Preservation requirements for Supplier packages

Project development (PD)


Technical and professional requirement, TR2343, Final Ver. 2.03, published 2019-05-10

Owner: Chief Engineer


Validity area: All locations

Governing Document Template Ver.: 9.1


Requirements: Preservation requirements for Supplier packages Classification: Internal

1 Objective, target group and provision ............................................................................................................. 3


1.1 Objective ................................................................................................................................................. 3
1.2 Target group ........................................................................................................................................... 3
1.3 Provision ................................................................................................................................................. 3
2 Requirements .................................................................................................................................................... 3
2.1 General ................................................................................................................................................... 3
2.2 Special instructions for electrical and electronic equipment .................................................................... 4
2.3 Special instructions for instrument equipment ........................................................................................ 4
2.4 Special instructions for mechanical equipment ....................................................................................... 5
2.5 Documentation ........................................................................................................................................ 5
3 Additional information ...................................................................................................................................... 6
3.1 Definitions and abbreviations .................................................................................................................. 6
3.2 Changes from previous version .............................................................................................................. 6
3.3 References ............................................................................................................................................. 6
App A Available preservation records and check lists ............................................................................................. 7
A.1 Mechanical Preservation Record and Preservation Maintenance Check List ......................................... 7
A.2 Electrical Preservation Records and Preservation Maintenance Check List ........................................... 9
A.3 Instrument Preservation Record and Preservation Maintenance Check List ........................................ 10

Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 2 of 10
Requirements: Preservation requirements for Supplier packages Classification: Internal

1 Objective, target group and provision

1.1 Objective
The objective of this document is to describe the general Preservation requirements for Supplier
Packages.

The Preservation activities performed on Supplier Packages form an important basis for subsequent
equipment installation, Commissioning and Start up of the different systems on the project. Resultant
information and specific documentation is also carried forward for utilisation during the production phase.

It is very important that sufficient attention is paid to the fulfilment of the specified requirements.

All Preservation records will be issued through a web based link from the Company completion system
ProCoSys. All necessary information can be found there, and all required documentation/results shall be
given electronically into the system.

1.2 Target group


Package/Equipment Suppliers to projects with tagged equipment

1.3 Provision
Preservation Manual (WR2364) (Equinor/All locations/On- and offshore)

2 Requirements

2.1 General
Supplier has the full responsibility for the equipment during manufacturing period and shall deliver the
equipment initially preserved according to his own approved preservation instructions and agreed
Company special preservation requirements.

The preservation instructions shall take into consideration possible situations which may occur during the
complete project period, and the Supplier shall be aware that his preservation instructions and initial
preservation form the basis for preservation maintenance throughout the whole project development
period.

Initial preservation shall be based on outdoor storage under salient weather conditions and for the
applicable project period.

Special Supplier requirements regarding storage and maintenance preservation exceeding minimum
requirements in Company's Preservation Manual shall be specified on Preservation Records.

All skids, equipment, piping and bulk orders shall be clean, dry, dustfree and free from any corrosion prior
to initial preservation and transport.

Prior to release, all in/outlets from units/skids shall be plugged/ blanked. Unless otherwise specified,
flanges shall be blanked with oil resistant rubber gaskets or self adhesive flange protector and steel or
water resistant plywood blanks with galvanised bolts sufficient to provide mechanical protection and
water/dust tight sealing. Threaded openings shall have metal plugs compatible with the metallurgy of the
component being capped or plugged. If IP rating is maintained, plastic plugs are acceptable for non
hydraulic/pneumatic systems.
Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 3 of 10
Requirements: Preservation requirements for Supplier packages Classification: Internal

Guidelines:
Drain out water in carbon steel piping systems. Prepare a mixture of preservation corrosion inhibitor and
water according to inhibitor manufactures recommendation. Flush through system with this mixture. Drain
out system ensuring that no water remains trapped in system.

Dinitrol 202 not to be used on cooling medium systems.

Lubricate door hinges, grease nipples and fasteners.

Machined and untreated carbon steel surfaces to be preserved by using a film of corrosion wax

Apply/fasten a 6 mm plywood board to all glasses in instruments/panel fronts. For panel fronts, a wooden
frame for corner protection shall be installed in addition to the front panel.

Aluminium sheeted glass fibre cloth, min. 0,3 KG per m², shall be used to envelope pressure gauges,
controllers, panels, junction boxes, temp. instruments, telecom. equipment, detectors, transmitters,
heaters, pushbutton stands and connection boxes.

Apply thin layer of non-acid vaseline to gaskets on door covers.

All ball valves to be locked in open position.

All exposed valvespindels shall be sprayed with lubricate oil and wrapped with vulke tape around the
yoke.
Gear boxes for valves shall be greased for life. ie filled 100% with grease Type :Equinor Uniway LI-62 or
similar. In addition the seal surface between lid and valve gear housing shall be sealed using silicone
Grease nipples shall be protected with " Grease nipple cap"

Packing of equipment for transportation shall protect the equipment against humidity, dust and mechanical
stress which may occur during outdoor storage, or loading and unloading operations. The enclosure used
for this purpose shall be constructed so as to allow for stripping down of the unit, enable receival
inspection and maintenance preservation to be carried out and be provided with hatches for access for
lifting, hook-up of piping, electrical/instrument cabling and tubing, without dismantling the entire enclosure.

