Professional Documents
Culture Documents
Is 13174 2 1994
Is 13174 2 1994
Is 13174 2 1994
Indian Standard
LTFECYCLECOSTING
PART 2 METHODOLOGY
UDC 657-471.1-015
Q BIS 1994
.
FOREWORD
This Tndian Standard was adopted by the Bureau of Indian Standards, after the draft finalized by the
Management and Productivity Sectional Committee, had been approved by the Management and
Systems Division Council.
With ever increasing investments both by industry and Government together with complications of the
continuous explosion in technology, considerable inflation in cost of materials, labour, energy, etc and
the changing international and national environments, decisions based ,on initial costs have often
proved to be counter-productive and uneconomical. In particular, where public money is involved, it
becomes necessary to ensure the maximum benefits out of every investment. In this situation, a
systematic methodology for assessing the total cost of an asset or proposed investment over its entire
operating life, particularly to equate various choices open to the decision making authority, becomes
essential.
Life cycle costing is a method to arrive at such an economic equitable assessment of competing design
alternatives. It takes into account every significant element of cost over the life of the asset and walks
out its total cost and benefits over its-entire economic life.
Economic life is decided in individual cases by the life cycle costing team in an organization taking
into account their own experience, experience of others using same or similar equipment, comments of
the suppliers, state of the technology, chances of obsolescence etc.
It is alternatively possible to decide comparison of life cycle cost ( LCC ) only on 5, 10 or 15 years
which management considers adequate for comparison purposes, even though the asset may have
economic use value far beyond that date. In other words, they have the option to maintain life as fixed
for all the alternatives and then calculate the LCC of each alternative for that life.
The calculation of the life cycle cost for the life of an asset exceeding 20 years will be faced with the
inevitable uncertainties regarding the actual life of the asset, its sub-assemblies and also the inevitable
changes in costs and prices of maintenance, operation, labour and many other inputs. lhe risks and
uncertainties in these factors can be reduced however by simulation exercises and sensitivity studies
using a computer. Such procedures are encouraged while using this standard not only for arriving at
the LCC but also for the value indices and a comparison thereof before final decisions are made.
This standard does not include methods for measuring the performance for different design choices,
equipments or options for investment. If comparison of performance vis-a-vis total life cycle costs,
that is, the value index is sought to be arrived at, this standard will help to calculate the denominator
only. It is advised that users ~of this standard should use their own methods for assessing the
performance.
Given equal levels of performance, the LCC comparison will itself enable the decisions b&g made.
Where levels of performance vary, the LCC techniques will be able to relate the total life cycle costs to
identifiable units of performance in such a way as to enable optimum decisions.
Even after a decision is taken at the initial investment stage or design, several options still exist for use
during the initial years or early stages of the asset’s life. It is possible to review the various perfor_
mance or cost parameters vis-a-vis many and frequent changes in technology, input costs and prices
etc, and re-evaluate the value index for the old as well as new options that have become available. In
such a case, the usage of this standard together with a value index estimation and comparison will still
enable new, perhaps radical decisions being made even if it may mean discontinuing part or whole of
such assets and replacing them by a new technology altogether. While this may be an extreme p~ssl_
bility, it is by no means rare. Many useful~good value medmm-level changes in operation and mainte_
nance will be found attractive by utilizing the methods set out in this standard.
In reporting the results of a test or analysis made in accordance with this standard, if the final value
observed or calculated, is to be rounded off, it shall be done in accordance with IS 2 : 1960 ‘Rules f&
rounding off numerical values ( revisrd )‘.
