CALCULATION FOR 1

WIDTH HEIGHT LENGTH VOLUME


P.C.C (1:4:8)
(FEET) (FEET) (FEET) (CFT)
EXCAVATION 2.5 3.875 50 484.375 CEMENT SAND CRUSH R.C.C (1:2:4)
P.C.C (1:4:8) 2.5 0.375 50 46.875 4.44375 22.20938 44.42344
BRICK WORK 2 0.75 50 75 R.C.C (1:1.5:3)
BRICK WORK 1.6 0.75 50 60
BRICK WORK 1.125 0.5 50 28.125 BRICK WORK (1:4) P.C.C (1:4:8)
BRICK WORK 0.75 3.7 50 138.75 TOTAL BRICKS CEMENT SAND
BRICK WORK 0.75 22 50 825 1126.875 15212.81 54.09 270.45 BRICK WORK (1:6)
D.P.C 0.75 50 37.5
BRICK WORK (1:5)
QTY. RATE COST
EXCAVATION 484.375
TOTAL BRICKS 15212.81 13000 197766.6 BRICK WORK (1:4)
TOTAL CEMENT 58.53375 1100 64387.13
TOTAL SAND 292.6594 5000 14632.97 PLASTER 13mm (1:3)
TOTAL CRUSH 44.42344 7000 3109.641
TOTAL DPC 37.5 PLASTER 13mm (1:4)
TOTAL AMOUNT 279896.3
TERAZZO 13mm (1:2)
CALCULATION FOR 100 CFT
CEMENT SAND CRUSH
BRICKS
(BAGS) (CFT) (CFT)
17.6 44 88

22.4 42 84

9.48 47.38 94.77

3.43 25.71 1350

4 25 1350

4.8 24 1350

1.02 3.81

0.81 4.06

1.64 18.67