Professional Documents
Culture Documents
Field Record of Concrete: Commercial & Office Building On Plot No. 373-1343 at Al Barsha First Dubai
Field Record of Concrete: Commercial & Office Building On Plot No. 373-1343 at Al Barsha First Dubai
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Concreting area:
Poured item:
loading Concrete Air Inspectors
Truck No. Qty (m2) Pour started Pour finished Slump Cube Nos.
started Temp. Temperature signature
Engineers comments:
Contractor to provide full Method Statement of the works as an attachment to this form.
Location: Basement Category:
Spec. ref.:
Contractors comments:
Engineers comments:
Status:
Project Manager: Date: Engineer: Date:
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Manufacturer:
Country of origin:
Specification ref.
2.Inspection report
Physical damage?
Details:
Remarks:
3. Engineer's comments:
The above material has been inspected on site and found at the time of inspection to be :
The Engineer's approval of this inspection shall not relieve the Contractor of his responsibilities to incorporate in the Works only such
materials that are in conformity with the contract requirements.
Project Manager: Date: Engineer: Date:
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Location: ground Floor slab This inspection requires the following disciplines:
Engineers comments:
Architect
Structural Engineer
Mechanical Engineer
✘ Electrical Engineer
Inspector
Surveyor
QA/QC
………………...
Resident Engineers comments:
Status:
Approved Approved with comments Not Approved revise and resubmit Rejected as comments
omments
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Contractors comments:
Engineers comments:
Architect
Structural Engineer
Mechanical Engineer
Electrical Engineer
Inspector
Surveyor
QA/QC
………………...
Resident Engineers comments:
Status:
Approved Approved with comments Not Approved revise and resubmit Rejected as comments
692311225.xls 09/19/2023
Project Manager: Date: Engineer: Date:
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Manufacturer: Supplier
Address: Address:
Contractors comments:
Engineers comments:
Emp.
Archt.
S.Eng.
M.Eng.
E.Eng
I.Des.
Status:
Approved Approved with comments Not Approved revise and resubmit Rejected as comments
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Sub-Contractor Nomination
Contractor: Al Mazrouei Bowyer Building Consultant: Arif & Bintoak
P.O. Box 51445 Consultant Architects & Engineers
Dubai P.O. Box 3670, Dubai, UAE.
United Arab Emirates
Sub-Contractor
Planned Planned Required on
Nomination Category Sub-Contractors Name Actual Submittal date Actual Submittal date STATUS
sumittal date approval date site
Reference
0 1 2 3 0 1 2 3
Dear Sir,
Please find attached supporting documents in respect to our proposed subcontractor for
the above works.
1. Name and classification. ✘
4. Full list of names, qualifications and experience of staff proposed for this project. ✘
6. Written confirmation that the proposed subcontractor will act and comply, in full conformity ✘
Contractors comments:
Engineers comments:
Emp.
Archt.
S.Eng.
M.Eng.
E.Eng
Status: I.Des.
Approved Approved with comments Not Approved revise and resubmit Rejected as comments
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Sub-Contractor Approval
Contractor: Al Mazrouei Bowyer Building Consultant: Arif & Bintoak
P.O. Box 51445 Consultant Architects & Engineers
Dubai P.O. Box 3670, Dubai, UAE.
United Arab Emirates
Sub-Contractor
Planned Planned Required on
Submittal Category Sub-Contractors Name Actual Submittal date Actual Submittal date STATUS
sumittal date approval date site
reference
0 1 2 3 0 1 2 3
0 1 2 3 0 1 2 3
Engineers comments:
Emp.
Archt.
S.Eng.
M.Eng.
E.Eng
I.Des.
