Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/336878502

Mine to mill optimisation in Sarcheshmeh copper mine, Kerman, Iran

Conference Paper · September 2019

CITATIONS READS

0 1,055

2 authors:

Nima Rafeeian Mohammad Taji


Islamic Azad University of Shahrood Islamic Azad University of Shahrood
4 PUBLICATIONS 4 CITATIONS 35 PUBLICATIONS 189 CITATIONS

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Creativity in architecture View project

Technical and Economical Studying of Shovel-Truck and Continuous Hauling System to Rock Fragmentation in Sarcheshmeh Copper Mine View project

All content following this page was uploaded by Mohammad Taji on 06 May 2020.

The user has requested enhancement of the downloaded file.


Helsinki Conference Proceedings 2019, R. Holmberg et al
© 2019 European Federation of Explosives Engineers, ISBN 978-0-9550290-6-6

Mine to mill optimisation in Sarcheshmeh copper mine,


Kerman, Iran

N. Rafeeian & M. Taji


Department of mining engineering, Sahrood branch, Islamic Azad universitey, Shahrood, Iran

A. Nikkhah
Blasting Sciences Research Centre, Tehran, Iran

ABSTRACT: Mine to mill optimisation will lead to a systematic reduction of production costs in an open
mine. In this paper, mine to mill optimisation has been designed and implemented in the Sarcheshmeh
copper mine. At first, databases have been provided. Then, specific drilling, specific charge and specific
loading indices have been calculated and measured. With the help of statistical analysis, the relation
between proper fragmentation of the blast and performance and efficiency of other production systems
was studied. Among the parameters under study, the specific charge and the hole diameter have a very
high correlation coefficient with and , so that in most of the proposed models, the correlation
coefficient was higher than 0.9. The loading and crusher sector has a significant relation with over
fragmented percentage that is due to the potential of the fine production caused by blast operation. The
optimisation of the effective parameters on fragmentation was studied by design of experiments (DOE)
method, where the specific charge was ranked first in terms of importance.

1 INTRODUCTION The mine-to-mill strategy is a multidisciplinary


combination and requires input from different
Optimisation of mine to mill is a systematic disciplines such as geological unit, planning unit,
strategy to reduce energy and cost in mining and drilling unit and blasting unit, production unit, and
processing. This method tries to minimise crusher and mill units (Silva et al. 2015). Blast is
consumed energy in all stages of optimisation of one of the main operations in any mining process.
the size reduction process (Adel et al. 2006). Mine Generally, it accounts for between 30% and 40%
to mill or M2M is actually a holistic operation of the mining costs, as well as having a direct
strategy to optimise mining and processing effect on part of the cost-effectiveness operation
operations. This method tries to minimise and related activities such as loading, transport,
consumed energy by particle size reduction safety, crusher and milling downstream activities
processes. (Ndibalema 2008).

- 169 -
Table 1. Mine to mill optimisation studies (optimisation domain).

Mechanical
Row Researchers Drilling Blasting crushing Loading Haulage Crushing Milling

1 Valery, W. et al. 2019 ✓ ✓ ✓ ✓


2 Kanchibotla, S.S. et al. 2018 ✓ ✓ ✓ ✓ ✓
3 Nageshwaraniyer, S.S. et al. 2018 ✓ ✓ ✓ ✓
4 Klein, B. et al. 2018 ✓ ✓ ✓
5 Johnson, C. 2018 ✓ ✓ ✓
6 Beyglou, A. et al. 2017 ✓ ✓ ✓ ✓
7 Zhang, Z. 2017 ✓ ✓ ✓ ✓ ✓
8 Jug, J. et al. 2017 ✓ ✓ ✓
9 Esen, S. 2017 ✓ ✓ ✓ ✓ ✓
10 Khademian, A., Bagherpour, R. 2017 ✓ ✓
11 Awuah-Offei, K. 2016 ✓ ✓
12 Valery, W. et al. 2016 ✓ ✓ ✓ ✓
13 Ebrahimi, E. et al. 2016 ✓ ✓ ✓ ✓
14 Carrasco, C. et al. 2016 ✓ ✓ ✓ ✓
15 Kanchibotla, S.S. et al. 2015 ✓ ✓ ✓ ✓ ✓
16 Silva, A.C. et al. 2015 ✓ ✓ ✓ ✓ ✓
17 Rosa, D.L. et al. 2015 ✓ ✓ ✓ ✓ ✓
18 Murr, D. et al. 2015 ✓ ✓ ✓ ✓ ✓
19 Ballantyne, G.R. et al. 2015 ✓ ✓ ✓ ✓
20 Perälä, A. et al. 2015 ✓ ✓ ✓ ✓
21 Eloranta, J. 2014 ✓ ✓ ✓ ✓
22 Nadolski, S. et al. 2014 ✓ ✓ ✓
23 Eloranta, J. 2013 ✓ ✓ ✓
24 Taji, M. et al. 2013 ✓ ✓ ✓
25 Choudhary, B.S. 2013 ✓ ✓ ✓ ✓
26 Beyglou, A.H. 2012 ✓ ✓ ✓ ✓ ✓ ✓ ✓
27 Rybinski, E. et al. 2011 ✓ ✓ ✓ ✓ ✓
28 Mwansa, S. et al. 2010 ✓ ✓ ✓ ✓ ✓
29 Hikita, D.H. 2008 ✓ ✓ ✓ ✓
30 Ndibalema, A. 2008 ✓ ✓ ✓ ✓ ✓ ✓
31 Esen, S. et al. 2007] ✓ ✓ ✓ ✓
32 Dance, A. et al. 2007 ✓ ✓ ✓ ✓
33 Bye, A. 2006 ✓ ✓ ✓ ✓
34 Adel, G. et al. 2006 ✓ ✓ ✓ ✓ ✓
35 Kose, H. et al. 2005 ✓ ✓ ✓ ✓
36 Palangio, T.W. et al. 2005 ✓ ✓ ✓ ✓
37 Eloranta, J. 2003 ✓ ✓ ✓
38 Kanchibotla, S.S. 2003 ✓ ✓ ✓ ✓
39 Workman, L. & Eloranta, J. 2003 ✓ ✓ ✓ ✓
40 Scott, A. et al. 2002 ✓ ✓ ✓ ✓ ✓ ✓ ✓
41 Valery, W. & Jankovic, A. 2002 ✓ ✓ ✓ ✓ ✓
42 Grundstrom, C. et al. 2001 ✓ ✓ ✓ ✓ ✓
43 Paley, N. & Kojovic, T. 2001 ✓ ✓ ✓ ✓
44 Eloranta, J. 2001 ✓ ✓ ✓
45 Strohmayr, S. & Valery, W. 2001 ✓ ✓ ✓ ✓ ✓
46 Valery, W. et al. 2001 ✓ ✓ ✓ ✓
47 Herbst, J.A. & Blust, S.L. 2000 ✓ ✓ ✓
48 Eloranta, J. 1999 ✓ ✓ ✓ ✓ ✓ ✓
49 Kanchibotla, S.S. et al. 1999 ✓ ✓ ✓ ✓ ✓
50 Kanchibotla, S.S. et al. 1998 ✓ ✓ ✓ ✓

