SIGIR Report January - 2007-Main Text
SIGIR Report January - 2007-Main Text
I am pleased to submit to the Congress, Secretary Rice, Secretary Gates, and the American people the
12th Quarterly Report from the Office of the Special Inspector General for Iraq Reconstruction (SIGIR).
This Report coincides with the third anniversary of my appointment as Inspector General on January
20, 2004. I soon will depart on my 15th trip to Iraq, to join the 55 SIGIR auditors, inspectors, and inves-
tigators who continue to provide aggressive in-country oversight of the U.S taxpayers’ investment in
Iraq’s reconstruction.
This Quarterly Report covers the last phase of the Iraq Relief and Reconstruction Fund’s (IRRF)
implementation. Virtually all of the IRRF’s $21 billion is now under contract, and approximately 80%
is spent. The end of the IRRF marks the beginning of a new phase in aid to Iraq, which will entail a
broader multilateral component and an increase in the Iraqi government’s responsibility for the overall
economic recovery effort.
This new phase, however, does not mark the end of oversight. To the contrary, more remains to be
done to account for past U.S. investment and to promote the highest and best use of future U.S funding
for Iraq. Recognizing the need for continuing oversight, Congress passed, and the President signed, the
Iraq Reconstruction Accountability Act in December 2006. This Act extended SIGIR’s jurisdiction to
include all FY 2006 appropriations for Iraq reconstruction, including the Iraq Security Forces Fund, the
Economic Support Fund, and the Commander’s Emergency Response Program. The Act requires SIGIR
to conduct a forensic audit to account for the use of the IRRF and effectively extends SIGIR’s organiza-
tional life through 2008.
During this quarter, SIGIR auditors completed 8 new audits, bringing the total number of completed
audit products to 82. These new audits include a review of U.S. efforts to support the capacity develop-
ment of Iraq’s ministries, an examination of the Department of State’s management of funding for Iraqi
police training and training support, a report on medical equipment purchased to support the primary
healthcare centers, and a statistical summary of security costs for major U.S. contractors in Iraq.
SIGIR inspectors assessed 15 projects this quarter, bringing to 80 the total number of assessments
completed. Significantly, 13 of the 15 projects SIGIR visited this quarter complied with contractual
requirements. SIGIR also provided a final assessment of the Baghdad Police College, which followed up
on last quarter’s quick reaction report. The final assessment confirmed that the project suffered a variety
of shortfalls, including poor construction quality, significant descoping because of budget overruns, and
the delivery of unfinished facilities.
SIGIR investigators continued work this quarter on 78 open investigations, including 23 cases under
direct Department of Justice (DoJ) supervision. SIGIR also facilitated the formation of the International
Contract Corruption Task Force to coordinate fraud investigations by its several members, including
the Federal Bureau of Investigation, the U.S Army’s Criminal Investigation Command, and the Defense
Criminal Investigative Service. In addition, SIGIR continued its participation on DoJ’s National
Procurement Fraud Task Force.
SIGIR remains dedicated to carrying out its charge to ensure effective oversight of the U.S invest-
ment in Iraq’s relief and reconstruction. I am proud of the dedicated service of the many SIGIR audi-
tors, inspectors, and investigators who continue to pursue their mission with professionalism, produc-
tivity, and perseverance.
Section 1: Section 3:
SIGIR Observations SIGIR Oversight
The Year of Transition in Review 4 SIGIR Audits 135
The End of the Iraq Relief and SIGIR Inspections 169
Reconstruction Fund 5 SIGIR Investigations 201
The Way Ahead 7 SIGIR Hotline 204
Notable SIGIR Activities This Quarter 9 SIGIR Lessons Learned Initiative 207
Impacts of SIGIR Operations 11 Legislation 209
The Human Toll 12
Section 4:
Section 2: Other Agency Oversight
Status of Iraq Reconstruction Introduction 213
Introduction: Sector Reports 17 Other Agency Audits 214
Status of Electricity 25 Other Agency Investigations 218
Status of Oil and Gas 37
Status of Water 51 Endnotes Endnotes-1
Status of Economic and List of Appendices Appendices-1
Societal Development 59 Acronyms and
Status of Security and Justice 79 Definitions Acronyms-1
Status of Health Care 93
Status of Transportation
and Communications 99
Contracts 109
Cost-to-complete Data 112
Sources of Funding 113
Anticorruption Update 129
table of contents
Dahuk
Erbil
Ninewa
Sulaymaniyah
Tameem
Salah al-Din
Diyala
Baghdad
Anbar
Babylon Wassit
Kerbala
Qadissiyah
Missan
Thi-Qar
Najaf
Basrah
Muthanna
SIGIR Summary of Performance
February 1, 2004 – January 31, 2007a
Audit
Reports Issued 82
Recommendations Issued 268
Dollars Saved and Recovered $49,700,000b
Impact of SIGIR Audits $57,500,000b
Inspections
Project Assessment Issued 80
Limited On-site Assessments Issued 96
Satellite Imagery Products Created 266
Impact of SIGIR Inspections $39,300,000
Investigations
Investigations Initiated 87
Investigations Closed or Referred 149
Open Investigations 78
Arrests 5
Convictions 4
Value of Funds Seized and Recovered $9,500,000
Hotline Contacts
Fax 13
Telephone 62
Walk-in 109
E-mail 307
Mail 26
Referrals 25
Total Hotline Contacts 542
Non-audit Products
Congressional Testimony 8
Lessons Learned Reports Issued 2
a
For details on Impact of SIGIR Operations, see Appendix C.
b
As of December 31, 2006.
SIGIR Observations
1
section
SIGIR OBSERVATIONS
This 12th Quarterly Report from the Special expected, and the security environment has
Inspector General for Iraq Reconstruction continued to deteriorate. Iraq thus requires a
(SIGIR) covers the conclusion of a significant new phase of investment. This phase urgently
phase in the U.S. reconstruction effort in Iraq needs further contributions from international
and the beginning of an important new one. donors through the International Compact for
During this quarter, SIGIR progressed on its Iraq.
program to provide aggressive on-the-ground Most important, the GOI must begin to
oversight of the Iraq Relief and Reconstruc- provide significant funding for the relief and
tion Fund (IRRF), producing 8 audits and 15 reconstruction effort. Ultimately, the sustained
inspections, and pushing forward 78 investiga- recovery of Iraq can be accomplished only by
tions into fraud, waste, and abuse in Iraq. Iraqis.
The Congress created the IRRF in 2003,1 On January 10, 2007, President Bush pre-
funding it with two appropriations amounting sented a new strategic direction for U.S efforts
to $21 billion. The IRRF served as the pri- in Iraq, which includes more U.S. investment
mary financial source for the U.S.-led phase of in Iraq’s economic recovery. This new funding
reconstruction in Iraq. As of the end of 2006, is intended to support the expansion of the
all of the IRRF was contracted, with nearly Commander’s Emergency Response Program
80% expended. In 2007, SIGIR will execute (CERP) and the Provincial Reconstruction
detailed reviews of what the American tax- Teams (PRTs). SIGIR has previously reviewed
payer received for this investment of U.S. dol- both programs, finding that CERP achieved
lars in Iraq’s reconstruction. success in smaller projects at the local level,
SIGIR previously observed that continued and that the PRT program, while facing
financial support from the United States and considerable security constraints, has made
other outside sources will be necessary to sup- progress in its efforts to aid provincial officials
port the ongoing recovery of Iraq. This support in developing their capacity to govern.
should aim at strengthening Iraq’s capability to In December 2006, Congress passed the
provide employment, restore essential services, Iraq Reconstruction Accountability Act of
and build the capacity of the Government of 2006, extending SIGIR’s jurisdiction to include
Iraq’s (GOI) ministries. oversight of all FY 2006 funds designated for
The Congress already has appropriated relief and reconstruction. The effect of this act
$11 billion beyond the IRRF to support relief will ensure that SIGIR will continue its over-
efforts, primarily for training and equip- sight work in Iraq through 2008.
ping Iraq’s security forces. Iraq’s security
forces, however, developed more slowly than
effective execution of the U.S. reconstruc- As the reconstruction program in Iraq pro-
tion program. The newly appointed U.S. gresses into 2007, the process of transitioning
coordinator for economic transition may the management of the program to Iraqi
help remediate these problems. SIGIR is control will accelerate. Ensuring the program’s
conducting reviews of the evolving roles successful transition hinges on making effec-
and responsibilities of U.S. agencies as tive progress on each of the foregoing issues.
internal reorganizations take place.
