Professional Documents
Culture Documents
Rebar Weekly Sub Contrat-4
Rebar Weekly Sub Contrat-4
RESOURCE UTILIZATION
ACTIVITY STATUS ACTIVITY DURATION
LABOR MATERIAL MACHINERIES
ACTIVIT Not
No ACTIVITY NAME UNITS Qty % Planned Actual REMARK
Y ID started/start Planned Planned Actual Actual
COMPLE Finished Finished TYPE NO DUR TYPE UNIT QTY TYPE NO. DUR.
ed/Complete Start Date Duration Start Date Duration
TION Date Date
d
Rebar production
for Mat
ATS1- slabs,beams and
Project only Straiting work is
1 B1FL-ST- Starter kg 21231 started 594% 02-Aug-21 A 16-Aug-21 12 28-Sep-21 2-Oct-21 61 1 1 Rebar φ16 berga 11,388.00 Grinder 1 6
cordinater done
0003 columns,Shear
wall & lift @ Area-
1
only Straiting work is
Forman Rebar φ24 berga
1 4 9,843.00 done
Bar-Bender 1 4
Daily Labor 2 4
Prepared By Approved By
(Senior Office Engineer) (Construction Manager)