Professional Documents
Culture Documents
Machine Elememts
Machine Elememts
A project is a
• Temporary endeavor with a specific beginning and end (i.e. has limited life)
• Creates a unique product, service or result (i.e. each project by definition is unique)
Most studies have shown that only 33% of the projects are successful (e.g. standish
group). Project management is a relatively new area of discipline and has great future
potential as work professionalization increases
Constraints are
• Time
• Cost
• Risk
• Scope
• Quality
• Resources
Stakeholder
• Stakeholders are people or organizations whose interests may be positively or
negatively impacted by the project
In a strong matrix, power rests with the project manager while in a weak
matrix power rests with the functional manager.
In a balanced matrix, both are equally powerful and project manager works
part time.
Project manager’s role in a weak matrix could be
Expediter: Acting as a staff assistant and communications coordinator. He cannot
personally make or enforce decisions
Coordinator: Similar to expeditor, except he has some power to make decisions and
reports to higher level manager
A “tight matrix” refers to locating the entire project team in the same room “ War
location” Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
More on Org Structure (Functional, Projectized and Matrix)
Advantages Disadvantages
People place more importance to functions
Easier management of specialists
and projects suffer
Clearly defined career paths No career path in project management
Only one supervisor PM has no authority
Advantages Disadvantages
Efficient projects Lack of professionalization in disciplines
Loyalty to projects No “Home”
Effective communication Less efficient use of resources
Advantages Disadvantages
Visible project objective Extra project administration
Better PM control on resources More than one boss
Better support from functions More difficult resource allocation
I P
Initiation Planning
Business changes
C
Closing
M&C E
Monitor &
Executing
Control
Large projects have several phases and each phase has all the above five processes
42 Total processes across all the process groups and knowledge areas
Project life cycle describes what is needed to complete the work while the project
management process describes what is needed to manage the project
Resources can be released anytime during the project but only after their work is
approved and other closure activities pertaining to their work are completed. They
should also document their lessons learned.
Progressive Elaboration
PM plan is finalized in planning but items like detailed estimate, project scope and
product scope can be clarified over time during execution and Monitoring &
controlling phase
Project Manager
He is assigned early during a project and is hence involved in project initiation
Planning gives one an ability to repeat the same project. Since projects are unique
this is an important part of project management.
It involves walking through the project and getting organized before it is actually done
Meetings are most important part of executing. Number of meetings can be reduced
by better planning.
The meetings are too important to discuss status of a project. These must be used to
review risks and upcoming contingency plans.
This group runs in parallel to Executing group (and NOT after its completion).
We choose to categorize some activities to be belonging to this group- does not mean
they happen after execution.
Project is not completed even if all the activities are completed. It gets completed in
the closing process group.
Integration management is the act of putting all the pieces of the project into a single
unit
Team members must focus on completing the work packages and sponsor must
protect the project from undue influences. PM is responsible for the integration
Integration involves balancing all the processes in knowledge areas of scope, time,
cost, quality, HR, communications, risk and procurement management with each
other
Project Title
It is a statement of
Description
the scope, objectives
Project Manager and authority level
and participants in a
project. It provides a
Business Case
preliminary
Resources assigned
delineation of roles
Stakeholders
and responsibilities,
Stakeholder requirements known
outlines the project
objectives, identifies
Product description/deliverables
the main
stakeholders, and
Project objectives
defines the authority
Approval requirements
of the project
High level risks
manager.
Project sponsor
Project Definition
Project Goals
Project Scope
Project Deliverables
Project constraints/Risks
Implementation Plan/Milestones
Communcations Plan
Constrained optimization
• Linear programming
• Integer programming
• Dynamic programming
• Multi-objective programming
Economic models
• Present Value (PV)
• Net present value (NPV)
• Internal rate of return (IRR)
• Payback period
• Benefit-cost ratio
If rate is 10% then 100/- next year is worth only 91/- today
Exercise-1: If project A gets 100/- in year 1 and 200/- in year 2. What is its PV. Assume
the interest cost is 10%.