Coalition Provisional Authority (CPA)—a Security and Justice. This sector focused
transitional governing entity established to on public-safety requirements (police training
manage the transfer of democratic sovereignty and infrastructure), national security (training
to a new Iraqi government. The realization and equipping the Iraqi Army), and justice
that Iraq’s infrastructure was significantly (development of the rule of law). Originally,
more dilapidated than expected drove CPA IRRF allocated $4.56 billion for security and
to develop a much broader reconstruction justice projects. The aggravated security situ-
plan. In November 2003, Congress responded ation required the shift of significant funding
by appropriating another $18.4 billion to the into this sector, increasing the total amount
IRRF, primarily to fund the CPA’s ambitious allocated to nearly $6.31 billion (an increase of
plan. IRRF 2 funding was allocated among all almost 30%).
the major infrastructure sectors, and major Electricity. Electricity projects focused on
design-build contractors were awarded very generation, transmission, and distribution net-
large, competitively bid cost-plus contracts. works. Originally, $5.56 billion was allocated to
The CPA initially expected to be in place in electricity—the largest initial allocation to any
Iraq for more than two years, but it concluded sector—which reflected the CPA’s emphasis on
operations on June 28, 2004, just over a year improving Iraq’s capacity to generate power.
after its inception. However, electrical grid output averaged just
June 2004—present, A New Approach to 4,260 MW this quarter, which is below pre-war
Programs and Contracting: During this phase, levels. The current allocation is nearly $4.24
a significant portion of IRRF 2 funding was billion.
shifted from infrastructure to security and Water. The initial program focused on
democracy. Three significant funding adjust- improving sewerage, access to potable water,
ments in late 2004 and early 2005 resulted in and solid-waste management services.
the reallocation of more than $5 billion. The Projects included large water-treatment facili-
security sector received the largest increase, ties, pumping stations, dams, and rural water
and the water sector suffered the most signifi- supplies. Originally, $4.33 billion was allocated
cant decrease. U.S. reconstruction leadership in this sector; however, the allocation to this
also began to move toward the use of direct sector eventually was cut by nearly 50% (to
contracts and away from design-build con- $2.13 billion).
tracts. Oil and Gas. Oil projects focused on
investing in repairing the oil infrastructure and
How IRRF Funds Were Spent in Each purchasing petroleum products. The IRRF 2
Sector: A Brief Overview allocation for this sector was originally $1.89
IRRF funding allocations among the sectors billion, but this was later reduced by 10% to
were as follows: $1.72 billion. The Iraqi oil revenues expected
to fund major infrastructure repairs have yet to systems and operations. Originally, IRRF
materialize, partly because attacks on pipelines allocated $870 million, and two design-build
and poor operations and maintenance of oil contractors were hired to complete the work.
facilities have reduced oil exports. Oil produc- But GRD-PCO soon realized that Iraqi firms
tion this quarter averaged approximately could complete much of the work in the trans-
2.17 million barrels per day, which is below portation subsector at a lower cost. Transpor-
pre-war levels. tation became the first subsector to shift from
Health Care. The original $793 million in design-build contractors to direct contracting.
allocations for this sector included funding for The current allocation for this sector is approx-
building or refurbishing hospitals and pri- imately $800 million.
mary healthcare centers (PHCs), repairing and Economic and Societal Development.
replacing equipment, providing primary health IRRF initially allocated $433 million to
care training, and constructing a pediatric hos- programs in this sector. After the June 2004
pital in Basrah. The construction of the PHCs, transition to the Iraqi Interim Government
a major component of this sector, was ham- and the subsequent program realignments,
pered by poor management by the contractor more money was added to this sector. This
and weak oversight by the U.S. government reflected the need to support the Iraqi elec-
in an increasingly insecure environment. The tions process and stimulate employment and
Basrah Children’s Hospital fell well behind economic development. Thus, more than $1
schedule and greatly exceeded its original billion was added to democracy programs, and
budget. The current allocation is approximately more than $660 million was added to private-
$820 million. sector development. The current allocation for
Transportation and Communication. this sector is approximately $2.21 billion.
Projects in this sector focused on airports,
ports, railroads, roads, and communication
2
section
Sector Summaries
Introduction
The security situation in Iraq continues to and ESF-funded activities; more in-depth
deteriorate, hindering progress in all recon- analysis will follow next quarter.
struction sectors and threatening the overall
reconstruction effort. Iraq Relief and Reconstruction
In this Report, SIGIR continues to highlight Fund (IRRF)
and analyze developments in these reconstruc-
tion sectors: electricity, oil and gas, water, To assess overall progress, SIGIR reviews three
economic and societal development, security aspects of reconstruction—activities, outputs,
and justice, health care, and transportation and and outcomes:
communications. • Activities: reconstruction at the project level
In addition to reporting on programs (e.g., an electric turbine, a water treatment
and projects funded with the Iraq Relief and plant, a primary healthcare center, a train-
Reconstruction Fund (IRRF) and the Iraq ing program for teachers)
Security Forces Fund (ISFF), this Report also • Outputs: results of the reconstruction
highlights the expanded oversight responsibili- projects (e.g., increased electricity genera-
ties assigned to SIGIR under the Iraq Recon- tion, increased capacity to treat wastewater,
struction Accountability Act of 2006, which more trained teachers)
include reporting on activities funded by the • Outcomes: potential effects of the project
FY 2006 Commander’s Emergency Response outputs for the people of Iraq (e.g., hours
Program (CERP) and the FY 2006 Economic of power, more Iraqis with access to clean
Support Fund (ESF) in the Foreign Assistance water, more Iraqi children vaccinated for
budget. CERP and ESF were appropriated to polio, higher literacy rates)
continue reconstruction started with IRRF
supplemental funds. SIGIR, the Gulf Region Division-Project
Section 2 also provides information on and Contracting Office (GRD-PCO),6 the DoS
contracts, including the costs to complete Section 2207 Report, and Public Law 108-106,
reconstruction projects in Iraq, updates on the as amended, use different definitions of the
sources of funding for Iraq reconstruction, and Iraq reconstruction sectors and project status.
a review of the continuing effort to support To compare the various definitions of sectors,
Iraqi anticorruption programs. see Appendix D.
As of December 30, 2006, 12,395 projects constitutional referendum; other money was
(92%) had been completed in all sectors, with used to fund projects in 2006 and into 2007.
an additional 766 still ongoing (6%) and 351 Most of the IRRF dollars used to develop the
yet to begin (3%). For a breakdown of IRRF security and justice sector have been expended,
funds and projects, see Figures 2-1, 2-2, and and activities in this sector are now mostly
2-3. funded by the ISFF.
All funds that were not obligated by Sep- Congress was notified that IRRF funds have
tember 30, 2006, can be used to pay for legally been shifted in recent quarters to health care,
permitted adjustments on contracts signed refugees and human rights, and transportation
before September 30, 2006. These expired and communications to supplement a variety
funds will remain available for five years and of projects and programs.
will be obligated when they are to be used. For The oil and gas, electricity, and water sec-
a snapshot of IRRF funds by sector, see Table tors have the largest portions of the IRRF
2-1. remaining for expenditure.
Last quarter, the IRRF-funded education Finally, ministerial capacity development
and agriculture programs closed out opera- and sustainment initiatives became increas-
tions, with only a few tasks remaining. Most of ingly important in 2006 and are now central
the IRRF funding used in the democracy sub- components of the current reconstruction
sector was spent in 2005 on elections and the strategy for U.S.-funded projects.
Figure 2-1
Sector Shares of IRRF Funds
$ Billions
% of $18.44 Billion Figure 2-2
Source: IRMO, Weekly Status Report (1/2/2007) Status of IRRF Funds
$ Billions
Source: IRMO, Weekly Status Report (1/2/2007);
Transportation & DoS, Iraq Weekly Status (9/27/2006)
Communications
$.80
$18.07
1% Reconstruction Obligated
Health Care Management
$.82 $.21
Not Expended
Oil & Gas $3.51
$1.72 4%4% Security & Justice
$6.31 $13.74
9%
34% OCT 06
Water 12% Expended
$2.13 $14.56
DEC 06
12% 23%
Economic & Societal
Development
$2.21 Electricity
$4.24
Note:
Percentages do not add up to 100% due to rounding.
