Standing Committee on Concrete Technology

Annual Concrete Seminar 2007

High Workability Concrete for


Bored Pile Construction
©2005 Gammon Construction Limited. All Rights Reserved

CC Wai, Alan Wan


Gammon Construction Limited
©2006 Gammon Construction Limited. All Rights Reserved.

2
Sequence of Work in Bored Pile Construction

Sun Mon Tue Wed Thu Fri Sat

Week 1 Excavation

Week 2 Excavation Rock Drilling


©2006 Gammon Construction Limited. All Rights Reserved.

Week 3 Rock Drilling Airlifting Cage Concrete

3
©2006 Gammon Construction Limited. All Rights Reserved.

4
Presentation Scope

• Method of Concreting Bored Pile

• Problems and Defects

• Deficiencies in Current Practice

• Proactive Approach
©2006 Gammon Construction Limited. All Rights Reserved.

• The Way Forward

5
©2006 Gammon Construction Limited. All Rights Reserved.

6
Concreting of Bored Pile
General Setup
Concrete
Skip
Truck

Concreting
Platform
Ramp

Tremie
©2006 Gammon Construction Limited. All Rights Reserved.

Pipe

Concrete

7
Stages in Bored Pile Concreting

Extract Tremie Pipe Extract Temporary Casing

Tremie
Pipe Drop in
Concrete
Head

Temporary
Casing Concrete
Overbreak
©2006 Gammon Construction Limited. All Rights Reserved.

(1) (2) (3) (4)


8
©2006 Gammon Construction Limited. All Rights Reserved.

9
Grout
Cement
Concrete
QA / QC

• Slump tests / Flow table

• Check temperature ( 32o)

• Cube samples to determine concrete


strength
©2006 Gammon Construction Limited. All Rights Reserved.

10
©2006 Gammon Construction Limited. All Rights Reserved.

11
12:00

21:00
14:00

18:00
Concreting Takes Many Hours
Concreting Time Varies With Pile Length

30
25
Time (hours)

20
15
10
5
©2006 Gammon Construction Limited. All Rights Reserved.

0
0 20 40 60 80 100
Pile Length (m)
12
©2006 Gammon Construction Limited. All Rights Reserved.

13
Slump

Time
Slump Varies With Time
Common Problems Encountered

• Temporary casing cannot be withdrawn

• Tremie pipe cannot be withdrawn

• Blocked tremie pipe

• Reinforcement cage rides up with


©2006 Gammon Construction Limited. All Rights Reserved.

temporary casing

14
©2006 Gammon Construction Limited. All Rights Reserved.

15
Defects
©2006 Gammon Construction Limited. All Rights Reserved.
Honeycomb

• Reduced workability affects self compaction

16
©2006 Gammon Construction Limited. All Rights Reserved.

17
Air Voids
Entrapped Air Inside Concrete During Pouring

Air
Voids
©2006 Gammon Construction Limited. All Rights Reserved.

(1) (2) (3)


18
©2006 Gammon Construction Limited. All Rights Reserved.
Segregated Concrete

• Additive quantity needs fine-tuning

19
Remedial Actions

• Grouting

• High pressure water jet to remove “weak”


concrete, followed by pressure grouting

• Stitched pile
©2006 Gammon Construction Limited. All Rights Reserved.

• Additional pile

20
©2006 Gammon Construction Limited. All Rights Reserved.

21
Practice
Deficiencies in Current
First In …. Last Out

1* First few
truckloads
2 need to
3 remain
workable
throughout
concreting
18
©2006 Gammon Construction Limited. All Rights Reserved.

17
16
* Indicate order
of truckload
22
Deficiencies in Current Practice

• Large piles / deep piles mean large


concrete volume

• Specification / Contract Document


– Single slump value specified on drawing
– Workability vs time not considered
– Lack of flexibility in interpretation
©2006 Gammon Construction Limited. All Rights Reserved.

• Quality control
– Need to control consistency in material
properties

23
The Proactive Approach

• Need to Consider …..


– Specification
– Concrete volume (related to pile size
and depth)
– Site constraints (physical or
©2006 Gammon Construction Limited. All Rights Reserved.

environmental restrictions)
– Site location (travel time to site from
batching plant)
24
Route to Pile Acceptance

Pile
Acceptance

Concrete
Performance
©2006 Gammon Construction Limited. All Rights Reserved.

Material
Time
Consistency

Concrete Site Construction


Volume Constraints Procedure
25
SUCCESS STORY
Hong Kong – Shenzhen Western Corridor

Delivery
~ 3 hours
©2006 Gammon Construction Limited. All Rights Reserved.

Grade 45/20
•Designed slump
200mm
•Workability 5 hours
26
SUCCESS STORY
Hong Kong – Shenzhen Western Corridor

• Supplier formulated a special concrete mix


with enhanced workability

• Engineer relaxed concreting time to 5 hours

• Contractor checked workability prior to


pouring
©2006 Gammon Construction Limited. All Rights Reserved.

• Side-effect : minor segregation, need to pour


additional concrete to avoid undercasting

27
©2006 Gammon Construction Limited. All Rights Reserved.

28
Way Forward
Concrete Triangle

Constructability
Designer

Concrete Quality Slump


Consistency / Performance Retention
©2006 Gammon Construction Limited. All Rights Reserved.

Concrete
Contractor
Supplier

29
©2006 Gammon Construction Limited. All Rights Reserved.

30
The End