State House and Three Presidential Villas

CONCRETE PLACEMENT INSPECTION REPORT


Form: COSH-RAMS-02 DATE:
Location: TIME:

ITEM ACTIVITY YES NO


Concrete mix design has been approved
1
conforming requirement
Ambient temperature and weather condition
2
conform to requirement
Concrete specimens are prepared, and tests are
3
completed
Methods and equipment used for placing
4
concrete have been approved
It is not allowed to add water to concrete to
5
change its consistency on site
Height and methods for placing concrete conform
6
to design and construction specification
Vibration methods for concrete satisfy the
7
requirement of CONSULTANT inspector.
Exposed concrete surfaces conform to the
8
design drawing requirement
9 Concrete has been cured in time.
REMARKS:

CONTRACTOR CONSULTANT
APPROVAL CIVIL ENGINEER
ENGINEER

NAME

SIGNATURE

DATE