- 170 -
In studies conducted, an effective relationship Many optimisations have been made in
has been found between the use of explosive different mining and processing units with the
consumption and the grindability of ores. The view of optimizing mine to mill over the past two
energy from blasting energy and its distribution decades in mines around the world. Table 1
has shown that fragmentation in the primary illustrates some of these examples with their
crusher is highly influential, which has led application in different parts of the operation and
researchers to work hard to understand the downstream processes, and their relationship with
mechanisms involved in this process (Murr et al. mine to mill optimisation. In most cases, the effect
2015). Blast fragmentation is one of the most of the blasting operation in mine to mill projects
important blast results and outputs. The effect of has been pointed and emphasised as a key factor.
fragmentation, has been proven on the next stages
of the production cycle of loading, transport, and 2 METHODOLOGY
processes in the downstream process such as
crushing and milling. A good fragmentation not The statistical analysis methodology is to optimise
only improves production efficiency but also database consists of several categories of data.
reduces overall mining operation costs Data related to drilling holes and bench height,
(Kanchibotla 2003). In general, the main purpose blasting and drilling conditions, specific charging,
of a blasting operation is to achieve the specific loading, and specific crushing. The
fragmentation caused by the optimal blast and measurements from the mining site, combined
optimal fragmented muck pile shape for efficient with the size of the fragmented stone fractions
loading and transportation. It has also been proven resulting from the desired blast ( ) and ( ),
that an optimum blasting operation has had a has been combined into six blasting blocks to
positive and significant effect overall on the model the production process. Figure 1 shows the
economy of mining operations. To this end, a methodology of the research.
precise and systematic implementation of the mine This data has been used to develop site-specific
to mill concept will be required (Jankovic & models for fragmentation from blast, loading and
Valery 2002). primary crushing. This methodology allows

Create database

Drilling Unit Blasting Unit Loading Unit Crushing Unit

A. Collected Technical data B. Collected Technical data C. Collected Technical data D. Collected Technical data
unit drilling unit blasting unit loading unit crushing

Create database 𝑫𝟖𝟎 , 𝑫𝟓𝟎

Prediction optimal models

Figure 1. Flowchart of research methodology.