Figure 2-3
Status of IRRF Projects
Source: IRMO Rollup (12/30/2006);
USAID Activities Report (December 2006)
Not
Not Started Ongoing Sector Started Ongoing Completed Total
2% 6%
Electricity 27 161 345 533
Oil and Gas 29 28 57
Water 28 146 927 1,101
Completed
92% Economic and Societal Development 113 102 7,997 8,212
Security and Justice 175 95 2,555 2,825
Health Care 1 145 88 234
Transportation and Communications 7 88 455 550
13,512 Projects Planned Total 351 766 12,395 13,512
Table 2-1
Highlights of IRRF Activities this Quarter 425 projects funded by ISFF in FY 2005 and
SIGIR makes these observations about the FY 2006, 189 have been completed, 231 are
status of a number of sectors in the U.S. ongoing, and 5 have not yet started.10 Figure
reconstruction program: 2-4 shows the status of ISFF funds, which are
• During this quarter, the average peak allocated for projects in the security and justice
capacity of electricity generation nation- sector only.
wide fell below pre-war levels—4,260 vs. The goal of training and equipping 325,000
4,500 megawatts (MW). Because of inter- Iraqi soldiers and police officers was almost
dictions on the northern transmission lines reached this quarter in the security and justice
and the reluctance of local authorities in sector, and progress also continues in con-
the south to send power, less electricity struction and rule-of-law activities.
was available in Baghdad this quarter than However, the number of trained and
before the 2003 conflict. equipped Iraqi Security Forces (ISF) should
• This quarter, oil production fell below pro- not be confused with the number labeled
duction targets of 2.68 million barrels per “present for duty.” The number of soldiers
day (BPD) and nearly 2.17 million BPD for and police who are present for duty is lower
the entire quarter. Oil exports averaged 1.48 because of attrition, absence without leave, and
million BPD, which is less than the Iraqi scheduled leave. Concerns also remain about
goal of 1.65 million BPD. the effectiveness of the ISF and the ability of
• The Primary Healthcare Center (PHC) the Ministries of Defense and Interior to sup-
program continues to face challenges. To port them adequately.
date, only eight Model PHCs have been
completed, and seven are currently open. Overview of the ISFF Program
GRD-PCO reports that, of the 126 still
under construction, 50 are 90–100% com- In 2005, the ISFF program was established
plete, and 46 are 75–90% complete.8 under P.L. 109-13 to allow the Commander of
the Multi-National Security Transition Com-
Iraq Security Forces Fund (ISFF) mand-Iraq (MNSTC-I) to provide assistance to
As of December 31, 2006, almost 80% of the the ISF. According to P.L. 109-13, this assis-
$8.32 billion in FY 2005 and FY 2006 ISFF tance includes “the provision of equipment,
funds had been obligated, and 54% had been supplies, services, training, facility and infra-
expended. An additional $1.7 billion was structure repair, renovation, and construction.”
appropriated under the Department of Defense For the status of ISFF projects, see Figure 2-5.
Appropriations Act for FY 2007.9 Of the
Figure 2-4
Status of ISFF Funds – Security and Justice
$ Billions
Source: DoD Secretary of the Army Update (12/31/2006)
$6.59
Obligated
Not Expended
$2.07
Expended $3.36
$4.52 OCT 06
DEC 06
Note:
Totals are produced by combining financial detail
from ISFF 2005 and ISFF 2006 funds.
Figure 2-5
Status of ISFF Projects
Source: IRMO Rollup (12/30/2006)
Figure 2-6
Sector Shares of FY 2006 CERP Funds Figure 2-7
$ Millions Status of FY 2006 CERP Funds
% of $511.16 Million $ Millions
Source: Office of the Assistant Secretary of the Army Source: Office of the Assistant Secretary of the Army
Financial Management and Comptroller (9/30/2006) Financial Management and Comptroller (9/30/2006)
$509.66
Transportation & Obligated
Communications
$75.66
15% Economic & Societal
28% Development
$144.52 Not Expended
$362.68
Water 30%
$151.38 16%
Electricity
$83.39
6% 5% Expended
$146.98
Security & Justice Health Care
$30.31 $25.90
Note:
Note: For reporting consistency, CERP activities are mapped to SIGIR-defined sectors.
1. Historically, SIGIR calculates sector share of funds by dividing dollars See Appendix E for the CERP cross-reference.
allocated for each sector by total dollars appropriated. Allocation detail
at the sector and subsector level for CERP FY 2006 is currently unavailable;
therefore, the percentages in this graphic are calculated using dollars committed.
2. For reporting consistency, CERP activities are mapped to SIGIR-defined sectors.
See Appendix E for the CERP cross-reference.
Figure 2-8
Status of FY 2006 CERP Projects
Source: Office of the Assistant Secretary of the Army
Financial Management and Comptroller (9/30/2006)
Economic Track
Operations & Maintenance Sustainment $285
Capacity Development & Technical Training $60
Political Track
Ministerial Capacity Development (USAID) $60
Ministerial Capacity Development (IRMO) $45
Regime Crimes Liaison Office $33
Democracy Funding for IRI, NDI, NED $25
Policy & Regulatory Reforms $20
Civil Society, ADF, IFES $18
USIP $4
Civil Society, IREX $3
Table 2-2
Sector Summaries
SECTOR REPORT
Electricity
STATUS OF Electricity
This review updates the status of U.S. recon- These are the challenges in the electricity
struction projects to restore Iraq’s capacity to sector this quarter:
generate, transmit, and distribute electricity. • Insufficient operations and maintenance
SIGIR makes these observations about activi- (O&M) allocations by the GOI continue to
ties in the electricity sector this quarter:Oil and Gas limit the sustainability of U.S.-funded
• This sector receives the second-largest projects as responsibility is transferred to
allocation ($4.24 billion) of IRRF dollars. Iraqi operators.
At the end of this quarter, 65% of planned • Demand for electricity continues to outpace
IRRF-funded projects were complete, and generation capacity, and operations at
70% of the allocated dollars were expended. power plants continue to lack sufficient
As of January 2, 2007, nearly 96% of alloca- quantities of refined fuel to run generators
tions were obligated. For the status of IRRF at peak capacity.
funds in this sector, see Figure 2-9. • Sabotage of feeder lines limits the impact of
• U.S. projects have contributed 2,817 mega- U.S.-funded projects by reducing the hours
watts (MW)13 to Iraq’s generation capacity. of power that Iraqis receive in their homes
Democracy,
Actual peak production capacity thisEducation,
quar- and businesses.20
ter was below pre-war levels (4,500 MW), 14
Private sector
averaging 4,260 MW.15 The average daily development
load served, however, is a better measure of
how much power reaches Iraqis because it
measures distribution over time.16 During
Figure 2-9
this quarter, the daily load served averaged Electricity Sector as a Share of IRRF Funds
90,614 megawatt hours (MWh),17 roughly $ Billions
% of $18.44 Billion
1,000 MWh above the past winter quarters Source: IRMO, Weekly Status Report (1/2/2007)
Sector Summaries
Electricity
Electricity
development
$150 million21 was reported as not having been As of September 30, 2006, approximately
obligated. For the status of IRRF funds in this $67 million of the total commitment of $84
sector, see Figure 2-10. million had not been expended; approxi-
In this sector, 27 U.S.-funded IRRF projects
(5%) have yet to begin,22 and 65% have been Figure 2-10
completed. All but one project in this sector Status of IRRF Funds - Electricity
$ Billions
are scheduled to be completed by January Source: IRMO, Weekly Status Report (1/2/2007);
DoS, Iraq Weekly Status (9/27/2006)
2008. All but two electrical generation projects
have started, and 96% have been completed. $4.09
Obligated
Transmission projects are generally large, com-
plex, expensive, and central to the grid system. Not Expended
$1.14
The remaining distribution projects are gener-
ally smaller and less complex than the large-
OCT 06
scale generation and transmission projects. For Expended
$2.62
Figure 2-11
Status of IRRF Electricity Projects
Source: IRMO Rollup (12/30/2006)
USAID Activities Report (December 2006)
Not
Not Started Sector Started Ongoing Completed Total
5% Distribution 13 123 283 419
Completed
65% Transmission 12 33 12 57
Ongoing
30% Generation 2 50 52
Automatic Monitoring & Control System 5 5
Total 27 161 345 533
Sector Summaries
Overview Electricity
Figure 2-12
Electricity
Electricity as a Sector Share of FY 2006 CERP Funds
$ Millions
% of $511.16 Million
Source: Office of the Assistant Secretary of the Army
Financial Management and Comptroller (9/30/2006)
16%
Electricity
$83.39
Democracy
Security, Education,
Justice Private sect
developme
Sector Summaries
Electricity
Electricity
Source: DoS NEA-I electricity expert, response to SIGIR, January 16, 2007.
