Professional Documents
Culture Documents
IDS1 ServiceMAn Deutag
IDS1 ServiceMAn Deutag
IDS1 ServiceMAn Deutag
Top Drive
Drilling
System
Service Manual
SM00420
December 9, 1997
ii IDS-1 Contents
Contents
Book 1 – Description
Preface/Manual conventions
Safety information ........................................................... 1-5
Directional references ...................................................... 1-6
Manual layout.................................................................. 1-6
Chapter 1 Introduction
General description .......................................................... 1-7
iv IDS-1 Contents
Book 2 – Installation and commissioning
Preface/Manual conventions
Safety information ........................................................... 2-5
Directional references ...................................................... 2-6
Manual layout.................................................................. 2-6
Chapter 1 Installation
Installing the IDS-1 ......................................................... 2-7
Rig floor .................................................................... 2-7
Derrick ...................................................................... 2-9
Torque tube assembly .............................................. 2-11
Preinstallation checklist.................................................. 2-12
IDS and torque tube rig-up procedure ........................... 2-14
Installing the pipehandler ........................................ 2-19
Installing the cooling system .................................... 2-22
Installing the rotary hose .......................................... 2-22
Traveling block dolly rig-up procedure .......................... 2-23
Plumbing ....................................................................... 2-24
Air ........................................................................... 2-24
Derrick electrical termination ........................................ 2-25
Driller’s controls and instrumentation ........................... 2-26
Driller’s console ....................................................... 2-26
Throttle and torque limit controls ........................... 2-26
Wiring ..................................................................... 2-26
Service loops .................................................................. 2-28
Installation ............................................................... 2-28
Electrical loop .................................................... 2-29
Chapter 2 Commissioning
Checkout procedure....................................................... 2-31
Long term IDS storage procedures ................................. 2-33
Returning the IDS to service after storage ...................... 2-34
IDS installation checklists (FIP 0001) ............................ 2-34
IDS-1 Contents v
December 9, 1997
Book 3 – Operation
Preface/Manual conventions
Safety information ........................................................... 3-5
Directional references ...................................................... 3-6
Manual layout .................................................................. 3-6
Preface/Manual conventions
Safety information ........................................................... 4-7
Directional references ...................................................... 4-8
Manual layout.................................................................. 4-8
Chapter 1 Inspection
Inspecting the DC drilling motor .................................... 4-9
Inspecting the air exhaust muffler .................................. 4-10
Inspecting the derrick termination kit air
filter/regulator/lubricators .............................................. 4-11
Inspecting the pipehandler ............................................. 4-12
Nondestructive Examination (NDE) ............................. 4-13
Visual inspection...................................................... 4-13
Inspecting the elevator link eyes ......................... 4-13
Inspecting the torque tube ................................. 4-13
Inspecting the landing collar .............................. 4-15
Magnetic particle inspection .................................... 4-16
Ultrasonic inspection ............................................... 4-17
Inspecting safety valves....................................... 4-17
Inspecting the shaft liner assembly ................................. 4-18
Chapter 2 Lubrication
Lubricating the block ..................................................... 4-20
Lubricating the wash pipe assembly ............................... 4-21
Lubricating the cooling system ....................................... 4-22
Lubricating the drilling unit assembly ............................ 4-22
Lubricating the gearbox assembly ............................. 4-22
Initial oil change period ........................................... 4-22
Oil capacity.............................................................. 4-23
Lubricating the DC motor ....................................... 4-24
Lubricating the hydraulic system.................................... 4-27
Lubricating the alignment strut assembly ....................... 4-28
Lubricating the rotating head ......................................... 4-29
Lubricating the solid body elevator ................................ 4-30
Lubricating the safety valve actuator .............................. 4-31
Lubricating the upper IBOP safety valve ........................ 4-32
Lubricating the carriage assembly ................................... 4-32
Chapter 3 Maintenance
Adjusting the hydraulic assembly ................................... 4-41
Adjusting the counterbalance system .............................. 4-44
Adjusting the torque wrench .......................................... 4-46
Upper safety valve (IBOP) and safety valve
actuator system .............................................................. 4-48
Assembly and disassembly .............................................. 4-49
Pipehandler (PH-60d) ............................................. 4-49
Torque wrench disassembly ............................... 4-49
Replacing the torque wrench clamping
piston seal .................................................... 4-51
Replacing the front and rear piston seal........ 4-51
Replacing the rotating head glyd ring ................. 4-54
Replacing the extended reach link tilt
air actuator ......................................................... 4-57
Removing the tong die ............................................. 4-60
Front jaw ........................................................... 4-60
Rear jaw ............................................................. 4-60
Removing the jaws ................................................... 4-61
Front jaw ........................................................... 4-61
Rear jaw ............................................................. 4-61
IBOP assembly/disassembly ..................................... 4-61
Counterbalance system assembly/disassembly .......... 4-62
Carriage assembly/disassembly ................................. 4-64
Wash pipe assembly/disassembly .............................. 4-66
Shaft liner assembly/disassembly .............................. 4-67
Replacing/installing the seal ............................... 4-69
Alignment strut assembly/disassembly...................... 4-73
Local blower cooling system assembly/disassembly ... 4-75
Brake assembly/disassembly ..................................... 4-77
Hydraulic power unit assembly/disassembly ............. 4-78
Removing the drilling motor assembly ..................... 4-79
Replacing the safety wiring ............................................ 4-82
Safety wiring tips ..................................................... 4-84
IDS-1 Contents ix
December 9, 1997
x IDS-1 Contents
IDS-1
Integrated
Drilling
System
Description
December 9, 1997
Chapter 1 Introduction
General description .......................................................... 1-7
Safety information
Information pertaining to possible personnel injury and
equipment damage appears throughout this manual and is
formatted to draw the reader’s attention to important
information, a warning, or a caution note. See the examples
below and pay close attention to these important advisories.
Directional references
References to the right or left and front or back of components
described in this manual assume the perspective of the top drive
drilling system (IDS-1), standing behind the IDS-1 as it faces well
center.
Manual layout
This binder contains several separate books that you can remove
individually for convenience.
General description
Oil well drilling with a rotary table, kelly drive bushing, and a 45
ft. kelly was the industry standard for years. For decades the
driller extended the drill string using the “make-a-single-
connection” process with the rotary table, kelly, pipe tongs,
drawworks cathead, master bushing and bowls, and slips. Apart
from minor improvements, such as kelly spinners, this method of
handling pipe and joint makeup remained unchanged until the
advent of top drive drilling systems.
Varco produces an Integrated Drilling System (IDS) that rotates
the drill string and allows the addition of entire 93 ft. stands of
pipe. This eliminates two thirds of the conventional single-pipe
drilling connections.
The IDS integrates the drill pipe connection handling and drive
systems with the traveling block (Figure 1-1). It uses a torque
tube instead of traditional guide rails and bracing. The IDS
connects directly to the traveling block, thus eliminating the
drilling hook and shortening the IDS working height.
Crown Out
500 Ton Torque
Integrated Tube
Block Extended Support
Air Intake Bracket
Block Top
Torque
8 in Flex Tube
Cooling Duct
114 in.
500 Ton
Bail Rest Integrated Swivel Connection
Gooseneck Links
(Special)
C'Balance Torque
System Tube
Dolly
G.E. 752
Hi-Torque Torque
D.C. Motor Reaction
Arm
Planetary Bottom
Drive Train Torque
Gearcase Reaction
Mud Line Beam
Flange
Rotating
Head
Solid Body
Link Elevator
Tilt
IBOP
Actuator
Electrical (Remote)
& Fluids
Service Loops
Tool Joint 108 in.
350 Ton
Links
350 Ton
D/P Elevator
Drill Floor
Rotating head
The rotating head transfers pneumatic and hydraulic pressure
from stationary ports on the IDS drilling motor housing to
rotating ports on the rotating head (Figure 1-3). It features two
hydraulic passages, three pneumatic passages, and two spare
passages capable of transferring either pneumatic or hydraulic
fluid. All are rated at 2,000 psi.
The rotating head assembly consists of:
❏ A stationary flange
❏ Eight rotary glyd rings
❏ A swivel block
❏ A cam
❏ A return cylinder
❏ A cam follower
❏ Swivel block locking mechanism
Stationary Flange
Cam
Follower
Cam
Auto-Return
Cylinder
The hydraulic and air lines for the various pipe handler functions
(link tilt, torque wrench, etc.) run from their respective solenoid
valves to the stationary flange. The fluids travel from the flange to
the swivel block via sealed rotating passages.
Additional hoses connect the ports in the swivel block to the
corresponding devices (link tilt, etc.). The swivel block rotates
relative to the flange without twisting or damaging any hoses.
There is a lug for mounting the torque wrench hanger and holes
for attaching the torque arrestors on the swivel block.
The rotating head stationary flange bolts directly to the bottom of
the gearcase with the drive stem running through the center. A
return cylinder is also mounted on the stationary flange. The
return cylinder is hydraulically connected to the counterbalance
manifold. The rod end of the cylinder connects to a cam follower
assembly that tracks the cam mounted to the swivel block.
Counterbalance system
The counterbalance system prevents damage to tool joint threads
while making or breaking connections with the IDS. The IDS offsets
the weight of the drilling unit while stabbing into a connection. It
provides a cushioned stroke similar to that provided by the hook.
The counterbalance system (Figure 1-4) consists primarily of two
hydraulic cylinders and a counterbalance manifold. The hydraulic
cylinder assemblies connect the motor housing assembly with the
traveling block.
When properly adjusted, the counterbalance system supports all
but about 800 lb of the weight of the IDS over a full 8 to 10 in.
of travel.
When adding a stand to the string during drilling operations, the
driller takes a stand in the elevators and stabs it into the box in
the rotary. The driller continues to lower the IDS until the saver
sub touches the box of the new stand. At this point, only about
800 lb load is on the saver sub or drill pipe connection. The
counterbalance cylinders support the remainder of the IDS
weight. The driller then spins in and torques up the connection
and is ready to drill ahead. The system is preadjusted. Once
drilling resumes, the hydraulic power unit (HPU) can be turned
off and restarted for breaking out the connection at the floor after
drilling the stand down.
Becket
(Ref.)
Hydraulic Cylinder
Assemblies (2)
Motor Housing
(Ref.)
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,, Extended Air Intake Assembly
Explosion-Proof,
20 hp, 3450 rpm
Flexible Duct Hose AC Motor
Impeller
Housing Blower
Mount
Blower
Impeller
Bonnet
Intake
Duct
Drilling
Motor
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
Transition
Duct
Figure 1-5. IDS-1 local blower cooling system with extended air intake
The pipe handler provides two functions for IDS drilling systems:
Torque Arrestors
Rotating Head
Link Tilt
Safety Valve
Actuator
Torque Tube
Lower IBOP (inside)
Torque Wrench
Standard
350-Ton Links
Standard 350-Ton
Center-Latch BNC
Drill Pipe Elevator
Rotating Head
Assembly
Torque Arrestor
Assembly
Torque Arrestor
Assembly
500-Ton
Solid Body
Elevator
Solid Body
Elevator
Split Plate
Assembly
e Saver subs are load bearing components in IDS drilling systems and
must be inspected periodically along with other load bearing
components. See the Maintenance and Troubleshooting book for
more information.