IS 13174( h-t 2 ) : 1994
Indian Standard
LIFECYCLECOSTING
PART 2 METHODOLOGY
1
IS 13174 ( Part 2 ) : 1994
1. Total initial cost (in million rupees) 367.0 1 887.0 8 434.0 885.0
8. Rate of escalation for maintenance and 5% per year 5% per year 5% per year 5% per year
operating costs
2
IS L3174 ( Part 2 ) : 1994
Table 2 Life Cycle Cost (In Million Rupees) -Present Worth Method
(Clausrs 5.2 aid 5.2.1)
-r l- l- -r
BIIX Item Alb lative I L ve 11 L Alterna ‘e III Ah-m u? IV
1 %itial
rotal initial cost 367.0 367.0 1 887.0 1 887.0 8 434.0 8 434.0 885.0 S85.0
II Salvage and single
:xpenditure :
Year 1 to 4,84O/yr 840.0 ! 551.0
x upwf (3.037 3)
Year 5, Amt x pwf 140.0 79.4 700.0 397.2 4 loo.0 3 000.3
(for example 140
x 0.567 4)
Year 10, Amt x 20.0 6.4 100.0 32.2
wf (for example
r: x 0.322 0)
-0
Year 15, Amt x 30.0 5.5 150.0 27.4
pwf (for example
30 x 0.182 7)
Year 20, Amt x (36.7) (3.8) (188.7) (19.6) (421.7) (43.7) (674.3) (69.9)
pwf (for example
36.7 x 0.103 7)
Total 87.5 437.2 (43.7) 10 481.4
III Annual costs
Annual operation 1 041.0 7 775.6 4 023.0 30 049.4 3 213.0 23 999.2 5 625 .o 42 015.4
and maintenance
costs, Amouni x
upwf
(for example 1 041
x 7.469 4)
IV Life cycle cost 8 230.1 32 373.6 32 389.5 53 381.0
V Production capacity 0.u 3 1.33 1.38 2.25
VI Cost/Tonne 01 29 393.0 26 320.0 23 420.0 23 725.0
production
VII Difference in 5 973.0 2 900.0 0 305.0
cost/tonne front
Minimum
- - L
* NOTE - The initial cost has been assumed, for illustration purposes, as having spent in the first year, in actual prac.tice, this may be spread
over several years. In vjhich case the expenditure in each year will have to be discounted suitably.
worth values by using the applicable PW factors (see example,for life of 20 years at 12% discount
Annex A). Thereafter, all the present worth values v&l rate,upwf = 7.469 4. Therefore, AF = l/upwf =
be tatalled and annualised over the entire life to arrive 0.133 9.
at the comparative annualised cost of the different al- Block III (c) shows the annual cost of operation
ternatives. Table 3 gives the life cycle cost, for each of and maintenance which is taken from Table 1
the four alternatives using annualised cost method. This and would remain same for a?1 fh‘e 20 years of
table has been obtained from Table 1 by using the life for all the 4 alternatives. These figures
following steps: require no change.
a) Blocks I and II of Table 3 are obtained in the Block IV shows the total annualised cost and is
same way as for the present worth method (see obtained by adding the values for Blocks III (a),
5.2.1 and 52.2). III (b) and III (c).
b) Block III (a) and III (b) show the total initial cost Block V gibes the production rapacity for each
and salvage and single expenditure cost an- of the alternatives and~is taken from Table 1.
nualised over the entrie life by using the ap-
Block VI shows the annualised‘cost per tonne of
propriate atninortisation factors (AF).
production and is obtained by dividing the total
Ammortisation factors are obtained as
annualised cost (Block IV) by production’.
reciprocals of upwf given in Annex B. For
capacity (Block V). (I
3
IS 13174 ( Part 2 ) : 1994
Table 3 Life Cycle Cost (In Million Rupees) - Anuualised Cost Method
(Close 5.3 )
I
Ektimatcd
Alternative
Present
I r Ntemative
Estimated
II
Present
r Alternative
Estimated
III
Present
r Alternative
Stnated
IV
Present
(‘OS1 Worth Cost Worth Cost Worth Cost Worth
I ‘Initial
I&al initial cosl 3~67.0 367.0 I 887.0 1 887.0 8 434.0 8 434.0 885.0 885.0
Yc;w _!(I. .‘\I111 x (36.7) (3.8) (188.7) (19.6) (421.7) (43.7) (674.3) (69.9)
pwt’(for lwmplr
36.7 x It13 )
Total 87.5 437.2 (43.7) 10 481.4
III Annual Owning and
0perating Gets :
g) Block VII gives the difference between the an- for implementation, it is also possible to highlight this
nualised cost per tonne of production for the annual saving to the decision making authority by
alternative fro111 the minimum. showing what would be the impact of this recurring
5.3.2 While the figures in Block VII may themselves annual -cost benefit in the ~form of their present worth.
be used to make a decisibn on the choice of alternatives This may simply be obtained by multiplying the figures
in Block VII by upwf given in Annex B (See Block
4
IS 13174 ( Pm-t 2 ) : 1994
VIII). It may IX noted that the differcncr iu the life II iu Table 4 will bc obtained in the same way
cycle cost for the various alternatives will be equal to as given in 5.2.1 and 5.2.2 (see Blocks I nnd II
the figures worked out with present worth method (see of T&bk 2).
