METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
METHOD STATEMENT
Rubber Flooring
Revision history
Acceptance/Approvals
Sign.
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
TABLE OF CONTENTS
1. Scope.....................................................................................................................................4
2. References.............................................................................................................................4
4. Competence, responsibility.................................................................................................5
5. Introduction...........................................................................................................................6
6. Pre-installation Preparation.................................................................................................6
7. Subfloor Requirements........................................................................................................7
8. 4. Installation Process..........................................................................................................7
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
1. SCOPE
This Method of Statement elucidates the systematic procedures and paramount safety precautions entailed
in the installation of a suspended ceiling within the context of W15.10 BMW project at Hungary, Debrecen.
This meticulous plan serves as a comprehensive guide, meticulously detailing the steps necessary for the
secure, precise, and efficient installation of suspended ceilings.
2. REFERENCES
► Approved drawings;
► Approved materials
► Project Quality Plan;
► Project HSE Plan;
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
4. COMPETENCE, RESPONSIBILITY
Project Manager Responsible for the management of the site activities including the effective
application of the safety and quality system;
The Project Manager shall ensure that the key personnel are well aware of the
specifications and method statement.
Liaisons and corresponding with the Client’s Representative, Engineers, Local
Authorities, Sub-subcontractor and Supplier to ensure that the works are
carried out as per contractual requirement;
Monitoring and ensuring the Project is progressively positively in aspects of
cash flow, cost quality and timely completion.
Site Manager Responsible for overall construction activities and management of the project
construction team ensuring that all method statement, quality and safety
procedures are implemented and required approval permits are obtained.
Control of the daily operation of the construction activities on site.
HSE Personnel Exercise overall responsibility for HSE protection;
Manage the overall safety, health and environment activities in the
organization;
Responsible for planning, formulating and enforcing safety policies and
regulations; To identify variances and take correction actions to protect
personnel and property against accidents; To advise management on all
Occupation Safety & Health (OSH) matters.
Will be closely monitoring the site strict implementation of the MS and Risk
Assessment, the use of proper tools and equipment to maintain safety,
certifications of equipment and their adherence to safety regulations, reporting
of any unsafe work or stopping work that does not comply with HSE
procedures.
QA/ QC Personnel Implement, monitor and verify that all construction operations are being
conducting in accordance with the established quality procedure;
Monitor and review non-conformance and corrective actions, maintain records
and ensure the corrective actions are followed and complied;
Responsible to conduct qualified and competent person in quality field in order
to deliver project successfully;
Carry out inspection on site activities to ensure accordance with the execution
drawings and project specification;
Managing and witnessing material sampling, performance tests and
inspections if required;
Ensure inspection and test measurements are submitted based on quality
control requirements.
Date: Doc. ID:
Revision: 01 Page 6 of 15
2023.09.15 EXT_230914_0850_MS32_V001_BMW15.10_SYN_QA_MS_0032_01
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
5. INTRODUCTION
This method statement outlines the professional approach and detailed process for the installation of
noraplan® floor coverings. Proper installation is essential to ensure longevity, performance, and safety in
commercial and residential spaces.
6. PRE-INSTALLATION PREPARATION
Ensure that the following tools, necessary for the seam cutting process, shall be available:
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
• A hooked blade shall be used for detaching half-cut strips during the installation process.
The installer shall gather the necessary tools for a professional installation process, including:
The noraplan® floor coverings rolls shall be stored in an upright position to prevent deformation and maintain their
original integrity. This storage method ensures their optimal condition until installation.
7. SUBFLOOR REQUIREMENTS
• Ensure that the subfloor meets the necessary requirements for successful installation:
• Subfloor readiness: The subfloor should meet country-specific standards, including cleanliness, smoothness,
and flatness.
• Minimum temperature: Maintain a subfloor temperature of at least 15°C during the installation process.
Date: Doc. ID:
Revision: 01 Page 8 of 15
2023.09.15 EXT_230914_0850_MS32_V001_BMW15.10_SYN_QA_MS_0032_01
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
8. INSTALLATION PROCESS
The recommended installation method for noraplan® floor coverings shall be followed:
• Broadloom fashion: The noraplan® tiles shall be installed in a broadloom pattern for the best aesthetic and
performance results.
