Sr. No. Dust Mitigation Measures Complied / Non Complied/ Not Applicable
Dust / Wind breaking walls of appropriate height have been provided around the
1
periphery of the construction site.
Tarpaulin or green net on scaffolding around the area under-construction and the
2
building.
All vehicles including carrying construction material and construction debris
3
should be cleaned and wheels washed.
All vehicles including carrying construction material and construction debris are
4
fully covered and protected.
All construction debris and construction material of any kind is stored on the site
5
and not dumped on public roads or pavements.
No loose soil or sand and construction & Demolition waste or any other
6
construction material that causes dust shall be left uncovered.
No grinding and cutting of building materials in open area Wet - jet should be
7
used in grinding and stone cutting.
Unpaved surfaces and area with loose soil should be adequately sprinkled with
8
water to suppress dust.
Roads leading to or at construction sites must be paved and black topped i.e.
12
metallic roads (for >20,000 sqm built up area).
13 Installation of Anti -Smog Gun(S).
Dust mitigation measures shall be displayed prominently at the construction site
14
for easy public viewing.