DriveStem
(Ref.)
Solid Body
Elevator
Landing Collar
Actuator
Arm
Upper IBOP
Torque Tube
Lower IBOP
Saver Sub
Torque wrench
The torque wrench provides a means for making and breaking
out connections with the IDS drive stem. The torque wrench
assembly consists of (Figure 1-9):
❏ A hanger
❏ A torque tube
❏ A torque tube guide ring
❏ Two torque cylinders
❏ A clamping jaw
❏ A clamping piston
❏ A control manifold
❏ A lifting cylinder
❏ Two tube stops
❏ A stabbing guide
A hanger attached to the rotating head supports the torque
wrench. The torque wrench has two torque cylinders connected
to the torque tube.
The gripping jaw contains a 10 in. diameter clamping piston for
gripping the box end of the drill pipe. The torque tube contains a
female spline that engages a male spline on the lower section of
the upper IBOP during operation of the torque wrench.
Actuating the torque wrench raises it, engaging the splines on the
upper IBOP. From the control manifold it then receives
sequenced pressure to clamp the clamping piston on the box
connection. After the clamping pressure develops, another
sequence valve automatically opens and directs pressure to the
torque cylinders. The torque cylinders can rotate up to 25° while
developing a maximum torque of 60,000 ft lb.
An electrical push button on the driller’s console controls the
torque wrench operation. The driller presses the button until the
connection is made or broken. The driller then releases the
button and the unit automatically recycles to the READY
position. A two-position, directional control valve located on the
drilling unit adjusts the cycle.
The torque wrench can also make up or break out the saver sub
or lower IBOP. A manually operated valve on the rear of the pipe
handler selects either the makeup or breakout function.
IBOP Actuator
Hoses (Air)
Hanger
Torque Wrench
Hoses (Hydraulic)
Lift Cylinder
IBOP Actuator
Air Cylinders
IBOP Actuator
Arms
Stop Tube
Torque Tube
Torque Wrench
Manifold (Hidden)
Double Air
Actuator
Intermediate
Stop D/P Elevator
Link Clamp
Intermediate
Stop Release
Elevator links
Varco elevator links attach to the solid body elevator and support
the drill pipe elevator. Elevator link options include:
❏ Link tilt
❏ Remotely controlled IBOP valve
❏ Motor brake
❏ Motor spin-torque control
❏ Makeup torque limit
❏ Transfer switch (RT/IDS)
❏ Link position
Optional controls and status indicator lights are available.
Service loops
The service loops transfer the required electric and fluid services
between the derrick service stand pipes and junction boxes and
the corresponding junction boxes and fluid connections located
on the IDS. Of the two loops, one contains the electric cables,
and one contains air and hydraulic lines.
The electric loop contains four 646 MCM DC power cables, one
2/0 AWG drilling motor ground cable, and a composite cable
consisting of:
Optional equipment
Optional and auxiliary equipment is compatible with all IDS
models. All equipment is selected or adapted for your specific rig.
Some of the options include:
Q.D. Coupler
Air Cylinder
(2)
Relief Valve
Q.D. Coupler
Slip Assembly
(4)
Bowl Assembly
Guide Ring
Drill Pipe
Elevator
Drill Collar
Dolly
A
100 TON
VARCO
Perfection
, ,,,
,,,
,,, ,
,,,
Links (36")
91"
Square
Shoulder
Elevator
Lifting
Sub
37"
Drill
Collar
Wireline adapter
The wireline adapter (Figure 1-15) attaches to the pipe handler
and prevents wireline interference from damaging pipe and IDS
components. It can be used with a lubricator held in the elevators
by using 180 in. long casing elevator links.
View A-A
9/16 in. Max.
Wire Rope Dia.
Top Drive
Torque Wrench
20 in. Dia.
Sheave
Elevator Links
(180 in. long-
Customer furnished)
Elevator Links
(180 in. or longer-
Customer furnished)
View A-A
IDS specifications
Drilling motor/gearcase
Output horsepower 1,000 hp
Continuous torque 34,000 ft lb
Speed 155 rpm
Intermittent torque 38,100 ft lb @
1,400 Amps (for makeup)
Connections NC50 unless otherwise
specified
Water course 3 in. (76.2 mm)
Motor brake 38,700 ft lb @ 1,000 psi
Pipehandler
Breakout torque 60,000 ft lb
Hydraulic pressure 2,000 psi maximum
Hydraulic flow 30 to 35 gpm
Air pressure 90 psi minimum
Service loops
Electrical power cables (non-regulated areas)
4 x 646
Voltage 2,000 max
Length 86 ft. (flange to flange)
Composite cable 26 conductor, 14 gauge
4 conductor, 8 gauge
2 pair, 14 gauge
twisted and shielded
2 conductor, 5 gauge
1 pair, 6 gauge
twisted and shielded
Voltage 600 maximum
Ground cable 2/0 conductor tinned
copper ground
Diameter 5 in. ID SAE 100-R2
hose outer jacket
Fluids
Hydraulic pressure or return hose (3 total)
Length 86 ft. (flange to flange)
Size 3/4 in. ID, SAE 100-R9
Working pressure 3,000 psi
Air supply hose (2 each)
Size 1/2 in. ID, SAE 100-R2
Working pressure 150 psi
Maximum working pressure 3,500 psi
40,000
38,700 INTERMITTENT
1,000 H.P.
35,000
34,000 CONTINUOUS
TORQUE, CONTINUOUS (FT-LBS)
30,000
25,000
20,000
16,300 CONTINUOUS
15,000 REDUCED FIELD
REQUIRED
10,000
0
0 50 100 150 200 250 300
RPM
INTERMITTENT TORQUE VALUES ARE BASED ON 1,450 ARMATURE AMPS
WITH A 7 SECOND MAXIMUM DURATION AT FULL FIELD OF 57 AMPS.
May 12, 1994. A.N.
Installation
December 9, 1997
Chapter 1 Installation
Installing the IDS-1 .......................................................... 2-7
Rig floor ..................................................................... 2-7
Derrick ....................................................................... 2-9
Torque tube assembly ............................................... 2-11
Preinstallation checklist................................................... 2-12
IDS and torque tube rig-up procedure ............................ 2-14
Installing the pipehandler ......................................... 2-19
Installing the cooling system ..................................... 2-22
Installing the rotary hose ........................................... 2-22
Traveling block dolly rig-up procedure ........................... 2-23
Plumbing ........................................................................ 2-24
Air ............................................................................ 2-24
Derrick electrical termination ......................................... 2-25
Driller’s controls and instrumentation ............................ 2-26
Driller’s console ........................................................ 2-26
Throttle and torque limit controls ............................ 2-26
Wiring ...................................................................... 2-26
Service loops ................................................................... 2-28
Installation ................................................................ 2-28
Electrical loop ..................................................... 2-29
Chapter 2 Commissioning
Checkout procedure........................................................ 2-31
Long term IDS storage procedures .................................. 2-33
Returning the IDS to service after storage ....................... 2-34
IDS installation checklists (FIP 0001) ............................. 2-34
Safety information
Information pertaining to possible personnel injury and
equipment damage appears throughout this manual and is
formatted to draw the reader’s attention to important
information, a warning, or a caution note. See the examples
below and pay close attention to these important advisories.
Directional references
References to the right or left and front or back of components
described in this manual assume the perspective of the top drive
drilling system (IDS-1), standing behind the IDS-1 as it faces well
center.
Manual layout
This binder contains several separate books that you can remove
individually for convenience.
Rig floor
Although many rig floor layouts are possible, installing the torque
tube on the drawworks side of the derrick, or mast, and opposite
the V-door is an ideal arrangement for handling tubulars from the
V-door (Figure 2-1).
The location of the service loops and mud hose is an important
installation consideration for setback purposes, to ensure proper
clearance and to help prevent wear to the service loops and mud
hose. Other important installation considerations include the
location of:
C
L STANDPIPE
WELL MANIFOLD
75 FT MUD HOSE
WINCH
RATHOLE
DRAWWORKS
MOUSEHOLE
VEE DOOR
RAMP
CL CL
WELL WELL
IDS
SETBACK AREA
WINCH
DRILLER'S
CONSOLE
CL
WELL
Derrick
The IDS interfaces with the rig’s hoisting system and electrical
power system. Derrick and electrical system modifications are
required when installing the IDS on existing rigs.
For derricks that handle triples, the required swivel travel is about
100 ft. compared to about 75 ft. when using a kelly. It is
necessary to replace the regular rotary hose (which is normally 60
ft. long) with a 75 ft. hose. Extend the standpipe height to 73 ft.
to correctly position the hose loop. Position the hose loop about 7
ft. above the drill floor when the connection height is 4 ft. above
the rig floor.
Derrick height is a critical interface requirement. The integrated
drilling system has a length of about 29 ft. from the base of the
drill pipe elevator to the top of the integrated traveling block (500
ton). Handling a 93 ft. stand typically requires 97 ft., resulting in
an overall height from the floor to the top of the integrated
traveling block of 126 ft.
Derrick Derrick
Clear working height Crown clearance
152 ft. 26 ft.
147 ft. 21 ft.
142 ft. 16 ft.
136 ft. 10 ft.
Each rig has different crown clearance for efficient tripping.
Figure 2-2 illustrates typical derrick height interface requirements.
Installing the IDS with existing traveling equipment may require
an adapter, further reducing crown clearance.
Crown Out
21.34' Crown
Crown
Clear
Block Top
Block
147.64'
IDS Unit
Clear
83' Working
Service Height Bottom Torque
Loop Reaction Beam
Bracket
73'
Mud
Standpipe 93.0' 3'
Stand
12'
Off-Bottom
Drill Floor
Tool Joint
7.0' Min
Drill Floor 4 0'
Preinstallation checklist
The following assumes that all preinstallation planning and rig-up
is complete prior to installation of the torque tube assembly and
integrated drilling system (IDS). This includes:
,
9-1/2"
,
1-1/2"
,
,
18"
12"
A A
SECTION A-A
Torque Tubes
Connected
14. Tie snub-off lines to the drilling unit to keep the drilling unit
stable.
15. Slack off the blocks and remove the hoisting slings.
16. Attach the block links to the gearcase lifting ears on the
drilling unit. Secure the catch links.
17. Attach the counterbalance cylinder clevis to the lugs on the
IDS drilling motor.
18. Hoist slightly so the block links just contact the gearbox
lifting ears.
27. Lower the top torque tube approximately 1 in. above the true
alignment of the forward hinge bores. Use the 5 ft. pry bar in
the back of the installation guide to align the section and
insert a pivot pin.
e Align the flats on the head of the pivot pin and the forward hinge
bore throughout the insertion. Do not lift the torque tube until the
head of the pivot pin is fully seated in the counter bore. To prevent
damage to the pins and bores avoid using a sledge hammer to install
the pins.
