Duncan Quote02

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 3

PO Box 3442

Rivonia 2128
Rowley & Associates 083 651 1592 (cell)
083 118 651 1592 (Fax)
shawn@tamashi.co.za
SACAP reg No ST0772
Practice code TR0613

Professional Fees
(In respect of services rendered by a professional person registered with the SACAP )

12 September 2005
Duncan Muirhead (083 765 7412)

Cluster Development in Blackheath

As per your request please find below detailed fees:

Professional fees ( Professional fees based on 5% of building cost)

Estimated Total Area of units = 3000.00 sqm


3000sqm@R3000/sqm =R9 000 000.00

Total Fees =R 450 000.00 (to be finalized on final costings later)

A deposit of (30%) =R 135 000.00 (On commencement of drawings)

Balance to be divided Monthly over duration of project

Engineering fees(not included in fees)= to be established once drawings are complete


Council fees(not included in fees) = to be established once drawings are complete

Should you have any queries regarding the above please do not hesitate to contact the
undersigned.

Yours faithfully,
SHAWN ROWLEY

Accepted for and on behalf of ________________________Date________________

Banking Details:
Account name: S. ROWLEY
Branch: Nedbank Rosebank South Africa
Account Type: Cheque
Account number: 1958543500
Code: 195805

Turning dreams into Reality

1
Scope of works:

Stage 1: Site Planning

a. Design subdivisions
b. Site survey – existing trees, existing house, levels to generate contours
c. Draw and dimension subdivisions for landsurveyor
d. Prepare demolishsion drawing
e. Get electrical certificate that existing dwelling electrical cut off and that it is safe
f. Get sewer certificate for existing dwellings sewer cut off
g. Get terminators certificate that existing dwelling is rodent free

Stage 2: Site development plans

a. Design a typical unit to be approved by Council Town Planners


b. Design a typical units elevations and section to be approved by Council Town
Planners
c. Design and draw Gatehouse to be approved by the Council Town Planners
d. Design Main Electrical route (to be approved by electrician and engineers)
e. Design Main Sewer route (to be approved by engineers)
f. Design Main Water route (to be approved by engineers)
Note: Architect design and shows the route for the proposed services and
engineer approves layout and designs the correct falls that are required for
the services.
g. Design landscaping
h. Apply for building line relaxation, Design new building lines for each Erf
i. Design position of sub station(electrical engineer to advice on size of transformer)
j. Design security requirements (liase with specialist)
k. Circulate application (has to be done by applicant council does not do the
circulation. About 15 departments have to be visited to get their approval)
l. Take application to Council Town planning department for approval

Stage 3: Marketing

a. Liase with Estate agent as to the requirements for the marketing


b. Design and draw up all marketing material. (coloured plans, elevations and site
plan)
c. Develop marketing brochure
d. Liase with 3d artist for perspectives and site fly through

Stage 4: Design Concept development

a. Drawings to be designed and detailed further.


b. Design variations to clients specification
c. Approval of designs with the various clients
d.

2
Stage 5:
Technical documentation and municipal approval
a. Prepare drawings for Council submission
b. Prepare drawings for engineer to design concrete slab/roof and first
floor loading on foundations
c. Submit final drawings to municipality for approval (+/- 8 weeks for
approval)
d. Liase with Council throughout council process in order to alter any
problems they might have and also to speed up the approval process.
Stage 6:
Project inspection and liaison with contractor
a. Prepare drawings for construction after municipal approval
b. Finishing schedules
c. Window and Door schedules
d. Tiling layouts
e. Detailing
f. Liase with contractor
g. Liase with finishes suppliers
h. Site inspection on a regular basis(everyday for
duration of construction)
i. Site meetings once a week
j. Snagging of units
k. Desnagging of units