MEM 501 - Project Report Examplee
MEM 501 - Project Report Examplee
Winter 2022
0
Abstract
The main goal of the project is to build a 5-star hotel in one of Abu Dhabi city beaches,
discussing many activities involving planning a proper construction project. This report shows the impact
and value that will be added to Abu Dhabi government economy while discussing in detail the phases of
the project conception, planning, resources allocation, performance, cost, and the termination.
1
Table of Contents
Abstract.......................................................................................................................................................1
Table of Contents........................................................................................................................................2
Table of Figures...........................................................................................................................................3
List of tables................................................................................................................................................3
Introduction.................................................................................................................................................4
1. Project Conception, Definition, and Initiation.....................................................................................4
1.1 Project scope:....................................................................................................................................4
1.2 Project objectives:..............................................................................................................................5
1.3 Stakeholders......................................................................................................................................5
1.3.1 Stakeholders roles and responsibilities:......................................................................................5
1.4 Feasibility Study................................................................................................................................6
1.4.1 Technical Feasibility...................................................................................................................6
1.4.2 Economic Feasibility..................................................................................................................7
1.4.3 Operational Feasibility................................................................................................................8
1.4.4 Scheduling Feasibility.................................................................................................................8
1.5 Payback period..................................................................................................................................9
Project Planning..........................................................................................................................................9
2.1 Project Charter.............................................................................................................................9
2.2 WBS................................................................................................................................................11
2.3 WBS Complete Schedule.................................................................................................................13
2.4 Gantt Chart......................................................................................................................................15
3. Project Resources Allocation.................................................................................................................15
3.1 Resource Allocation........................................................................................................................15
3.2 RACI Matrix....................................................................................................................................16
3.3 Cost Calculation..............................................................................................................................18
4. Project Performance Monitor and Control.........................................................................................19
4.1 Work Overview Report....................................................................................................................20
4.2 Milestone Report.............................................................................................................................21
4.3 Late Tasks Report............................................................................................................................21
4.4 Resource Overview..........................................................................................................................22
5. Project Evaluation, Closeout, and Termination.....................................................................................22
2
5.1 Closeout Report...............................................................................................................................22
Conclusion.................................................................................................................................................23
Table of Figures
Figure 1: Hotel revenue...............................................................................................................................7
Figure 2: WBS...........................................................................................................................................12
Figure 3: WBS schedule.............................................................................................................................14
Figure 4: WBS schedule.............................................................................................................................14
Figure 5: Gantt chart..................................................................................................................................15
Figure 6: Resources allocation...................................................................................................................16
Figure 7: Cost calculation..........................................................................................................................19
Figure 8: Work overview report................................................................................................................20
Figure 9: Project overview.........................................................................................................................20
Figure 10: Milestone report.......................................................................................................................21
Figure 11: Late tasks.................................................................................................................................21
Figure 12: Resources overview.................................................................................................................22
List of tables
Table 1: Key dates.......................................................................................................................................8
Table 2: Project charter...............................................................................................................................9
Table 3: RACI Matrix...............................................................................................................................17
Table 4: Project closeout report.................................................................................................................23
3
Introduction
Abu Dhabi is one of the best tourist spots in United Arab Emirates (UAE) and the government of Abu
Dhabi is always supporting tourism and engage the people and organization to start several start-ups for
enhancing the tourism. Tourists from whole world will come to UAE as it is famous for the tourism. A
well-known company located in Abu Dhabi is planning to build a five-star hotel in one of the beaches of
Abu Dhabi. So, the company needs a complete and details project management plan for the project that
contains the estimated budget and time needed for completing the project. Along with that the resources
that are needed for completing the project will also need to recognize in the project management. This
plan will also contain the feasibility study, work breakdown structure, and closeout report for the same.
Abu Dhabi is famous for its tourism and support from the government for the foreigners and for
building new tourist places. There are some existing five start hotels are located in Abu Dhabi. The
specialty for this new hotel will be that is will be created in one of the beautiful beaches in Abu Dhabi.
Before starting the project, it is necessary to figure out the problems that they need to face during the
development process and benefits and profit that can earn by the company from the hotel. The first part of
the project management plan will be the project conception and definition that contains the feasibility
study.
4
4- To maintain the project quality according to the plan, without omitting any single part of project
work and hand over the project after revising entire the project work, to make ensure the owner
are satisfied with the project work.
5- To make sure the customer is satisfied, by finishing the project with the specification the
customer provided and exactly the customer wants.
1- To monitor the project works day-by-day and how the project team performance to avoid the
problems that are facing on the project activities to complete the project on time.