Exercise-2: For project B, you have to spend 20/- at the end of one year and 40/- at
the end of year 2. The revenue at the end of year 1 is 100/- and revenue at end of
year 2 is 200/-. What is the NPV? (r = 10%)
The equivalent interest rate of the future cash flows. Higher IRR is better (exceptions)
Exercise-1: Project A requires you spend 100/- today but will result in a total money
of 120/- at the end of one year. What is IRR for project A?
Exercise-2: For project B, you have to spend 120/- at the end of one year and 40/- at
the end of year 2. The revenue at end of year 2 is 200/-. What is the IRR?
Exercise-1: Exercise-2:
100*(1+r) = 120 120*(1+r)+40 = 200
=> R = 0.2 = 20% ⇒1+r = 160/120 = 1.33
⇒r = 33%
Benefit cost ratio present value of total benefits with present value of total costs
BCR = Benefits/Costs
Exercise-1: Project A requires you spend 300 and will yield 100/- each year starting at
the end of year-1. What is the payback period
Exercise-2: For project B, you have to spend 100/- now and 100/- at the end of one
year. You will receive 50 at the end of one year and 200 at the end of second year.
What is BCR? r = 10%
Exercise-1: Exercise-2:
Cost = 300. PV of benefits = (50/1.1)+(200/1.12) = 210
Benefit for n years = 100*n PV of costs = 100+(100/1.1) = 191
300 = 100*n => n = 3 BCR = 210/191 = 1.1
(BCR > 1 is good project)
Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
Economic value added
Additional value generated after covering for the financing cost (Like interest cost etc)
Exercise-1: Project A requires you to spend 100/- today. It will generate 130/- at the
end of one year. You have an option to invest in a partner company which will give
you 20% returns. What is the economic value of undertaking project A?
Exercise-1:
Revenue generated = 130
Cash to invest = 100
FV @ 20% = 100 * 1.2 = 120
EV of project A = 130-120 = 10
Opportunity cost
Opportunity given up by choosing one project over another
Sunk cost
Money already expended
Exercise-1: Project A requires you to spend 100/- today and will complete after two
years with profit of 50. Project B requires you to spend 50/- and will complete after
year one with a profit of 50. What is the opportunity cost of project A.
Exercise-2: You have a project to replace all the CRT monitors in your office with LCD
monitors. There are 100 monitors and you have already replaced 50 of them, each at
a cost of 4,000/-. A new technology based monitor (OLED) is available in the market.
This monitor costs only 2,000/- and has better quality than LCD. What should you
pursue? LCD or OLED? (For reasons of compatibility there must be only one kind of
monitors in office)
Exercise-1: Exercise-2:
You will project B with profit of 50 Total cost of LCD = 4000*100 = 4Lakh
=> Opportunity cost of A = 50 Money to spend now = 4000*50 = 2Lakh
Money with OLED = 2000*100=2Lakh
OLED
Copyright: NucleusIMS (An ISB Management is better
Institute), www.nucleusIMS.com
Depreciation
Exercise-1: Project A requires you to buy an equipment with 1000/- which is useful
for 10 years. What is the straight line depreciation in first year.
Exercise-2: Project A requires you to buy an equipment with 1000/- which is useful
for 5 years. What is the sum of years depreciation for first year.
Exercise-1: Exercise-2:
Dep = 1000/10 Digits are 5, 4, 3, 2, 1
= 100/- Sum of digits = 5+4+3+2+1 = 15
First year depreciation = (5/15)*1000
Second year depreciation = (4/15)*1000
Exercise-3: You are working for Dr Reddy’s lab and have to buy a large biological
reactor for making insulin injections. The same identical reactor is for sale both in
China and Germany. The cost of reactor from China is 96 crores while from Germany
it is 100 crores. Indian government requires you do straight line depreciation with
china imported equipment but allows double declining depreciation with Germany.
Where would you buy. Assume useful life of 3 years and interest rate of 10%.