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
REF. 3RD BASEMENT PLAN AIRCONDITIONING LAYOUT C001 REV. - CO DATED 13.01.2009 ISSUED FOR CONSTRUCTION
REF. 2ND BASEMENT PLAN AIRCONDITIONING LAYOUT C002 REV. - CO DATED 13.01.2009 ISSUED FOR CONSTRUCTION
REF. 1ST BASEMENT PLAN AIRCONDITIONING LAYOUT C003 REV. - CO DATED 13.01.2009 ISSUED FOR CONSTRUCTION
REF. GROUND FLOOR PLAN AIRCONDITIONING LAYOUT C004 REV. - CO DATED 13.01.2009 ISSUED FOR CONSTRUCTION
KINDLY CLARIFY THE FRESH AIR SUPPLY (FRESH AIR FAN) FOR THE BASEMENT VENTILATION SYSTEM TO ALLOW US PROCEED
Engineers comments:
Emp.
Archt.
S.Eng.
M.Eng.
E.Eng
I.Des.
This clarification does not constitute a variation to the Contract Sum or Contract Period.
Project Manager: Date: Resident Engineer: Date:
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Engineers comments:
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
MATERIAL SUBMITTAL
Contractor: Al Mazrouei Bowyer Building Consultant: Arif & Bintoak
Address: P.O. Box 51445 Consultant Architects & Engineers
Dubai Address: P.O. Box 3670
United Arab Emirates Dubai, UAE.
Sub-Contractor
Address: Tel:337 28 88 Fax:337 03 52
Date Submittal prepared: Submittal Reference: Rev. No.
10.02.09
J326_MS-07
Material description: EMACO R303 Catalouge ref:
Manufacturer: BASF Construction Chemicals UAE LLC Supplier BASF Construction Chemicals UAE LLC
Delvery method:
Contractors comments:
Engineers comments:
Emp.
Archt.
S.Eng.
M.Eng.
E.Eng
I.Des.
Status:
Approved Approved with comments Not Approved revise and resubmit Rejected as comments
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Date: 11.03.09
Contracto Al Mazrouei Bowyer Building ConsultaArif& Bintoak
Address: P.O. Box 51445 Consultant Architects & Engineers
Dubai Address P.O. Box 3670
United Arab Emirates Dubai, UAE.
A. Weather conditions:
Max. Temp. Max. Rh
Rain Dusty ✘ Sunny Cloudy
Min. Temp Min.Rh.
B. MAN POWER (Main Contractor)
PM. ENG. FOR. Clerk Ch. Hand SF Mason Carp Helper Scaff. O/Boy Watch M Operator TOTAL
1 1 1 1 1 46 1 3 16 2 1 1 75
Ref. Sub Contractor ENG. FOR. Fitter Op Ch. Hand Labour Total
1 MEP
2 Al Shirawi 5 5
3 Saleh Construction
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
F. WORK EXECUTED
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
D. EQUIPMENT
Ref. Item Qty Ref. Item Qty
1 Loader / Shovel 9 Welding Equipment
2 Roller 10 Air Compressor
3 Dumper 11 Generator
4 Cocrete vibrato 12 Tower crane
5 Carpentry machine 13 Mobile crane
6 Power Float 14
7 Pick-up truck 15
8 Water cooler 16
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
F. WORK EXECUTED
Item Description of work Location Qty
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
Instruction By:
Emp.
Archt.
S.Eng.
M.Eng.
E.Eng
I.Des.
692311225.xls 09/19/2023
1399
Commercial & Office Building on Plot No. 373-1343 at Al Barsha First Dubai
TECHNICAL SUBMITTAL
Contractor: Al Mazroie Bowyer Building Consultant: Arif & Bintoak
Address: P.O. Box 51445 Consultant Architects & Engineers
Dubai Address: P.O. Box 3670
United Arab Emirates Dubai, UAE.
Sub-ContracAMBB MEP
Address: Tel:337 28 88 Fax:337 03 52
Location: Category:
Spec. ref.:
B.O.Q. ref.: Purpose:
Expected start date:
Contractors comments:
Engineers comments:
Status: