OPERATION FACILITY TEAM (GTI)

DAILY REPORT
Location Gubug Flowstation / ORF RBG3 Date Sabt &Minggu8-9/07/23
Project Rental Early Production Facilities (EPF) for RBG Block I Field Weather Cerah
Reported by Gus Wahid

SoW Progress
No Permit No Category Description Location Executor
Number [%]
1. Hot Work * Pemotongan dan perakitan besi RBG IP JMK

2. Cold Work * Cor lantai Kerja GEG A dan B 100%


* Cor lantai Kerja DEG 100%
* Pemasangan papan begesting utk foundation Bulding skid 90%
* Set -up Coalescing Separator (1) dan gas Heat Exchanger/Elect
Heater(2) di Pondasi Membrance separator skid-1 (P-4) angkur bolt
masuk di skid
* Set -up Coalescing Separator(3) di Pondasi Membrance separator
skid-1 (P-4) angkur bolt tdk masuk di skid
* Set -up 1st stage membrant separator (8 dan 7 ) di pondasi skid -2
(8)angkur bolt belum masuk (7) angkur bolt Masuk
* Set -up Membrant separator (6 ) di pondasi skid -2 angkur bolt tdk
masuk di skid
* Set -up 2st stage membrant separator (5 ) di pondasi skid -2 angkur
bolt masuk di skid
* Set -up 2st stage membrant separator (4 ) di pondasi skid -2 angkur
bolt tidak masuk di skid

Tomorrow Act. Plan


Target
SoW
No Permit No Category Description Location Progress Executor
Number
[%]
1. Hot Work * Pemotongan dan perakitan besi RBG TIS JMK

2. Cold Work * Pekerjaan Pengecoran utk foundation Bulding skid


Pekerjaan Lifting :

* Menggeser dan Penempatan API separator ke Pondasi P-19

JMK

Indentifikasi bahaya dan resiko


No
1 Hazards: Manual Handling/ Cuaca buruk / Bahaya H2S/ Paparan Panas/ Handtools.

Kontrol: Sarung tangan/ Jaga komunikasi /Pengetesan Gas / Banyak minum air / Gunakan tool yg sesuai .

Documentation
Pemotongan dan Perakitan Besi Cor lantai Kerja GEG A dan B 100%

cor lantai kerja DEG 100% * Pemasangan Papan begesting utk foundation Bulding Skid

Penempatan Coalescing Separator(1) angkur bolt masuk di skid Penempatan Heat Exchanger (2 ) angkur bold masuk di skid

Penempatan Coalescing Separator(3) angkur bolt tidak masuk di skid Penempatan Coalescing Separator(3) angkur bolt tidak masuk di skid

* Set -up 1st stage membrant separator (8 dan 7 ) di pondasi skid -2 * Set -up 2nd stage membrant separator (4 ) di pondasi skid -2 angkur
angkur bolt no 8 belum masuk bolt tidak masuk di skid
* Set -up Membrant separator (6 ) di pondasi skid -2 angkur bolt tdk
masuk di skid
* Set -up 2nd stage membrant separator (5 ) di pondasi skid -2

Page: 1 of 1