Information
Inspection floor #
Jobsite name
Location
Conducted on
Prepared by
Description
Following are the normal procedures for field inspection of the curtain wall installation.
These procedures are carried out by the Superintendent, Project Manager, Field crew
lead man, Glazing crew, or Insulation crew
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 1/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
-Embeds are inspected by Project Superintendent during the initial framing of the slabs
to make sure that the layout is per the embed drawings furnished by JAMCo. Any
questions are addressed and corrected.
-The aluminum tee's and steel anchors are installed per the layout required to match the
shop drawings. Any questions are addressed and corrected
-The steel anchors are tack welded in place per the layout. The mulls are installed and
held into place by temporary drill flex. After checking to make sure everything is correct
per the layout, and any adjustments made, the welding of the steel anchors is
completed. Inspection of the welds is ongoing during the installation process.
-The curtain wall is adjusted to its proper elevation, and bolts installed to secure the
mulls to the anchors. Inspection of the installation is on-going by the lead man,
superintendent, and project manager.
-The prep crew installs the gasket, setting blocks, weep baffles, and are instructed to
make sure bolts, anchors, and welds are installed properly. Any questions are brought
to the attention of the lead man and superintendent. Corrections are made if necessary.
-The galvanizing crew is instructed to make sure that all anchors and bolts are installed
before setting the glass. Verify dril-flex screws are removed before installing glass at
wind load clip area. Any questions are brought to attention of the lead man, and
superintendent.
-The installation crew is told to look at each anchor to make sure bolts are installed
before covering up the wall.
Any time during the installation there are questions that the superintendent feels that
our in house engineers need to be involved, they are contacted. If JAMCo's PE needs to
be involved they are contacted. Corrections are made per engineers directions.
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 2/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Embeds to be checked
Floor Number
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Yes No N/A
Yes No N/A
Contractors field installation crew has latest set of JAMCo embed drawings dated
___________
Yes No N/A
Heavy duty embeds are are installed where required per JAMCo embed drawings.
Yes No N/A
Yes No N/A
Yes No N/A
Date checked
Add signature
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 3/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Floor Number
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Wind load or dead load anchors installed per the shop drawings & on correct floor
Yes No N/A
Verify back of aluminum anchors have isolator tape or coating to concrete slab
Yes No N/A
Verify steel anchors have isolator coating to insure dissimilar metals do not come in
contact
Yes No N/A
Check T-bolts (4.6 or 8.8) as required and installed in proper location per shop drawings
Yes No N/A
Yes No N/A
Yes No N/A
Yes No N/A
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 4/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Yes No N/A
Yes No N/A
Date checked
Add signature
Floor Number
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Bolted connection to anchor checked -- size, type, strength, and quantity. Per shop
drawings.
Yes No N/A
Bolted connection to anchor checked; nylon washer, isolators, slip pads, nut type are
torqued tight. Per shop drawings
Yes No N/A
Remove temporary Dril-Flex screws at wind load clips after clip is bolted.
Yes No N/A
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 5/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Yes No N/A
Yes No N/A
Date checked
Add signature
Glazing to be checked
Floor Number
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Prior to internal seals, insure installers have proper solvent, clean rags, and training on
silicone installation procedures.
Yes No N/A
Yes No N/A
Check gasket corners are siliconed into curtain wall, and gaskets have molded
corners/silicone seal
Yes No N/A
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 6/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Yes No N/A
Yes No N/A
Check internal seals, gasket installation, setting blocks (size and placement), weep
baffles, edge blocks.
Yes No N/A
Yes No N/A
If glass has capacity tubes, caulk end of tube as directed by Viracon's written
instructions prior to setting glass.
Yes No N/A
Perform structural and weather seal silicone pull test and log results
Yes No N/A
Date checked
Add signature
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 7/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Insulation to be checked
Floor Number
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Yes No N/A
Yes No N/A
Check that fasteners are not to long, and will not come in contact with gaskets or glass
Yes No N/A
Yes No N/A
Check that insulation is being cut and installed tight to the upper and lower horizontals.
Yes No N/A
Check that mullion wraps are proper width and installed tight to top and bottom where
required
Yes No N/A
Check that aluminum is cleaned with solvent prior to foil tape installation
Yes No N/A
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 8/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Check that all tape is sealed to foil face of insulation and foil backing is free from
holes/damage
Yes No N/A
Date checked
Add signature
Floor Number
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Yes No N/A
Yes No N/A
Yes No N/A
Date checked
Add signature
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 9/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Floor Number
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Check sealant MFG pre-construction testing results for primer to be used if any
Yes No N/A
Hold pre-construction sealant installation meeting with sealant installer. Check that
sealant installer is using the proper primer, solvents, silicone, and color
Yes No N/A
Yes No N/A
Yes No N/A
Obtain written test reports from MFG and file in this book
Yes No N/A
Date checked
Add signature
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 10/11
8/29/23, 7:01 PM Field Inspection and Quality Control Log - SafetyCulture
Floor Number
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Yes No N/A
Prepare and review testing procedures, specifications, and type & quantity of test
included in JAMCo bid
Yes No N/A
Yes No N/A
Date checked
Add signature
The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's
solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice.
You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should
independently determine whether the template is suitable for your circumstances.
https://public-library.safetyculture.io/products/field-inspection-and-quality-control-logAyzEe 11/11