28. Slightly raise the IDS assembly using the drawworks. Remove
the guide rod and grease the bore of the taper pin.
29. Continue to raise the IDS assembly until the torque tube
clears the drill floor.
30. Install a taper pin while pushing the torque tube back into
position.
e Varco recommends having rig floor personnel in a riding belt install the
taper pin. If the torque tube is slightly rocked, install the pin by hand. To
prevent damage to the pins and bores avoid using a sledge hammer to
install pins.
31. Repeat steps 24-30 for each subsequent torque tube section.
32. Attach the top torque tube section to the crown bracket using
the supplied hardware.
33. Lower the IDS assembly to relieve pressure on the chock
assembly. Unpin the lock assembly, rotate it back and pin it
back into the stored position.
34. Pin the bottom section of the torque tube to the reaction
beam.
35. Slide the solid body elevator onto the drive stem and support
it up against the rotating head with adequate rigging and an
air winch. Be certain the link tilt mounting bosses are
opposite the torque wrench mounting clevis on the rotating
head.
Torque Tube
Top Bracket
Hanger
Link
Chain
Shackle (4)
Link
Top
Section
Retaining
Pin (6)
Taper
Pin (6)
Intermediate
Section (5)
Bottom
Section
Pivot
Pin (6)
Figure 2-4. Typical torque tube with pinned connections derrick/mast interface
O-Ring
Split Landing
Collar (2)
Drive Stem
500-Ton
Rotating
Head
Link Tilt
Torque
Arrestors
500-Ton
Solid Body
Elevator
Splined
Upper Solid Body
Safety Elevator
Valve Split Plate
Safety Valve
Actuator
Torque
Wrench
Elevator
Links
Saver Sub
Drill Pipe
Elevator
n Never operate the top drive with the exhaust duct covers
attached to the spark arrestors on the air exhaust ducts. Doing
so severely restricts air flow through the motor, causing
overheating and potential damage. They can also fall off
during operation and injure personnel working below. Attach
the covers only during shipping and storage.
z Verify that mounting holes have been predrilled and tapped prior
to installing the traveling block dolly.
1. Lower traveling block to rig floor.
2. Install both dolly mounting pads to the traveling block using
four 1.25 in. bolts and lockwashers per mounting pad.
3. Safety wire the bolts per the procedure described in the
Maintenance and Troubleshooting book.
4. Install the block dolly to the traveling block by attaching
dolly/arms and pins to the mounting pad.
5. Install pin retainers to the top of the dolly pins using 5/8 in.
bolts and safety wire.
6. Slowly hoist the traveling block while guiding the dolly into
the torque tube.
Plumbing
The plumbing connections should terminate near the service loop
bracket. The hoses at the end of the service loop may be as short
as 12 ft. The mating halves are pre-assembled on the service loop.
Specifications for specific lines is described in the following
section.
Air
Air lines should be schedule 40, 1 or 1 1/2 in. pipe in the case of
the purge supply for the IDS. Install a shut-off valve at drill floor
or racking board level. The air lines connect to the filtered and
lubricated supply. The derrick connections are reduced to 1 in.
NPT female for the purge line (if required) and 1/2 in. for the air
line in order for the fluids service loop to match.
Driller’s console
This unit contains all of the unique IDS controls, along with
gauges indicating output torque, and output rpm.
Mount the driller’s console within easy reach and in plain view of
the driller while the drawworks brake and clutches are being
operated. The gauges must be easily seen by the driller during
drilling operations. Provide appropriate cable glands for the
electric cables.
Wiring
Refer to the engineering drawings for the electrical schematics.
IDS
Control
Console
IDS
Blower
MCC
Service
Loop IDS
SCR Motor
RT
RT Blower
Motor
Electrical Rotary Table
IDS
Control
Console
Drill Floor Derrick
Connections Connections
Transfer Instrument
Panel J-Box
IDS
Blower
MCC
Service
Loop IDS
SCR Motor
DW-B
DW-B Blower
Motor
Mechanical Rotary Table
Service loops
Installation
Install the service loops as follows:
1. Fabricate the appropriate brackets and clamps to attach the
service loop mounting bracket to the derrick structure.
2. Place the service loop derrick mounting bracket at the height
specified on the derrick interface engineering drawing. Locate
it on the side of the derrick adjacent to the brackets on the
IDS and as far as practical away from well center to allow an
adequate bend radius for the service loops. The bracket must
be located far enough from the corner of the mast or derrick
to ensure that the loops do not catch under the torque tube
during operations, but far enough back to provide clearance
for tong lines, the stabbing board, tugger lines, etc.
3. Do not unpack the service loops from the shipping protective
crate until they are ready to hang in the derrick. Lift the
service loops onto the pipe deck (still in the crates) and then
remove them from the crates with the lifting eyes provided.
Electrical loop
1. Connect the pre-terminated wire ends at the motor J-boxes
using the appropriate glands. Refer to the electrical schematic
provided to ensure proper terminal block assignments.
2 Connect the pre-terminated wire ends of the IDS service loop
to the pre-terminated ends of the stationary service loops (if
used) with connectors provided, or intor the derrick J-box.
3. Terminate the opposite end of the stationary service loop or
derrick cables to the transfer panel. Refer to the electrical
engineering drawing for proper connections.
Checkout procedure
1. Fill the gearbox with specified gear oil (Refer to the Lube
specification chart in the Mainenance and Troubleshooting
book).
2. Tighten the drilling unit shaft liner. Refer to the adjustment
procedure in the Mainenance and Troubleshooting book.
3. Momentarily turn on the IDS blower motor. Verify that the
direction of rotation is counterclockwise as viewed through
the motor louvers and verify the current.
4. Assign the SCR to the IDS and verify that the direction of
rotation is clockwise.
5. Turn on the HPU and adjust for 2,000 psi output pressure
and check for leaks.
6. Adjust the counterbalance system hydraulic as outlined in
Book 4. Verify that the counterbalance-mounted pressure
relief valve operates at 1,800 ± 100 psi.
7. Slowly raise the IDS with the drawworks and verify smooth
travel along the length of the torque tube. Also verify that
there is adequate clearance at the pipe racking level. Lower the
IDS to the rig floor level.
IDS-1 Installation 2-31
December 9, 1997
Operation
December 9, 1997
Safety information
Information pertaining to possible personnel injury and
equipment damage appears throughout this manual and is
formatted to draw the reader’s attention to important
information, a warning, or a caution note. See the examples
below and pay close attention to these important advisories.
Directional references
References to the right or left and front or back of components
described in this manual assume the perspective of the top drive
drilling system (IDS-1), standing behind the IDS-1 as it faces well
center.
Manual layout
This binder contains several separate books that you can remove
individually for convenience.
e The brake on the top end of the TDS drilling motor armature shaft is
a static, or parking brake. It is not a running or dynamic brake. It is
not intended to, nor is it capable of, slip-releasing the wind-up torque
in the drill string. Using the brake to slip-release the drill string
wind-up torque causes the brake to heat up and can destroy the brake
lining.
When the TDS motor brake holds the down-hole torque, Varco
recommends using the following procedure to safely release the
torque in the string:
1. Use the hand throttle to develop motor torque equal to the
wind-up torque held by the parking brake.
2. Release the parking brake.
3. Reduce the drill current, reducing motor torque, as the drill
string slowly releases the wind-up torque.
4. Turn the hand throttle off and reset the drill current to the
normal operating position after the pipe unwinds completely.
Counterbalance system
Pipehandler operation
Rotating head
To operate the swivel block locking mechanism, pull down the
locking lever, pulling the locking pin out of one of 24 locking
slots in the cam (Figure 3-1). With the locking lever in the
vertical position, manually rotate the swivel block to the desired
position and release the locking lever, setting the pin.
The perimeter of the cam is machined with an indented area
where the cam follower normally rests. The rod end of the cam
follower is under pressure. When the cam follower is located on
this indented area, the return cylinder rod is fully retracted. When
the swivel block and cam is rotated to another position by the
drill string, the ramp of the cam extends the return cylinder rod.
Releasing the elevator automatically returns the system to its pre-
selected (indented) position.
Stationary Flange
Cam
Follower
Cam
Auto-Return
Cylinder
DriveStem
(Ref.)
Solid Body
Elevator
Landing Collar
Actuator
Arm
Upper IBOP
Torque Tube
Lower IBOP
Saver Sub
Torque wrench
The primary function of the IDS torque wrench is to breakout
the drill string from the saver sub before making a connection.
The IDS torque wench can also make connections if necessary–
i.e., when replacing the lower IBOP or saver sub, or while
backreaming, or when adding a pup joint to the drill stem.
The torque wrench has a control manifold with the following
components (Figure 3-3):
Make/Break
Recycle Clamp Torque Valve
Sequence Sequence Sequence Torque
Valve Valve Valve Wrench
Manifold
20
10
00
B
RECYCLE CLAMP TORQUE
2500
500
PRV
30
0
Hydraulic
00
Pressure LIFT
Inlet LOWER
Lift/Lower
Flow Control
Valve
Pressure
Gauge
0 - 3000 PSI
Pressure Torque
(psi) (ft lb)
100 3,000
200 6,000
300 9,000
400 12,000
500 15,000
600 18,000
700 21,000
800 24,000
900 27,000
1,000 30,000
1,100 33,000
1,200 36,000
1,300 39,000
1,400 42,000
1,500 45,000
1,600 48,000
1,700 51,000
1,800 54,000
1,900 57,000
2,000 60,000
z P/N 78652-1 includes 3 1/2 in. IF saver subs, while P/N 78652-2
does not. By purchasing the latter, the user assumes responsibility
for obtaining appropriate 6 5/8 in. reg. x 3 1/2 in. IF saver subs
separately. Specifications for these are available from the factory or
any Varco service center.
Drilling ahead
10. Dope the saver sub pin and stop the spin out mode.
11. Open the drill pipe elevators.
12. Switch the IDS motor from reverse to FORWARD.
13. Hoist the IDS to the racking board level to get the next stand.
14. Thoroughly dope the box connection in the rotary table.
15. When the IDS is fully raised, extend the elevators to the
derrickman.
16. The derrickman latches the elevator on the next stand.
17. Hoist the pin off setback area and clear the box with the
stand.
18. Release the link tilt.
19. Stab the connection at the floor and set the backup tong.
20. Switch the IDS to SPIN IN mode.
21. Continue to slack off approximately two feet to stab the upper
connection of the stand with the IDS.
22. Slack off to allow connections to shoulder up (lead with the
drawworks, do not follow).
23. Switch to TORQUE and hold for approximately six seconds.
The makeup torque is pre-set.
24. Verify full makeup to the correct value on the torque meter,
and back up tong load cell.
