FS Project Schedule

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 26

Activity Description 2023 2024

Days START END


TASK Q3 Q4 Q1 Q2
Task 1: Preparation
Develop Survey Methedology 10 10-Aug-23 20-Aug-23
Vendor for Geotechnic Survey 15 10-Aug-23 25-Aug-23
Administration Preparation 20 10-Aug-23 30-Aug-23
Task 2: Assigment for FS
Assignment Letter 1 9-Sep-23 10-Sep-23
Geotechnic Survey 10 11-Sep-23 21-Sep-23
Waste Survey 10 11-Sep-23 21-Sep-23
Climate Survey 10 11-Sep-23 21-Sep-23
Final Layout 10 11-Sep-23 21-Sep-23
Report Writing 25 11-Sep-23 6-Oct-23
Submit FS Document 1 7-Oct-23 8-Oct-23
Tangsel Stakeholder Meeting 4 9-Oct-23 13-Oct-23
Approval 1 14-Oct-23 15-Oct-23
Task 3: Bidding Process
Bidding Committee formed 10 7-Oct-23 17-Oct-23
Bidding Process 35 18-Oct-23 22-Nov-23
Winner Annoucement 10 23-Nov-23 3-Dec-23
PPA 35 4-Dec-23 8-Jan-24
Task 4: DEVELOPMENT
Earth Work 150 4-Dec-23 2-May-24
FEED+EPC 35 4-Dec-23 8-Jan-24
DED+Construction+Instalation 600 3-May-24 24-Dec-25
Mobilization Plant 540 9-Jan-24 2-Jul-25
Test 60 25-Dec-25 23-Feb-26
Commissioning 5 24-Feb-26 1-Mar-26
Enter to Grid 10 2-Mar-26 12-Mar-26
COD 2 13-Mar-26 15-Mar-26
Operation & Maintenance 7300 16-Mar-26 11-Mar-46
PPAs Extension Sign 10 12-Mar-46 22-Mar-46
PPA 2 23-Mar-46 25-Mar-46
COD 2 26-Mar-46 28-Mar-46
Operation & Maintenance 3650 29-Mar-46 26-Mar-56
Overhaul 10 29-Mar-51 8-Apr-51
Transfer 10 27-Mar-56 6-Apr-56
2024 2025 2026 2046 2051 2056
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Activity Description Hari Awal

TASK
1 Phase 1 PREPARATION
2 PreFS Submitted 1 20-Mar-2023
3 Tangsel Stakeholder Meeting 20 21-Mar-2023
4 Approval for start FS Study 5 10-Apr-2023
5 Phase 2 STUDY
6 Consultant Appoinment 8 14-Apr-2023
7 FS 60 21-Apr-2023
8 Report 5 19-Jun-2023
9 Public Hearing 5 23-Jun-2023
10 Final Report 5 27-Jun-2023
11 Phase 3 GOV. BIDDING
12 Bidding Committee formed 20 2-Jul-2023
13 Bidding Process 60 22-Jul-2023
14 Winner Annoucement 3 20-Sep-2023
15 PPA 35 23-Sep-2023
16 Task 4 DEVELOPMENT
17 Site Survey 60 29-Oct-2023
18 FEED+EPC 120 29-Dec-2023
19 DED+Construction+Instalation 600 27-Apr-2024
20 Mobilization Plant 120 18-Dec-2025
21 Test 60 17-Apr-2026
22 Commissioning 60 15-Jun-2026
23 Enter to Grid 5 13-Aug-2026
24 COD 2 17-Aug-2026
25 Operation & Maintenance 7300 18-Aug-2026
26 PPAs Extension Sign 10 12-Aug-2046
27 PPA 2 21-Aug-2046
28 Operation & Maintenance 3650 22-Aug-2046
29 Overhaul 10 1-Mar-2051
30 Transfer 10 19-Aug-2056
Q1 Q2
Jan Apri
Feb Mei
MarJun

2023 2024 2025 2026 2046


Akhir
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

20-Mar-2023
9-Apr-2023
14-Apr-2023

21-Apr-2023
19-Jun-2023
23-Jun-2023
27-Jun-2023
1-Jul-2023

21-Jul-2023
19-Sep-2023
22-Sep-2023
28-Oct-2023

28-Dec-2023
26-Apr-2024
17-Dec-2025
16-Apr-2026
15-Jun-2026
13-Aug-2026
17-Aug-2026
18-Aug-2026
12-Aug-2046
21-Aug-2046
22-Aug-2046
18-Aug-2056
11-Mar-2051
29-Aug-2056
Q3 Q4
Jul Okt
Agu Nov
Spt Des