Note: The GAO report, “Securing, Stabilizing, and Rebuilding Iraq: Key Issues for
Congressional Oversight,” reports that U.S. projects have added an estimated 2,093
MW, January 2007, p. 73.
Sector Summaries
Overview Electricity
Electricity
Source: Pre-war level: UN/World Bank Joint Iraq Needs Assessment, 2003, p. 28.
Democracy
Note: GAO recently reported the pre-war level as 4,300 MW (GAO Report 06-697T, April 25, 2006, p. 19).
Security, Education,
Goal: Joint U.S.-Iraqi Electricity Action Plan, March 12, 2006, p. 2.
Justice Private sect
Current Status: IRMO, Weekly Status Report, July-September 2006. developme
Table 2-4
Figure 2-13
Electricity Load Served
Weekly Average Electricity Load Served, Megawatt Hours (MWh)
Source: IRMO Weekly Status Reports, DoS, Iraq Weekly Status, (9/28/2005 - 12/26/2006)
5%
0%
0% *Target
110,000 MWh
-5%
-10%
-15%
-20%
-25% Est.
-30%
-35%
S O N D J F M A M J J A S O N D
2005 2006
Previous Quarters Current Quarter * Target is a constant based on a goal set in summer 2005
Sector Summaries
Electricity
Electricity
Table 2-5
Distributing power from generation facili- This resistance to power-sharing has resulted
ties to Iraqi homes remains a major challenge. in Baghdad averaging 4-8 less hours of power
For the hours of power available to Iraqis daily than in other parts of the country.38 To
compared to pre-war levels, see Table 2-5. decrease Baghdad’s long-term reliance on
Multiple challenges in this sector associated power transfers from the rest of the country,
with distributing and transmitting power have the GOI plans to expand generation connected
left Iraqi consumers frustrated by the low and directly to the Baghdad loop to include more
inconsistent supply of electricity. generation facilities.39
Baghdad averaged only 6.5 hours of power Private generators are used throughout
per day this quarter because of attacks on Baghdad to meet the gap between supply and
power lines that feed the capital, as well as demand. As SIGIR reported last quarter, high
political issues inhibiting the transfer of demand is attributable to government subsi-
power from large plants in both northern and dies, a growing economy, and a surge in the
southern Iraq. Baghdad does not have enough consumer purchases of appliances and
power plants to meet its own needs. electronics.40
In the north, sabotage and weather-related Because the GOI struggles to distribute
damage of transmission lines have prevented power equitably and reliably, SCADA is being
the transfer of power to Baghdad. In addi- constructed to maximize the availability of
tion, Baghdad has received no power from the electricity across Iraq. Six of the seven SCADA
Haditha Dam since December 4, 2006.36 The projects are underway. The system is pro-
dangerous security situation has delayed or jected to cost $109 million and is estimated
prevented repairs. to be completed by April 2007.41 SCADA is
In the south, contentious relationships expected to limit the number of power outages
between the “recently empowered provincial by increasing automation and implementing
authorities and the centrally managed elec- control mechanisms.42 GRD-PCO notes that
tricity authority” account for major disparities SCADA is also expected to accomplish these
in the rationing and distribution of electricity goals:
supplies between the south and Baghdad.37
Sector Summaries
Overview Electricity
Electricity
Sector Summaries
Electricity
Electricity
Figure 2-14
Electricity Distribution and Hours of Power
Source: IRMO Daily Electricity Report (10/1/2006 - 12/31/2006)
Population Data: MNC-I, response to SIGIR (12/6/2006) Daily Average Total Hours Estimated Governorate
Oil and Gas
of Power Served Population in Millions
>15 Ninewa 2.52
Basrah
Muthanna
Import Power
Dry Gas Line
400 kV Line
Thermal Power Station
Natural Gas Power Station
Substation
Hydroelectric Station
million program,50 which aims to help the As of December 2006, $308 million was
Ministry of Electricity develop, implement,
elec_map.ai programmed for Operations, Maintenance,
and sustain an effective O&M plan. The and Sustainment (OMS); 21 projects ($288
contractor will help provide O&M services million) are in progress; and 5 ($20 million)
at thermal and gas turbine power plants. are complete. The OMS program is sched-
• FY 2006 ESF provided an additional $278.6 uled to finish by October 2007.52
million for O&M in the electricity sector.51
Sector Summaries
Overview Electricity
Electricity
Figure 2-15
Electricity Demand vs. Capacity
Weekly Average Gigawatts (GW)
Source: IRMO, Weekly Status Reports (12/14/2005 - 12/26/2006)
10
Demand*
8
6 Est.
0
12/14 1/14 2/14 3/14 4/14 5/14 6/14 7/14 8/14 9/14 10/14 11/14 12/14
2005 2006
Sector Summaries
Electricity
Electricity
Figure 2-16
Unmet Electricity Production Caused by Water and Fuel Shortage
Megawatts (MW), Weekly Average
Source: IRMO Daily Electricity Report (10/1/2006 - 12/26/2006)
800
700
600
500
400
300
200
100
0
10/1 10/8 10/15 10/22 10/29 11/5 11/12 11/19 11/26 12/03 12/10 12/17 12/24 12/31
Thermal Gas Turbine
Hydro Diesel
Sector Summaries
Overview Electricity
Electricity
Figure 2-17
Actual vs. Feasible Electricity Production
Megawatts (MW)
Source: IRMO Daily Electricity Report (10/1/2006 - 12/31/2006)
3500
3,381
3000
2,906
2500
2000
1,926
Democracy
1500 Security, Education,
Justice Private sect
1000 51% developme
39%
500 33%
342 282
0
Gas Turbine Thermal Hydro Diesel Imports
Feasible Capacity Actual Capacity
Note:
1. Diesel power produced only 233 MW, less than 1%
of the total feasible production.
2. Imported power provides less than 1% of Iraq’s electricity.
• IRMO estimates that Iraq could save $4 transmission lines.64 Last quarter, a SIGIR
billion each year by initiating programs to audit (SIGIR-06-038) noted that $216.2 mil-
transfer flared natural gas to power plants lion went to improve Iraq’s capacity to protect
for electricity production. its electricity infrastructure. IRMO and the
Ministry of Electricity continue to take steps to
As Figure 2-17 demonstrates, 61% of fea- improve data on attacks on electricity infra-
sible capacity at gas turbine facilities that pro- structure. The audit found that attack rates
duce electricity goes unmet. Gas turbine plants varied between January 2005 and April 2006,
lose nearly 2,000 MW production because but they were down from April to June 2006.
heavy fuel oil is used instead of natural gas. A DoS oil expert cautioned against drawing
conclusive links between the number of attacks
Security elec_prod.ai and energy supply, because strategic attacks—
although they may occur less frequently—can
The lack of security continues to challenge the have equally debilitating effects.65 Repair teams
electricity sector, leading to project delays and sent in after attacks continue to face threats,
increased costs for security services.63 A major including kidnapping and murder.66
concern is protecting linear assets, particularly
Sector Summaries
SECTOR REPORT
Sector Summaries
Democracy,
Education,
Private sector
Pipeline construction
in northeastern Iraq.