25. Switch to DRILL mode.
26. Unlatch the back-up tong.
27. Open the IBOP.
28. Start the mud pumps.
29. Hoist and pull slips
30. Drill ahead.
December 9, 1997
Set slips on Unlatch elevator Pickup stand with Lower block to Pull slips
string Raise block elevator stab motor into Start circulation
Stop circulation Stab bottom of top of stand Begin drilling
IDS-1 Operation
1 2 3 4 5
Drilling ahead
December 9, 1997
Set slips on Unlatch elevator Pickup single with Lower block to Pull slips
string Tilt links to elevator stab motor into Open IBOP
Stop circulation mousehole Stab bottom of top of single Start circulation
IDS-1 Operation
Close IBOP Latch drill pipe single onto string Spin in motor Begin drilling
Breakout connection elevator around and single
using pipehandler single Makeup both
and drilling motor connections with
(in reverse) motor in
torque mode
Figure 3-5. Drilling ahead with singles
1 2 3 4 5
Tripping
Tripping
Perform tripping in the conventional manner. Use the link tilt
feature to tilt the elevator to the derrickman so the derrickman
can latch it around the pipe quickly.
The link tilt has an intermediate stop which is adjustable to set
the elevator at a convenient working distance from the monkey
board. Tilt the intermediate stop out of the way to allow the
elevator to reach the mousehole.
Unlock the rotation lock and rotate the pipehandler to position
the elevator in any direction. The elevator returns to its original
position if rotated by the drillstring.
When a tight spot or key seat is encountered while tripping, the
driller can spin the drilling motor into the stand at any height in
the derrick. Circulation and rotation can be established
immediately to work the pipe through the tight spot.
Reaming out
The IDS permits reaming out of an open hole to prevent pipe
sticking and to reduce key seat formation, without affecting
racking functions associated with normal tripping (i.e., there are
no singles to contend with). The pipehandler torque wrench can
break out 90 ft. stands in the derrick.
Use the following procedure to ream out of the hole (Figure 3-6):
1. Hoist the block while circulating and rotating the drilling
motor until the third connection appears.
2. Stop circulation and rotation and set the slips.
3. Break out the drilling motor from the top of the stand using
the pipehandler torque wrench. Hold a backup at the floor
and spin out the drilling motor.
4. Break out the stand at floor level using rig tongs and pipe
spinner.
5. Pick up the stand with the drill pipe elevator.
6. Rack the stand back.
7. Lower the IDS to the floor.
8. Stab the drilling motor into the box, spin up and torque it
with the drilling motor and backup tongs.
9. Resume circulation and continue reaming out of the hole.
Reaming out
3-25
1 2 3 4 5
December 9, 1997
Running casing
For casing operations, longer elevator links (180 in.) must be used
to allow clearance for the cementing head under the torque
wrench in the pipehandler. As long as the links, elevator, and
traveling block are rated for 500 tons, the IDS is rated at 500 tons
for casing operations.
By attaching a short piece of hose to the saver sub in the
pipehandler, the casing can be filled while lowering by using the
remotely controlled upper IBOP valve to start and stop the fluid
flow.
e Rotating the elevators with the IDS motor damages the landing
collar.
Maintenance
and
Troubleshooting
December 9, 1997
Chapter 1 Inspection
Inspecting the DC drilling motor .................................... 4-9
Inspecting the air exhaust muffler .................................. 4-10
Inspecting the derrick termination kit air
filter/regulator/lubricators .............................................. 4-11
Inspecting the pipehandler ............................................. 4-12
Nondestructive Examination (NDE) ............................. 4-13
Visual inspection...................................................... 4-13
Inspecting the elevator link eyes ......................... 4-13
Inspecting the torque tube ................................. 4-13
Inspecting the landing collar .............................. 4-15
Magnetic particle inspection .................................... 4-16
Ultrasonic inspection ............................................... 4-17
Inspecting safety valves....................................... 4-17
Inspecting the shaft liner assembly ................................. 4-18
Chapter 2 Lubrication
Lubricating the block ..................................................... 4-20
Lubricating the wash pipe assembly ............................... 4-21
Lubricating the cooling system ....................................... 4-22
Lubricating the drilling unit assembly ............................ 4-22
Lubricating the gearbox assembly ............................. 4-22
Initial oil change period ........................................... 4-22
Oil capacity.............................................................. 4-23
Lubricating the DC motor ....................................... 4-24
Lubricating the hydraulic system.................................... 4-27
Lubricating the alignment strut assembly ....................... 4-28
Lubricating the rotating head ......................................... 4-29
Lubricating the solid body elevator ................................ 4-30
Lubricating the safety valve actuator .............................. 4-31
Chapter 3 Maintenance
Adjusting the hydraulic assembly ................................... 4-41
Adjusting the counterbalance system .............................. 4-44
Adjusting the torque wrench .......................................... 4-46
Upper safety valve (IBOP) and safety valve
actuator system .............................................................. 4-48
Assembly and disassembly .............................................. 4-49
Pipehandler (PH-60d) ............................................. 4-49
Torque wrench disassembly ............................... 4-49
Replacing the torque wrench clamping
piston seal .................................................... 4-51
Replacing the front and rear piston seal........ 4-51
Replacing the rotating head glyd ring ................. 4-54
Replacing the extended reach link tilt
air actuator ......................................................... 4-57
Removing the tong die ............................................. 4-60
Front jaw ........................................................... 4-60
Rear jaw ............................................................. 4-60
Removing the jaws ................................................... 4-61
Front jaw ........................................................... 4-61
Rear jaw ............................................................. 4-61
IBOP assembly/disassembly ..................................... 4-61
Counterbalance system assembly/disassembly .......... 4-62
Carriage assembly/disassembly ................................. 4-64
Wash pipe assembly/disassembly .............................. 4-66
Shaft liner assembly/disassembly .............................. 4-67
Replacing/installing the seal ............................... 4-69
Alignment strut assembly/disassembly...................... 4-73
Local blower cooling system assembly/disassembly ... 4-75
Brake assembly/disassembly ..................................... 4-77
Hydraulic power unit assembly/disassembly ............. 4-78
Removing the drilling motor assembly ..................... 4-79
Replacing the safety wiring ............................................ 4-82
Safety wiring tips ..................................................... 4-84
Safety information
Information pertaining to possible personnel injury and
equipment damage appears throughout this manual and is
formatted to draw the reader’s attention to important
information, a warning, or a caution note. See the examples
below and pay close attention to these important advisories.
Directional references
References to the right or left and front or back of components
described in this manual assume the perspective of the top drive
drilling system (IDS-1), standing behind the IDS-1 as it faces well
center.
Manual layout
This binder contains several separate books that you can remove
individually for convenience.
Visual inspection
Upper
Eye
(Hook)
C
C
❏ Grooves or other radial wear marks indicating that the bore of the
solid body elevator is rubbing on the outside diameter of the
landing collar retainer shell
❏ Radial grooves on the inside diameter of the retainer shell
❏ Wear, corrosion, or fatigue cracks on the inside or outside
diameter of the landing collar halves
❏ Evidence of drive stem contact with the solid body elevator
❏ Evidence of inside bore wear on the solid body elevator
indicating contact with the drive stem. Wear on the inside
shoulder of the elevator should not exceed 1/8 in.
❏ Evidence of wear, corrosion or fatigue cracks on the safety
links
Replace the appropriate part(s) if any of the above conditions
exist. Use the following procedure to reassemble the landing
collar:
1. Replace the existing O-ring.
2. Install one new roll pin and safety links on the split landing
collar halves.
3. Coat the landing collar halves with a generous amount of
water resistant grease.
4. Place the landing collar halves on the drive stem with 15°
taper closest to the IDS.
5. Drive in the remaining roll pin.
6. Reinstall the IBOPs and pipehandler.
Ultrasonic inspection
In addition to the Magnetic Particle Inspection, Varco also
recommends performing an Ultrasonic Inspection of the above
components to detect any erosion of the inside diameter. Any erosion
reduces the load-carrying capability of the part. Any subsurface
irregularity can also compromise a component’s integrity.
Details on Ultrasonic Inspection procedures are in the
publication: ASTM A-388 Std. Practice for Ultrasonic Examination
of Heavy Steel Forgings.
e Because the shaft liner conducts drilling mud from the wash pipe to
the output stem through the hollow DC motor armature shaft, it is
subject to internal erosion and corrosion from the mud. Inspect it at
regular service intervals (about six months). Failure to regularly
inspect the shaft liner leads to drilling unit internal washout. If there
is little or no wear after the first inspection, extend the inspection
interval a reasonable length of time. Shaft liner wear is a function of
solids and pH control of the mud used. Some rigs report marginal
wear on shaft liners after two years of service.
Use the following procedure to visually inspect the shaft liner
assembly:
1. Remove the washpipe assembly from between the gooseneck
and the shaft liner. Both nuts have left-hand threads.
2. Clean the bore of the shaft liner and inspect for visible signs
of pitting, corrosion or erosion.
z Use flashlight and mirror (if necessary) to visually inspect the bore
of the shaft liner. A Bore-o-Scope is best for inspection, if
available.
3. Remove the shaft liner and perform ultrasonic testing if
inspection indicates erosion or corrosion.
Grease Fittings
6 Places
Grease Fitting
Oil capacity
The IDS holds approximately 10-15 gallons of oil, but oil
capacities vary according to the type of cooling systems, etc.
installed. Always fill the transmission to the middle of the sight
glass using the hand pump supplied by Varco. Use the following
procedure to fill the transmission for the first time on a new top
drive:
1. Use the hand pump to fill the gearbox to the top of the sight
glass (approximately 10-15 gallons). Connect a hand pump
and hose to the fittings on the bottom of the gearbox and
open ball valve when filling.
2. Operate the IDS 10-15 minutes and check the sight glass.
3. The oil level should be near the middle of the sight glass. If
the oil level is below the middle of the sight glass, add more
oil until the level reaches the middle of the sight glass. If the
oil level is at, or above the middle of the sight glass, do not add
any additional oil to the gearcase.
After installation and initial operation of the IDS, always fill the
transmission to the middle of the sight glass.
When draining oil from the drain plug at the bottom of the
gearcase, only the 10-12 gallons of oil at the bottom of the
gearcase actually drains. Oil still remains in the rotating head
cavity (approximately 1-2 gallons), the oil lube/pump/cooler
system (approximately 1-2 gallons).
Fro
nt
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
Remove Grease ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
Plugs and install ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
Grease Fitting to ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
Permit Lubrication. ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
2 Places Total. ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
Centralizer
Bearing Vent
Grease Fittings
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,,,,,,
Grease
Fitting
Grease
Fitting
Grease Fitings
Grease Fitting
Grease Fitting
Grease Fitting
500 Ton
Solid Body Elevator
Grease Fittings
2 places
as shown.
Open
Position
Actuator Shell
Grease Fitting
Crank Arm
Grease Port
Actuator Arm
Groove
Upper IBOP
Valve
Carriage Frame
Torque Arm
Grease Fittings
2 Each Side
(4 Total)
Grease Fittings
,,,,
At Carriage Rollers
,,,,
,,,,
,,,,
,,,,
6 Each Side
,,,,
,,,,
,,,, (12 Total)
Grease Fitting
1 Each Side
(2 Total)
Grease Fittings
2 places as shown
and 2 places
opposite side.
