WBS Outline Graphic
WBS Outline Graphic
1
OUTLINE FORMAT
MSU UNIVERSITY HOTEL
(7-STORY BUILDING W/ ROOFDECK)
2
1.3.4.1.3. Energy Analysis
1.3.4.2. Plumbing
1.3.4.2.1. Load Requirements
1.3.4.2.2. Specifications
1.3.5. Electrical System
1.3.5.1. Load Requirements
1.3.5.2. Lighting Requirements
1.3.5.3. Rough-in
1.3.5.4. Finish
1.3.5.5. Communication and Security Design
1.3.5.5.1. Specifications
1.3.6. Fire Protection System
1.3.6.1. Load Requirements
1.3.6.2. Specifications
1.4. Internal Design
1.4.1. On-site Utilities
1.4.1.1. HVAC Design
1.4.1.1.1. HVAC Equipment
1.4.1.1.2. Ductwork and Piping
1.4.1.1.3. HVAC Controls
1.4.1.2. Plumbing
1.4.1.2.1. Domestic Water System
1.4.1.2.2. Sanitary Sewer System
1.4.1.2.3. Stormwater Management System
1.4.1.2.4. Gas System
1.4.1.3. Power Distribution
1.4.1.3.1. Distribution System
1.4.1.3.2. Emergency Power System
1.4.1.4. Lighting Design
1.4.1.4.1. Interior Lighting Design
1.4.1.4.2. Exterior Lighting Design
1.4.1.4.3. Lighting Controls
1.4.1.5. Communication and Security Design
1.4.1.5.1. Telecommunications
1.4.1.5.2. Security and Access Control
1.4.1.6. Fire Protection System
1.4.1.6.1. Fire Alarm System
1.4.1.6.2. Fire Suppression System
1.4.1.6.3. Life Safety Design
1.4.2. Site Work
1.4.2.1. Site Grading and Preparation
1.4.2.2. Site Improvement
1.4.2.2.1. Fencing
1.4.2.2.2. Landscaping
1.4.2.2.3. Irrigation
1.4.2.3. Earthwork
1.4.2.3.1. Excavation and Grading
1.4.2.3.2. Soil Stabilization
1.4.2.3.3. Compaction
1.4.2.3.4. Backfilling
1.4.2.4. Paving
3
1.4.2.4.1. Sub-base
1.4.2.4.2. Concrete
2.0. Procurement
2.1. Overhead Crane
2.2. Site Work Contractor
2.3. Architectural Bid
2.3.1. Commercial Contractor Bid
2.3.2. Industrial Contractor Bid
2.4. Legal and Regulatory Compliance
3.0. Construction
3.1. Site Construction
3.1.1. Utilities
3.1.1.1. HVAC Design
3.1.1.1.1. Ductwork and Piping
3.1.1.1.2. HVAC Controls
3.1.1.2. Plumbing
3.1.1.2.1. Domestic Water System
3.1.1.2.2. Sanitary Sewer System
3.1.1.2.3. Stormwater Management System
3.1.1.2.4. Gas System
3.1.1.3. Power Distribution
3.1.1.3.1. Distribution System
3.1.1.3.2. Emergency Power System
3.1.1.4. Lighting Design
3.1.1.4.1. Interior Lighting Design
3.1.1.4.2. Exterior Lighting Design
3.1.1.4.3. Lighting Controls
3.1.1.5. Communication and Security Design
3.1.1.5.1. Telecommunications
3.1.1.5.2. Security and Access Control
3.1.1.6. Fire Protection System
3.1.1.6.1. Fire Alarm System
3.1.1.6.2. Fire Suppression System
3.1.1.6.3. Life Safety Design
3.1.2. Site Work
3.1.2.1. Site Grading and Preparation
3.1.2.2. Site Improvement
3.1.2.2.1. Fencing
3.1.2.2.2. Landscaping
3.1.2.2.3. Irrigation
3.1.2.3. Earthwork
3.1.2.3.1. Excavation and Grading
3.1.2.3.2. Soil Stabilization
3.1.2.3.3. Compaction
3.1.2.3.4. Backfilling
3.1.2.4. Paving
3.1.2.4.1. Sub-base
3.1.2.4.2. Concrete
3.2. Building A, B, and C
3.2.1. Structural
3.2.1.1. Foundations
4
3.2.1.2. Structural Frame
3.2.2. Mechanical System
3.2.2.1. HVAC
3.2.2.2. Plumbing
3.2.3. Electrical System
3.2.3.1. Rough-in
3.2.3.2. Finish
3.2.4. Fire Protection System
3.2.5. Architectural
3.2.5.1. Room Finishes
5