Professional Documents
Culture Documents
IP MS 12 Cement Plaster
IP MS 12 Cement Plaster
METHOD STATEMENT
FOR
CEMENT PLASTER
1. OBJECTIVE
The objective of this method statement is to provide general guidelines for all plastering
work and related inspection activities.
2. SCOPE
This method statement covers the activities in connection with the application of plaster
at all project sites.
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
6 PROCEDURE
6.1 Quality Inspection Plan (QIP) specific to project requirements shall be made and
inspection activities shall be recorded either on the formats as given under
“Related Documents” or those supplied by customer.
6.2 Portland cement for plaster shall conform to the requirements as specified in
customer’s specifications and for its approval by customer use Doc. No.
QA&QC/FRM-199.
6.3 All sand used in plaster shall also conform to the requirement as specified in the
customer’s specifications and for its approval by customer use Doc. No.
QA&QC/FRM-174, 178,179.
6.4 All the ingredients for plastering shall be proportioned by volume as indicated on
the project specifications. The preparation of mix shall not be in a bulk quantity.
Approval of mix design for mortar use Doc. No. QA&QC/FRM-180.
6.5 Mechanical mixers, mixing boxes, platforms and all related tools shall be cleaned
before and after mixing each mix.
6.6 Plaster mortar shall be thoroughly mixed with the specified amount of water until
uniformity in color and consistency is obtained.
6.7 Prior to the plasterwork ensure that all the conduits for electrical works ducts,
pipes, brackets, doors, windows, ventilators and all other fixtures on the walls
6.9 Before commencement on block wall the surface to be plastered shall be treated
with cement sand slurry (one part cement and one part sand by volume)
6.10 The slurry shall be applied with a brush upon the surface previously been well
wetted.
6.11 The treatment of slurry shall be allowed to dry out for 24 hrs.
6.12 The first coat shall be roughened before the finishing coat is applied.
6.13 Make sure the minimum thickness of plaster should be as per project
specifications.
6.14 The plaster surface should not be wavy and should be perfectly in plumb.
6.15 The plaster works shall be cured for at least ten days by sprinkling water or as
mentioned in specifications.
Mixing Pans, Hand Tools For Plaster, Plumb Lines, Water Tank/Bouser and Mixing
Machine.
8. HSE INSTRUCTIONS
8.1 All the workers shall use personal protective equipment during cement plaster
activity.
8.3 Any person alone shall clean in the presence of a supervisor and the machines
such as mixers etc. never.
8.5 Scaffolding with toe boards & guardrails etc. will be prepared as per approved
specifications if needed.
8.6 Mortar buckets must be in good condition and not to be used for other than
material.
8.7 Cement sand mortar shall not be retained for more than ½ hrs in open air.
8.8 No trash, rapes, shopping bags, papers, cans, bottles or any other litter should
be left in the open.
8.9 Any liquid fuel spills and accidental waste disposal should be avoided and
properly cleaned up.
9 RELATED DOCUMENTS