SARANA PRASARANA TAHAP-2 PANCANAKA GREEN SEMESTA

No Pekerjaan Volume Harga Satuan Jumlah Harga


A Cut & Fill 16.897 M2
1 pengukuran awal 1 ls -
2 Moob Demob 1 ls -
3 Cut & fill alat berat (excavator doser ) 30 hari -
4 sewa dump truck (asumsi 2 truck) 20 hari -
-
B Jalan -
1 Urugan Sirtu (tebal =25cm) jalan orion 156 m3 600,000.00 93,600,000.00
2 Urugan Sirtu (tebal =25cm) cluster orion II 128 m3 600,000.00 76,800,000.00
3 Urugan Sirtu (tebal =25cm) cluster orion III 148 m3 600,000.00 88,800,000.00
4 Urugan Sirtu (tebal =25cm) cluster aldebaran V 114 m3 600,000.00 68,400,000.00
5 Urugan Sirtu (tebal =25cm) jl. Auriga 184 m3 600,000.00 110,400,000.00
6 Kanstien jalan orion 141 m1 135,000.00 19,035,000.00
7 Kanstien jalan cluster orion I 86 m1 135,000.00 11,610,000.00
8 Kanstien jalan cluster aldebaran IV 60 m1 135,000.00 8,100,000.00
9 Kanstien jalan cluster orion II 194 m1 135,000.00 26,190,000.00
10 Kanstien jalan cluster orion III 210 m1 135,000.00 28,350,000.00
11 Kanstien jalan cluster aldebaran V 155 m1 135,000.00 20,925,000.00
12 Kanstien jalan Auriga 183 m1 135,000.00 24,705,000.00
13 Kanstien taman sekitar gerbang masuk 62 m1 135,000.00 8,370,000.00
14 Paving jalan orion 623 m2 150,000.00 93,450,000.00
15 Paving jalan cluster orion I 276 m2 150,000.00 41,400,000.00
16 Paving jalan cluster orion II 511 m2 150,000.00 76,650,000.00
17 Paving jalan cluster orion III 593 m2 150,000.00 88,950,000.00
18 Paving jalan cluster aldebaran V 455 m2 150,000.00 68,250,000.00
19 Paving jalan Auriga 736 m2 150,000.00 110,400,000.00
-
C Jembatan -
C.1 Saluran Plat Duiker -
1 Saluran Plat Duiker Area Jalan orion 36 m1 350,000.00 12,600,000.00
2 Saluran Plat Duiker Area cluster orion II 6 m1 350,000.00 2,100,000.00
3 Saluran Plat Duiker area cluster orion III 6 m1 350,000.00 2,100,000.00
4 Saluran Plat Duiker cluster aldebaran IV 6 m1 350,000.00 2,100,000.00
5 Saluran Plat Duiker cluster aldebaran V 14 m1 350,000.00 4,900,000.00
6 Saluran Plat Duiker cluster Auriga 12 m1 350,000.00 4,200,000.00
78 -
C.2 Gorong-gorong -
1 jalan orion I -
Bis Beton Ø 60 87 m1 500,000.00 43,500,000.00
2 jalan aldebaran IV -
Bis Beton Ø 60 54 m1 500,000.00 27,000,000.00
3 cluster orion -
Bis Beton Ø 60 120 m1 500,000.00 60,000,000.00
4 cluster orion II -
Bis Beton Ø 40 194 m1 400,000.00 77,600,000.00
5 cluster orion III -
Bis Beton Ø 60 103 m1 500,000.00 51,500,000.00
6 cluster aldebaran V -
Bis Beton Ø 60 106 m1 500,000.00 53,000,000.00
7 cluster Auriga -
Bis Beton Ø 60 108 m1 500,000.00 54,000,000.00
-
C.3 Bak Kontrol -
ukuran 60x60 42 bh 500,000.00 21,000,000.00

Total 1,479,985,000.00