Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

SITE 05-03

page 1 of 1
Inspection Request (IR)
Project Title Nesma & Partners Co. PMC AECOM
Construction Pace 322122
Supervision Contract No.
Consultant
Contractor Nesma & Partners Co. IR Number
Revision 00 Date 10 / Sep / 2022
To: Construction Supervision Consultant
The following items are ready for your inspection on: time 09 : 00 AM date ______
11 / ______
Sep / __________
2022

Shop Drawing Ref. CPM Activity No.


District Area Plot 09
Level Basement Axis As per highlighted plan
Appd. Method Statement ITP AVR-NP-PACE-ITP-C-002/R00
Description

Inspection to check the form work and Blinding concrete @Footing Area plot no 09.

Attachments EXCAVATION LAYOUT PARTIAL PLAN


We certify that the above items have been coordinated by the following:

Electrical Work FF & PH Work HVAC Work


IR No. IR No. IR No.
name and signature name and signature name and signature

Elevators Work Others Work


IR No. IR No. IR No.
name and signature name and signature name and signature

Site Engineer Quality Control Engineer Project Manager


name and signature name and signature name and signature

Received by Construction name and signature date


/ /
Supervision Consultant
Construction Supervision Consultant’s comments

Approval: Approved Not Approved Approved, as Noted


name and signature date
Received by Contractor / /
Construction Supervision name and signature date
/ /
Consultant
*All requests must be submitted at least 24 hours prior to the required inspection time.
Distribution: Employer Project Director Contractor PMC