(4 Total)
Lubrication schedule
Lubricant Number
Frequency Location Code* of Points
Daily Torque wrench 1 12
Daily Gearbox oil (check level) 2 1
Daily Hydraulic reservoir assembly 4 1
Daily Rotating head 1 5
Daily IBOP actuator arms 1 6
Daily Safety valve actuator cranks 1 2
Daily Drilling motor shaft
liner assembly bearing 3 2
Daily Wash pipe assembly 1 1
Daily Hydraulic pressure filter † – –
Daily Gearbox upper seals 1 1
Each trip Drill pipe elevator 1 7
Each trip Carriage assembly 1 18
Weekly Lower attachment assembly 1 8
Weekly Alignment strut assembly 1 2
Weekly Solid body elevator 1 2
Weekly Master bushing wear guide 1 4
Weekly Link tilt Check condition
750 hrs/3 mos. G.E. drilling motor
lower bearing 3 1
1,500 hrs/6 mos. G.E. drilling motor
commutator bearing 3 1
Monthly Spark arrestors † – –
Every 3 months AC blower motor 1 2
Every 3 months Change gearbox oil 2 1
Every 3 months Suction strainer/oil filter † – 1
Every 3 months Change hydraulic oil – –
* See Lubricant specifications table
† Check condition and replace as necessary
Lubricant specifications
IDS transmissions operate under a combination of heavy and
shock loads. Under these conditions oil tends to extrude out of
the gear mesh. Keeping an effective film of oil on the gear mesh
requires oil with an AGMA “extra pressure” rating, and a
minimum viscosity of 100 SUS at operating temperature.
Varco drilling systems also operate under a wide variety of
temperatures. Select lubrication for the IDS based on the
minimum ambient temperature to be expected before the next oil
change. Under all but the most severe operating conditions, Varco
recommends changing the oil every three months. Introducing an
oil viscosity greater than required by the ambient temperature can
damage the gearbox due to reduced oil flow.
All oils change viscosity with temperature and EP oil is no
exception. The IDS transmission lubrication system is limited to
pumping oils of a maximum of 9,000 SUS viscosity.
Varco recommends measuring the oil temperature with a contact
thermometer.
The following tables will aid in your lubricant selection and keep
your IDS transmission operating properly:
Min. ambient temperature Oil type required Varco part number
°F °C
Below 20° -6° See following note See following note
20° to 60° -6° to 16° 2 EP, ISO 68 56004-1
45° to 85° 7° to 30° 4 EP, ISO 150 56004-BSC
Above 70° 21° 6 EP, ISO 320 56004-2
1 2
General Purpose Grease Gear Oil
Ambient
temperature Above -20˚ Below -20˚C Above 21˚C 7˚ to 30˚C -6˚ to 16˚C
range
Exxon Lidok EP2 Lidok EP1 Alpha LS-320 Spartan EP150 Spartan EP68
Gulf Gulf Crown EP32 Gulf Crown EP31 EP Lube HD320 EP Lube HD150 EP Lube HD68
Mobil Mobilux EP2 Mobilux EP1 MobilGear 632 MobilGear 629 MobilGear 626
Shell Alvania EP2 Alvania EP1 Omala 320 Omala 150 Omala 68
Statoil Uniway EP2N Uniway EP1N Loadway EP320 Loadway EP150 Statoil
Texaco Multifak EP2 Multifak EP1 Meropa 320 Meropa 150 Meropa 68
Total Multis EP2 Multis EP1 Carter EP 320 Carter EP 150 Carter EP 68
Union Unoba EP2 Unoba EP1 Extra Duty NL6EP Extra Duty NL4EP Extra Duty NL2EP
NGL1 2 1 - - -
3 4
Motor Grease Hydraulic Oil
Ambient All
temperature temperatures -10˚ to 85˚C -15˚ to 75˚C
range
NGL1 - - -
AGMA - 1 -
ISO Viscosity - 46 32
Grade
18. Lower the set point of the differential unloading valve (UV)
to 2,200 psi. The pump fills the brake accumulator (BA) to
2,200 psi. Then the pump unloads. The pump remains
unloaded until the brake accumulator pressure decays to
about 1,600 psi.
19. Make sure the (UV) set point remains 2,200 psi while
observing several cycles of loading and unloading.
20. Tighten the relief valve jam nut.
21. Install a 0-3,000 psi pressure gauge on test point BR and
adjust the brake pressure control (PCB) one turn clockwise
from the minimum setting.
22. Operate the brake directional valve (DV) and verify that BR is
at pressure in one DV position and at 0 psi in the other DV
position.
23. Place the DV valve in the position that pressurizes the BR and
adjust PCB to 1,400 psi.
24. Tighten the jam nut on PCB and cycle the DV to verify that
BR alternates between 0-1,400 psi.
25. Install 0-3,000 psi pressure gauge on test point CB and adjust
the counterbalance pressure control (PCC) to the maximum
setting (fully clockwise).
26. Adjust the cylinder mounted relief valve to 2,000 psi and
tighten the jam nut. If this valve is difficult to adjust when
pressure is applied, lower the PCC setting to minimum and
adjust the relief valve. This process takes time because there is
a delay while filling and draining the counterbalance
accumulator.
27. Adjust PCC to 1,200 psi as measured at CB.
28. Tighten the jam nut on PCC (refer to the counterbalance
adjustment procedure).
29. Turn the electric motor off and inspect the IDS for external
leaks. The counterbalance accumulator and brake
accumulator are still filled with pressurized hydraulic oil.
30. Inspect the hydraulic system for hissing sounds, indicating
high internal leakage.
31. Open the ball valve (SV) and listen for hissing, indicating
counterbalance accumulator bleed down and decreasing
pressure at CB.
32. Close the SV and verify that the hissing stops.
z Any slight adjustment causes the gearbox to lift off of the links.
10. Tighten locknut.
Pressure Reducing
Valve
Counterbalance Valves
Brake Valve
Make/Break
Recycle Clamp Torque Valve
Sequence Sequence Sequence Torque
Valve Valve Valve Wrench
Manifold
00
20
10
00
B
RECYCLE CLAMP TORQUE
2500
500
PRV
30
0
Hydraulic
00
Pressure LIFT
Inlet LOWER
Lift/Lower
Flow Control
Valve
Pressure
Gauge
0 - 3000 PSI
Pipehandler (PH-60d)
IBOP Actuator
Hoses (Air)
Hanger
Torque Wrench
Hoses (Hydraulic)
Lift Cylinder
IBOP Actuator
Air Cylinders
IBOP Actuator
Arms
Stop Tube
Torque Tube
Torque Wrench
Manifold (Hidden)
Disassembly
1. Remove the slotted hex nut and cotter pin attaching the two
halves of the stabbing guide together at the front and swing
the guides out to each side.
2. Vent the clamping cylinder as follows: disconnect the
hydraulic lines to the clamp port and front unclamp port on
the clamp body cylinder at the torque wrench manifold clamp
and unclamp ports.
3. Remove the jaw pins from the rear clamping jaw and remove
the jaw.
4. Remove the two screws holding the jaw spacer to the front
clamp cylinder piston and remove the spacer and jaw spacer.
5. Remove the two screws holding the clamp clevis to the rear
clamp cylinder piston.
6. Remove the pins holding the clamp body to the clamp clevis
and remove the clamp clevis. Be sure to remove the spacer
from the piston rod slot.
7. Push in the cylinder gland from the rear cylinder head
retainer ring and remove the ring with a screwdriver.
8. Attach the sliding hammer to the rear piston rod and carefully
pull the piston until the cylinder gland can be removed.
9. Continue to pull until the piston comes out.
10. Using a piece of wood or brass bar, tap the front clamp piston
from the front and remove it from the rear.
11. Remove and discard the piston seals, rod seals and rod wipers.
12. Remove the front piston rod seal and rod wiper from the
clamp cylinder body and discard.
13. Inspect the clamp cylinder bore thoroughly for dirt, burrs,
nicks, gouges and pitting. Repair and clean as necessary.
Assembly
1. Insert a new front rod seal and rod wiper in the clamp
cylinder body and lubricate with clean hydraulic fluid.
2. Install a new piston seal in the front piston groove and
lubricate with hydraulic fluid.
3. Insert the front piston into the clamp cylinder body with the
two jaw spacer screws holes orientated vertically.
4. Gently and evenly tap the piston into place until the rod
appears beyond the front cylinder bore.
5. Install new piston seal in rear piston groove and lubricate with
hydraulic fluid.
6. Insert rear piston into the clamp cylinder body with the two
screws holes on the rod oriented to the horizontal position.
7. Gently tap piston into place until there is enough space
between the piston face and retaining ring groove to insert
cylinder gland and retainer ring.
8. Install rod seal and rod wiper in inside grooves of the cylinder
gland.
9. Install piston seal in outside groove.
10. Lubricate all seals with hydraulic fluid.
11. Insert cylinder gland into bore rod and piston seals first. Push
gland past retainer groove and install retainer ring.
12. Insert the spacer and attach the clamp clevis to the rear
cylinder rod with the two hex head cap screws and flat
washers. Tighten firmly and lockwire.
13. Adjust orientation of the clamp clevis and attach to the clamp
body using the two clevis pins and cotter pins.
14. Attach the rear clamping jaw spacer to the front piston rod
using the spacer and two hex head cap screws and flat
washers. Tighten firmly and lockwire.
15. Attach the clamping jaw with the two jaw pins.
16 Swing the stabbing guide back into position and attach with
the slotted nut and cotter pin.
17. Reconnect the hydraulic lines from the clamp body cylinder
clamp port and front unclamp port at the torque wrench
manifold clamp and unclamp ports.
18. Reinstall and adjust the torque wrench (refer to Adjusting the
torque wrench earlier in this chapter).
Disassembly
1. Order eight replacement glyd rings, two gearcase seals, a
flange gasket, and an excluder cap gasket from Varco. Contact
the nearest Varco Service Center for details about building an
appropriate stand for working on the rotating head when it is
removed from the IDS for service or maintenance.
2. Disconnect the hydraulic and air hoses from the rotating head
rotating block to the various pipehandler components.
3. Support the torque wrench.
4. Disconnect the IBOP actuator arms and hoses.
5. Remove the pin attaching the hanger to the rotating block
clevis, and remove the torque wrench.
6. Support the link tilt and solid body elevator while removing
the pins attaching the torque arrestors to the rotating block.
7. Remove the torque arrestors, link tilt and solid body elevator.
8. Place the rotating head stand, built prior to disassembly,
under the IDS and lower the IDS until the rotating head rests
on the stand.
9. Remove the flange nuts and lift the block, leaving the rotating
head on the stand.
10. Remove the quick disconnect fittings from the rotating block
hydraulic lines and drain the hydraulic fluid from the system.