Sector Summaries
Not
Sector Started Ongoing Completed Total
Completed Water Injection Pump Station 10 9 19
49%
Southern Region Projects 13 6 19
Ongoing
51% Northern Region Projects 9 9
Dedicated Power 1 2 3
LPG/LNG Plant Refurb 5 1 6
General Projects 1 1
Total 29 28 57
57 Projects Planned
Figure 2-20
Status of IRRF Funds - Oil and Gas
$ Billions
Source: IRMO, Weekly Status Report (1/2/2007);
DoS, Iraq Weekly Status (9/27/2006)
$1.14 EPC 57 0 29 28
OCT 06
Expended Non-construction source: USACE-GRD, Bi-weekly Situation Report, December
$1.29 25, 2006, p. 13.
DEC 06
Table 2-6
Sector Summaries
Democracy,
Education,
Private sector
Sector Summaries
Figure 2-21
Gas and Oil Infrastructure by Governorate oil and Gas
Source: CIA Country Profile Map
Democracy
Security, Education,
Justice Private sect
developme
November 2006. This project was designed rently 30% complete, and GRD-PCO reports
to improve the continuous long-term power that it is scheduled to be finished by the end
supply to the Basrah Refinery. GRD-PCO of July 2007 although the original completion
reported that a training project for plant opera- date was December 2006.85 This delay stems
tors is also complete.84 from an assessment of equipment that revealed
The Qarmat Ali project is designed to pro- a need for replacement parts. GRD-PCO notes
vide treated water for injection wells to main- that project costs will increase because of this
tain oil reservoir pressure and to help sustain additional procurement, but does not state by
production levels in one of the largest southern how much.
oil fields. Phase I is complete. Phase II is cur-
Sector Summaries
Democracy,
Education,
Private sector
Sector Summaries
Democracy
Security, Education,
Justice Private sect
Oil and Gas Projects production target from 2.5 million BPD to
The major outcome of U.S.-funded projects in 2.68 million BPD, the GOI has decreased its
this sector is revenue generated by increased estimated 2007 crude oil production average to
crude oil exports. Table 2-7 presents recon- 2.1 million BPD. Figure 2-22 shows a crude oil
struction project metrics against pre-war levels production breakdown between the northern
and U.S. and Iraqi end-state goals. and southern oil fields, and figure 2-23 shows
The 2006 GOI budget anticipated an average crude oil production nationwide. As the GOI
crude oil production of 2.3 million BPD, with struggles to stabilize services, pay employees,
revenues generated from an estimated 1.65 and foster economic development, officials
million BPD exported at an estimated price look to the oil and gas sector to boost govern-
Current Oil and Gas Project Benefits vs. Pre-war Level and Goal
Pre-war Level Quarter U.S. End-state Iraqi End-state
Outcomes Metrics (2003) Average Goals Goals
Oil Production Capacity (million BPD) 2.8 2.68 3.0 2.8
Oil Production (Actual) (million BPD) 2.58 2.17 Not Available 2.8
Export Levels (million BPD) Not Available 1.48 2.2 (capacity) 1.65
Natural Gas Production Capacity (MSCFD) Not Available 730* 800 Not Available
LPG Production Capacity (TPD) Not Available 1,700* 3,000 Not Available
*Data for these figures is taken from a GRD-PCO report of December 1, 2006, and does not constitute a full
quarterly average.
Sources: Pre-war numbers—DoE Country Analysis Brief, meeting with DoE officials on May 31, 2006. Quarter Average—
IRMO Monthly Import and Export Production, January 6, 2007.); DoS, Iraq Weekly Status reports, July-October, 2006 (oil
production and exports); GRD-PCO, “Sector Consolidated Results Update Meeting,” September 10, 2006, p. 3 (natural gas
production capacity and LPG production capacity). U.S. end-state goals—GRD-PCO, “Iraq Reconstruction Report,” October
5, 2006, p. 3 (production capacity); DoS, response to SIGIR, July 24, 2006 (export capacity); Iraqi end-state goals—meetings
and discussions with DoS officials for April 2006 Quarterly Report; DoS, IRMO Weekly Status Report, May 16, 2006, p. 9
(Iraqi export target).
Table 2-7
Sector Summaries
Democracy,
Education,
Private sector
Figure 2-22
Crude Oil Production by Region
Millions of Barrels Per Day, Monthly Average
Source: IRMO Monthly Import, Production, and Export Report (December 2006)
3.0
Target
2.5
South
2.0
1.5
1.0
0.5
North
0
2003 2004 2005 2006
South North
Sector Summaries
2.12
40% 2.05
30%
2.41 2.42
20% 2.28 2.29 Current Period
1.71
10%
1.41 2.54
Target
2.45 2.44
-10% 2.31
2.15 2.21 2.15 2.16 2.18 2.13 2.23 2.35
-20% 2.10 2.12 2.14 2.152.09 2.07 2.25
1.92 2.17 1.94 2.24 2.16
-30% 1.90 2.08 2.09 2.13 1.90
.93 1.98 2.10
-40% 1.56
-50%
-60% .60
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Figure 2-24
Monthly Crude Oil Exports and Revenue Raised
Millions of Barrels Per Day (MBPD)
Source: DoS, Iraq Weekly Status (1/4/2006 - 12/27/2006); IMF SBA (Iraqi Target) Average
Month Oil Price
Jan $54.16
10% Feb 53.02
Target 1.67 1.68 1.68 1.62 Mar 52.98
1.65 MBPD
1.60 Apr 61.10
-10% 1.51 1.55
1.47 1.51 Monthly May 63.19
1.44 Revenue
-20% Jun 60.26
1.32 $ Billions
-30% 3 Jul 65.08
1.05 Aug 66.88
-40% 2
Sep 57.24
-40% 1
Oct 52.01
0 Nov 51.24
J F M A M J J A S O N D
2006 Dec 56.12
Sector Summaries
Figure 2-25
Winter Fuel Refinery Production (2003 - 2006)
Millions of Liters
Oil and Gas Source: IRMO Monthly Import, Production, and Export Report (12/2006)
10
Current Quarter
8
Democracy, 6
Education,
Private sector
development 4
0
2003 2004 2005 2006
Gasoline Diesel Kerosene
Note:
This quarter, winter 2006, refined fuel production is the lowest it
has been (compared to other winters) since the U.S.-led invasion in 2003.
Refined fuels include kerosene (to heat homes), gasoline (to
fuel automobiles) and diesel (to power electricity generators).
Sector Summaries
Democracy
Security, Education,
Justice Private sect
on for refined fuel imports. Turkey holds signed an agreement with Kurdistan to supply developme
the bulk of Iraq’s debt and is also the leading 2 million liters of kerosene per day.102
source of Iraq’s imported refined fuel. On Storing LPG, diesel, kerosene, and gasoline
November 21, 2006, Iraq paid $80 million to throughout Iraq remains insufficient, especially
Turkey, which followed another $80 million at refineries. Attacks, threats, and insufficient
payment in October. The GOI requested and storage capacity for refined fuel have led to the
received an additional $800 million from the repeated shutdown of the Baiji refinery.103 Also,
Council of Representatives to continuing pur- DoS reports that some refined fuel storage
chasing refined products because it does not facilities are under insurgent control.104 To
budget for fuel imports.101 address distribution in Baghdad, the security
Transporting refined fuel imports from plan includes the renovation of 18 gasoline sta-
Turkey into the market remains cumber- tions.105 Figure 2-26 shows the average days of
some, particularly because these shipments are refined fuels in storage.
moved by truck from the border. In preparing To help alleviate repeated shortages and
for shortages of refined fuels during the winter provide a stable supply of refined fuels in
months, several Iraqi governorates have signed the future, the GOI has sought to improve
deals with neighboring countries to import its refining capacity. On October 7, 2006, it
kerosene, including Iran. This quarter, Iran inaugurated a small refinery in Najaf with
Figure 2-26
Quarterly Average Inventory of Critical Refined Fuels
Quarterly Average Days of Stock
Source: DoS, Iraq Weekly Status (9/2004 - 12/2006)
25
20
15 Target
10
0
SEP DEC MAR JUN SEP DEC MAR JUN SEP DEC
Diesel Kerosene
Gasoline Liquid Petroleum Gas
Sector Summaries
Democracy,
Education,
Private sector
Sector Summaries
Democracy
Security, Education,
Justice Private sect
developme
of the Ministry of Oil has decreased over the Another problem, smuggling, occurs when
last year as experienced bureaucrats retire or pipelines are tapped or trucks are intercepted.