• Optional methods: If applicable, nora® nTx or nora dryfix™ ed may be considered for quicker installation. The
corresponding installation recommendations shall be referred to for detailed instructions.
8.2. Seam Cutting
To achieve precise and seamless installation, the following steps shall be followed for seam cutting:
• The width of the sheet shall be measured and ensured that it does not exceed the maximum specified width
(1.22 m for most noraplan® variants, 1.20 m for noraplan® ultra grip). The factory-cut edge shall be aligned
with the uncut edge for an accurate fit.
• The factory-cut edge alongside a steel straight edge shall be straightened using a nora® seam cutter or a
railcut (such as Wolff). The straight edge shall be kept approximately 1 cm off the factory-cut edge. This shall
slightly slit the sheet underneath, ensuring a clean cut.
Date: Doc. ID:
Revision: 01 Page 9 of 15
2023.09.15 EXT_230914_0850_MS32_V001_BMW15.10_SYN_QA_MS_0032_01
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
• In practice, it's best to detach the half-cut strip using a hooked blade. The underlying edge after embedding the
noraplan® floor covering shall be avoided as this could compress the seam and affect the performance and
appearance of the flooring.
• The arrows on the back of the noraplan® floor covering shall still be aligned and pointing in the same direction
after the cutting process.
• When unrolling noraplan® floor coverings, the sheets shall be overlapped as necessary and aligning the
factory-cut edge with the uncut edge.
Date: Doc. ID:
Revision: 01 Page 10 of 15
2023.09.15 EXT_230914_0850_MS32_V001_BMW15.10_SYN_QA_MS_0032_01
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
• After seam cutting, half of the sheets shall be folded back. The subfloor and the back of the floor covering shall
be vacuum cleaned.
• To avoid a visible adhesive line in the sheet, adhesive tape shall be applied in the area where the sheets are
folded back. The adhesive shall be spread onto this tape, and the tape shall be removed while the adhesive is
still fresh. This shall ensure a straight adhesive line.
• Acrylic adhesives shall be used as suitable adhesives for noraplan® floor coverings. The serrated blade
recommended by the manufacturer shall be used to apply the adhesive, and nora® AC 100* is recommended
for adhesive application.
Date: Doc. ID:
Revision: 01 Page 11 of 15
2023.09.15 EXT_230914_0850_MS32_V001_BMW15.10_SYN_QA_MS_0032_01
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
• The noraplan sheets shall be moved approximately 10-20 cm into the fresh adhesive to avoid an adhesive line.
• The required airing time shall depend on the temperature, humidity, and absorbency of the subfloor. It shall be
ensured that the adhesive's open time is not exceeded. The adhesive transfer to the back of the floor covering
shall be checked carefully. Additional information provided by the adhesive manufacturer shall be observed.
Date: Doc. ID:
Revision: 01 Page 12 of 15
2023.09.15 EXT_230914_0850_MS32_V001_BMW15.10_SYN_QA_MS_0032_01
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
• When embedding the floor covering, the entire back of the floor covering shall be completely covered with
adhesive. Flooring edges shall be positioned without applying pressure. Under no circumstances should they
be pressed or crushed. If joints are to be sealed, the joint width shall not exceed 0.3 mm.
• Any adhesive residues on the surface of the flooring shall be removed immediately with nora® liquid wax.
• During the installation and bonding of the adhesive, noraplan® floor coverings shall be protected against
extreme heat or temperature fluctuations caused by direct sunlight or glazed elements reaching down to the
floor.
• Except for noraplan® ed and noraplan® ec, the seams of the flooring may be sealed with nora® hot welding
rod, following the processing recommendation for "Joint sealing". This sealing process shall be carried out 24
hours after installation at the earliest.
• The floor covering shall be carefully rubbed on its entire surface into place, for instance, with a cork board. It
shall then be pressed down into position both longitudinally and transversely with a heavy iron roller
(approximately 50 kg). If acrylic adhesives are used, this procedure shall be repeated after a while (depending
on the temperature), particularly at the ends and seams.
