Project Task Responsible Person Starting Date Due Date Days Spent

Project-A Task 1 Manager X 1/01/2022 20/01/2022 9


Project-A Task 2 Manager Y 2/01/2022 21/01/2022 10
Project-A Task 3 Manager Z 4/01/2022 22/01/2022 6
Project-A Task 4 Manager P 4/01/2022 23/01/2022 9
Project-A Task 5 Manager Q 5/01/2022 24/01/2022 19
Project-A Task 6 Manager R 5/01/2022 25/01/2022 20
Project-A Task 7 Manager S 6/01/2022 26/01/2022 10
Project-A Task 8 Manager T 6/01/2022 27/01/2022 11
Project-A Task 9 Manager U 6/01/2022 28/01/2022 12
Project-A Task 10 Manager U 6/01/2022 29/01/2022 23
Project-A Task 11 Manager V 11/01/2022 30/01/2022 10
Project-A Task 12 Manager F 12/01/2022 31/01/2022 5
Days Required Progress Status
19 47% In Progress
19 53% In Progress
18 33% In Progress
19 47% In Progress
19 100% Completed
20 100% Completed
20 50% In Progress
21 52% In Progress
22 55% In Progress
23 100% Completed
19 53% In Progress
19 26% In Progress
Task Days Spent Days Required Progress Remaining Status
Task 1 9 19 47% 53% In Progress
Task 2 10 19 53% 47% In Progress 120%
Task 3 6 18 33% 67% In Progress
100%
Task 4 9 19 47% 53% In Progress
80%
Task 5 19 19 100% 0% Completed
Task 6 20 20 100% 0% Completed 60%

Task 7 10 20 50% 50% In Progress 40%

Task 8 11 21 52% 48% In Progress 20%


Task 9 12 22 55% 45% In Progress
0%
Task 1 Task 2 Task 3
Task 10 23 23 100% 0% Completed
Task 11 10 19 53% 47% In Progress
Task 12 5 19 26% 74% In Progress

Overall Project Completion 60% Project Rep


Total day Required
Total day spent
Overall Progress
Chart Title Task St
120%

100%

80%

60%

40% In Progress
75%
20%

0%
Task 1 Task 2 Task 3 Task 4 Task 5 Task 6 Task 7 Task 8 Task 9 Task 10 Task 11 Task 12

Progress Remaining Completed

Proje

Project Report Task Status


Total day Required 238 Completed 3 25%
Total day spent 144 In Progress 9 75%
Overall Progress 61%

Task Status
Days Spent Days Required Completed In Progress
3 9 Days Spe
144 238
Task Status

Completed
25%

In Progress
75%

Completed In Progress

Project Report

Days Spent Days Required


Task Days Spent Days Required Progress Remaining Status
Task 1 9 19 47% 53% In Progress
120%
Task 2 10 19 53% 47% In Progress
Task 3 6 18 33% 67% In Progress 100%
Task 4 9 19 47% 53% In Progress
80%
Task 5 19 19 100% 0% Completed
Task 6 20 20 100% 0% Completed 60%

Task 7 10 20 50% 50% In Progress


40%
Task 8 11 21 52% 48% In Progress
Task 9 12 22 55% 45% In Progress 20%

Task 10 23 23 100% 0% Completed


0%
Task 11 10 19 53% 47% In Progress Task 1 Task 2 Task 3 Task 4

Task 12 5 19 26% 74% In Progress

Task Status P

Completed
25%

In Progress
75%

Completed In Progress D
Chart Title

sk 1 Task 2 Task 3 Task 4 Task 5 Task 6 Task 7 Task 8 Task 9 Task 10 Task 11 Task 12

Progress Remaining

Project Report

Days Spent Days Required

You might also like