9) Question 1) E

2)D

3)A

4)C

5)B

11)Question Monthly Productivity = units produced /hr per machine *no.of machines

Monthly Productivity in jan =2300/325*3

Monthly Productivity in Feb =1800/200*5

Monthly Productivity in Mar= 2800/400*4

Monthly Productivity in Apr= 3000/320*4

Average of the monthly productivity

17) Navy Contract

Total labour

Total working hours = two weeks(40 per week)

Total man hours 25*80

Navy contract Productivity

Army Contract

Total labour
Total working hours = Three weeks(40 per week)

Total man hours 35*120

Army contract Productivity

From the above figures it is verymuch clear that Army contract


machine *no.of machines

2.3590

1.8000

1.7500

2.3438

2.0632

ct 2300 Devices

r 25

eeks(40 per week) 80

25*80 2000

ductivity 1.15

act 5500 Devices

r 35
weeks(40 per week) 120

35*120 4200

ductivity 1.31

ar that Army contract workers more productive