- 171 -
customised blast patterns that can optimise and this mine is 1763 milliard tons with cut-off grade
extend the loading and primary crusher. The of 0.25% and average grade of 0.60%. The height
purpose of this methodology is to minimise the of benches of Sarcheshmeh copper mine is 12.5 m
overall cost of the whole process, reduce energy and the width of benches is 8.75 m. A wide bench
consumption, and ensure that the changes created with the width of 23.75 m is periodically placed
will always have a positive effect on the entire for each of the four benches. Final slope of the
mining operation. This methodology also allowed wall of mine is currently equal to 34 to 36°. Also,
the mine to increase its production significantly. the width of mine roads is considered as 30 m and
In this study, the blast team has modified the its slope as 8% (Sarcheshmeh 1 2015).
blast parameters and evaluated the effects of these
changes by computer application and site 3.1 Database description and data collection
measurements in-situ. Implementation of this
study began with Sarcheshmeh mine by collecting To investigate the mine to mill in Sarcheshmeh
six blast blocks used in blasting operation. copper mine, drilling unit database, blast unit,
Blast patterns include specifications for drilling loading unit, and crusher unit was created as
holes (spacing, burden, hole diameter, hole below. Tables 4 and 6, illustrate the database
height). bench height, blasting block size, specific required for six blasting blocks.
drilling, specific charge, specific loading and
specific crusher have also been included in these 3.1.1 Drilling unit
patterns.
Production holes are drilled with a diameter of 6,
Table 2. Description of collected parameters to 9, 9.5, and 10 inches. Paying attention to ore and
create database. waste of the drilling pattern of 5 × 6, 5 × 6.5, 6 ×
7, 7 × 8, 7 × 8.5, 7 × 9, 7.5 ×9, 7×9.5, 7.5 ×10 m
Parameter (unit) Symbol are designed and implemented. Sub-drilling is 2.5
Diameter (inch) D m and the mean length of 14.5-15 m holes
Hole length (m) H (Sarcheshmeh 2 2015).
Burden (m) B
3.1.2 Blast unit
Spacing (m) S
Volume of blast block ( Nonel and detonating cord are applied for
Specific drilling ( initiation system and Pentolite booster and
Emuline depending on hole diameter used as
Specific charge ( booster. In dry mining conditions, ANFO or a
combination of ANFO with emuline are used and
50% input dimensions (cm)
in wet conditions Emulan is the main charge
80% input dimensions (cm) (Sarcheshmeh 2 2015). The largest and smallest
volume of blasting blocks is taken 105525.29 and
Tonnage of loading per hour (ton/h) 7875.02 cubic metres respectively. Moreover, the
Specific loading (h/m3) average blasting blocks volume has been equal to
47132.87 cubic metres. To investigate blast
Specific crushing fragmentation, image analysis method was used to
obtain the passing distribution curve of blasting
patterns. In this study, Split Desktop software was
used to measure fragmentation in Sarcheshmeh
3 CASE STUDY - SARCHESHMEH COPPER copper mine.
MINE The fragmentation efficiency index was
calculated according to Equation 1 (Taji 2014):
The Sarcheshmeh porphyry copper deposit is the
biggest copper mine in Iran and one of the (1)
largest Oligo-Miocene deposits in the world.
Sarcheshmeh mine is situated in south of Iran at In which: FE Fragmentation efficiency
30° N, 56° E and about 160 km southwest of index (%), F: Fine fragmentation (%), B:
Kerman city. This mine is located in a semi-arid boulder (%).
climate with a mean annual precipitation of 440 Based on this index, fragmentation rate is
mm (Khorasanipour et al. 2012) and the reserve of divided into six categories, which can be obtained

- 172 -
Figure 2. The location Sarcheshmeh copper mine (S-E of Iran) (Seifpanahi-Shabani et al. 2014).

Table 3. The degree of fragmentation (Taji 2012).

Class I II III IV V VI
Efficiency (%) 95< 85-95 75-85 65-75 50-65 50>
Qualitative Excellent Very good Good Moderate Unsuitable Very poor

to determine the fragmentation quality of each In the Ore, the size of the inlet opening of
blasting block by Table 3. To determine the fine Sarcheshmeh copper mine crusher mill is 1524
fragmentation as well as the boulder, there are mm and the jaw is 203 mm. In this case, the lower
several methods. The most common ones, by limit of coarse aggregate should be 122
considering the sizes of the inlet opening and the centimetres and the upper limit of the fine
primary crusher jaw, calculate the appropriate size fragmentation is considered as 8 centimetres. In
in which boulder 80% of the inlet opening of the Sarcheshmeh copper mine, in addition to cable
primary crusher and also fine fragmentation is shovel and hydraulic, mechanical shovels also
considered to be a one-fifteenth boulder size (Taji perform the loading operation. Since this machine
2014). does not have the ability to load boulders, and also

- 173 -
Table 4. Fragmentation efficiency blasting recorded in the blast block.

Blast Rock type Fine fragmentation (%) Boulder (%) Efficiency (%)
1 Dike +AN 4.68 8.59 70 0 79
2 AN 2.60 6.2 82.5 0 75.25
3 SP+ Dike +BD 6.55 11.85 53 0 84.10
4 SP+ Dike 1.64 25.73 35 11 78.5
5 SP+ Dike 10.39 24.49 35 0 89.50
6 LF+ Dike 6.72 14.13 50 0 85

S.c.Porgh: Sarcheshmeh Porphyry, AN: Andesite, L.F.Porph: Late Fine Porphyry, QS: Quartz Sericite, Bio:
Biotite, SQ: Sericiti Quartz.

Table 5. Collected database relating to drilling, blasting, loading and crushing units.

Blast B S D Fe F
NO.
(m) (m) (Inch) (Cm) (Cm) % %
1 7 9.5 9.5 0.018 0.322 4.68 8.59 0.005 0.167 79.00 70.00
2 7 9.0 6.0 0.037 0.256 2.60 6.20 0.002 0.167 75.25 82.50
3 7 9.0 10.0 0.019 0.369 6.55 11.85 0.003 0.178 84.10 53.00
4 5 6.0 6.0 0.024 0.381 10.46 25.73 0.006 0.178 78.50 35.00
5 7 9.0 9.5 0.019 0.436 10.39 24.49 0.005 0.178 89.50 35.00
6 7 9.0 9.5 0.019 0.329 6.72 14.13 0.002 0.178 85.00 50.00

