Cable Selection
Cable Selection
B
Sizing
Mohamed Yousry
©Mohamed U3
Derating Factors
©Mohamed U3
Derating Factors
1- Air Temperature
2- Ground Temperature
3- Depth of Burial
©Mohamed U3
4- Trefoil or Flat Formation Factor for 3ph single 5- Trefoil or Flat Formation Factor for 3ph multi-core
core laid in ground laid in ground
©Mohamed U3
6- Grouping Factor for 3ph multi core cable laid in 7- Grouping Factor for 3ph single core cable laid in
air air
©Mohamed U3
Relation between
(Protective
device ,Cable &
Load)
©Mohamed U3
Sizing of CB & C.S.A of 1- Calculate The Load Current (Ib).
Cables
2- Calculate The Rating of C.B
©Mohamed U3
1- Calculate The Load Current (Ib). For Single Phase Loads:
𝑝 = 𝑉 ∗ 𝐼𝑏 ∗ 𝑝. 𝑓
𝑆 = 𝑉 ∗ 𝐼𝑏
𝑝 = 𝑠𝑞𝑟𝑡(3) ∗ 𝑉 ∗ 𝐼𝑏 ∗ 𝑝. 𝑓
S= 𝑠𝑞𝑟𝑡(3) ∗ 𝑉 ∗ 𝐼𝑏
©Mohamed U3
2- Calculate The Rating of C.B
Then take the next step rating from
C.B rating Standard.
©Mohamed U3
3- Calculate The Derating Factors according to
installation.
𝐶.𝐵 𝑅𝑎𝑡𝑖𝑛𝑔
𝐼𝑐𝑎𝑏𝑙𝑒 =
𝐷.𝐹1∗𝐷.𝐹2∗𝐷.𝐹3…
©Mohamed U3
For Neutral Cable: According
to IEC:
• If C.S.A <= 35𝒎𝒎𝟐 ∴ 𝐂. 𝐒.𝐀 𝐟𝐨𝐫 𝐧𝐞𝐮𝐭𝐫𝐚𝐥
= 𝐂. 𝐒.𝐀 𝐟𝐨𝐫 𝐥𝐢𝐧𝐞
(full-Neutral)
©Mohamed U3
Cable Description Formula
No of cables // (no of core + N)mm² A/B/C/D
©Mohamed U3
How to write Cables on
SLD • Cables:
(4x240) 𝑚𝑚2 CU/XLPE/PVC
(3x240+1X120) 𝑚𝑚2 CU/PVC/PVC
2//(4x240) 𝑚𝑚2 CU/XLPE/PVC
©Mohamed U3