Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

1 Sub Structure

D-EXCAVATION AND EARTH


WORK
CLEARING SITE

A Clearing and removing all debris from site


B (Approx. area 244m²) 244 m² 450.00 109,800

EXCAVATION

C Excavate trench for beam foundations n.e.


D 1m 20 m³ 1,500.00 30,330

E Excavate pit for Pile Caps n.e.


F 1m 9 m³ 1,500.00 13,335

EARTHWORK SUPPORT

G Earthwork support to side of all excavation


H (If necessary) 90 m² 1,650.00 149,045

Anti Termite Treatment

I Application of anti termite treatment


J Horizontal surface in accordance with the
K manufacture's specifications and to the
L approval of Engineer 254 m² 500.00 127,000

Reinforced cement concrete Grade 25


in the following

M In 150 mm thick ground floor slab 11 m3 30,000.00 335,700

To Collection 765,210

iTWO costX EDUCATIONAL VERSION Page 1 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

1 Sub Structure (Continued)

N In Ground beam 20 m3 30,000.00 606,600

O In Pile cap 9 m3 30,000.00 266,700

FORMWORK

P To sides of ground beam 90 m² 2,500.00 225,825

Q To sides of pile Cap 44 m² 2,500.00 109,975

Piling Works

R 600mm dia piles (17 Nr) approx. Depth


S 6.0m 102 m 25,000.00 2,550,000

Sub Structure 894

To Collection 3,759,100

iTWO costX EDUCATIONAL VERSION Page 2 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

1 Sub Structure (Continued)

COLLECTION

Page 1: 765,210
Page 2: 3,759,100

Sub Structure
Carried to Summary: 4,524,310

iTWO costX EDUCATIONAL VERSION Page 3 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

2 Architectural

G - MASONRY WORK

External Walls

225mm thick approved type common brick


work in 1:5 cement and sand mortar as
shown on the drawings and specification

A To ground floor 62 m2 450.00 28,013

Internal Walls

150mm thick approved type common brick


work in 1:5 cement and sand mortar as
shown on the drawings and specification

B To ground floor 24 m2 450.00 10,917

H - WATERPROOFING

Wet area waterproofing

Horizontal area

Baralastic or equivalent waterproofing


system for bathrooms, pantry and balcony,
all accordance as per the drawings and
specification

C To ground floor 7.00 m2 800.00 5,600

To Collection 44,530

iTWO costX EDUCATIONAL VERSION Page 4 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

2 Architectural (Continued)

Internal floor

20mm thick rough cement render floor in 1:3


cement sand mortar, as per the drawings
and specification (Ref : FF -06)

D To ground floor 395 m2 650.00 256,750

External wall

Rough cement sand (1:5) plaster on brick


walls as per drawings and specification

E To external brick walls 102 m2 600.00 61,032

Internal wall

16mm thick Smooth wall plastering with


putty to brick wall in cement and sand 1:5
including all angle, corner and stop beads
where required as per the drawings and
specifications (Paint measured elsewhere)

F To ground floor 292 m2 500.00 145,830

Internal ceiling

Smooth soffit plaster with two coats of lime


putty including all angles, corners and
expanded where required in accordance
with local code of practice and as specified
To Collection 463,612

iTWO costX EDUCATIONAL VERSION Page 5 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

2 Architectural (Continued)

in drawings and specification (Paint


measured elsewhere)

G To ground floor 133 m2 360.00 47,916

SKIRTING FINISHES

Internal

100mm high homogeneous, approved


coloured, matt, floor tile skirting, match to
floor finish as per the drawings and
specifications

H To ground floor 94 m 200.00 18,804

Architectural 1,109

To Collection 66,720

iTWO costX EDUCATIONAL VERSION Page 6 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

2 Architectural (Continued)

COLLECTION

Page 4: 44,530
Page 5: 463,612
Page 6: 66,720

Architectural
Carried to Summary: 574,862

iTWO costX EDUCATIONAL VERSION Page 7 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

3 MEP

Plumbing

A 20 mm dia Cold Water Supply pipe 11 M 150.00 1,653

B 25 mm dia Cold Water Supply pipe 30 M 180.00 5,452

C 32 mm dia Cold Water Supply pipe 2 M 200.00 402

D 40 mm dia Cold Water Supply pipe 12 M 240.00 2,779

E 50 mm dia Cold Water Supply pipe 4 M 260.00 933

F 20 mm dia Cold Water Supply pipe Riser 3 M 210.00 630

G 25 mm dia Cold Water Supply pipe Riser 9 M 240.00 2,160

H 32 mm dia Cold Water Supply pipe Riser 9 M 270.00 2,430

I 50 mm dia Cold Water Supply pipe Riser 0 M 300.00 0

J 11/2" dia: brass Gate valve 2 Nos 550.00 1,100

K 20 mm dia L angles 4 Nos 500.00 2,000

Electricity

POINT WIRING

Point wiring for small power

Cables including conduits with all conduit 17 Nr 360 6,120

To Collection 25,660

iTWO costX EDUCATIONAL VERSION Page 8 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

3 MEP (Continued)

accessories, cable glands, termination and


connections, draw wires, laying, jointing,
etc., as per drawings and specification.

Ground floor

L 13A switched socket outlet 26 Nr 450 11,700

Ground floor

M Surface mounted lamp (Prime cost:


N Rs 1500.00) 38 Nr 2,500 95,000

O Cable Trunk 88 M 460 40,480

P Cable Length 348 M 650 226,148

ACMV

Q Equipment 30 Nr 5,000 150,000

R Duct 69 M 750 51,870

S Duct Riser 21 M 275 5,775

T Duct Ancialiries 6 Nr 430 2,580

MEP 729

To Collection 583,553

iTWO costX EDUCATIONAL VERSION Page 9 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

3 MEP (Continued)

COLLECTION

Page 8: 25,660
Page 9: 583,553

MEP
Carried to Summary: 609,213

iTWO costX EDUCATIONAL VERSION Page 10 of 11


QS Yohan
Bill of Quantities Practice 01

Item Description Quantity Unit Rate Total

COLLECTION SUMMARY PAGE NO

Sub Structure 1-2 4,524,310


Architectural 4-6 574,862
MEP 8-9 609,213
Total Amount: 5,708,384

iTWO costX EDUCATIONAL VERSION Page 11 of 11


QS Yohan

You might also like