for the being operation of the project, the lower six shovel 5.7 cubic metres, 8 trucks with 220
limit of boulder is considered as 100 cm. Table 4 tons, 60 trucks with 136 tons, 40 trucks with 100
illustrates the size of the aggregate characteristic tons and also 35 and 60 ton trucks (Sarcheshmeh 2
and the fragmentation efficiency of six blasting 2015). Specific loading with the symbol ( ),
blocks of the ore. It can be concluded that 70% of specific loading of the jth blasting block (hours per
blasting blocks of this mine are in good condition cubic metre), which is calculated by dividing the
in terms of fragmentation. With an average of total time available for loading machineries of jth
these blasting patterns, the fragmentation blasting block (per hour) to the total volume of the
efficiency was calculated as 81.89%. j-th blasting block (cubic metre) (Taji 2012).
In addition, , in comparison with ,
shows better performance and fragmentation 3.1.4. CRUSHER UNIT:
efficiency so the correlation coefficient of
fragmentation efficiency obtained with and Rock fragmentation in the first stage is carried out
is respectively 0.675 and 0.595 (Nikkhah by a primary crusher of the Gyratory 1524-2260
2015). mm (Sarcheshmeh 2 2015). Specific crusher with
symbol ( ), Specific crusher of jth blasting block
3.1.3. LOADING UNIT: ( ), is calculated by dividing the total
energy consumption of j-th blasting block (per kw)
loading and transport operation by two shovel by on total tonnage of entering rock to crusher j-th
15 cubic metres, four shovel by 12 cubic metres, blasting block (per cubic metre) (Nikkhah & Taji

- 174 -
Table 6. Statistical data descriptions.

Parameter N Mean Std. Deviation Minimum Maximum


B (m) 6 6.67 0.816 5 7
S (m) 6 8.583 1.2813 6.0 9.5
D (inch) 6 8.417 1.8819 6.0 10.0
H (m) 6 15.00 0.000 15 15
6 12.500 0.0000 12.5 12.5
6 0.02267 0.007339 0.018 0.037
6 0.34883 0.061271 0.256 0.436
6 6.9000 3.11214 2.60 10.46
6 15.1650 8.17603 6.20 25.73
6 0.00383 0.001722 0.002 0.006
6 0.17433 0.005680 0.167 0.178
Fe 6 81.8917 5.22307 75.25 89.50
F 6 54.2500 19.00987 35.00 82.50

62018). The specific fixed gravity and specific process of changes can be learned.
gravity of fragmented rock resulting from the A statistical analysis was conducted using
blasting operation is 2.57 and 1.8 tons per cubic multi-parametric linear curve fittings on the data
metre, respectively. presented in Tables 4 and 6. Here the goal of the
multi-parametric linear curve fitting method was
4 DATA ANALYSIS to determine the priority of the effective
parameters mine to mill optimisation.
SPSS Statistics version 22, a statistical application The Durbin-Watson test has been used to
and data management by Windows, was used for compare the predictive accuracy of linear
the statistical analysis. By examining the regression. In the Durbin-Watson test, the
dependent and independent variables, the obtained value is between 0-4 (Mirzadeh 2010).
relationship between each is obtained and the The predicted model is acceptable. Different linear

Table 7. Regression relation of with drilling and blasting unit.

Predict model R R2 Durbin-


Watson

1 0.981 0.962 1.04


2 0.849 0.721 2.166
3 0.875 0.766 2.508
4 0.963 0.927 1.906
5 0.838 0.703 2.449
6 0.967 0.934 1.068
7 0.801 0.642 2.090
8 0.959 0.920 1.392
9 0.970 0.941 0.946

- 175 -
Table 8. Regression relation of mining and drilling and blasting units.

Predict model R R2 Durbin-


Watson

Loading unit 1 0.889 0.791 2.444


1 0.977 0.955 1.550
Crushing
unit 2 0.951 0.904 1.885

models have been tested and the model has the The first matter is the design of the test and its
highest coefficient and the simplest one has been correct model, and the second is analysis and
chosen as the best equation. statistical analysis. These two issues are closely
related; because the analysis method depends on
4.1 Relationship between with the applied design and is used to reduce the
drilling and blasting unit oscillation during the test (Sadeghi-Avalshahr et
al. 2012). The design process of the tests is as
In regression analysis, among the studied follows (Sadeghi-Avalshahr et al. 2012):
parameters, specific drilling, specific charge, hole
distances and hole diameter have been effective on − Selection of signal factors and noise factors
, and in the study of , it was found that the along with corresponding levels. The signal
factors are in fact the input parameters of the
specific charge and hole diameter have the most
problem that change during the tests in order
effect. Nevertheless, correlation coefficient of the
to achieve optimal condition, in terms of
proposed models expresses that specific charge
selective levels and the matrix of tests. Noise
and diameter of the hole are more significant
factors also refer to all factors that make
compared to specific drilling (Table 7).
changes, but are assumed constants during
tests.
4.2 Relationship between mining units with
drilling and blasting units − Calculation of the loss function to determine
the variation between the test results and the
Linear regression was used in order to predict and desired values of this function according to
determine the effective parameter on the loading the problem conditions, which is computed
and crushing unit. Among input parameters, with the help of formulas 2 to 5.
affects the specific loading, and due to the high First mode: The smaller value represents the
potential of fine fragmentation producing, and optimal mode:
specific loading was significantly related to the
model, effects more on specific crushing. (2)

5 MINE TO MILL OPTIMISATION USING Second mode: The larger value represents the
DESIGN OF EXPERIMENTS (DOE) optimal mode:
METHOD
(3)
In the mineral industry and in the factories, tests
are daily carried out to increase the knowledge and Third mode: Nominal size is desirable:
identification of the various processes in them.
Understanding the process behaviour, amount of (4)
variability and its effect on the process is essential
for continuous improvement of the quality of the Where n is the number of repetitions and
product. There is a need for practical testing to denote measured outputs, and is the
find the right answer to numerous questions in desirable nominal size.
business, industry, research. Designing some tests
on the way of tests is used as a powerful technique − Calculation of signal-to-noise ratios for each
to achieve this goal. of the following equation:

