task Name March 01 May 01 July 01 September 01 November 01 January 01 March 01


04/01 04/29 05/27 06/24 07/22 08/19 09/16 10/14 11/11 12/09 01/06 02/03 03/03 03/31 04/28
1 PRELIMINARY PROGRAMME
2 SITE HANDOVER
3 PRELIMINARIES AND GENERAL REQUIREMENTS
4 Contactual Obligations / Documents
5 Surety / Guarantees
6 Contractor All Risk Policy
7 Safety File / Works Programme
8 Site Establishment
9 Offices
10 Equipments & Tools
11 CLO Appointment & Labour Recruitment
12 OHS Requirements
13 CONTSRUCTION WORKS
14 Mass Earthworks & Clearing
15 Clearing & Grubbing
16 Cut / Fills & Spoils
17 Excavations
18 Building Works
19 Foundations
20 Brick Works
21 Waterproofing
22 Roofing
23 Plustering
24 Plumbing
25 Paint Works
26 Tilling
27 Extenal Works
28 FINISHING OFF & COMPLETION
29 Cleaning and Finishing Off
30 Practical Completion 03/29

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Summary Duration-only Progress
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only

You might also like