leave Iraq.114 When pipelines are offline, vehicles are the
Iraq’s South Oil Company sought to pur- only means of transport for exports and
chase four new tugboats to pull tankers into oil imports.119 This reliance on trucks increases the
terminals, especially during the winter when fear that drivers have ties to the insurgency or
the weather on the gulf becomes threatening, are vulnerable to threats and violence.120
but the Ministry of Transportation has held up
the transaction, noting price issues and lines of Budget Execution
authority for the purchases.115 The State Com-
pany for Oil Projects has yet to begin construc- During his visit to Iraq last quarter, the
tion of oil storage facilities in the south because Inspector General visited the Ministry of Oil to
the Chinese company it signed an agreement confer with the Deputy Minister, Chief Budget
with in 2003 has not supplied the materials.116 Officer, and Director of Plans. Those meetings
confirmed widely voiced concerns that the
Corruption and Smuggling Ministry of Oil has had problems executing its
capital budget. In January 2007, GAO reported
For the last four quarters, SIGIR has reported that as of August 2006, “the ministry had spent
on the debilitating effects of corruption on less than 1% of its $3.5 billion budget.”121 The
the Iraqi oil industry. This quarter, corrup- DoS Bureau of Near Eastern Affairs (NEA)122
tion remains a challenge. The Ministry of Oil noted that the Ministry of Oil has struggled to
has acknowledged that corruption signifi- comply with bureaucratic funding procedures
cantly affects the production and distribution instituted by the Ministry of Finance. Capital
of refined fuels. In its January 2007 report, projects are affected by the budget process
GAO affirmed the Ministry’s acknowledge- because allocations are made for only one year
ment, noting that “widespread corruption and at a time. For example, a three-year project
smuggling affect the distribution of refined oil would be required to submit a budget request
products such as gasoline.”117 every year. If funding is approved in the first
An oil expert with DoS confirmed that oil year but denied or delayed in later years, the
skimming occurs in Iraq. Skimming means project is delayed.123 This is a government-wide
over or under-reporting flows as the fuel is problem in Iraq and is particulary significant
transferred from the pipeline to the mode of for the Ministry of Oil, the major revenue-gen-
transport. The IMF has identified metering erating ministry in the country.
as a priority mechanism to limit skimming.118
Sector Summaries
Democracy,
Education,
Private sector
Sector Summaries
SECTOR REPORT
Status of Water
This review updates the status of U.S. recon- projects. An additional 382 projects are
struction projects to increase access to clean ongoing, and 3 projects have not started.
water and sewerage services in Iraq and Figure 2-28 shows this sector’s funding as
improve water resource management capa- a share of the total CERP.
Democracy,
Security, bilities. Education,
Justice SIGIR makes these observations about SIGIR sees these challenges in the water
Private sector
activities in the water sector this quarter: sector this quarter: development
• The water sector has expended all but 30% • A major concern for sustainment of U.S.-
($.65 billion) of its IRRF allocation ($2.13 funded projects is the GOI’s insufficient
billion). Figure 2-27 shows this sector’s O&M budget. In 2006, the GOI allocated
funding as a share of the total IRRF. Only 9% of its $259 million water budget for
about 3% of water projects have yet to maintenance activities, according to an
start, and 84% are complete.129 IRMO budget expert.130
• The water sector receives the largest • A remaining challenge is measuring
portion of FY 2006 CERP commitments how much potable water the Iraqis will
($151.38 million). Nearly 80% of the obli- receive and how much sewage will be
gated FY 2006 CERP funds ($149.81 mil- treated when U.S. projects are
lion) remains unspent; $31.52 million was completed.131
used to complete 323 of the planned 708
Water
$2.13 12%
30%
Water
$151.38
Sector Summaries
Water
Figure 2-29
Status of IRRF Water Projects
Source: IRMO Rollup (12/30/2006);
Democracy,
Security, USAID Activities Report (December 2006) Education,
Justice Private sector
development
Activities in the Water Sector tion date of June 2006135 was pushed back to
As of January 2, 2007, more than 80% of U.S.- October 2006136 and then to April 2007 to
funded sewerage projects were finished, and increase output and provide network connec-
84% of potable water projects were complete. tions to five cities.137 The Ministry of Elec-
For the status of projects in the water sector, tricity is connecting two feeder lines that will
see Figure 2-29. This quarter, approximately provide permanent power to the facility; the
$120 million was expended in the water sector, plant is currently using generator power. The
a decrease from the previous four quarters. completed water treatment plant will provide
As of January 2, 2007, 97% of the sector’s 240,000 cubic meters of water capacity per
IRRF funding had been obligated, but only day, which is sufficient to serve an estimated
approximately 66% of the total allocation had 555,000 people.138
been expended.132 Water was the last of the
Figure 2-30
major construction sectors to undertake recon- Status of IRRF Funds - Water
$ Billions
struction in Iraq. For the status of IRRF funds Source: IRMO, Weekly Status Report (1/2/2007):
in this sector, see Figure 2-30. DoS, Iraq Weekly Status (9/27/2006)
$2.06
Key Projects Completed Obligated
Sector Summaries
Water
Water
Security,
Justice
Additionally, the Nassriya Drainage Pump been operational since March 2006 because
Station was 64% complete, as of December of the failure of the sweep-arm assembly in
25, 2006,139 and is scheduled for completion in the clarifier tank. Before the U.S. contractor
June 2007. Cost overruns and schedule delays turned the facility over to the Iraqi operator,
for this project, however, have pushed its cost the contractor appears to have provided insuf-
to $147.7 million, nearly double its original ficient operational testing and ineffective plant
obligation of $82.3 million.140 The overruns and operator training.142 For more information, see
delays are largely the result of the addition of section 3 of this Report.
the Industrial Services Water Building, unfore- The $22.9 million project to restore the
seen site conditions, and increased security Sharq Dijla Water Treatment Plant was fin-
costs.141 GRD-PCO and IRMO are considering ished in October 2006.143 The restored capacity
options for the future of this project. will be sufficient to serve an additional 196,000
This quarter, SIGIR inspectors visited the cubic meters of water per day, with the poten-
Al Kasik Water Storage Tanks ($4.9 million) tial to serve an additional 392,000 people.144
and Al Kasik Waste Water Treatment Plant Last quarter, GRD-PCO introduced a
($2.7 million). SIGIR found that although the $116 million Small Potable Water Program,
work on the water storage tanks met appli- which focuses on contracting directly with
cable standards, the wastewater treatment Iraqi firms. When completed, these projects
plant completed in February 2006 has not are expected to add 419,000 cubic meters
Sector Summaries
Water
Democracy,
Security, Education,
Justice Private sector
development
of potable water treatment capacity, poten- tionally, nine centralized sewage treatment
tially serving up to 3.2 million people. As of facilities have been rehabilitated. The outputs
December 10, 2006, 179 of 323 projects were of these IRRF-funded projects appear in Table
completed (55%). These projects employ 2-8, which shows the current and anticipated
approximately 3,400 Iraqis.145 The Potable capacity provided by completed water projects.
Water Rehabilitation Program ($59 million)
is the largest of these projects and has the Outcomes of IRRF-funded Projects
potential to provide improved water sources to in the Water Sector
1.8 million Iraqis.146 It is difficult to measure how much water Iraqis
On October 30, 2006, the Basrah Sew- actually receive as an outcome of U.S.-funded
erage Project was completed. Final electrical projects or whether the water is potable.149 To
connection to the sewer pump stations was measure the impact of U.S. reconstruction
completed on December 18, 2006. The project efforts in the water and sanitation sector and
scope included assessing a sewer system, con- on the recommendation of a 2005 GAO audit,
structing and rehabilitating sewage collection IRMO developed a set of metrics and standard
networks, constructing four new pumping sta- methodologies to track potential impacts of
tions, upgrading equipment in the wastewater U.S. reconstruction efforts for the water sector.
treatment plant, procuring sewer jet trucks, SIGIR reports on two primary IRMO water
and installing the hospital’s main sewer line.147 sector metrics:
• maximum additional system capacity
Outputs of IRRF-funded Projects • additional people served at standard level
To date, the United States has constructed or of service, considering actual system
rehabilitated 21 potable water treatment facili- conditions150
ties and 200 smaller water systems.148 Addi-
Table 2-8
Sector Summaries
Water
Water
Source: GRD-PCO, response to SIGIR, January 18, 2007. IRMO reports the anticipated end-state
goal for additional people potentially served in sanitary sewage as 5.2 million people.
a
The estimated end-state is based on the estimated date for completing all water projects. All
planned GRD-PCO projects will be completed by April 2007 (IRMO, Information Memorandum
from Acting IRMO Director to Deputy Chief of Mission, April 19, 2006).