11. Remove the cotter pin from the return cylinder clevis pin.
12. Remove the hex-slotted nut and remove the clevis pin.
13. Push the cam follower away from the rotating block cam.
14. Remove the safety wire from the hex-head screws attaching
the rotating block to the stationary flange.
15. Support the rotating block and remove the ten screws.
16. Remove the rotating block and glyd rings.
17. Remove the excluder cap and gasket.
18. Remove the glyd rings from the rotating block and discard.
19. Remove excluder cap gasket and replace with new gasket.
Assembly
1. Lubricate the eight new glyd rings with hydraulic fluid and
insert them into the glyd ring grooves inside the rotating
block.
2. Place the excluder cap and gasket on the bottom of the
rotating block.
3. Using a tugger or other support, carefully mate the rotating
block to the stationary flange.
4. Reinstall the 10 hex-head screws and torque to 250 ft lb.
5. Safety wire the screws per standard safety wire procedures
described in this book.
6. Reinstall the quick disconnect hydraulic fittings on the
rotating block.
7. Attach the return cylinder rod to the clevis with the clevis pin
and install the slotted hex-head nut and cotter pin.
8. Reinstall the pipehandler components per the procedures
detailed in the Installation and Commissioning book.
Gearcase
Seals Stationary Flange
Cam Follower
Return Cylinder
Clevis (2)
Cotter
Pin (2)
Cam Follower
Return
Cylinder
Return Cylinder
Clevis Pin (2)
Retainer Ring
Disassembly
1. Disconnect the air hose from the rotating head rotating block
to the link tilt assembly.
2. Support the link tilt and remove the two upper and two lower
screws attaching the link tilt to the solid body elevator.
3. Lower the link tilt to the floor with the air actuator to be
replaced facing up.
4. Remove the cotter key and pin from one end of chain
connecting the two sealing plates.
5. Remove the safety wire from the four hex-head cap screws
holding the air actuator sealing plate to the link tilt base or
lever and remove the screws.
6. Lift the lever or base off the air actuator sealing plate, and
rotate it 180° on the link tilt pivot pin and lay down.
7. Remove the 18 nuts and washers holding sealing plate to the
air actuator and remove the plate.
8. Using a pry bar or screwdriver, pry the air actuator away from
the screws attaching the actuator to the hanger plate and
remove the screws using a hex wrench.
9. Remove and discard the air actuator.
10. Remove any burrs or gouges on sealing surfaces of the hanger
and sealing plates.
Lever Weldment
Nuts,
Lock Washers (18)
Pressure
Regulator
Sealing Air Actuator (2)
Plate Base
Bolt (4) Hanger Plate
Quick
Exhaust
Valve
Lever
Intermediate
Stop (2)
Connecting Chain
Assembly
1. Place a new actuator on the hanger plate.
2. Attach the air actuator to the hanger plate with the 18 button
head cap screws. Coat the screw threads with locktite before
installation.
e The air actuator has aluminum neck bead rings on both sealing
surfaces. These beads must be compressed equally to ensure a good air
seal. This requires more than one tightening pass to accomplish.
Over-torquing may cause hex sockets to strip.
4. Torque the cap screws to the hanger plate at 80 ft lb.
5. Insert the eighteen 1 7/8 in. bolts into the neck ring of the air
actuator.
6. Reinstall the air actuator sealing plate, coat the bolt threads
with locktite and fasten with the lockwashers and nuts
provided.
7. Torque the nuts to the sealing plate at 80 ft lb (see caution
above).
8. Lift and rotate the link tilt lever or base to line up with the air
actuator sealing plate. Attach with the four hex-head cap
screws and torque to 250 ft lb.
9. Safety wire the four screws.
10. Reconnect the chain between the two sealing plates.
11. Reinstall and adjust the link tilt per the Installation book.
Front jaw
(Figure 4-15)
1. Remove the cotter pin from the retaining bolts and slotted
nut.
2. Remove the nuts securing the die retainer to the jaw.
3. Remove the die retainer from the jaw.
4. Remove the tong dies from the jaw.
Rear jaw
1. On rear the jaw, remove the cotter pins from the retaining
bolts and slotted nuts.
2. Support the retaining bolt while removing the slotted nut.
3. Remove the retaining bolt from the piston jaw.
4. Support the remaining retaining bolt while removing the
slotted nut and upper die retainer.
5. Remove the retaining bolt and lower die retainer.
6. Remove the tong dies from the jaw.
Front jaw
1. Loosen the socket head cap screws securing the jaw assembly
to the torque wrench body.
2. Support the jaw and remove the socket head cap screws and
washers from the jaw assembly and the torque wrench body.
3. Remove the front jaw assembly from the torque wrench body.
Rear jaw
1. Loosen the socket head cap screws securing the jaw assembly
to the piston.
2. Support the jaw assembly and remove the socket head cap
screws and washers from the jaw assembly and piston.
3. Remove the rear jaw assembly from the piston.
IBOP assembly/disassembly
Refer to the IBOP Service Manual (included as a separate book in
this manual) for assembly/disassembly procedures for the upper
and lower IBOPs.
Bracket
Cotter Pin
Shackle
Rod End
Clevis
Clevis Pin
Bracket
Carriage assembly/disassembly
Replacement parts for the IDS carriage assembly are included in the
Expendable Spare Parts Kit. Refer to the engineering drawing and
Figure 4-19 when performing the following procedure:
1. Attach a tugger line to support the weight of the carriage
assembly prior to disassembly from the drilling motor.
2. Loosen six 5/8 in. bolts and lockwashers and remove the
grease cap from the drilling motor end of the carriage
assembly.
3. Loosen three 3/4 in. bolts and remove the bearing retainer
from the torque arm.
4. Detach the torque arm from the brake/torque hub assembly.
5. Repeat steps 1-4 for opposite torque arm.
6. Lower the carriage assembly off of the torque tube and
relocate in suitable work area.
7. Remove either torque arm from the carriage, by loosening
and removing two
5/8 in. bolts, lockwashers and retainer plate.
8. Drive the pivot pin from the carriage from the opposite side
of the pin, taking care not to damage the pin.
Reassembly
1. Observe the condition of the uppermost seal in the centralizer
housing at the top of the drilling motor.
2. If replacement is warranted, pack a clean rag just below this
seal to keep dirt out of the centralizer bearings.
3. Remove the retaining ring just above the seal with a
screwdriver; and pry the seal upwards and out of the
centralizer housing. Do not damage the bearing below the seal
during this process.
4. Tap the new seal back into place taking care not to dent the
metal case. Make sure that the garter spring in the seal is
towards the bearing (or downwards). Push the top of the seal
case just past the retaining ring groove, but no further.
5. Replace the retaining ring, making sure it fully installs into
the groove.
6. Withdraw the packing rag and any debris which might be on
the seal or bearings.
7. Completely clean the replacement shaft liner with solvent.
8. Remove any burrs on the lower threads. Make sure that there
is no corrosion or impact damage to the lower end face or
sealing surface below the lower threads.
9. Replace the excluder on the shaft liner and install the lifting
cap.
25. Slowly rotate the throttle until the handle of the torque tool
contacts the bonnet surface.
Bearing
Retainer Cap Screws
Spherical
Rod End
Bearing
Bearing
Retainer
Flexloc
Nut
Thrust
Washer
Cap Screws
Strut
z Parts required for repair of IDS drilling motor, gearbox, brake and
wash pipe assemblies are included in Expendable Spare Parts Kit
No. 96361.
1. Open the IDS motor guard.
2. Remove the electrical wires from the blower motor.
3. Remove the flexible duct hose.
4. Remove the four bolts connecting the blower mounting
bracket to the bonnet.
5. Remove the bolts connecting the blower impeller housing to
the transition duct.
6. Hoist the blower assembly off of the IDS and place on a clean
work space on the derrick floor.
7. Remove the blower intake duct on the side of the blower
motor.
8. Remove the taper lock bushing from the blower impeller.
9. Remove the blower impeller.
10. Remove the bolts connecting the blower housing to the
blower mount.
11. Remove the impeller housing.
12. Unbolt the four bolts connecting the blower motor feet to the
blower mount.
13. Lift out the motor.
Reverse the above procedure to install a new motor in the local
cooling system (Figure 4-21).
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,
,,,,,,,,,,,,, Extended Air Intake Assembly
Explosion-Proof,
20 hp, 3450 rpm
Flexible Duct Hose AC Motor
Impeller
Housing Blower
Mount
Blower
Impeller
Bonnet
Intake
Duct
Drilling
Motor
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
Transition
Duct
Brake assembly/disassembly
Refer to the engineering drawings while performing the following
procedure:
1. Disconnect the hydraulic hoses at the lower motor adapter
plate.
2. Remove the brake assembly from the drilling motor by
removing the carriage assembly. (See the procedure in the
previous section on carriage assembly.)
3. Remove eight 1 in. bolts and lockwashers from the brake/
torque hub assembly.
4. Lift the brake/torque hub assembly from the drilling motor
and place on a suitable working surface.
5. Loosen the adjustment nut on the spring return bolt to
reduce spring tension.
6. Remove the spring return bolt and the return spring.
7. Remove the retaining plate.
8. Remove the brake pads.
9. Remove the retaining ring and slide the piston from the
caliper housing.
Inspect the disassembled parts for wear or damage. Replace worn
or damaged parts. Reassemble the brake assembly in reverse order
of disassembly.
❏ IBOP
❏ Pipehandler assembly
❏ Actuator assembly
❏ Solid body elevator
❏ Counterbalance system
❏ Carriage assembly
❏ Cooling system
❏ Wash pipe
❏ Shaft liner assembly
❏ Alignment strut assembly
If the drilling motor assembly requires replacement, use the
following procedure to remove the hydraulic-pneumatic/electrical
assembly:
a. Attach a lifting sling to the assembly.
b. Remove the transition duct cover and disconnect power
cables per the interconnect drawing (see engineering
drawing).
c. Remove the fourteen 1/2 in. bolts holding the transition
duct to the drilling motor.
d. Take up the slack on the lifting sling prior to removing
any additional fasteners.
e. Remove the four 3/4 in. set screws. Two set screws are
located on the other sides of the mounting plate assembly.
f. Remove the two 1 in. bolts adjacent to the spark arrestor
assembly and lift the hydraulic-pneumatic/electrical
assembly from the drilling motor.
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,,
,,,,,,,,,,,,,,,,,
Use the size and type of safety wire required in the applicable
specifications and drawings. Whenever possible, use double-twist
safety wiring.
1
2
3 4
n Do not nick the wire with the edge of the hole in the fastener.
Position the safety wire so the pull exerted by the wire tightens
the nut. For best results, let the wire leave the fastener in a
clockwise direction
❏ Twist the safety wire so the loop around the bolt or head has
sufficient tension to keep it from slipping up and over the
bolt head, with resulting slack in the safety wiring.
