(1500 ID X 85 THK)
DRG NO:-P21-OHR-023366
BOILER NO ;-WH-O712-HO
REF:- I.B.R
A safety officer shall be presents all time for Safety Briefing at site.
Job Safety Analysis (JSA) must be carried out for all crane lifts and all other
tasks that have potential risk to personnel of equipment.
Pre lift study before any lifting activity.
Lift briefing and Safety briefing before any lift; assign responsibility to
all personnel involved. (Signalman, Rigger to crane driver, etc.)
Ensure all equipment required for installation is on hand and in position
before lift i.e. Chain blocks, Hammer, and Spanners. Etc.
Tag lines must be used to control lift.
Ground conditions must be ready before activities.
Set up safety rope around lifting area of Steam Drum area and put notice
board entered “KEEP OFF EXCEPT PERSONEL CONCERNED”.
Lifting equipment should be in certification and tagged.
Crane and other machinery shall be inspected and certified.
START
CONTROL POSITION OF
STEAM DRUM TO BE LIFTED
BY RIGGER FOREMAN,
RIGGER SUPERVISOR
Inspection by QC and
safety department
Finish
Lifting
All conditions adapted to the lifting procedure. Prior to commencement of
lifting works, assuredly carry out check of lifting equipment.
Assembly and erection: - Erection steam drums accordance with the Erection
Plan and drawings.
34 meter boom
2 NOS.WIRE
length
ROPE SLING
LENGTHS (58MM
X 5 METER)
(L) 5mtr
55 TONES ‘’Bow’’
SHACKLE 2 NOS
5.6 mtr
L-6mtr H-5.71 6 mtr
Safe Crane Capacity = 330.0 Ton (as per load chart with 75 % lifting capacity,
70 MT counter weight. 34 meter boom length and 18 meter radius, load lifting
capacity = 50.0 MT)
Reduced Capacity of Sling
Vertical load of sling = 40 MT
Measure length (L) = 5.0 mtr
Measure height = 4.142 meter
Reduction factor (RF) = 4.142/5.0 mtr = 0.828
Reduction sling rating in this configuration = .828 (RF) x 40.0MT =
33.136 MT
Conclusion:-
Reduction sling rating in this configuration = 33.136 MT is greater
than 30.0% of Minimum vertical rated capacity required for this lift
= 25.62 MT
DRUM LIFTING
Preparation
INSPECTION
It is necessary to record all inspection during various phases of erection
progress and to verify inspection sheets are in compliance with drawings