Created by the
sponsor/customer and
describes the needs, product
scope and how project fits
their strategic needs
Strategy for managing the project and the processes in each knowledge area. How to
plan the project based on the needs and how to manager and control the project
The baseline includes scope baseline, schedule baseline and cost baseline
Baselines once fixed should be difficult to change and changes must be asked for in
the monitoring & controlling process group
Deviations from baselines are mostly (almost always) due to inadequate risk
identification
Controlling a project to the baselines and the rest of the project management plan is
so important that the PM needs to think twice in advance about where there might
be changes and what to do to limit the negative effects of changes
Changes are much more costly than if work was included from the beginning
Change control system is part of organization assets and includes standard forms,
reports, processes, procedures and software to track and control changes
Configuration management plan helps manage the version of scope, schedule and
other components of the project management plan
As part of project planning the PM identifies existing processes to use on the system
and may also create his own. These efforts improve efficiency of work completion by
team members.
Project documents are the documents used to manage a project and are not part of
project management plan. e.g. SOW, Charter, contracts etc.
Project management plan is a formal document used to manage the execution of the
project and must receive formal approval by the management.
Before you can complete the “develop project management plan” process and
project execution starts a kickoff meeting should be held.
It is a control function (process) done from initiation to closing of the project. This
results in change requests and updates to PM plan and project documents.
It makes sure work is properly sequenced and starts only when authorized.
Any action to bring expected future project performance in line with the project
management plan. It is not about rectifying something which went wrong.
During monitoring and controlling processes, changes may be requested that affect
any part of the project. These can be accepted or rejected in the integrated change
control process. This looks at the impact of change on all knowledge areas like quality,
risk, time, cost, HR etc
Changes are usually controlled by the change control board which comprises of PM,
customers, experts, sponsors etc
• Scope management is the process of defining what work is required and making sure
all of that work and ONLY that work is done
• You must plan in advance how you will determine the scope, manage it and control it
• Requirements are gathered from all stakeholders and not just the person who
assigned the project
• Determine requirements making sure all requirements support the business need of
the project
• Sort through and balance the needs of stakeholders to determine product scope and
project scope
• Create WBS to break up the scope to smaller and more manageable pieces
Some issues are very complex and require management intervention. Broad guidelines
exist however prefer in this order
• Requirements traceability matrix helps track the requirements over the life of the
project to ensure they are accomplished
Unique Requirement Source of SRS / FR # Module Test Successful Test Modification of Comments
Case(s) Verification
Number Requirement Requirement
This is concerned with what is and what is not included in the project and its
deliverables
• Product analysis helps analyze the objectives and description of the product stated by
the customer and turn into tangible deliverables
• The project scope statement along with the WBS and WBS dictionary comprise the
scope baseline which is part of project management plan
WBS breaks the project into smaller and more manageable tasks
• Quality control and Verify scope are similar in that both involve checking for the
correctness of work. The difference is the focus on effort and who is doing the
checking.
• In QC, the QC department checks to see if the quality requirements specified for the
deliverables are met, In verify scope it is the customer who checks before accepting the
deliverables.
• Control scope involves measuring project and product scope performance and
managing scope baseline changes
• Need to measure scope performance against the baseline to see magnitude of any
variances. Next see if any updates to scope baselines or other parts of project
management plan are needed
• Remember that unrealistic schedule is a project manager’s fault and not that of senior
management (This assumes that the PM is the one who created the schedule)
• It is PM’s job to see if the needed end date can be met and create options to make it
happen, all BEFORE project execution even starts
It includes:
• The scheduling methodology and scheduling software to be used on the project
• Establishment of a schedule baseline for measuring against during the
monitoring and controlling process group
• Identification of the performance measures that will be used on the project, to
identify variances early
• Planning for how schedule variances will be managed
• Identification of schedule change control procedures
The process involves taking the work package in WBS and breaking down further
to reach activity level. In order to do this you need the scope baseline and the
team so that activities can be defined more accurately and make estimates better.
Other Information
• Rolling Wave Planning: Plan at higher level and then wait until project work
begins to start next level of planning
• After completion, Define activities will result in activity list and details of the
activities being completed
• Milestones are significant events within the project schedule
• Take the activities and milestones and start to sequence them into how work is
performed. This will create a network diagram
Once the activities are sequenced, the type and quantity of needed resources is determined
Once the previous time management processes are completed the next step is to compute
the amount of time each activity is expected to take. For this you will need activity
resource requirements, resource calendars, organizational process assets, enterprise
environmental factors. [Duration = Time to complete+1]
The time estimates gathered during estimating are also used to create the risk register
during risk management process
A B C
P: 12 P: 9 P: 14
M: 9 M: 6 M: 6
O: 6 O: 3 O: 4
Project must have reserves to accommodate for risks that remain after the completion of
risk management activities.