- 176 -
Figure 3. Algorithm for optimisation of dependent parameters through test designing.

orthogonal array. For this purpose, first, the degree


(5)
of freedom was calculated using Equations 6 and
− Calculation of the signal-to-noise ratio for 7, then, according to the degree of freedom, the
each level of the parameters. In the Taguchi minimum number of tests was calculated from
method, the levels of the parameters that have equation (Sadeghi-Avalshahr et al. 2012).
the highest signal-to-noise ratios (regardless According to Table 10, this includes three levels
of the type of loss function) are presented as with three input parameters. Using the Equation 8,
optimal levels at least 27 tests were designed, then the response
function variable was obtained for each level of
− Determination of the significance of each of the total input parameters using SPSS model 1
the parameters using the ANOVA (Table 10).

− Data analysis and prediction of output in Table 9. Input parameters and corresponding levels.
optimal mode
Level Input parameter
5.1 Optimisation S (m) D (inch)
1 8.5 9 0.256
By analysing the statistics, it was determined
from the case study database of specific charge, 2 9 9.5 0.329
spacing and hole diameter are effective 3 9.5 10 0.381
parameters. In order to predict optimal mode of
with the aim of implementing the mine to
For each factor = (number of levels - 1) (6)
mill approach, first, the input parameters
corresponding levels was formed (Table 9). In For each factor = (number of levels - 1)
classification, sometimes it is necessary to * (number of levels - 1) (7)
eliminate a level. The level that its frequency for
parameter is less, must be removed. Then, select Minimum number of tests = Total amount of
the appropriate orthogonal array in the next step. freedom of factors +Total degrees of freedom of
The number of required degrees of freedom interactions+ degree of freedom for the total
must be calculated to select the appropriate average (8)

- 177 -
Main Effects Plot for SN ratios
Data Means
S D

-10
-12
-14
Mean of SN ratios

-16
-18
8.5 9.0 9.5 9.0 9.5 10.0
Sc

-10
-12
-14
-16
-18
0.256 0.329 0.381
Signal-to-noise: Smaller is better

Figure 4. Signal-to-noise ratios for different parameter levels.

Table 10. Designing of input parameters tests. Table 11. Response table for signal to noise ratios,
where smaller is better.
Test Parameters Response
number variable Parameter
S (m) D (inch) Level S (m) D (m)
1 8.5 9 0.256 3.177436
2 8.5 9 0.256 3.177436 1 -14.757 -14.192 -8.658
3 8.5 9 0.256 3.177436 2 -13.943 -13.634 -15.145
4 8.5 9.5 0.329 6.182199
5 8.5 9.5 0.329 6.182199 3 -13.005 -13.880 -17.902
6 8.5 9.5 0.329 6.182199 Delta 1.752 0.558 9.244
7 8.5 10 0.381 8.325311
Rank 2 3 1
8 8.5 10 0.381 8.325311
9 8.5 10 0.381 8.325311
10 9 9 0.329 5.720199
11 9 9 0.329 5.720199 The statistical analysis of variance was used
12 9 9 0.329 5.720199 to find out the relative importance of the
13 9 9.5 0.381 7.863311 parameters on each of the outputs, (Equations 9
14 9 9.5 0.381 7.863311 & 10) (Park 1995).
15 9 9.5 0.381 7.863311
16 9 10 0.256 2.743936
17 9 10 0.256 2.743936 (9)
18 9 10 0.256 2.743936
19 9.5 9 0.381 7.401311
20 9.5 9 0.381 7.401311 (10)
21 9.5 9 0.381 7.401311
22 9.5 9.5 0.256 2.281936
23 9.5 9.5 0.256 2.281936
Where is the sum of squares of each
24 9.5 9.5 0.256 2.281936 parameter, is the mean of the sum of squares
25 9.5 10 0.329 5.286699 for each parameter, is the degrees of
26 9.5 10 0.329 5.286699 freedom of factors, and is the sum of the
27 9.5 10 0.329 5.286699
total squares.

- 178 -
Table 12. Analysis of variance for SN ratios.

Source DF Seq SS Adj SS Adj MS F P


S (m) 2 4.613 4.613 2.3063 8.95 0.101
D (inch) 2 0.470 0.470 0.2349 0.91 0.523
2 135.124 135.124 67.5621 262.07 0.004
Residual Error 2 0.516 0.516 0.2578
Total 8 140.722

importance to , but also in this situation, the


Table 13. Input parameters corresponding levels. value of F is base of the variance results. A
parameter with a larger F value will be regarded as
Level Input parameter
an effective parameter in operational conditions.
S (m) D (inch) Here it is also apparent that the F value of specific
1 8.5 9 0.018 0.256 charge is greater than the value of F of other
parameters, which is the confirmation of previous
2 9 9.5 0.019 0.329
calculations.
3 9.5 10 0.024 0.381
5.2 Optimisation

As Table 11 illustrates, the specific charge The corresponding levels, were provided to
parameter takes the first place among the input optimise the , using the parameters of spacing,
parameters and the rest of the parameters have diameter of the hole, specific drilling and specific
subordinate effect on . This was calculated by charge, (Table 13). Then, the required number of
performing a variance analysis the results have degrees of freedom was first calculated to select
been presented in Table 12. The value of P should the orthogonal array, next the response function
be at a significance level of less than 0.005%. This variable was calculated using the model 9
does not mean that these parameters are, like the of Table 8 for each level of the total input
specific charge, at the same level in terms of parameters.

