FACILITIES MANAGEMENT
HARBOR BUILDINGS RECTIFICATION PROJECT
S. A. BAYTUR INSPECTION CHECKLIST
S.A. BAYTUR QA/QC DIVISION - 20-02-18 - REV.00
PROJECT TITLE Contract Number CONTRACTOR / SUBCONTRACTOR
LOCATION:
ACTUAL INSPECTION DATE & TIME WORK PERMIT
RFI-PLUMB-
/ / @ YES o NO o
ITEM
ACCEPTANCE CRITERIA PASS FAIL N/A RE-INSP DATE
No.
A General
A2
The entire system in each apartment shall be tested to 10.35 Bar (150 psig)
A4
and checked for completely functional operational and water distribution.
A5 The branch lines shall be tested at 1-1/2 times the normal working pressure.
This pressure shall be held for at least 2 hours. The water utilized for tests
A6
shall be obtained from a potable source of supply.
Portion completed shall be tested and proved tight under a water pressure not
A7
less than the working pressure of the system.
Page 1 of 2
REMARKS:
REFERENCE DOCUMENTS:
1. International Plumbing Code(IPC), 2006.
2. Construction Specifications Section 15410, 15050.
3. Building Services Piping ASME B31.9.
Witnessed Hold
QC INSPECTOR
Witnessed Hold
KAUST HRP Representative