® ™
DRILLING SYSTEMS
Feb. 2, 1994
Feb. 2, 1994
Feb. 2, 1994
Contents
GENERAL DESCRIPTION.............................................................................. 1
PH-60 IBOP/ACTUATOR UPGRADE KIT.......................................................... 5
Introduction .................................................................................................. 5
Principle Features ................................................................................... 5
Remote IBOP Actuator Improvements ........................................................ 7
Internal Valve Mechanism Improvements.................................................... 8
INSTALLATION ............................................................................................ 9
OPERATION .............................................................................................. 16
Erosion Prevention of the Ball and Seats in the Lower IBOP Valve .......... 17
LUBRICATION ........................................................................................... 18
INSPECTION ............................................................................................ 21
Magnetic Particle Inspection ...................................................................... 21
Safety Valve Inspection Procedures .......................................................... 21
Visual Inspection ................................................................................... 22
ADJUSTING THE SAFETY VALVE ACTUATOR ................................................. 23
MAINTENANCE ......................................................................................... 25
Seal Replacement ..................................................................................... 25
Shop Assembly and Disassembly ............................................................. 27
Disassembly.......................................................................................... 28
Assembly .............................................................................................. 32
IBOP Valve Testing in the Shop ............................................................ 39
APPENDIX ................................................................................................ 40
i
Feb. 2, 1994
ii
Feb. 2, 1994
Varco/BJ
Safety Valves
(IBOPs)
GENERAL DESCRIPTION
The Varco/BJ Drill Stem Upper Safety Valves (IBOPs) are ball type valves with full internal
openings to provide unrestricted flow of drilling fluids. The IBOPs are rated at 15,000 psi
working pressure.
If the driller notices a kick developing, the upper IBOP can be closed remotely, and the lower
IBOP can be closed manually. The lower IBOP can be broken out by the torque wrench and left
in the string if required.
The splined upper valves are an integral part of the Varco pipehandler of the TDS Drilling System
(Figures 1 & 2). A remotely operated actuator is attached to the upper IBOP and may be operated
at any height in the derrick from the driller’s console. The upper IBOP can also be operated
manually using a 7/8" hex wrench.
There is a port on the upper IBOP below the valve crank for a grease fitting and reducer bushing
for purging any debris that may get in the wave spring area.
1
Feb. 2, 1994
Link Rotating
Tilt Head (Ref.)
Link
Adapter
Torque
Arrestor
Link
Splined Adapter
Support
Upper Plate
Safety
Valve
Safety Valve
Actuator Torque
350 Ton Wrench
108" Links
(Ref.)
Plain Lower
Safety Valve
Saver
350 Ton
Sub
Center-Latch
Drill Pipe
Elevator
(Ref.)
2
Feb. 2, 1994
Link Rotating
Tilt Head (Ref.)
Link
Adapter
Torque
Arrestor
V
Link a
r
Splined Adapter c
o
Support
Upper Plate
Safety
Valve
Safety Valve
Actuator Torque
350 Ton Wrench
108" Links
(Ref.)
Plain Lower
Safety Valve
Saver
350 Ton
Sub
Center-Latch
Drill Pipe
Elevator
(Ref.)
Figure 2. Typical Safety Valve in Relation to Other TDS Assemblies (PH-85, PH-60d)
3
Feb. 2, 1994
Thread
Protector
Body
Retaining Ring
Upper Seat
Plug
Back-up Rings
N
OPE
Back-up
CL SD
Rings
O-Ring
O-Ring
Ball
Sleeve
Grease/
Mud Seal
Seat
Wave Thread
Spring Protector
Back-up Ring
O-Ring
4
Feb. 2, 1994
Introduction
Installation of this comprehensive upper IBOP valve and actuator upgrade kit onto an existing
PH-60 pipe handler will dramatically improve the reliability of the remote-operated system, both
as a primary safety valve and as a mud saver while drilling ahead.
Maintenance and operating costs will be greatly reduced, allowing a minimum planned
maintenance interval of six months for the upper IBOP.
PRINCIPLE FEATURES
❏ The new actuator shell is solid steel and bronze lined—eliminating bolted-on external guides.
❏ The new cylinders operating the upper IBOP are 45% larger for positive closure and they
eliminate the need for periodic adjustment.
❏ The dual external crank assemblies share the operating loads. Each is reinforced, with
improved sealing and retention.
❏ The new ball rotation stops (renewable) are enclosed in pressure-sealed cavities, grease-
packed, and completely isolated from mud caking and corrosion to ensure full bore opening.
5
Feb. 2, 1994
ACTUATOR CYLINDER
MOUNTING BRACKET
REQUIRES NO ADJUSTMENT
LARGE BORE,
LONG STROKE IBOP
ACTUATOR CYLINDERS (2)
SOLID, ONE-PIECE,
JOURNAL-GUIDED
IBOP ACTUATOR SHELL
REINFORCED DUAL
EXTERNAL CRANKS AND
HOUSINGS WITH IMPROVED
BALL ROTATION STOPS
IMPROVED DESIGN
DUAL-CRANK
UPPER IBOP VALVE
6
Feb. 2, 1994
1. Air cylinders which operate the IBOP are increased in both diameter and stroke. The 45%
larger piston area ensures positive, complete ball rotation under the most arduous conditions.
A 60% increase in available cylinder stroke eliminates the need for sensitive position
adjustments, both at initial rig-up as well as over the life of the system.
2. A solid, one-piece, journal-guided design (as on current PH-85 models) replaces the current
multi-piece actuator shell assembly, eliminating the separately attached (and vulnerable)
guide roller assemblies. The bronze-lined internal diameter of the new actuator shell rides
directly on the IBOP outer diameter. The new design is very robust, requires no adjustments,
and is able to withstand punishing environments without damage.
3. Dual external operating cranks, as on the PH-85, replace the single crank arrangement. This
change reduces the operating and environmental forces on the internal and external components
by 50%. It also provides a balanced reaction force to the actuating levers. This force balance
allows elimination of the bolt-on guide roller assemblies.
Each of the two external crank housings is anchored to the IBOP body with 1/2" screws
instead of the 3/8" screws used in the previous design. The crank housings are also secured
to react the ball stop torque using a close-tolerance fit between the base of the housing and
the machined recess in the IBOP valve body. When required, jacking screws make removing
the housings easier.
7
Feb. 2, 1994
1. Internal stress concentrations at the valve’s operating crank bores are eliminated. They are
replaced with a smooth bore through the ball and seat region. This significantly lowers the
maximum stress in the valve body and effectively eliminates the possibility of leaks caused
by cracking at the crank bores under corrosive mud conditions.
2. Contact between a strut on the internal crank and a shoulder in the IBOP body causes ball
rotation stop in the previous design. The crank was easily replaced, but the body was not
repairable after stop shoulder wear. The wear-induced loss of ball stop accuracy over
extended use could eventually allow the ball to over-travel, leading to washouts.
In the new design, the IBOP body is no longer part of the ball rotation stop. Only the internal
cranks (2) and external crank housings (2) need replacement should they ever become worn.
The external crank housings in the new design serve as the ball rotation stops. Each external
crank housing has two struts which contact the internal crank to stop the ball precisely at the
open or closed position. The torque required to stop the ball is then shared by four surfaces
rather than the previous design’s single surface.
The stop device is no longer in the ball and seat cavity, it is now in the sealed, lubricated
regions beneath the external cranks. This eliminates the presence of caked drilling fluid
around the stop mechanism and is more reliable.
3. A second ball-actuating crank is added to the valve, as in the latest generation pipehandler,
the PH-85. This effectively cuts the operating forces in half on the critical ball actuating and
locating components, decreasing wear and eliminating mechanical failure.
8
Feb. 2, 1994
INSTALLATION
The following installation procedure assumes that all other rig components are already installed.
1. Use slips to install a joint of drill pipe into the rotary table.
2. Install the saver sub hand tight onto the drill pipe.
3. Install the lower IBOP hand tight onto the saver sub.
4. Install the upper IBOP hand tight onto the lower IBOP.
CAUTION
The same care should be taken with these valves as would be any
other threaded valve. Be sure to use a thread compound with 60%
lead by weight or Kopper Kote. Varco does not recommend using
a zinc thread compound. If making up new threads for the first
time, use the following procedure:
9
Feb. 2, 1994
Torque (ft-lb)
Components I.D. Connection O.D. (min.) (max.)
Upper IBOP Safety 3" 6-5/8 API Reg. 7-3/4 50,000 70,000
Valve to Lower
IBOP Valve
Lower IBOP Valve 3" 6-5/8 API Reg. 7-3/8 46,000 64,000
to Saver Sub
Lower IBOP Valve 3" 7-5/8 API Reg. 8-5/8 66,000 85,000
to Saver Sub
* 500 Ton
** 650 Ton
6. Install the dual crank PH-85 and the PH-60d upper IBOP safety valve actuator as follows
(Figures 5 & 6):
a. Carefully grind off any raised tong marks on the O.D. of the safety valves.
b. Open the valve exactly halfway (45 degree rotation of the actuator).
c. Orient the levers on the crank assemblies horizontally as shown.
d. Slide the shell up onto the valve with the actuator arm groove on the bottom.
e. Hold the shell in position relative to the valve operating sockets.
f. Using the bolts provided, install the two crank assemblies, sliding the safety tabs through
and the cam follower into the horizontal slot. Use the lock tabs on the retaining screws
and locktite on the bolt threads to secure the assemblies.
g. Manually operate the actuator to ensure free movement though a full 90° of crank travel.
10
Feb. 2, 1994
Install the single crank PH-60 upper IBOP safety valve actuator as follows (Figures 7 & 8):
a. Carefully grind off any raised tong marks on O.D. of the safety valves.
b. Open the valve exactly halfway (45 degree rotation of actuator).
c. Orient the lever on the crank assembly horizontally as shown (be sure the safety wire
groove on side of crank body is to the right and the safety tab is on the left).
d. Slide the shell up onto the valve with the roller groove at the bottom.
e. Hold the shell in position relative to the valve operating socket.
f. Using the two bolts provided, install the crank assembly, sliding the safety tab through
and the cam follower into the horizontal slot. Use locktite on the bolt threads. Safety wire
the bolt heads, routing lock wire around the right side of the crank body through the safety
wire groove.
g. Install the two roller assemblies nearest the crank slot, and then using shims provided,
install the third roller assembly, maintaining .005" to .010" clearance between the third
roller assembly and the safety valve body with the shell vertically centered on the valve.
h. Manually operate the actuator to ensure free movement through full 90° of crank travel.
NOTE
When the actuator is in the lowest position, the valve should be
open.
7. Install the torque wrench assembly and adjust as necessary (refer to the TDS Service Manual
for the installation and adjustment procedures).