Table 2). The difference in these values, if auy, will be AS 5 percent inflation in ‘Maintenance and
b)
due to the rounding off errors. Operating Costs’ is being assumed, this 5 per-
5.4 PW Method with Inflation/Deflation cent inflntion will have to be considered in
5.4.1 The Present Worth Method and Annualised Cost addition to the 12 percent discount rate and
Method discussed in 5.2 and 5.3 for calculation of life accordingly, the upwf has to be calculated from
cycle cost, assumed no inflation in 20 years period. But, the expression given in 5.4.1. The value ofupwf
it is also possible to calculate the life cycle cost by conies out to be 10.87 and accordingly the
taking into consideration the inflation. For example, prencnl worth for ‘Maintrnance and Operating
Table I provides for esralaTion factor for ‘Maintenance Costs’for each alternative is shown in Block III.
and Operating Costs’ @ 5% per year. The effect of It may be noted that the present worth with
inflation on LCC calculations will be to increase the inflation (as given in Table 4) is much higher
present worth of future expenditure. The expression for than in Table 2.
pwf and upwf in such cases, by taking into considera- Blocks IV to VII are obtained as given in 5.2.4
tion both the discount rate ( i ) and escalation rate ( r )
Cl
to 5.2.7.
for a given time period (t ), my be obtained as follows:
Item l- Alternative I l-
-L
Alternative II -I- Alternative 111
l- Alternative IV
6
IS 13174 ( Part 2 ) : 1994
Based on quotations suitably checked/modified as per purchaser’s assessment, where necessary. Item 5.6 estimated by purchase.
6.1.3 The average annual costs (given in 4.1 of Table and 3% for the remaining period.
5) have been reduced to present worth by using the India - 5% per year for first 3 years, 3%
relevant uniform present worth factors (upwf) (given in thereafter for 6 years and 4Y0 therc-
Annex B) aud are showu in Block III. after for the remaining period.
6.1.4 Blocks I, II and III have been added algebraically
to arrive at the LCC. The figures are shown in the Block 6.3.2 The various steps in calculation of LCC (see
IV. Table 8) are as follows..
Table 7 gives the life cycle cost for each of the 4 Since 6.3.1 provides escalation for ‘Annual costs of
alternatives by annualised cost method. It is compiled maintenauce aud operation’ and ‘Single blocks of
ou the same lilies as Table 4. The method has already expenditure’only, Block I in Table 8 for initial cost will
been illustrated in Table 1. The uuifom annual costs is be obtained in the same way as given ill 6.1.1 ( see
worked out ou the basis of 01.01.1991 base instead of Block I of Table 6 ).
figures havingbcen reduced to PWon 01.01.1991 base
as in Table 6. This ‘anlortization’ is only a different 6.3.2.2 Single expenditure
method of the same cvaluatiou but will lead to identical Block II (a) would be calculated by taking the escala-
results. This is illustrated in Table 7.
. tion rates as &ven in 6.3.1 for all the 4 countries
separately. This escalation will be takeu in addition to
6.3 Present Worth Method with Intlation
the 10% discount rate and accordingly pwf has to be
6.3.1 The inflation rates have been assumed as under: calculated from the expression given in 5.4.1.
a) Auuual costs of maintenance and operation 5% In the case of USA (in Table 8), for i = lo%, t = 18 and
per year for the first three years, 3% thereafter r = 3% per year for the first 7 years, 2% for the next 8
for six years and 4% thereafter for the entire years and 3% for the remaining period, the pwf may be
remaining life of the asset. calculated as under :
b) For single blocks of expenditure : a) Since the rate of escalation is different for
Japan - 1% per year for the first IO years different years (with discount-ralc remaining the
and nil thereafter. same that is lOYo), the total period of 18 years
Germany - 2% per year for the first five years has to be divided accordingly, that is,
and 1?h for the remaining period. 18 years = (First 7 years @ 3% escalation) and
U.S.A. - 3% per year for the first seveu (Next 8 years (@2% escalation) and (Rcnlaining
years, 2% Ihr the next eight years 3 years (cr!3% escalation)
IS 13174 ( Part 2 ) : I994
17 0.4 0.079 1
I
IV 12.093 1 16.842 2 12.426 7
V 0 4.749 1 0.333 6
- L i - - - -
= pwf (t =7yea rs, r=3%) X pwf (2 =%yeaIS, r = 2%) economic life of the machine is given as 18 years.