Two types of reserves for risks- Contingency reserves and Management reserves
Contingency reserves- For risks which remain after plan risk response process
Management reserves- For unknown risks
Contingency reserves are under the control of project manager while management
reserves are under the control of top management.
Develop Schedule
Difference between time estimate and schedule is that schedule is calendar
based.
Critical path method is the determination of the longest path in the network diagram and
critical path is the path of longest duration in the network diagram and determines the
shortest time to complete the project
Near critical path is a path close in duration to critical path. The closer it is to critical path,
the more risk project has
Total Float/Total Slack: Time an activity can be delayed without delaying the project end
date or an intermediary milestone
Free Float/Free Slack: Time an activity can be delayed without delaying the early start date
of its successor
Project Float: Project float is the amount of time a project can be delayed without delaying
the externally imposed project completion date required by the customer or management.
Fast tracking- Doing critical path activities in parallel that were originally in series.
Increases risk and needs more communication. This involve a time vs. risk tradeoff.
Crashing- Making cost and schedule tradeoffs to determine how to compress the
schedule. Always involves increased cost. This involve a time vs. cost tradeoff.
Resource leveling: Produce a resource limited schedule. The schedule from this is almost
always longer than the project schedule.
Critical Chain method: It takes both activity and resource dependency directly into
account. Buffers are added to the activities at few locations and these buffers are
managed.
When to use Gantt/Bar and not Network diagram: To track progress and to report to team
Control accounts are placed at selected management points of the Work Breakdown
Structure (WBS) to monitor cost and schedule performance of significant elements of
work. Control accounts are a management control point for cost summarization, scope
description, and variance analysis & reporting, responsibility assignment, and corrective
action planning. Each Control account contains one or more work packages and planning
packages, but each work package / planning package may be associated with only one
control account. Control accounts are also referred to as cost accounts
Cost management plan is created during project management plan creation and includes
• Specifications on how estimates should be stated
• Level of accuracy needed for estimates
• Reporting formats to be used
• Rules for measuring cost performance
• Whether costs will include both direct and indirect costs
• Control thresholds
Lifecycle costing includes looking at the total cost during the entire life of the product
Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
Value analysis and Estimate costs
• Involves finding a less costly way to do the same work. This means team is looking to
decrease project cost with same scope
The estimate costs process is where the estimates for each activity are made
• Must be based on WBS
• Must be done by person doing the work
• PM must not accept constraints from management but must analyze needs of the
project and come up with own estimate and reconcile any differences
• PM must meet agreed upon estimates
• Estimates can be decreased by eliminating or reducing risks
Types of costs
Variable costs: Cost of soaps in hotel given to guests
Fixed costs: Cost of having an attendant at the hotel
• Scope baseline
• Project schedule
• HR plan
• Risk register
• Policies on estimating, templates, processes, procedures, lessons learned etc
• Company culture etc
• PM costs
Estimates made during early project phase are less accurate than the ones which
are made later
Range of estimates
ROM (Rough order of magnitude): - 50% to 100%
Budget estimate: -10 to 25%
Definite estimate: +/- 10%
Total cost of project needs to be computed so that the organization can set aside this
money and is called budget.
Cost aggregation
Activity costs are rolled into work package costs and work package costs are rolled into
control account costs and control account costs into project costs
Progress reporting
Sometimes It is not practical to report the project progress continuously based on the
progress of activity level.
50/50 Rule
20/80 Rule
0/100 Rule
PV – planned value
EV – Earned value
AC – Actual cost
BAC – Budget at completion (Initial Budget)
EAC – Estimate at completion (Revised Budget)
ETC – Estimate to complete
VAC – Variance at completion (Difference between Initial budget and revised budget)
EAC = AC + (BAC-EV)
ETC = EAC-AC
VAC = BAC-EAC
It is the ratio of work remaining to budget remaining for the project. TCPI is the calculated
projection of cost performance that a project must achieve on the remainder of the
project work to reach a specified end result.