Main Effects Plot for SN ratios


Data Means

S D
10

-10
Mean of SN ratios

-20

8.5 9.0 9.5 9.0 9.5 10.0


Sd Sc
10

-10

-20

0.018 0.019 0.024 0.256 0.329 0.381

Signal-to-noise: Smaller is better

Figure 5. Signal-to-noise ratios for different levels of parameters.

- 179 -
As shown in Table 14, the specific charge Technical report, Virginia Polytechnic
parameter takes the first place among the input Institute & State University, page 157.
parameters, and other parameters hold subordinate
places, indicating that the consumed energy Awuah-Offei, K. 2016. Energy efficiency in
(explosives) plays a significant role in the crushing mining: a review with emphasis on the role of
process. operators in loading and hauling operations.
Journal of cleaner production 117, pp. 89-97.
Table 14. Response table for signal to noise ratios, Ballantyne, G. R., Foggiatto, B., Carrasco, C.,
where smaller is better.
Hilden, M. & Powell, M.S. 2015. The impact
Parameter of grade engineering on SAG milling.
International conference on semi-autogenous
Level S (m) D (m) and high pressure grinding technology, SAG
1 -18.321 -19.188 -18.730 8.414 Conference 2015, Vancouver.
2 -5.387 -5.534 -12.610 -20.200 Beyglou, A.H. 2012. Improvement of
3 -12.358 -11.343 -4.725 -24.280 blast-induced fragmentation and crusher
Delta 12.934 13.654 14.005 32.694 efficiency by means of optimised drilling and
blasting in Aitik, Masters thesis, 54 pages.
Rank 4 3 2 1
Beyglou, A., Johansson, D., & Schunnesson, H.
2017. Target fragmentation for efficient
loading and crushing - the Aitik case. Journal
6 CONCLUSION of the Southern African institute of mining and
In this research, mine to mill optimisation was metallurgy, vol.117 no.11, ISSN 2411-9717.
studied. The purpose of this study is to rank the
Bye, A. 2006. The strategic and tactical value
parameters affecting the fragmentation of the mine
of a 3D geotechnical model for mining
to mill. For this purpose, key and effective
optimisation, Anglo Platinum, Sandsloot open
parameters of the units of drilling, blast, loading
pit. Journal of the Southern African institute of
and crushing were compiled. Then, using
mining and metallurgy, Volume 106, No.2, pp.
statistical analysis, significance level and the
97-104.
effective parameters on fragmentation of blasting
operation were studied. In regression analysis and Carrasco, C., Keeney, L., Napier-Munn, T.J. &
among the studied parameters, parameters of Bode, P. 2016. Unlocking additional value by
specific drilling, specific charge, hole spacing and optimising comminution strategies to process
hole diameter were effective on , and in the grade engineering streams. Minerals
study of , it was found that the specific charge engineering, Vol.103, pp. 2-10.
and diameter of the hole are the most effective, but
the correlation coefficient of the proposed models Choudhary, B.S. 2013. Firing patterns and its
Indicates that specific charge and hole diameter effect on muckpile shape parameters and
are more significant than specific drilling. Also, fragmentation in quarry blasts. International
the high correlation coefficient of the proposed journal of research in engineering and
models indicates a significant relation between the technology, Volume 02, Issue 09, pp. 32-45.
specific charge and fragmentation caused by the
blast. Subsequently, with the design of classifying Dance, A., Valery, W., Jankovic, A., LaRosa, D.
tests, the ranking of the effective parameters of the & Esen, S. 2007. Maintaining the benefit -
mine to mill was studied, which has had a how to ensure mine to mill continues to work
significant impact on the specific charge. This for you. Proceedings of Ninth mill operators
result itself indicates that the energy consumed by conference, Fremantle, Australia, pp. 215-223.
explosives plays a significant role in the crushing
process. Ebrahimi, E., Monjezi, M., Khalesi, M.R. &
Armaghani, D.J. 2016. Prediction and
REFERENCES optimisation of back-break and rock
fragmentation using an artificial neural
Adel, G., Kojovic, T., & Thornton, D. 2006. Mine network and a bee colony algorithm.
to mill optimisation of aggregate production. Bulletin of engineering geology and the

