P&R Infraprojects Ltd.

9MW Dah & 9MW Hanu Sheps, Leh-UT Ladakh


RCC M20 Rate Analysis per CUM for 66KV Switchyard HANU Project

Sl. No. Items Description Unit Qty. Rate Amount


1 Cement Bags 8.2 745 6,109.00
2 Aggregate 20mm Cft 35.28 60 2,117.00
3 Coresand Cft 17.14 60 1,028.00
4 Shuttering Sqm 4 700 2,800.00
5 T&P LS 1 1500 1,500.00
6 Labour Charges Cum 1 4000 4,000.00
5 Wastege ( On Sr. No. 1-4) Percentage 5% 12054 603.00
7 Store Handing Charges (On Sr. No.1-5) Percentage 5% 13554 678.00
8 Design & Drawing Charges (On Sr. No.1-7) Percentage 5% 18835 942.00
10 Water Charegs (On Sr. No.1-7) Percentage 2% 18835 377.00
11 Contractor Profit (On Sr. No.1-10) Percentage 20% 20154 4,031.00
Total Amount 24,185.00
Add: GST Percentage 18% 24185 4,353.00
Net Amount 28,538.00