2- Adopt an effect monitoring system to handle goods, materials and other services which are used
in the project to control the budget.
3- Supervise the all the project works, to ensure that the works are carryout according to the plan
provided, to maintain the quality of the work.
4- Get the continuous feedback from owner or consultant that the owner has selected, to provide the
product the customer actually wants.
5- Continuous monitoring of weather forecast, to organize the work schedules, suppliers’
transportation, to mitigate the obstacle facing on the project performance.
1.3 Stakeholders
Stakeholders of this project defined as all internal and external stakeholders. Internal stakeholders
who involved in this project are Investors, investing for the project, Board of Directors, Managing
director, Organizational staffs, Project manager, Project team members, Contractor and Suppliers.
External stakeholders are government agencies, Architectures, Consultants, Competitors, Tourists, and
banks.
1- The project investors will oversee the research of the business and finalized the budget for the
project and investing on project.
2- Project board of directors will be establishing the organization mission and vision, establish the
plan and provide resources required for the project.
5
3- Managing director will develop the organization strategic plan in an effective manner and
accountable for overall performance of organization. Managing day-to-day activities of the
business, authority delegated from board and implementing board policies and strategy, allocating
resources required to achieve the objectives.
4- Project Manager responsibility is completing the project on time, within the provided or given
budget, and maintain the quality criteria provide training for the project staffs, maintain the
project quality, identify the project procurement, develop and approve project charter, define the
goals and objectives.
5- Project Teams members responsible are performing the project activities. They also help
obtaining commitments to complete the project within schedule and limited budget.
6- Contractors will carry out the task handover according to the design and plan and contract they
may be a construction or electrical.
7- A Supplier will supply good and material according to the contract, which are required for the
project and should maintain the quality standard of the according to the contract.
In the initial phase of the project, a detailed feasibility study will be conducted to understand the
scope of the project perfectly. After conducting the feasibility study, a feasibility report will be created
that will explains whether the project will be successful in the current environment. It will judge the
project practically to provide a detailed study report. There are various types of feasibility study,
Technical Feasibility, Economic Feasibility, Operational Feasibility, and Scheduling Feasibility.
The technical feasibility study will be conducted to determine the resources that are needed for the
completion of the project and the technical specifications for the project. The development process for the
five-star hotels will consist of getting the approvals, construction of the building, interior works, and the
grand opening of the hotel. The following specialists are needed for building the five-star hotel:
Project Manager: Responsible for managing the whole process of building the five-star hotel
from the beginning to the opening of the hotel
Finance Manager: Responsible for managing all the finance for the project and controls the flow
of budget.
6
Legal Advisor: Responsible for help the company for getting the necessary approvals and
provide legal advises during the project.
Building Contractor: Responsible for constructing the building according to the plan and
complete it on time within the budget.
Human Resource Manager: Responsible for hiring necessary staffs for the hotel after the
construction.
Quality Assurance Manager: Responsible for maintaining the quality of the building, interior,
and other things.
Technical Staffs: Responsible for the technical things in the hotel including the CCTV and all
other technical details.
Marketing Manager: Responsible for marketing the hotel for getting customers to the hotel.
Economic feasibility study will contain the analysis on the cost of the project and the estimated
turnover from the hotel. This will help the company to analyze whether it will be beneficiary or non-
beneficiary for the company and determine that whether the project will be a cost-effective project or not.
The estimated budget for the proposed project will be AED 76,273,280.00 including the construction and
interior works. The estimated completion time for the project will be 1280 working days.
As any 5-star hotel the primary revenue is coming from the renting of booked room, and our hotel is
containing 200 rooms. The revenue of the rent for the hotel rooms, suits and apartments is calculated as
below:
Hilton Hotel
Revenue
20 suits 10 apartments
200 Rooms
revenue revenue
Figure 1: Hotel revenue
7
1.4.3 Operational Feasibility
The operational feasibility study will analyze the existing system and describes how the proposed
system will be useful. For getting the operational feasibility study, it is necessary to understand the
requirements of the system in a detailed manner. The proposed project of Building a five-star hotel in
Abu Dhabi will going to implement the following operations:
The hotel should contain 200 single rooms, 20 suits, and 10 apartments.
The hotel should contain 5 meeting rooms for the corporate.
There will be 4 restaurant and coffee shop included in the hotel.
It should contain the reception and guest areas.
An IT centre will be created for managing all the technical related works.
And three elevators and staircases inside the building.