X pwf (t =3years, r =3%) Hence, the entire annual cost of the machine would be
calculated ou 20 years time period (see 6.3.1).
p\vr=(+qx(~~x(yq The expression for pwf and upwf for a given discount
rale (i), escalation rate (r) and period (t) is given in
=0.283 2 5.4.1. For example, upwf (i = 10% r = 4%, t = 11 years)
Since a siugle expenditure of 0.5 million will = em> = 8.447 7
have to be incurred at the end of the 18th year, l-t,
the prcscut worth of Rs 0.5 million would be 0.5 where6=(1+0.04)/1.1
X 0.283 2 = 0.141 6 uiillion.
b) Likewise, the remaining values for the other Therefore, upwf for uniform annual cost
countries can be calculated i;l the same way. = upwf(11 yr at 4%) escalation) X pwf (6 yr at 3%
6.3.2.3 Since there is no escalation on disposal cost, Block escalation) X pwf (3 yr at 5% escalation) + upwf
II (b) will bc calrulatcd in the same \vay as in Table 6. (6 yr at 3% escalation) X pwC (3 yr at 5%
6.3.2.4 Block II would be obtained by adding II (a)and escalation) t upwf (3 yr at 5% escalation)
11 (b). = x.447 7 x 0.674 0 x 0.869 7 + 5.122 9 x 0.869 7
6.3.2.5 lu Block III, the timr lapse behveeu estab- t 2.866 6 = 12.273 8
.lishiug the need for the machine and the date ol’conl- 6.3.2.6 Block IV could be calculated by adding Blocks
tuissioning of the machine is 2 years. In addition, the 1, II and III.
IS 13174 ( Part 2 ) : 1994
Year IS- Present Year EsIinw Present Year Esti- Present Year Esti- Present
mated Worth -ted Worth mated Worth mated Worth
Cost cost Cost (‘ost
I a) C’oncepr, feasibility etc 0.2 0.200 0 n.2 0.200 0 0.2 0.200 0 0.2 0.200 0
h)Tenderingtodelivcry
0.909 1) I 0.3 0.272 7 1 0.3 , 0.2727 1 l 0.3 0.272 7 1 0.3 0.2727
(for example 0.3 x
c) Training skills 2 0.6 0.495 8 2 0.6 0.495 r; 2 Ct.6 0.495 8 2 0.6 0.495 d
(for example 0.6 x
0.826 4)
d) Purcbasc COSI~~LXO 1 4.5 3.718 s 2 4.1 3.470 9 2 6.5 5.371 6 2 3.7 3.057 7
(for example45 x ONXj4)
II a) Single Lxpenditure 6 0.S 0.455 6 7 0.5 0.256 6 7 0.3 0.154 0 5 0.4 0.248 4
_ _ I7 0.4 0.079 1
b) Disposal cost 20 (0.4) (0.059 4) 20 (0.4) (0.059 4) 20 (0.4) (0.059 4) 20 (0.4) (0.059 4)
I
Toto/ 1.349 4 0.455 4 0.638 x 0.700 2
OS0 7 0.036
cost from minimum
6.4 It is assumed that all the 4 offers : ones. They are appropriate in varying degrees to dif-
a ) will cater for the specified tonne-kilo-nletres fercnt types of assets such as buildings, bridges,
identically, hydraulic works, machinery, industrial projects etr, but
none of them is or can bc totally accurate, even as no
b) have identical wnrking lift (1X years), and
forecasting of inflation can be accurate. Nevertheless,
c) are identical in other aspects as well, such as,
such important factors cau be quantified in numerical
ease of maintena rice, accessibility, in- terms to the possible extent, f’nr example annual
digenisability, export potential (after manufac-
average Gross Tonne Kilo Metre (GTKM) expected to
turing the locomotives in India) etc.