If TCPI is one (1.0), then the remaining project work must be executed at the same
cost performance level as the completed project work. If TCPI is less than one
(<1.0), then the remaining project work can be executed at a lower cost
performance level than the project completed work. If TCPI is greater than one (>
1.0), then the remaining project work must be executed at a better cost
performance level than the project completed work till date.
BAC = $115,000
CPI = EV/AC = $55,000/$75,000 = 0.733
EV = $55,000
AC = $75,000.
New budget approved is $125,000. Calculate TCPI
TCPI allows you to calculate the amount of cost performance improvement that must be
made on the remaining workNucleusIMS
Copyright: to reach(AnaISB
set goal. Institute), www.nucleusIMS.com
Management
Quality management
Lack of attention results in more rework and defects and costs time and money
Process Group
Plan quality Planning process group
Perform quality assurance Executing process group
Perform quality control Monitoring and controlling
What is quality?
Implies you need to have all the stated and unstated requirements and project
scope statement
Quality management
Includes creating and following policies and procedures to ensure that a project
meets the defined needs it was intended to meet from the customer’s perspective
Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
Quality Theorists
• Juran: Developed the 80/20 principle (80% of problems contributed by 20% causes)
• Edward Deming: TQM and Deming cycle (Do small increments before making large changes)
• Philip Crosby: Prevention over inspection (Better to prevent errors than inspect later)
Marginal analysis
• Benefits or revenues to improving quality are equal to cost of achieving this
quality. This tells when to stop trying to improve quality.
Used to monitor things like project performance figures such as cost and schedule
variance. It is also useful for monitoring the quality of technical process parameters.
Some examples: How long does it take to answer a customers query in a BPO. How long
does it take for us to fix a bug reported by a customer. etc
Rule of 7
• 7 data points grouped on one side of mean (even though within control limits)
A pharmaceutical company follow 3-sigma policy. They produce one lakh tablets a
month. How many defective tablets would you find?
Implement
Hand off
Process Group
1. Sponsor
2. Team
3. Stakeholders
4. Functional Manager
5. Project Manager
• Is a stakeholder
• Provides funding
• Gives PM authority outlined in the charter
• Helps organize work into appropriate projects
• Sets priorities between projects
• Assign specific individuals to team and negotiate with project manager regarding
resource
• Let project manager know of other projects that may impact the project
• provide subject matter expertise
• Approve the final schedule during schedule development
• Recommend changes to project
• Improve staff utilization
HR Plan includes
• Roles and responsibilities
• Project organizational charts
• Staffing management plan
To create a rewards and recognition system ask how will you motivate and reward not just
the team but every individual member
Shows the number of resources used per time period and where there is a spike in the
need for resources
Halo effect
Refers to the tendency to promote someone due to their technical competence
• Formal
• Reward
• penalty
• Expert- comes from being a technical or PM expert
• Referent- comes from other person liking you
• Withdrawal-Give up. Anyway you will not listen to me, I will do what you tell me
• Collaborating-I will listen to you now, but next time you will have to listen to me
Expectancy theory – employees who believe their efforts will lead to effective
performance and who expect to be rewarded for their accomplishments remain
productive as rewards meet their expectations
Mc Gregor’s theory
X Type- People need to be watched everytime.
Y Type- People are willing to work without supervision
Maslow Theory
Herzberg’s theory
Hygiene factors – working conditions, salary, personal life, relationships at work, security
status.
Motivating factors- Responsibility, Self-actualization, professional growth, recognition
Poor hygiene factors may destroy motivation but improving them in mist circumstances
will not improve motivation
• Communications can be informal & formal, written and verbal but it is always
proactive and thorough in a PMP world.