- 180 -
environment, Volume 75, Issue 1, pp. Jankovic, A & Valery, W. 2002. Mine to mill
27–36. optimisation for conventional grinding circuits
a scoping study. Journal of mining and
Eloranta, J. 1999. Blasting down the cost of metallurgy, 38(1–4):49–66.
taconite pellets. Proceedings of the 72nd
annual meeting of the Minnesota section of the Johnson, C. 2018. Effect of wave collision on
SME, Duluth, Minnesota. fragmentation, throw, and energy efficiency of
mining and comminution. Energy efficiency in
Eloranta, J. 2001. Optimised iron ore blast designs the minerals industry, pp. pp 55-70.
for SAG/AG Mills. Proceedings of the
international conference on autogenous and Jug, J., Strelec, S., Gazdek, M. & Kavur, B. 2017.
semi-autogenous grinding technology, Fragment size distribution of blasted rock
Vancouver, BC, Canada ,Vol. 1, pp. 262-270. mass. IOP Conference series: earth and
environmental science, Volume 95, ISSN
Eloranta, J. 2003. Characterisation of the pre and 1755-1307.
post blast environments. Proceedings of the
annual conference on explosives and blasting Kanchibotla, S.S., Morrell, S., Valery, W. &
technique. Volume 2, pp. 263-272. O'Loughlin, P. 1998. Exploring the effect of
blast design on SAG mill throughput at
Eloranta, J, 2013. Optimising non-ideal blasting KCGM. In mine to mill conference. Brisbane.
for ideal grinding. ISEE 39th Annual
conference on explosives and blasting Kanchibotla, S.S., Valery, W. & Morrell, S. 1999.
technique, Eloranta & Associates Inc. Modelling fines in blast fragmentation and its
impact on crushing and grinding. In Explo
Eloranta, J. 2014. Non-ideal blasting for ideal ‘99–a conference on rock breaking, The
grinding - part two. Technical paper, Eloranta Australasian Institute of Mining and
& Associates Inc. Metallurgy, Kalgoorlie, Australia, pp. 137-
144.
Esen, S., La Rosa, D., Dance, A. & Valery, W.
2007. Integration and optimisation of blasting Kanchibotla, S.S. 2003. Optimum blasting - Is it
and comminution processes. EXPLO minimum cost per broken rock or maximum
conference, Wollongong, NSW, The value per broken rock? Fragblast, 7(1), pp.
Australasian Institute of Mining and 35-48.
Metallurgy, pp. 1-10.
Kanchibotla, S.S., Vizcarra, T.G., Musunuri,
Esen, S. 2017. Evaluating the fragmentation data S.A.R., Tello S., Hayes A. & Moylan, T. 2015.
from copper and gold mines. 43rd Annual Mine to mill optimisation at Paddington gold
conference on explosives & blasting operations. International conference on
technique. semi-autogenous and high pressure grinding
technology, SAG Conference 2015,
Grundstrom, C., Kanchibotla, S., Jankovich, A., Vancouver.
Thornton, D. & Pacific, D.D.N.A. 2001. Blast
fragmentation for maximising the sag mill Kanchibotla, S.S., Morrison, R., Tello, S., &
throughput at Porgera gold mine. In Chenje, T. 2018. Blasting versus crushing
Proceedings of the annual conference on and additional grinding – pros and cons.
explosives and blasting technique, Volume 1, 12th International symposium on rock
pp. 383-400. fragmentation by blasting, pp.349-361.

Herbst, J.A. & Blust, S.L. 2000. Video Sampling Khademian, A. & Bagherpour, R. 2017.
for mine to mill performance evaluation. Environmentally sustainable mining through
Model calibration and simulation. control, proper selection of explosives in blasting
pp.157-166. operation. Environmental earth sciences,
76:166. https://doi.org/10.1007/s12665-017-
Hikita, D.H. 2008. The influence of blasting on 6483-2. Accessed July 2019.
Kemess hypogene ore milling. Doctoral
dissertation, Queen’s University, Canada, 180 Khorasanipour, M., Tangestani, M.H., Naseh, R.
pages. & Hajmohammadi, H. 2012. Chemical

- 181 -
fractionation and contamination intensity of mining operation in open-pit mines. Case
trace elements in stream sediments at the study: Sarcheshmeh copper mine. Volume 28,
Sarcheshmeh porphyry copper mine, SE Iran. Issue 110, Page 267-272.
Mine water environment, 31, 199–213.
Palangio, T.W., Palangio, T.C. & Maerz, N.
Klein, B., Wang, C., & Nadolski, S. 2018. Energy- 2005. Advanced automatic optical blast
efficient comminution: best practices and fragmentation sizing and tracking. European
future research needs. Energy efficiency in the Federation of Explosives Engineers
minerals industry, pp. 197-211. conference proceedings, Brighton, pp. 259-
267.
Kose, H., Aksoy, C.O., Gönen, A., Kun, M. &
Malli, T. 2005. Economic evaluation of Paley, N. & Kojovic, T. 2001. Adjusting blasting
optimum bench height in quarries. Journal of to increase SAG mill throughput at the Red
the Southern African institute of mining and Dog mine. In proceedings of the annual
metallurgy 105, No. 2, pp. 127-135. conference on explosives and blasting
technique, Volume 1, pp. 65-82.
Mirzadeh, M.R. 2010. Statistical analysis with
SPSS. Teheran: Taymaz Pub. Park, S.H. 1995. Robust design and analysis for
quality engineering. Chapman & Hall First
Mwansa, S., Dance, A., Annandale, D., Kok, D. & Edition, London, 1995.
Bisiaux, B. 2010. Integration and optimisation
of blasting, crushing and grinding at the Perälä, A., Alli, J., Raatikainen, J. & Auranen, I.
Newmont Ahafo operation. Technical report. 2015. On-line analyser optimising mill feed
Metso Process Technology & Innovation. at FQM Kevitsa nickel-copper-PGE mine.
IFAC-PapersOnLine, Volume 48, Issue 17,
Murr, D., Workman, L., Eloranta, J., & pp. 161-165.
Katsabanis, P. 2015. Blasting influence on
comminution. International conference on Rosa, D.L., Caron, K., Valery, W., Diaz, R. &
semi-autogenous and high pressure Mamani H. 2015. Blast fragmentation impacts
grinding technology, SAG Conference 2015, on downstream processing at goldfields Cerro
Vancouver. Corona. 11th international symposium on rock
fragmentation by blasting, pp. 333-341.
Nadolski, S., Klein, B., Kumar, A. Davaanyam, Z.
2014. An energy benchmarking model for Rybinski, E., Ghersi, J., Davila, F., Linares, J.,
mineral comminution. Minerals engineering Valery, W., Jankovic, A., Valle, R. & Dikmen,
65, pp. 178–186. S. 2011. Optimisation and continuous
improvement of Antamina comminution
Nageshwaraniyer, S. S., Kim, K., and Son, Y. J. circuit. Proceedings of fifth international
2018. A mine to mill economic analysis model conference on autogenous and semi-
and spectral imaging based tracking system for autogenous grinding technology.
a copper mine. Journal of the Southern
African institute of mining and metallurgy, Sadeghi-Avalshahr, A., Babakhani, A., Mostajab,
Volume 118, No.1, pp. 7-14. H. & Zebarjad, S.M. 2012. Optimisation of
powder metallurgy process parameters for
Ndibalema, A. 2008. Capturing economic benefits production of nitinol memory alloy using
from blasting. The international conference on Taguchi method. The 6th joint conference of
surface mining The Southern African Institute Iranian metallurgical engineering society and
of Mining and Metallurgy 2008, pp. 97-112. Iranian foundry mens society.
Nikkhah, A. 2015. Technical and economical Sarcheshmeh Copper Complex 1 2015. Report of
studying of shovel-truck fleet and continuous calculating the reserve of Sarcheshmeh
hauling system to rock fragmentation in Copper Mine. Computer and technical services
Sarcheshmeh copper mine. Shahrood, Iran. department of Sarcheshmeh Copper Mine.
Masters thesis, Department of Mining
Engineering, Shahrood Branch, IAU; 2015. Sarcheshmeh Copper Complex 2 2015. Report of
Sarcheshmeh copper mine development plan.
Nikkhah, A. & Taji, M. 2018. The effect of the Sarcheshmeh Copper Mine Engineering,
underground water on production costs and Design Department.