be hauled by the locomotives, namely
6.4.1 There are extant nlethods to arrive at a numerical Jnl,ane,Yse oflcr
assesment of the total functional performance of any
asset, considering the factors stated above or similar 16 h x 40 km x 300 days x 1500 1
9
IS 13174 ( Part 2 ) : 1994
Table 8 Present Worth Method With Escalation (Base Date 1 January 1991)
(C/mm 6.3.2)
Year Estim- Present Year E-slim- Present Year Esti- Present Year Esti- Present
ated Worth ated Worth nated Worth mated Worth
Cost Cost Cost cost
I a)(bncept, feasibility,etc 0.2 0.200 0 0.2 0.200 0 0.2 0.100 0 0.2 0.200 0
b)Tendering to delivery 1 0.3 0.272 7 1 0.3 0.272 7 I 0.3 0.272 7 I 0.3 0.272 7
(for example 0.3 x
0.9w 1)
c) Training skills 2 0.6 0.495 8 2 0.6 0.495 8 2 0.6 0.4958 2 0.6 0.495 8
(for example 0.6 x
0.8’6 4)
d) Purchase cosUL,oco 2 4.5 3.7188 L 4.2 3.4709 2 6.5 5.371 6 2 3.7 3.057 7
(for example 4.5 x
ll.S26 4)
II a) Single Expenditure 6 0.8 0.479 4 7 0.5 0.289 0 7 0.3 0.189 3 s 0.4 0.305 0
_ _ 17 0.4 0.149 7
b) Disposal cost 20 (0.4) (0.059 4) 20 (0.4) (0.059 4) 20 (0.4) (O.OS9 4) ‘0 (0.4) (0.059 4)
III iJniform annual costs 0.7 8.591 7 1.o 12.273 8 1.14 13.992 1 8.9 10.923 7
(for example 0.7 x
12.273 8)
10
IS 13174 ( Part 2 ) : 1~994
1 Total initial cost (Rs) 800 COO 500 000 350 000
replacing worn out parts of the joinery. Periodical 8 PRIXAUTIONS WHILE (:ALC:IJLATING LCC
maintenance given in the table is rncant for doing the
While applying the LCC techniques one must take into
routine annual painting/polishing work to the joinery.
account :
These are average annual figures.
The price of services since these are likely to
The annual cost of repairs, as given in the table, have
change over a period of lime; some consistency
been computed with the help of data given in Annex C.
over short periods, such as, six months or one
The data given in this Annex, which is for illustrative
year shall be assumed to make the calculations
purposes only, is applicable for northern part of the
country. and is based on 1989-90 price level for a given worthwhile and realistic.
type 01 construction. This cost information can be What applies to expenses and costs in terms of
updated for price level at any future date with the help the time value money will equally apply to
of maintenance cost indicts which can be worked out earnings and profits during the operation and
using weightage diagram given in Annex D. The pro- use ofthe assets. Corresponding tables must be
cedure of computing the maintenance cost index as prepared using this standard and the associated
given in the Annex is self explanatory. discount factor tables to arrive at such earn-
7.1 Present Worth Method ings/profits.
7.1.1 The LCC has been worked out using present Estimation of costs and earning must be made
worth method only and the iltilation in cost has not been taking into account the past data which should
considered for simplification purpose. Table 10 gives be analyzed using statistical aids, simulation
the Life Cycle Cost for each of the three alternatives. methods, and forecasting techniques so as to
The computation has been based on the cost inforna- nla ke the LCC comparison as realistic as pos-
tion/data given in Table 9 : siblc. For this purpose, LCC comparisons
covering a lesser period of at the most five years,
a> Block 1 gives the initial cost of each of the
would be more reliable than for 15 years, that is
allernatives.
the longer the period the less the accuracy.
b> Block II consists of single expenditure to bc Computer system can be developed to review
incurred after a period of 10 years. The present the position from time to time. It is advisable
worth of each expenditure has been worked out Cormanagement to review the positions annual-
using present worth factors (pwf) using expres- ly and review their decisions, if not in initial
sion as given in 5.2.2 with 12 percent discount investment at least in operation/main-
rate. The present wor(h of salvage/scrap value tenancc/replarellielit or extensive modifications
has also been computed on the salue basis and subsequently. Such reviews nlay also influence
is represented by bracketed figures which has to the economic life.
be subtracted.