Table 2-9
Sector Summaries
Water
Figure 2-31
Security,
Water Sector Sustainment Program (WSSP) Project Map
Democracy,
Education,
Justice Source: GRD-WSSP (10/24/2006 - 11/27/2006) Private sector
development
Water Treatment Plants
A Kirkuk
B Dujail
Waterway Dahuk C Shark Dijlah
Water Treatment Plant D Najaf
Wastewater Treatment Plant E Garma
Erbil
Rural Water Project Location F Jubaileh
Ninewa
G R-Zero
Sulaymaniyah
A
Tameem
Wastewater Treatment Plants
Salah al-Din
H Rustimiyah North
I Rustimiyah South
J Hilla
B
Baghdad C K Najaf
H Diyala
I
Anbar
Wassit
Babylon
J
Kerbala
Missan
K
Qadissiyah
D
Thi-Qar
Najaf
E
F
Basrah G
Muthanna
Waste Water Treatment Plant.153 to ensure that the Iraqis have the means and
The Water Sector Sustainment Program ability to carry out sustained operations at an
(WSSP) responds to the challenge of sustaining acceptable level of service.154 This $116 million
water_map.ai
U.S.-funded water projects by adding O&M program includes $52 million for O&M facility
assistance at major water facilities in Iraq and support and $21 million for capacity develop-
supplying capacity-development functions ment and training. An additional $6.3 million
Sector Summaries
Water
Water
Security,
Justice
was recently added for plant optimization work • follow-up training, including mentoring,
conducted by local Iraqi firms in support of the classroom training, on-the-job training, and
Baghdad Security Plan. workshops160
Figure 2-31 shows the locations of WSSP • use of a scorecard to rate key operational
projects by governorate. areas at selected facilities, which GRD-PCO
The sustainment program intends “to assist reports has been a very effective tool for the
the Iraqi people in the proper operation and oversight and management of the WSSP
maintenance of selected water or wastewater program161
facilities.” It includes supplying sufficient parts • daily training, with contractor and Iraqi staff
and consumables, as well as providing technical working together, at the 11 facilities previ-
assessments and follow-on specialized repairs ously covered under the WSIS program
or optimization activities.155 The WSSP builds • continuing operations support at 40 major
on completed sustainment projects: facilities and 69 rural water projects (Rural
• USAID’s Water Sector Institutional water O&M support activities include pro-
Strengthening Program (WSIS) ($25 mil- viding operators, maintenance technicians,
lion)156 ended in April 2006, providing instruction material, security, chemicals,
O&M support for 11 major water and waste- and minor repair support.)
water treatment facilities.157
• GRD-PCO’s Management Systems Training The WSSP is also implementing Phase II of
Program ($14.5 million) for the Ministry of the Capacity Development Program (CDP).
Municipalities and Public Works158 will help This quarter, CDP provided 11 workshop
build capacity in Baghdad and eight local trainings for 174 personnel at the Ministry
governorates.159 of Water Resources and the Ministry of
Municipalities and Public Works, as well as the
The ongoing WSSP program is scheduled Baghdad Amanat (the public works directorate
to be completed in March 2007. The capacity for the city of Baghdad).162
development component of the WSSP includes:
Sector Summaries
Water
Democracy,
Security, Education,
Justice Private sector
development
Sector Summaries
Democracy
Security, Education,
Justice
SECTOR REPORT
Private sec
developme
Status of
Economic and
Societal
Development
Democracy,
Education,
Private sector
development
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
Figure 2-33
Economic and Societal Development
as a Sector Share of FY 2006 CERP Funds
Figure 2-32
$ Millions
Economic and Societal Development Sector % of $511.16 Million
as a Share of IRRF Funds
Source: Office of the Assistant Secretary of the Army
$ Billions
Financial Management and Comptroller (9/30/2006)
% of $18.44 Billion
Source: IRMO, Weekly Status Report (1/2/2007)
Economic & Societal
Development
28% $144.52
12%
Economic & Societal
Development
$2.21
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Figure 2-34 Development
Status of IRRF Funds - Economic and Societal Development
$ Billions
Source: IRMO, Weekly Status Report (1/2/2007);
DoS, Iraq Weekly Status (9/27/2006)
$2.21
Obligated
Not Expended
$.23 $1.88
OCT 06
Expended
$1.98
DEC 06
Figure 2-35
Status of IRRF Economic and Societal Development Projects
Source: IRMO Rollup (12/30/2006); USAID Activities Report (December 2006)
Not
Not Started Sector Started Ongoing Completed Total
1% Ongoing Democracy Building Activities 110 97 5,913 6,120
1%
Schools 1 2 807 810
Civic Program 446 446
Completed Education 444 444
98%
Agriculture 1 373 374
Public Buildings Construction and Repair 1 7 8
Migration and Refugee Assistance 3 2 5
Vocational Training 4 4
8,212 Projects Planned
Market-Based Reforms 1 1
IRRF status of funds soc.ai
Total 113 102 7,997 8,212
have also been used to strengthen Iraq’s new As of early December 2006, 5,913 of the
democracy at the grassroots level by bolstering 6,120 IRRF projects in the democracy sub-
the legitimacy of the political system, devel- sector had been completed (97%). Addition-
oping institutional capacity, strengthening ally, 135 CERP-funded projects had been com-
civil-society organizations, and inculcating a pleted as of September 30, 2006; an additional
stronger sense of promoting civic involvement 108 projects are in progress.
among Iraq’s citizens. In 2006, the U.S. provided $315 million
from the Economic Support Fund (ESF) for
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
projects identified by the Provincial Recon- positions. A further concern is that, as an NCT
struction Development Committees (PRDCs) assessment notes, “systems for documenting
in each of the 18 provinces. These projects measurements in capacity building have not
included the construction of roads, schools, yet been developed and put in place.”171 On the
sewers, and telecommunication upgrades. As other hand, senior USAID officials interviewed
of December 2006, 33 projects were funded, this quarter emphasized the positive impact of
and $68 million was expended. PRTs, noting that local Iraqi officials in many
In a national address on January 10, 2007, governorates are beginning to view the PRTs
President Bush expressed his intention to as their key interlocutors for development
“double the number of Provincial Reconstruc- issues.172
tion Teams (PRTs)” in Iraq.164 PRTs work to Forty-five million dollars in ESF funds go to
decentralize U.S.-funded reconstruction efforts the National Capacity Development Program
by placing combined military-civilian teams at (NCDP), which helps the GOI strengthen its
the provincial level to strengthen governance core functions. Its activities include developing
capacity and help Iraqis prioritize development of key ministries, the Prime Minister’s office,
needs.165 This quarter, DoS reported that the participating inspectors general, and various
PRTs are focusing more on small-scale anticorruption organizations.173 The program
projects to help ensure that Iraqis quickly see uses Ministry Advisory Teams to provide
the benefits of working with the government.166 public policy and programmatic advice, and
Currently, there are seven U.S. PRTs and three work with the ministries to develop and
Coalition PRTs operating in Iraq; the office in address their respective priorities. It also sup-
Erbil is a Regional Reconstruction Team (RRT) ports the national public administration cen-
that has not yet been officially opened.167 ters in their efforts to train ministry employees
The ability of PRTs to engage with local and develop core competencies.174 The Inter-
governments has been “directly related to national Republican Institute (IRI), National
support from the coalition force” in each Democratic Institute (NDI), and other grantees
governorate, according to a joint operational also receive ESF funds to continue to con-
assessment of PRTs completed this quarter by duct IRRF-funded democracy activities at the
MNF-I, MNC-I, and the National Coordina- national level.
