DAILY REPORT
Location Gubug Flowstation / ORF RBG3 Date Sabt &Minggu8-9/07/23
Project Rental Early Production Facilities (EPF) for RBG Block I Field Weather Cerah
Reported by Gus Wahid
SoW Progress
No Permit No Category Description Location Executor
Number [%]
1. Hot Work * Pemotongan dan perakitan besi RBG IP JMK
JMK
Kontrol: Sarung tangan/ Jaga komunikasi /Pengetesan Gas / Banyak minum air / Gunakan tool yg sesuai .
Documentation
Pemotongan dan Perakitan Besi Cor lantai Kerja GEG A dan B 100%
cor lantai kerja DEG 100% * Pemasangan Papan begesting utk foundation Bulding Skid
Penempatan Coalescing Separator(1) angkur bolt masuk di skid Penempatan Heat Exchanger (2 ) angkur bold masuk di skid
Penempatan Coalescing Separator(3) angkur bolt tidak masuk di skid Penempatan Coalescing Separator(3) angkur bolt tidak masuk di skid
* Set -up 1st stage membrant separator (8 dan 7 ) di pondasi skid -2 * Set -up 2nd stage membrant separator (4 ) di pondasi skid -2 angkur
angkur bolt no 8 belum masuk bolt tidak masuk di skid
* Set -up Membrant separator (6 ) di pondasi skid -2 angkur bolt tdk
masuk di skid
* Set -up 2nd stage membrant separator (5 ) di pondasi skid -2
Page: 1 of 1