8. Use the torque wrench to make up the saver sub to the lower IBOP.
9. Use the torque wrench to make up the lower IBOP to the upper IBOP.
11
Feb. 2, 1994
Crank Assembly
Retaining Screw
And Lock Tabs
Crank
Assembly
Slot
Actuator
Shell
Crank Arm*
Actuator Arm
Lock Tabs Groove
Crank
Assembly
Safety Wire
Groove
Upper IBOP
Valve
*Note Orientation
Cam Follower
Figure 5. Installing the IBOP and Safety Valve Actuator Shell for the PH-85 & PH-60d
12
Feb. 2, 1994
Open Closed
Position Position
Actuator
Shell
Crank Arm
Grease Port
Actuator Arm
Groove
Upper IBOP
Valve
Figure 6. PH-85 & PH-60d IBOP Actuator Shell in the Open and Closed Positions
13
Feb. 2, 1994
Crank
Crank Assembly Assembly
Roller Retaining Screw
Assembly (3)
Slot
Roller
Assembly
Actuator (3)
Shell
Crank*
Roller
Assembly (3) Actuator
Arm
Groove
Safety
Valve
Safety Wire
Groove Shim
Crank
Assembly
*Note Orientation
Figure 7. Installing the Single Crank IBOP and Safety Valve Actuator Shell for the
PH-60
14
Feb. 2, 1994
Open Closed
Position Position
Actuator
Shell
Crank Arm
Grease Port
Actuator Arm
Groove
Upper IBOP
Valve
Figure 8. Single Crank PH-60 IBOP Actuator Shell in the Open and Closed Positions
15
Feb. 2, 1994
OPERATION
Operating the switch on the driller’s console to the IBOP Close position causes the two (2)
actuator air cylinder rods to extend moving the arms and the actuator shell body upward. This
upward movement causes the crank assemblies to rotate 90°, closing the IBOP ball valve.
Operating the switch to the Open position retracts the cylinder rods and opens the IBOP.
16
Feb. 2, 1994
Erosion Prevention of the Ball and Seats in the Lower IBOP Valve
To maintain normal torque levels on the ball, operate the lower IBOP valve fully open and fully
closed at least one time each shift change. The valves can partially open without being externally
actuatedwhen there is a loss of friction between the ball and upper, pin end seats. The ball and
seats erode when the lower IBOP is actuated with the valves partially open. Varco/BJ recommends
removing the lip seal from the spring loaded (floating) seat to correct this problem.
Perform the following procedure to remove the lip seal from the floating (pin end) seat (Figure 9):
2. Disassemble the valve and remove the lip seal from the floating (pin end) seat.
3. Replace the O-rings and back-up rings on the fixed and floating seats.
17
Feb. 2, 1994
LUBRICATION
Lubricate the IBOPs weekly at the lubrication fitting located directly below the actuator crank
in the recessed counter bore. There are three reasons for lubricating the valve:
Use the following procedure to lubricate the IBOP valves (Figures 10 & 11):
1. Remove the plug from the 1/4" N.P.T. port of the valve body, while listening for a release of
pressure. A release of pressure indicates the mud/grease seal is not functioning properly —
the valve should be serviced.
4. Lubricate the valve with approximately 10 full strokes from a manual grease gun or an
equivalent amount from an air powered grease injector. The grease pressure should not
exceed 300 psi. Pressures greater than 300 psi may cause the mud/grease seal to extrude into
the clearance between the floating seat and the valve body.
5. Remove the grease fitting and the reducer bushing and reinstall the 1/4" N.P.T. plug,
tightening securely.
CAUTION
The plug must be replaced in the valve prior to use to maintain
pressure integrity.
18
WAVE SPRING
MUD/ GREASE SEAL
L L
FLOATING
SEAT
19
PRESSURE
SEALS
SPRING
CAVITY
VALVE
BODY
PRESSURE PLUG
Feb. 2, 1994
GREASE PORT
WAVE SPRING
FLOATING
SEAT
20
PRESSURE
SEALS
SPRING
CAVITY
VALVE
BODY
PRESSURE PLUG
Feb. 2, 1994
GREASE PORT
Feb. 2, 1994
INSPECTION
21
Feb. 2, 1994
Recommended
Inspection Areas
NOTE
Repairing valve body cracks is not practical because of the close
tolerances of internal components and the metallurgy of the valve
material. Remove from service and scrap any safety valve body
showing positive crack indications.
VISUAL INSPECTION
Whenever connections are broken, clean and check them for the following:
1. Thread and shoulder condition. Threads should be inspected for galling, stretching or other
abnormal conditions. Check shoulders for any marks, gouges or other damage.
2. Outer surface. Examine for excessive tong marks and corrosion. Check splines on upper
safety valve for wear.
NOTE
Remove any surface imperfections on upper (splined) safety
valves after the valve is made up into string to prevent remote
actuator malfunctions, causing the valve to wash out.
22
Feb. 2, 1994
NOTE
There is only one crank on upper IBOPs for the PH-60 pipehandler.
There are also three roller assemblies.
23
Feb. 2, 1994
DriveStem
(Ref.)
Link
Cylinder Adapter
Adjustment
Bolts (4)
Landing Collar
Eye Bolts (2) Upper IBOP Valve
Actuator Shell
Upper IBOP Valve
Actuator Air Cylinders (2) Crank Assy(Shown with
Valve OPEN. Note Crank
Assy Position
CLOSE
OPEN
*1 Inch Actuator
Arm
Cylinder
Gland Upper IBOP
Cylinder Rod
in OPEN End
Position Torque Tube
*IMPORTANT
Lower IBOP
Saver Sub
Figure 13. Adjusting the Safety Valve Actuator System for the PH-85, PH-60d &
Single Crank PH-60
24
Feb. 2, 1994
MAINTENANCE
Seal Replacement
Replace seals at six month intervals under normal operating conditions (Figure 14). If there are
signs of wear, replace the ball and seat every six months. If the valve is used with oil-based or
high salt content drilling fluids, shorter intervals may be necessary.
13 19
2 17 6 1 10 18 5 14 15
20 7 16
8
2X 4
9
12
11
12 7/8" Hex
Note: Dual Crank Remote IBOP Shown
Single Crank Remote and Lower IBOP
have similar construction.
25
Feb. 2, 1994
Parts List
ITEM DESCRIPTION PART NUMBERS QYT. / KIT
3 O'RING 90441-9 1 1 1
7 POLYSEAL 96439 1 1 1
11 O'RING 89141-11 1 2 2
15 BODY - - -
16 O'RING 89141-3 1 1 1
17 NYLON PLUG 2 2 2 2
19 PLUG 1 1 -
BALL/SEAT SET
Refer to the Appendix for Part Numbers
26
Feb. 2, 1994
Before disassembly, thoroughly clean the valve using a high-pressure wash or steam cleaner or
mild acid bath. If available, an ultrasonic cleaner is ideal, because it not only cleans the valve,
but also serves to loosen internal components. Follow these general rules while working on the
valve:
1. Take proper precautions while working with the components of the valve to make sure
precision matched surfaces and seal contact surfaces are not damaged.
2. After removing each part, thoroughly clean the exposed area to prevent damage to other parts
as they are removed.
7.5"
3"
22"
Load Bar
15.25"
3"
Maximum
Seat Puller For All Models Nut Wrench for DSV Models
Varco Part No. 79489-14 Varco Part No. 89141-18
27
Feb. 2, 1994
DISASSEMBLY
Starting with the valve in the closed position, disassemble the IBOP as follows:
Figure 16
Figure 17
28
Feb. 2, 1994
Figure 19
8. Re-insert the upper seat
wrench into the upper seat.
Figure 20
29
Feb. 2, 1994
Figure 21
Figure 22
Figure 23
30
Feb. 2, 1994
Figure 24
Figure 25
31
Feb. 2, 1994
ASSEMBLY
NOTE
The steel stabilizer ring
should be inside the seal
when properly installed.
Figure 27
32
Feb. 2, 1994
Figure 28
Figure 29
33
Feb. 2, 1994
Figure 30
Figure 31
34
Feb. 2, 1994
Figure 32
35
Feb. 2, 1994
Figure 34
Figure 35
Figure 36
36
Feb. 2, 1994
37
Feb. 2, 1994
NOTE
The grease pressure should not exceed
300 psi. Excess pressure can cause the
mud/grease seal to extrude.
Figure 39
38
Feb. 2, 1994
Testing IBOP safety valves requires proper test plugs for the valve ends and a hydrostatic test
pump capable of reaching 10,000 or 15,000 psi (cold working pressure of the valve). Use the
following procedure to test IBOPs:
1. Rotate the valve crank to the Open position.
2. Install test plugs into both ends of the valve. Connect the hydrostatic test pump to the plug
in the splined end of the upper IBOP (box end of the lower IBOP). Connect a bleed valve
to the plug in the opposite end.
3. Place the valve in the vertical position (splined end down for upper IBOP, box end down for
lower IBOP) with the ball and the bleed valve in the Open position.
4. Fill the valve with hydraulic oil. Note: Water can be used when hydraulic oil is impractical,
but using water increases the liklihood of corrosion in the valve body—especially when the
valve is not in use for a prolonged period of time.
NOTE
Open and close the valve five times to release trapped air and
overflow through the bleed valve for approximately 30 seconds to
assure complete filling of the valve cavity.
5. Open the bleed valve to reduce internal pressure to zero psi. Rotate the ball to the Closed
position.
6. With the bleed valve Open, pressurize the lower cavity to the rated cold working pressure plus
1,000 psi and hold for three minutes. Allowable seepage is 1,000 over the duration of the test.
7. Open the bleed valve to reduce the internal pressure to zero psi. Disconnect the hydrostatic
test pump and the bleed valve. Reverse the orientation of the valve (splined end up for upper
IBOP, box end up for lower IBOP).
8. Connect the hydrostatic test pump to the test plug opposite the splined end of the upper IBOP
(pin end of the lower IBOP).
9. Fill the valve cavity with water while rotating the ball full open to closed five times to release
trapped air. Overflow through the bleed valve for 30 seconds. Pressure to the cold working
pressure plus 1,000 psi and hold for three minutes. Allowable seepage is 1,000 psi over the
duration of the test.
10. Open the bleed valve to reduce the internal pressure to zero psi. Open and close the valve to
insure smooth operation.
11. Measure the torque required to operate the valve. A torque value of less than 50 ft-lbs. is
acceptable.
12. Drain the valve cavity and remove the test plugs. Open and close the ball several times to
release trapped fluid. When testing with water, coat the valve internals with a preservative
to prevent oxidation and install thread protectors.
39
Feb. 2, 1994
APPENDIX
IBOP Part Numbers
40
Feb. 2, 1994
98977-500 STD Upper Valve, PH60 Dual Crank 99468-2 99468-1 65170014
98977-502 H2S 6 5/8 Box X 6 5/8 Pin 99469-SP - 98966
98977-501 NAM Landing Collar Design 99468-2 99468-1 65170014
99461-500 STD Upper Valve, PH60 Dual Crank 99468-2 99468-1 65170014
H2S 6 5/8 Box X 6 5/8 Pin 99469-SP - 98966
NAM Landing Collar Design 99468-2 99468-1 65170014
41
Feb. 2, 1994
42
Feb. 2, 1994
43
Feb. 2, 1994
44
Feb. 2, 1994
45
Feb. 2, 1994
46