FS Project Schedule
FS Project Schedule
FS Project Schedule
TASK
1 Phase 1 PREPARATION
2 PreFS Submitted 1 20-Mar-2023
3 Tangsel Stakeholder Meeting 20 21-Mar-2023
4 Approval for start FS Study 5 10-Apr-2023
5 Phase 2 STUDY
6 Consultant Appoinment 8 14-Apr-2023
7 FS 60 21-Apr-2023
8 Report 5 19-Jun-2023
9 Public Hearing 5 23-Jun-2023
10 Final Report 5 27-Jun-2023
11 Phase 3 GOV. BIDDING
12 Bidding Committee formed 20 2-Jul-2023
13 Bidding Process 60 22-Jul-2023
14 Winner Annoucement 3 20-Sep-2023
15 PPA 35 23-Sep-2023
16 Task 4 DEVELOPMENT
17 Site Survey 60 29-Oct-2023
18 FEED+EPC 120 29-Dec-2023
19 DED+Construction+Instalation 600 27-Apr-2024
20 Mobilization Plant 120 18-Dec-2025
21 Test 60 17-Apr-2026
22 Commissioning 60 15-Jun-2026
23 Enter to Grid 5 13-Aug-2026
24 COD 2 17-Aug-2026
25 Operation & Maintenance 7300 18-Aug-2026
26 PPAs Extension Sign 10 12-Aug-2046
27 PPA 2 21-Aug-2046
28 Operation & Maintenance 3650 22-Aug-2046
29 Overhaul 10 1-Mar-2051
30 Transfer 10 19-Aug-2056
Q1 Q2
Jan Apri
Feb Mei
MarJun
20-Mar-2023
9-Apr-2023
14-Apr-2023
21-Apr-2023
19-Jun-2023
23-Jun-2023
27-Jun-2023
1-Jul-2023
21-Jul-2023
19-Sep-2023
22-Sep-2023
28-Oct-2023
28-Dec-2023
26-Apr-2024
17-Dec-2025
16-Apr-2026
15-Jun-2026
13-Aug-2026
17-Aug-2026
18-Aug-2026
12-Aug-2046
21-Aug-2046
22-Aug-2046
18-Aug-2056
11-Mar-2051
29-Aug-2056
Q3 Q4
Jul Okt
Agu Nov
Spt Des
3650
Batas formula
Activity Description Assigned to Days START END Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023 11
Final Report 5 27-Jun-2023 1-Jul-2023 11111
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023 11111111111111111111
Bidding Process 60 22-Jul-2023 19-Sep-2023 111111111111111111111111111111111111111111111111111111111111
Winner Annoucement 3 20-Sep-2023 22-Sep-2023 111
PPA 35 23-Sep-2023 28-Oct-2023 111111111111111111111111111111111111
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023 1111111111111111111111111111111
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056
3650
Batas formula
Activity Description Assigned to Days START END Nov-23 Dec-23 Jan-24 Feb-24 Mar-24
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023 111111111111111111111111111111
FEED+EPC 120 29-Dec-2023 26-Apr-2024 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056
3650
Batas formula
Activity Description Assigned to Days START END
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056
3650
Batas formula
Activity Description Assigned to Days START END
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056
3650
Batas formula
Activity Description Assigned to Days START END
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056
3650
Batas formula
Activity Description Assigned to Days START END
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026 1111111111111
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056
3650