Note: Under no circumstances shall preservation products containing hazardous chemicals be used.

2.2 Special instructions for electrical and electronic equipment


All electrical and electronic equipment exposed to humidity shall be protected with vapour corrosion
inhibitor VCI, according to Manufacturers recommendation.

Insulation resistance:

All electrical equipment shall have the insulation resistance measured for motors, heaters, generators,
converters and transformers". Measurements shall be recorded on preservation record EP-01.
Measurements must be taken and recorded not more than 1 month prior to delivery date.

2.3 Special instructions for instrument equipment


Instrument equipment containing electronic components shall be protected with vapour corrosion inhibitor
VCI or equivalent, according to Manufacturers instructions.

Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 4 of 10
Requirements: Preservation requirements for Supplier packages Classification: Internal

All openings in hydraulic/pneumatic tubing shall be provided with steel caps or solid shank steel plugs
compatible with the metallurgy of the component being capped or plugged. Non-metallic plugs shall not be
used.

Gaskets/O-rings on instrument equipment to be greased with acid free vaseline.

2.4 Special instructions for mechanical equipment


The Mechanical discipline covers the following disciplines: Piping, HVAC, Safety, Architectural, Surface
protection, Insulation and Structure.

Bolts used for temporary blinds shall not cause corrosion on equipment.

All exposed unpainted machined surfaces shall be coated with preservation wax.

Coat all carbon steel flanges on gasket faces, including access hatch covers with preservative wax

Prepare a mixture of vci and oil in pump housing/gear house to avoid corrosion, according to inhibitor
manufactures recommendation and supplier preservation instuction

Open flexible hose connections to be plugged.

Any additional heating or vapour corrosion inhibitor requirements within temporary enclosures for sensitive
equipment shall be adhered to.

Greased bearings to be greased. Check Sub-Supplier information.

On insulated units, where the insulation could be exposed to damage during storage or installation, the
insulation shall be protected with 10 mm plywood sheets.

2.5 Documentation

2.5.1 Preservation record


The Preservation Records will, after being filled in and signed by Supplier in ProCoSys and verified by
Company or his Representative, document that preservation is performed in accordance with the projects
requirements.

One of the following codes will be given on the Preservation Record:

Status "OK"
This status means that the Supplier has completed the check items and there is no further work
associated with these inspections.

Status "PA"
This means that the Supplier has not completed all work or checks associated with this tag. "PA" means in
principal that work must be completed prior to delivery. If the supplier is unable to complete the work prior
to delivery, acceptance of the applicable equipment must be agreed with Company or his representative.

The outstanding work or checks shall be recorded on a Punch List by clicking on the Punch List button on
the screen and fill in the information.

If an inspection item on the Preservation Record is not applicable for the Supplier, the Supplier shall mark
this item with “NA”

Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 5 of 10
Requirements: Preservation requirements for Supplier packages Classification: Internal

Standard Preservation Records and Maintenance Check Lists are available. See forms included in
Appendix A.

2.5.2 Preservation documentation


Supplier is responsible for attaching the Preservation Documentation into ProCoSys when all initial
preservation activities are physically completed.

The Preservation Documentation shall include:

• Material safety datasheets for preservation products being used


• Supplier extra Preservation requirements
• Procedure for removal of preservation products used
• Supplier instruction for preservation during construction at fabrication site

3 Additional information

3.1 Definitions and abbreviations


Company
Company means the Equinor project organization responsible for executing the Project.

Preservation
Preservation means that the equipment and systems are protected against potential external and internal
deterioration.

Initial preservation
Initial preservation means application of specified preservatives and fitting of specified protection to any
equipment/system by Suppliers prior to delivery to maintain the equipment/system unimpaired.

Preservation maintenance
Preservation maintenance means periodic maintenance to keep the initial preservation intact and
maintained in accordance with Company or his Representative's and Suppliers preservation requirements.

Preservation records
The preservation records form the basis for documentation of preservation during all phases of a project.
For each of the three main disciplines; Mechanical, Electrical and Instrument, standard preservation
records have been developed. Piping, HVAC, Insulation, Surface Protection, Structural and Safety are
included in Mechanical discipline.

Supplier extra preservation maintenance requirements


Any extra preservation requirements, to keep initial preservation intact and functioning during storage and
fabrication period.

3.2 Changes from previous version


Minor changes in section 2

Small change from version 2 to version 2.01 in section 2.2.

3.3 References
“Project development” (FR05) (Equinor/All locations/On- and offshore)
“Preservation Manual” (WR2364) (Equinor/All locations/On- and offshore)

Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 6 of 10
Requirements: Preservation requirements for Supplier packages Classification: Internal

App A Available preservation records and check lists

A.1 Mechanical Preservation Record and Preservation Maintenance Check List


MP01 Preservation Record Mechanical

Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 7 of 10
Requirements: Preservation requirements for Supplier packages Classification: Internal

Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 8 of 10
Requirements: Preservation requirements for Supplier packages Classification: Internal

A.2 Electrical Preservation Records and Preservation Maintenance Check List


EP01 Preservation Record Electrical

Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 9 of 10
Requirements: Preservation requirements for Supplier packages Classification: Internal

A.3 Instrument Preservation Record and Preservation Maintenance Check List


IP01 Preservation Record Instrument

Project development (PD), Technical and professional requirement, TR2343, Final Ver. 2.03,
published 2019-05-10
Page 10 of 10