8
1.5 Payback period
The investment for building a five-star hotel in Abu Dhabi is estimated as 76,273,280
AED and expecting an annual payback of 12,500,000 AED from all the incomes related to this
Investment
Payback Period =
Cash flow per year
76,273,280
Payback Period = =6.1
12,500,000
That means the payback period for this five-star hotel will be approximately 6 years.
Project Planning
2.1 Project Charter
The project charter will describe the objectives, advantages, risks of the proposed project. The project
charter for Building a Five start Hotel in Abu Dhabi is given below:
Project Charter
Description
9
The proposed project of building a five-star hotel will be developed in one of the beaches in
Abu Dhabi. The new initiative will attract the tourists from worldwide to UAE especially to
Abu Dhabi. The project will contain the construction of building, interior works, and hiring
the necessary staffs.
Purpose
The main purpose of this project of building a five-star hotel is to invite tourists to the hotel
as it will be developed in the beach. The long-term goal of this project is to provide a huge
amount of job vacancies to the people including the foreigners as well.
Project requirements
The main requirement is the funding in order to compete other luxurious hotels and to attract
in terms of the design and to have a great experience
Objective
The primary objective of this project is to build a new five-star hotel in Abu Dhabi beach that
will invite tourists and also the UAE residents to the hotel to spend time there especially
during the vacation.
Scope
The scope of this project is the growing tourism industry that will invite the tourists from the
entire world. Due to the COVID – 19, now the tourism has comparatively less scope but most
of the people took vaccination and the tourism field will come back with more energy in the
coming years.
Acceptance criteria
The success criteria should meet in order to accept the project which are:
Adhere to the deadline
Follow the specifications
Customer satisfaction
10
Adhere to safety
2.2 WBS
Work Breakdown Structure (WBS) is created for a project for developing the project step by step.
In WBS, the project is divided into small parts called chunks. These small parts are then assigned to the
corresponding resources. The project manager will create the project management plan for the project that
will ease the monitoring process and allow them to track the progress of the project development. The
WBS of Building a Five Start Hotel in Abu Dhabi is given below:
11
1.0 Build a Five Star
Hotel
1.3 Building
1.1 Legal approval 1.2 Budget Approvals 1.4 Interior Works 1.5 Hiring staffs 1.6 Marketing
Construction
1.1.2 Get legal licences 1.2.2 Get approvals for 1.5.2 Housekeeping 1.6.2 Advertising in
1.3.2 Land Scaping 1.4.2 Design Exterior
anPermits the budget. staffs Social medias
1.3.8 Reception
1.3.9 IT Centre
Figure 2: WBS
12
2.3 WBS Complete Schedule
The WBS complete schedule for the project is then created using the MS Project and identifies
the resources and allocates them for each activity in WBS and the time needed to complete each activity.
The project consists of multiple tasks with a specific start and finish time. The schedule shows the
availability of the manpower. The main factors needs to be taken into consideration are:
Task to be done
Task deadline
The concerned personnel to complete the task
In this stage, the following steps should be determined in order to create the schedule:
13
Figure 3: WBS schedule
14
2.4 Gantt Chart
The Gantt chart is the actual flow of the project development with timelines that will get from the
MS Project.
Identifying and allocating the resources to the appropriate activities is one of the most essentials parts
of the project management plan. The resource allocation will be done in the beginning of the project so
that the resources can utilize their skills for the successful completion of the project. Each activity is
allotted to a single resource and the entire resources are working together to achieve the final goal of the
project. The resources are required to ensure the completion of project which can be divided to
manpower, cost and the materials as the following resources are needed to build 5 star hotel:
1- Project Manager
2- Finance Manager
3- Legal Advisor
4- Building Contractor
15
5- Human Resource Manager
6- Quality Assurance Manager
7- Technical Staff
8- Marketing Manager
9- Building Materials
10- Furniture
11- Design Materials
12- Electrical Materials
13- Opening Ceremony (Cost)
In RACI matrix, every task in the project is listed with the resources and their responsibilities.
The notations used in the RACI matrix are listed below:
16
Table 3: RACI Matrix
Task Name
Legal Advisor
Contractor
Marketing
Assurance
Technical
Resource
Manager
Manager
Manager
Manager
Building
Finance
Human
Quality
Project
Staff
1.0 Build a Five Star Hotel
1.1 Legal approval
1.1.1 Build project R C I A
development plan
1.1.2 Get legal license and I A R C
permits
1.2 Budget Approvals
1.2.1 Create a Budget Plan A R C I
1.2.2 Get approvals for the A R C I
budget.