• By following these revised instructions, a clean and accurate seam cut, proper adhesive application, and
effective placement of noraplan® floor coverings shall be achieved.
Date: Doc. ID:
Revision: 01 Page 13 of 15
2023.09.15 EXT_230914_0850_MS32_V001_BMW15.10_SYN_QA_MS_0032_01
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
• The noraplan® floor covering will be fully serviceable only 72 hours after installation.
• Wet or damp cleaning of the floor covering shall only be carried out after the adhesive has fully bonded, which
typically occurs after approximately 48 hours.
• In entrance areas with heavy traffic, shall install door mats or similar measures of sufficient size.
• Verification of the Quality documents/Performance Certificate, Technical data sheet received from the
Manufacturer shall be done.
• A visual inspection shall be conducted to ensure that the installed noraplan® floor coverings are free from any
visible defects, such as cuts, tears, or uneven seams. Any issues shall be identified and shall be addressed
and corrected before completing the installation.
• The seams of the noraplan® floor coverings shall be inspected to ensure proper alignment and secure
bonding. The seams shall be checked for any gaps, bumps, or unevenness. If any issues are found, they shall
be repaired or reinstalled as necessary.
• The adhesive used shall be verified to have properly bonded the floor covering to the subfloor. The adhesive
lines shall be inspected to ensure they are continuous and evenly applied. Any areas with weak adhesion or
gaps shall be addressed and repaired.
• The flatness of the installed noraplan® floor coverings shall be checked to ensure a smooth and even surface.
A straight edge or level shall be used to identify any raised or uneven areas. These areas shall be corrected to
achieve a satisfactory installation.
• Detailed records of the installation process shall be maintained, including the types of adhesive used, curing
times, and any deviations from the recommended procedures. This documentation shall serve as a reference
for future maintenance and warranty purposes.
• By implementing these quality control measures, the installed noraplan® floor coverings shall meet the
required standards, providing a durable and visually appealing flooring solution
* The quantity / number of the above-mentioned tools and equipment may vary depending on site conditions,
requirements, and availability at the time of execution.
Date: Doc. ID:
Revision: 01 Page 14 of 15
2023.09.15 EXT_230914_0850_MS32_V001_BMW15.10_SYN_QA_MS_0032_01
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
If the natural light required for safe work is not sufficient, artificial general light of 50-100 lux must be
provided.
Tools and equipment must be used in accordance with their intended purpose. Before starting work, hand
tools must be inspected.
Wrong or defective tools must be replaced. None of the works are allowed to be performed with faulty tools.
Number of personnel
Job title Number of personnel
Site Manager 1
Site Engineers 1 (or more)
QA/QC Manager 1
QA/QC Engineer 1
HSE Manager 1
Surveyor Engineer 2 (or more)
Machinery Operators As per requirement
Skilled Workers As per requirement
HSE section of this document is to identify the standard proactive processes of planning HSE for the site
mobilization and demobilization work, to ensure that foreseeable hazards are identified and mitigation measures
are implemented in a standard manner.
All necessary HSE measures will be taken according to the approved risk assessment and HSE Plan.
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1
Protective helmet Vis clothes Protective boots Eye Protection Harness Safety gloves
All activities All activities All activities All activities Work at height Manual handling
The equipment operators shall possess the required licenses and certificates.
The project safety officer is responsible along with the site engineer for ensuring that all operations are
carried out with due regard to the safety of all project personnel and property.
Tools and equipment shall be inspected by authorized person before carried out to work.
Barricades and sign posts for warning shall be provided on site.
Smoking at construction site is not absolutely allowed.
Ensure every worker to wear safety harness when working at height.
Extension wires shall be hanged to right position to prevent short circuit and electric shock.
EMERGENCY PROCEDURES
• Emergency Response materials are readily available and attended when hazardous atmospheric condition
exists or may develop, with all workers trained and aware of the hazard and safe work process.
METHOD STATEMENT
Site: Debrecen,
Project: BMW Plant W15.10
HRSZ: 0260/1