An important assumption nmdc so far is that all
C) Block III indicates the costs of annual repairs the alternatives will provide equal quality/per-
and consumables and periodical maintenance as formance/productivity over the assumed 20
per SUI\I of iteul No. 2 and 3 of Table 9. The years life cycle. In filet, in many cases, none of
presenl worth has been computed using the these aspects will be exactly equal. In such a
uniform present worth factors (upwl] as given case, the life cycle costs will have to be calcu-
in 5.2.3. lated on parametric basis, that is unit rate basis.
(9 Block IV gives the total life cycle cost derived The existing methods of business acumcn/intui-
from Blocks I, II and III. tion/probability calculations will have to be
11
IS 13174 ( Part 2) : 1994
(Kepair and Periodic:ll s 000 54,755 16 000 114 510 20 O(K) 149 388
Maintenance)
Am t x upwf
(S 000 X 7.469 4)
resorted to with information from variety of 9.2 However, some of the alternatives may have life
Govemnent or private sources as applicable to cycle costs close to each other and the difference may
arrive at the expected trends during the es- not be significant. In such cases, the decision maker
timated life for each of the alternatives. has the option of choosing an alternative which may be
nlarginally superior in respect of certain factors, such
e) Different discount rates have been chosen in
as,acressibility, less retrainingofworkers, no necessity
this standard fnr illustrative purposes only. In
for import etc. It inay be noted that the word ‘marginal’
actual application, the discount rate must be is important as otherwise the original estimation was
carefully chosen keeping in view the type and that LCC have been calculated for equal level of per-
ualure of industry, the overall price indices in formance or on parametric basis. This will be vitiated
the country and the prevailing rates of cost of if the total performance ratings are substantially dif-
capital. ferent for the various alternatives.
9.3 Thu decision mkcr may also look for iniaginative
or scientific wavs tij inll,rove
1 the LCC. In fact. a
9.1 Priulc facie, the alternativewhich is the least in Life scrutiny of the life cycle cost comparison may motivate
Cycles Cost for c<luA life period/performance rating the generation of a large number of ideas in order to
will autonlaticaily be selected. maximize the performance/reduce cost or achieve both.
12
IS 13174 ( Part 2 ) : 1994
ANNEX C
( Clulm?7 )
MAINTENANCE COST OF VARIOUS SPECIFICATIONS
(Cost in Rupees Per Year)
Base. Year 1989-90
1. Plastering: m2 of Plaster
(i) Cement Plaster in CM 1 : 6, 15 mm thick 0.32
(ii) Lime SURKHI Plaster in LS 1 : 2, 15 mm thick 0.26
2. Flooring: m2 of Floor
(i) Indian Patent Stone Flooring 40 mm thick 1.15
(ii) Marble Chips Flooring 40 mm thick 0.33
15
IS 13174(Part2): 1994
ANNEXD
(Cluc4se 7 )
WEIGHTAGE DIAGRAM FOR COMPUTATION OF MAINTENANCE
COST INDEX FOR BUILDING
Material and Lnbour uni; Rate 1989 Weigh Mlrintenmce Cost Indq 1991
Maintenance Cost Index iti 1991 with respect IO basic year 1989 = 146.3
10
Brueau of Indian Standards
BIS is a statutory institution established under the Bureau of Indian Standards Act, 1986 to promote
harmonious development of the activities of standardization, marking and quality certification of goods
and attending to connected matters in the country.
Copyright
BIS has the copyrlght of all its publications. No part of these publications may be reproduced in any
form without the prior permission in writing of BIS. This does not preclude the free use, in the course
of implementing the standard, of necessary details; such as symbols and sizes, type or grade
designations. Enquiries relating to copyright be addressed to the Director ( Publications ), BIS.
Amendments are issued to standards as the need arises on the basis of comments. Standards are also
reviewed periodically; a standard along with amendments IS reaffirmed when such review indicates that
no changes are needed; if the review indicates that changes are needed, it is taken up for revision.
Users of Indian Standards should ascertain that they are in possession of the latest amendments or
edition.
This Indian Standard has been developed from Dot No. MSD 4 ( 65 ).
--
Headquarters:
Manak Bhavan. 9 Bahadur Shah Zafar Marg, New Delhi 110002 Telegrams : Manaksanstha
Telephones : 331 01 31, 331 13 75 ( Common to all offices )