FLOWTRONIX PRIVATE LIMITED.

Annexure - A
Proposal No.: FT/F/Q-4009/22/5580A Date: 22-03-2022
Client: Fatima Fertilizers. Rev-01
Design, Supply and Installation services at Fatima Fertilizers • Khanewal Road • Multan.

ACTIVITY CHART - Level 1

Sr. No. Activity Description Time Duration


Estimated Completion
1 CABLE TRAY LAYOUT AND PLANS DEVELOPMENT 45 Days 15/06/2022
2 CABLE TRAY INSTALLATIONS 60 Days 15/08/2022
3 INSTALLATION OF POSITION SWITCHES 30 Days 15/07/2022
4 CABLE LAYING ACTIVITY 70 Days 10/09/2022
5 WIRING TERMINATIONS ON-SITE AND CONTROL 45 Days 25/09/2022
6 COMPLETION OF COMPLETE PROJECT - Handover 07 Days 05/10/2022

Expected Manpower 30 Person Team