Classification tools such as power/interest grids and salience models can be used
to group stakeholders by qualifications like authority level, impact or influence or
requirements
High interest, low influence, expert on high Invite the stakeholder to participate in risk
risk areas management process
Low interest, source of most requirements, Make sure requirements are clear and send
not easy to work with reports
High interest, high influence, not supporter Understand why he is not a supporter and
of project plan on dealing with him on those reasons
Involve stakeholder in team meetings,
High interest, high influence, a supporter of
report to this person and include the
project
information stakeholder requested
Moderate interest, high influence, a project Invite the stakeholder to officially join the
supporter and working with you project team
Moderate interest, high influence because he Plan to meet with the stakeholder
identified many risks and supporter of the periodically to see if he has identified any
project more risks
Moderate interest, nervous about completing Plan to find and forward relevant literature to
his/her activities assigned stakeholder and arrange for a training
Other stakeholders
Active management of stakeholder expectations makes them feel their concerns and
needs are at least considered even if they are not agreed to.
Types of reports
• Communications can be informal & formal, written and verbal but it is always
proactive and thorough in a PMP world.
Classification tools such as power/interest grids and salience models can be used
to group stakeholders by qualifications like authority level, impact or influence or
requirements
Influence Influence
Project Success Influence 3
Project Failure Influence 2
Importance Importance
Command Level 2
Legitimacy within the organization 4
Ability to get attention 5
Attitude Attitide
Project Will 5
Expectation for Failure 2
Expectation for success 5
Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
Communications Management: Managing stakeholders
High interest, low influence, expert on high Invite the stakeholder to participate in risk
risk areas management process
Low interest, source of most requirements, Make sure requirements are clear and send
not easy to work with reports
High interest, high influence, not supporter Understand why he is not a supporter and
of project plan on dealing with him on those reasons
Involve stakeholder in team meetings,
High interest, high influence, a supporter of
report to this person and include the
project
information stakeholder requested
Moderate interest, high influence, a project Invite the stakeholder to officially join the
supporter and working with you project team
Moderate interest, high influence because he Plan to meet with the stakeholder
identified many risks and supporter of the periodically to see if he has identified any
project more risks
Moderate interest, nervous about completing Plan to find and forward relevant literature to
his/her activities assigned stakeholder and arrange for a training
Other stakeholders
Active management of stakeholder expectations makes them feel their concerns and
needs are at least considered even if they are not agreed to.
Types of reports
Although risk processes are done in a sequence they are done often during the
course of project, starting in initiation all the way to the end of the project
Through risk management, the project changes from being in control of the
project manager to the project manager being in control of the project.
Process of risk management will help prevent many problems on projects and
make others less likely. This reduction in uncertainty means saving in terms of cost
and time
Plan risk management answers the question of how much time to be spent on risk
management based on the needs of the project. Who will be involved and how
you will go about performing risk management
Risks generated by
• Customer
• Lack of PM Effort
• Lack of knowledge of project management
• Suppliers
• Resistance to change
• Cultural differences
This involves creating a short list of the previously identified risks and is a subjective
technique. To perform this you need
• Probability of each risk occurring, using a standard scale
• Impact of each risk occurring using a standard scale
• It is CRITICAL to give a standard risk rating matrix along with this information. This is
considered a separate and distinct activity
Risk categorization: What will we find if we regroup the risks by categories or work
packages?
Risk Urgency assessment: Qualitative risk analysis also includes listing of risks which need
to be quickly addressed
Note that quantitative risk analysis is a more objective evaluation but also requires more
time and cost to evaluate
Fare 900
Airline A
Late 4,000
On time 70%
Airline B
Fare 300
Late 4,000
Outputs
• Project management plan updates
• Project document updates
• Risk register updates
Residual risks-Risks after risk planning
Contingency plans- action if +ve or –ve risks happen
Risk response owners
Secondary risks – Risks created by risk response
Risk triggers – events triggering contingency plans
Contracts
Fallback plans-plan if contingency plan does not work
Reserves Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
Risk response terms
Updated risk
Residual Risks
Register/Watch List
Do not have a
Have a Plan Work around
Plan
Not in risk register
Secondary Risks
Contingency Plan
[New risks]
• Document non critical risks in a watch list and revisit them periodically
• You can choose a combination of risk response strategies
• During the execution of project you frequently watch out the list of risks to see if any
has increased in importance
• The most important item to discuss in team meetings is risk
Risk reassessments: Team needs to periodically review risk management plan and risk
register and adjust them as required
Risk Audits: Have a team verify that all risk related procedures like identification, planning
and responses are being done
Reserve analysis: Checking to see how much reserve remains and how much might be
needed
Process Group
Plan procurements Planning
Conduct procurements Executing
Administer procurements Monitoring and controlling
Close procurements Closing
• Request for proposal (RFP)- Detailed proposal on how work will be finished
• Invitation for Bid (IFB)- Request total price to do the complete work
• Request for quotation (RFQ) – Price quote per item, hour or other unit of
measure
Seller selection
Organizations use different means to select sellers and these methods are dictated
by law or internal policies. If there are competing submissions the buyer might ask
for presentations from the sellers to help select a seller.
Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
Procurement management notes
Procurement process does not end when the contract is entered into. Once the
contract is signed, the procurement must be administered and this involves
making sure all the requirements of the contract, even ones that seem
unimportant are met.
Seller can be sometimes internal to an organization but for PMP Exam, assume
seller is an external party.
There is a procurement manager for managing contracts, then what is the role of
a project manager?
• First it is the project manager’s project and he is ultimately responsible for it.
• Secondly project manager is the best person to understand the risks in the
project and hence can help in choosing the best contract.
Type of
Advantages Disadvantages
organization
There is higher levels of expertise Attention of a procurement manager
due to functionalized nature divided across multiple projects
Department will provide with Difficult for the project manage to
continuous training, support etc get help when needed
Centralized
Standardized practices help with Project manager not in control of the
efficiency and understanding process
Individuals have a clear career path
There is no “home department” for
Project manager has easier access
the procurement manager after the
to contracting expertise
project
Difficult to maintain high level of
Procurement manager is more
De-centralized loyal to the project
contracting expertise within
company
There may be very little
standardization, high duplication and
inefficiencies in the process
Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
Inputs to procurement process
• Performance: This type conveys what the final product should be able to
accomplish, rather than how it should be built or what its design characteristics
should be (e.g. I want a racing car that can reach 100miles/hour in 2 seconds).
• Functional: Conveys the end purpose or result, rather than specific procedure
(e.g. The car must be able to hold two cup holders and a small refrigerator).
• Design: Conveys what precisely needs to be done, e.g. Building construction
Performance and functional are typically used for IT, IS, High-tech, R&D and
innovation projects. Design is normally used in construction and equipment
purchasing.
Copyright: NucleusIMS (An ISB Management Institute), www.nucleusIMS.com
Types of contract
Cost Reimbursable
• When exact scope of work is uncertain and therefore costs cannot be estimated
accurately enough to effectively use a fixed price contract. This allows the buyer to pay
seller allowable incurred costs to the extent prescribed in contract.
Cost contract
• Seller receives no fee (e.g. NGO organization)
• Contract = cost
• Price
• Profit
• Cost
• Target Price – The price to use for performance measurement
• Sharing ratio – Describes how cost overruns or cost savings will be shared with
buyer (e.g. 80/100). The first number is what buyer keeps and second number is
what seller keeps
• Ceiling Price – Highest price seller will pay
• Point of total assumption – Only for fixed price incentive fee contracts.
Represents the amount after which seller bears all the loss of a cost overrun.
Cost is estimated at 210,000 and the fee at 25,000. The project is over and the
buyer has agreed that the costs were in fact 200,000. Because the sellers costs
came in lower than estimated costs the seller shares the savings – 80% to buyer
and 20% to seller. Compute final price and fee
Teaming agreement
• Sellers joining hands to win the contract. e.g. oil field bidding, government
contracts etc.
• Bonds – Payments that must be purchased. e.g. payment bond will protect the
buyer from claims of nonpayment by the seller
• Force majeure – Situation by the act of god like natural calamities
• Liquidated damages – Estimated damages for specific defaults estimated in
advance
• Material breach – Breach so large that it may not be possible to complete the
work under contract
• Retainage – Money withheld from payment and paid back when work is
completed
• Time is of the essence – Means delivery dates are strictly binding and not
sticking to time will be a material breach
Material breach and Time is of essence helps buyer to get higher compensation in
times of dispute, but also increase the cost of contract
• Single source: Directly deal with preferred seller without procurement process.
You may have worked with them before.
• Sole source: There is only one source, e.g. patented product
Conducting procurements
Advertizing
Qualified seller’s list
Bidder conferences
Seller proposal
Weighting system
Independent estimates
Screening system
Objectives of a negotiation
• Obtain a fair and reasonable price
• Develop good relationship with seller
Negotiation tactics
Claims administration
A claim is the assertion that the buyer did something that has hurt the seller and
the seller is asking for compensation
Termination
A contract can be terminated before it is completed. Contract usually has
provisions for termination
Closure
A contract can be closed either by
• Completing the work in contract
• Terminating the contract
Professional and social responsibility is broken down into the following categories in the
code of ethics and professional conduct:
• Responsibility
• Respect
• Fairness
• Honesty
Make decisions based on the best interest of the company rather than your best
interest
• If you discover project is suffering because you have not created a project management
plan. If you tell management about it you may lose your job. What will you do?
PMI expects the professionals to stay engaged and further the profession. Any time PM
has an opportunity to share lessons learned, mentoring, teaching there is a good chance
it is the right answer
You may encounter situation that poses a situation where the project would benefit but
society would suffer. The project manager should avoid all such situations. If the
situation is not untenable then the project manager should disclose the situation and as
a last resort resign the project.
Do not study the chapters and prepare in isolation. You must be able to put it all
together. The process diagram of all the processes put together is a great tool. Also Full
length exams help you in this direction.
• Make sure you are thinking about large projects when studying and taking the final
exam
• Practice picking an answer from two or three right answers
• Decide in advance what notes you will write down when you are given scratch paper in
the exam
• Plan you strategy for the exam. When will you take the breaks and for how long
• Expect to see questions you cannot answer or even understand. This happens to
everyone and there is no reason to get annoyed or doubt your abilities during the exam
• Visit the exam site once before the exam to make yourself familiar with the location and
facilities available
• Do not over study. It is not worth trying to get comfortable all the material available.
• Start with Andy Crowe- Then to PMBOK4 - Finish all the (10+1 PMBOK) online exams
• Make sure you are comfortable during the exam. Wear a sweater which you can remove if needed.
• Bring a snack (Multi grain bars). Keep them in the locker in case you feel hungry.
• You will get scratch pad (5 pages) and pencil during the exam. You will have 15 minute tutorial to
practice. Use this time to jot down in the scratch pad anything you want to write down.
• If you want a new scratchpad you will have to surrender the previous one.
• You will answer one question at a time and can review the questions anytime. You can move back and
forth with the exam questions.
• The exam is NOT adaptive
• Use deep breathing to relax, if you are feeling nervous in the exam
• Smile during the exam- This will make you feel calm
• Use all the exam time. Do not leave early unless you have reviewed all the answers at-least twice
• Control your frustration and focus on the exam. You might dislike or disagree with some questions or
answers. You may be surprised at the number of questions you mark for review. This is very normal.
• Answer the questions from PMI’s perspective of large groups and not from your experience of small
project teams
• READ ALL THE FOUR CHOICES AND THEN DECIDE THE ANSWER
• eliminate answers which are improbable, so you should in general have 2 answers to choose from
• There can be more than one right answer, but only one BEST answer
• Watch out for statements which are true but do not answer the question
• Options that represent broad and sweeping generalizations tend to be incorrect. So watch out for
“Never”, “Always”, “Must”, “completely” etc
• In the fill-up-blanks the correct answer may not be grammatically correct
• Do not get stuck. If you find a question difficult, review it later and move ahead.
• People feel that PMP content is more in regards to “White collar professions”- probably it is partially
true.
• Pace yourself- You should answer roughly about 55 questions in one hour (200 questions in 4 hours)
• You are requested to ask for any support or help till your examination time
• If you need any text book, we can arrange it for personal, non commercial use
• You will get support for career change or job change, long after today. Please do not
hesitate to contact if and when you need any help from the Institute.
• For immediate help, you can welcome to come over on Saturdays or Sundays and take
paper based or online exams.
• Please intimate Pradeep at-least one day in advance if you need paper based test.