1.3 Building Construction
1.3.1 Hire a Contractor to R A I C
construct Hotel Building
1.3.2 Land Scaping I A R C
1.3.3 Create Parking Space I A R C
1.3.4 Manager Office I A R C
1.3.5 Rooms and suits I A R C
1.3.6 Restaurant and I A R C
Coffee shops
1.3.7 Guest area I A R C
1.3.8 Reception I A R C
1.3.9 IT Centre I R C A
1.3.10 Electrical Work I R C A
1.4 Interior Works
1.4.1 design Interior A I R C
1.4.2 Design Exterior A I R C
1.4.3 Install Appliances A I R C
1.5 Hiring staffs
1.5.1 Customer Service A I R C
Staffs
1.5.2 Housekeeping Staffs A I R C
17
1.5.3 Front Desk Staff A I R C
1.5.4 Kitchen Staffs A I R C
1.5.5 Restaurant Staffs A I R C
1.5.6 Management Staffs A I R C
1.6 Marketing
1.6.1 Develop Marketing I A C R
Plan
1.6.2 Advertising in Social I A C R
medias
1.6.3 Invite Chief Guests I A C R
1.7 Grand Opening R I C A
The project manager will manage the budget to ensure the coverage on the staff salaries and the
purchases of the materials. Each resource in the project has a standard rate for their work. After assigning
the resources to the activities, the overall cost of the project will be calculated. And the estimated cost for
the proposed project is AED 76,273,280.00. This total cost for the project is calculated based on the
resources allocated for each task. For example, let’s take the task ‘Build Project Development
Plan’ task, and calculate the cost for it.
Resources needed for this task = Project Manager and Legal Advisor.
Cost of project manager for this task = 192 * 450 = 86,400 AED.
Cost of legal advisor for this task = 192 * 380 = 72,960 AED.
18
Total cost for this task = 86,400 + 72960 = 159,360 AED.
Same like this, the cost for each task is automatically calculated by the MS Project and
added up to get the total cost for the project.
The project development process should be monitored continuously to track the progress of the
project. The project management plan created will contains the time duration and deadline for each
activity in the project and the milestones are listed. The milestones should be delivered in the exact
deadline. If any of the process is not completed on time, then they are called exceeding activities and the
activities that done before the deadline are called succeeded activities. Monitoring the activities with their
deadlines will help to figure out the distractions and deviations in the development process and allow the
19
project manager to control it by taking action against it. The following reports will help the project
manager to understand the progress of the project development.
20
Figure 9: Project overview
4.2 Milestone Report
21
4.4 Resource Overview
The project closeout report will contain the assurance that is given to the higher authority that the
project will be complete successfully or not. This hotel construction project has very huge scope in the
tourism industry as it will create in the beach. So that the project will be a successful one that can retrieve
the capital as profit within a few years. In the closing phase, a report will show the if the project was a
success or not as its include the main points of the project to provide a clear picture of the performed
tasked in addition to the following:
22
Project completion
Follow the project management process
Conclusion
The opening of a new five-star hotel in Abu Dhabi will be a new initiate as it is created in a
beach. The project will contain a great scope in the tourism of Abu Dhabi. The project management plan
will be created by the project manager for this project. An efficient project management plan is necessary
for successfully complete the project within the desired time and budget. Before starting the
documentation for this project, the team members did a thorough study about the scope and benefits of
the project. Each team members worked in the preparation of the document and from this we learned a lot
new technologies that will help us in the future.
23
References
Gantt charts: Planning and scheduling team projects. (n.d.). Management Training and
Leadership Training -
Online. https://www.mindtools.com/pages/article/newPPM_03.htm
MS project - Status reporting. (n.d.). Biggest Online Tutorials
Library. https://www.tutorialspoint.com/ms_project/ms_project_status_reporting.htm
Project Closeout report. (n.d.). Visual Paradigm Community Circle. https://circle.visual-
paradigm.com/docs/project-management-lifecycle-guide-through/closeout-phase/how-
to-develop-project-closeout-report/
Project monitoring & controlling phase. (n.d.). Online Work Management Software |
Workfront. https://www.workfront.com/project-management/life-cycle/monitoring-
controlling
Simplilearn. (2012, July 15). Feasibility study and its importance in project
management. Simplilearn.com. https://www.simplilearn.com/feasibility-study-article
What is resource allocation in project management? (2022, January 25).
TimeCamp. https://www.timecamp.com/blog/2018/04/resource-allocation-project-
management/
What is work breakdown structure in project management? (n.d.). Versatile & Robust
Project Management Software | Wrike. https://www.wrike.com/project-management-
guide/faq/what-is-work-breakdown-structure-in-project-management/
24