Site accomplishment report for the actual concrete pouring of batch-1 (Phase-1) for Ground
floor beam and floor slab.
A. Cleaning of slab, girders and beams phenolic board forms of debris and dirt to
accommodate fresh ready-mix concrete.
B. Concrete pouring of phase-1 ground floor slabs, girders and beams.
PHASE-2 PHASE-1
CONCRETE CONCRETE
POURING POURING
Cleaning
Rear part of Ground Floor (Multi-media, Study room, Laundry/Ironing and part of Dirty kitchen)
Ground floor Powder Room, Outdoor T&B, Living, Informal Area and part of Dining area and Den
end
Again, I thank you for giving me the opportunity to serve your needs.
Respectfully yours,
Reyman V. Tulayba
Architect UAP
0017397