2046 2051 2056


Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Activity Description Assigned to Days START END Progress Mar-23 Apr-23 May-23 Jun-23
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
1 Phase 1 PREPARATION
2 PreFS Submitted 1 20-Mar-2023 20-Mar-2023 1
3 Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023 11111111111111111111
4 Approval for start FS Study 5 10-Apr-2023 14-Apr-2023 11111
5 Phase 2 STUDY
6 Consultant Appoinment 8 14-Apr-2023 21-Apr-2023 11111111
7 FS 60 21-Apr-2023 19-Jun-2023 111111111111111111111111111111111111111111111111111111111111
8 Report 5 19-Jun-2023 23-Jun-2023 11111
9 Public Hearing 5 23-Jun-2023 27-Jun-2023 111
10 Final Report 5 27-Jun-2023 1-Jul-2023
11 Phase 3 GOV. BIDDING
12 Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
13 Bidding Process 60 22-Jul-2023 19-Sep-2023
14 Winner Annoucement 3 20-Sep-2023 22-Sep-2023
15 PPA 35 23-Sep-2023 28-Oct-2023
16 Task 4 DEVELOPMENT
17 Site Survey 60 29-Oct-2023 28-Dec-2023
18 FEED+EPC 120 29-Dec-2023 26-Apr-2024
19 DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025
20 Mobilization Plant 120 18-Dec-2025 16-Apr-2026
21 Test 60 17-Apr-2026 15-Jun-2026
22 Commissioning 60 15-Jun-2026 13-Aug-2026
23 Enter to Grid 5 13-Aug-2026 17-Aug-2026
24 COD 2 17-Aug-2026 18-Aug-2026
25 Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
26 PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
27 PPA 2 21-Aug-2046 22-Aug-2046
28 Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
29 Overhaul 10 1-Mar-2051 11-Mar-2051
30 Transfer 10 19-Aug-2056 29-Aug-2056

3650
Batas formula
Activity Description Assigned to Days START END Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023 11
Final Report 5 27-Jun-2023 1-Jul-2023 11111
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023 11111111111111111111
Bidding Process 60 22-Jul-2023 19-Sep-2023 111111111111111111111111111111111111111111111111111111111111
Winner Annoucement 3 20-Sep-2023 22-Sep-2023 111
PPA 35 23-Sep-2023 28-Oct-2023 111111111111111111111111111111111111
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023 1111111111111111111111111111111
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056

3650
Batas formula
Activity Description Assigned to Days START END Nov-23 Dec-23 Jan-24 Feb-24 Mar-24
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023 111111111111111111111111111111
FEED+EPC 120 29-Dec-2023 26-Apr-2024 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056

3650
Batas formula
Activity Description Assigned to Days START END
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056

3650
Batas formula
Activity Description Assigned to Days START END
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056

3650
Batas formula
Activity Description Assigned to Days START END
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056

3650
Batas formula
Activity Description Assigned to Days START END
TASK ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Phase 1 PREPARATION
PreFS Submitted 1 20-Mar-2023 20-Mar-2023
Tangsel Stakeholder Meeting 20 21-Mar-2023 9-Apr-2023
Approval for start FS Study 5 10-Apr-2023 14-Apr-2023
Phase 2 STUDY
Consultant Appoinment 8 14-Apr-2023 21-Apr-2023
FS 60 21-Apr-2023 19-Jun-2023
Report 5 19-Jun-2023 23-Jun-2023
Public Hearing 5 23-Jun-2023 27-Jun-2023
Final Report 5 27-Jun-2023 1-Jul-2023
Phase 3 GOV. BIDDING
Bidding Committee formed 20 2-Jul-2023 21-Jul-2023
Bidding Process 60 22-Jul-2023 19-Sep-2023
Winner Annoucement 3 20-Sep-2023 22-Sep-2023
PPA 35 23-Sep-2023 28-Oct-2023
Task 4 DEVELOPMENT
Site Survey 60 29-Oct-2023 28-Dec-2023
FEED+EPC 120 29-Dec-2023 26-Apr-2024
DED+Construction+Instalation 600 27-Apr-2024 17-Dec-2025 111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111
Mobilization Plant 120 18-Dec-2025 16-Apr-2026 1111111111111
Test 60 17-Apr-2026 15-Jun-2026
Commissioning 60 15-Jun-2026 13-Aug-2026
Enter to Grid 5 13-Aug-2026 17-Aug-2026
COD 2 17-Aug-2026 18-Aug-2026
Operation & Maintenance 7,300 18-Aug-2026 12-Aug-2046
PPAs Extension Sign 10 12-Aug-2046 21-Aug-2046
PPA 2 21-Aug-2046 22-Aug-2046
Operation & Maintenance 3650 22-Aug-2046 18-Aug-2056
Overhaul 10 1-Mar-2051 11-Mar-2051
Transfer 10 19-Aug-2056 29-Aug-2056

3650
Batas formula