- 182 -
Scott, A., Morrell, S. & Clark, D. 2002. Tracking Valery, W., Duffy, K.A., Jankovic, A. & Tabosa,
and quantifying value from mine to mill E. 2016. Complete optimisation from mine to
improvement. In Proceedings value tracking mill to maximise profitability. Gold and
symposium, Brisbane, Australia, pp. 77-84. Technology, Hatch Ltd. Volume 32, No. 2.
Seifpanahi-Shabani, K., Ardejani, F.D., Badii, K. Valery, W., Duffy, K.A. & Jankovic, A. 2019.
& Olya, M.E. 2014. Acid mine drainage Mine to mill optimisation. SME mineral
treatment by perlite nanomineral, batch and processing and extractive metallurgy
continuous systems. Archives of mining handbook, pp. 335-346.
sciences. 59. 10.2478/amsc-2014-0008.
Available from: Workman, L. & Eloranta, J. 2003. The effects of
https://www.researchgate.net/figure/Perlite- blasting on crushing and grinding efficiency
reservoirs-in-the-Zanjan-mines-N-W-of-Iran- and energy consumption. Proceedings of the
and-Sarcheshmeh-copper-mine-S-E- 29th conference on explosives and blasting
of_fig1_262997302, accessed 14 July 2019. techniques. International Society of Explosive
Engineers, Cleveland OH.
Silva, A.C., Martins, P.A.A., Silva, E.M.S.,
Fonseca, A.L.S., Ferrari, A.J.D., Cunha, E.B., Zhang, Z-X. 2017. Rock mechanics related to
Silva, V.M., Matthew, V.O. & Vilela, D.R.T. mining engineering. 3rd Nordic Rock
2015. Fragmentation optimisation – adopting Mechanics Symposium. International Society
mine to mill for reducing costs and increasing for Rock Mechanics and Rock Engineering,
productivity. 11th international symposium on ISBN 978-951-758-622-1.
rock fragmentation by blasting. pp. 363-368.
Strohmayr, S. & Valery, W. 2001. SAG mill
circuit optimisation at Ernest Henry mining.
Proceedings of an international conference on
autogenous and semi-autogenous grinding
technology, Vol. 3, pp. 11-42.
Taji, M., Ataei, M., Goshtasbi, K. & Osanloo, M.
2012. A new approach for open pit mine
blasting evaluation. Journal of vibration and
control, Vol. 12, No. 11, PP: 1738-1752.
Taji, M., Ataei, M., Goshtasbi, K. & Osanloo, M.
2013. ODM: a new approach for open pit mine
blasting evaluation. Journal of vibration and
control, Vol. 19 No. 11, pp. 1738-1752.
Taji, M. 2014. Structure of desired fragmentation
by blast operation in metal mines. Research
plan, Tehran, Mining Industries Development
and Renovation Organisation.
Valery, W., Morrell, S., Kojovic, T., Kanchibotla,
S.S. & Thornton, D.M. 2001. Modelling and
simulation techniques applied for optimisation
of mine to mill operations and case studies. VI
Southern hemisphere meeting on mineral
technology, Vol. 1, pp. 107-116.
Valery, W. & Jankovic, A. 2002. The future of
comminution. Proceedings of 34th
international conference on mining and
metalurgy, Bor Lake, Yugoslavia pp. 287-298.

- 183 -
View publication stats

You might also like