tion Team (NCT).168 For example, the PRT
team leader in Basrah reported in December Outputs of U.S. Democracy Projects
that “the team itself cannot long be sustained
as a body in exile.”169 This quarter, ministers U.S.-funded initiatives aimed at improving
from the United Kingdom relocated personnel local governing capacity in Iraq have had
from the Basrah PRT to Kuwait because of mixed results. Since 2003, the Community
escalating violence.170 Security conditions have Action Program (CAP) has operated in Iraq to
also hampered recruitment for civilian PRT promote democracy and help mitigate conflict
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Development
at the local level. The CAP aims to provide modules.180 The PMP noted that the unfulfilled
citizens with improved access to quality health initiatives related to training staff on orga-
care, education, recreation, water, sewerage, nizational assessments, establishing satellite
and other services by improving infrastructure centers, and providing multiple, human rights
and providing assistance to war victims.175 This awareness and issues trainings.181
quarter, the program has established more than Last quarter, SIGIR reported on the activi-
66 community action groups throughout the ties of NDI and IRI in Iraq. Those activities
country, creating more than 7,637 short-term continued this quarter, primarily with ESF
jobs.176 Additionally, CAP completed 327 com- funding. This quarter, NDI continued to focus
munity-based projects, valued at $11 million. on training and seminars. They have held
The CAP works closely with CAGs and PRTs, seminars for political parties and non-govern-
most recently emphasizing initiatives to gen- mental organizations (NGOs) on the antici-
erate income and employment.177 pated provincial council elections and consti-
The Iraq Civil Society Program (ICSP) tutional referendum, consulted with members
began as a $59.1 million contract in 2004 of the Council of Representatives, debriefed the
(increased to $60.9 million, which includes $8 Multi-party Women’s Caucus after the national
million in ESF funds) with the goal of fos- conference, and conducted voter education.
tering participatory democratic governance in In December, NDI sponsored a delegation of
Iraq.178 The ICSP has since supported services Iraqi civic leaders who traveled to Romania to
to Civil Society Resource Centers (CSRCs), study civic development and advocacy.182
worked to strengthen capacity and technical IRI continues to support civil society
skills by delivering civic education workshops, groups, work with political parties to
advanced women’s advocacy programs, and strengthen their structures and broaden their
provided training for government officials bases of support, and support the development
on anticorruption and human rights.179 The of institutions in the Council of Representa-
program is scheduled to terminate on June 30, tives. This quarter, IRI organized strategic
2007. planning sessions for the civil society coali-
A November 2006 USAID audit on its ICSP tions, “Civic Coalition for Free Elections,” and
contractors’ Performance Monitoring Plan “Yalla Shabab,” a coalition of NGOs. IRI also
(PMP) found that only 17 of 35 intended civil- held training sessions for Research Directorate
society initiatives have been accomplished to staff, analyzing legislation and issues.183
date, 8 others failed to meet their objectives,
and documentation was not available for Outcomes of U.S. Democracy Programs
the final 10. Program achievements include
establishing 4 regional CSRCs, awarding small The results of U.S. and other democracy
grants to civil-society organizations, and programs are difficult to measure because
adapting 83 capacity-building training they evolve over time. Nonetheless, it is fair
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Development
for women and women’s groups, especially Although the ARDI contract will not
secular women, who report receiving death be extended, USAID is issuing an RFP for
threats for not abiding by strict and conser- a follow-up project, potentially using ESF
vative dress codes. Armed groups in search funding.198 The contract for this new follow-
of fathers and brothers have taken reprisal on program, known as Inma, is currently in
on mothers, sisters, and wives.194 the procurement process and expected to be
awarded by USAID in February or March
Agriculture 2007.199 However, ARDI employees may have
USAID has been responsible for most IRRF already been demobilized, and it may prove
funding for the agriculture sector through the difficult to bring them back.200
Agriculture Reconstruction and Development Additionally, the U.S. Department of
Program for Iraq (ARDI). Agriculture (USDA) awarded $5.3 million
in December 2006 to the Iraq Agriculture
Agriculture Projects Extension Revitalization Project (IAER) to
Completed and Underway strengthen agriculture extension and training
initiatives at Iraqi universities. As part of this
In December 2006, the ARDI program offi- project, a team of five U.S. universities will
cially closed; it had worked to increase the partner with universities across Iraq. The U.S.
capacity of the private sector in agronomic universities have specialized programs in arid-
crop production, increase cultivation of high- land agriculture, strong extension programs,
value agricultural cash crops, improve animal experience in Middle East agro-ecologies
health infrastructure and livestock produc- similar to the various regions of Iraq, and 13
tion, and improve the use and management of professors of Iraqi descent on their faculties.201
water on agriculture lands.195 Projects included IAER has a number of objectives: establish
establishing feed-lot cooperatives, sheep- links between Ministry of Agriculture exten-
raising cooperatives, and private veterinary sion agencies and Iraqi agricultural colleges,202
service providers; strengthening honey-pro- strengthen university capacity development,
ducer and agriculture input associations; and and provide training and support to Iraqis. The
building the capacity of local NGOs to imple- project will also provide specialized training
ment projects.196 Additionally, the $4 million and work with the private sector; it is sched-
allocated for the Iraq Marshlands Restoration uled to operate until September 2008.203
Program was fully expended by the end of this An additional $2.5 million was designated
quarter.197 to USDA staff who are currently supporting
As of early December 2006, 373 of the 374 this project, and the Ministry of Higher Educa-
IRRF-funded projects in the agriculture sector tion and the Ministry of Science and Tech-
had been completed, and the remaining project nology will also be involved.204
had yet to begin.
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Development
ARDI Outputs
From 2005 to 2006, ARDI conducted wheat seed multiplication programs in two northern
governorates, which provided 3,000 metric tons of higher quality, ”certified +1” wheat seed to
wheat producers.a
ARDI helped establish with the State Board for Date Palm Development 21 date palm mother
orchards in 13 governorates. From 2004 to 2006, ARDI provided 80,000 date offshoot plants to the
Crop and Livestock mother orchards, which will produce 240,000 new offshoots per year.a
Management
7,406 farmers cleaned their saved wheat seed between September 2005 and January 2006,
producing more than 35,000 metric tons of cleaned wheat seed.a
40 private veterinary service providers were established, 10 each in Ninewa, Kirkuk, Dahuk, and
Salah al-Din. The providers offer services to rural areas not served by government clinics.b
68 veterinary clinics were rehabilitated, serving more than 5.7 million animals and 135,000 breeders.b
ARDI rehabilitated irrigation systems, impacting 282,038 hectares.c
Land Irrigation ARDI rehabilitated more than 1,100 km of irrigation infrastructure, which brought water to 283,000
hectares of land and benefited more than 85,000 farm families.a
ARDI trained more than 215 mechanics, mostly in rural areas, as part of the tractor-repair program to
improve infrastructure for repair and maintenance services for agricultural machinery.b
A wholesale price information system was established in all 18 governorates for dissemination by
Training and mass media (radio, SMS, e-mail) to farmers and traders of 60 fruits, dry goods, animal products, and
Capacity agricultural inputs.a
Development
ARDI also provided business management, association-building, and facilitation training to 19
NGOs active in agriculture development, 293 agricultural cooperative members in 15 newly-formed
cooperative associations, 4,300 beekeepers and honey producers, a national association of 233
independent pesticide dealers, and 526 extension specialists.a
Table 2-10
approximately 3,000 agribusinesses have gener- To comply with the Stand-By Arrangement
ated at least 50% gains in income, including with the IMF, Iraq has asked the Coalition and
honey producers, mechanics, and tractor other donors for advice under the Economic
owners.214 Governance program on how to phase out
ARDI projects led to an increase of wheat the Public Distribution System (PDS), which
production of 56% in areas cultivated by subsidizes food items by an estimated $3 bil-
these initiatives, including replacing old lion annually. The Iraqis are expected to ramp
seed varieties, introducing more productive down the PDS over the next 3-5 years.216
growing techniques, cleaning wheat seeds,
implementing pest-control techniques, and Challenges
introducing salt-tolerant seed varieties.215 This
should help the Iraqis reduce their dependence SIGIR sees two major challenges in the agricul-
on imported wheat. ture sector: inadequate security and the need
to develop market-friendly laws and policies.
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Development
Sources: DoS, Section 2207 Report, October 2006, p. 17 (Total Schools and Schools Needing Repair, MNF-I data);
GRD-PCO, response to SIGIR, January 4, 2007 (PCO projects); all other metrics unchanged since last quarter.
Table 2-11
targets of violent attacks. In 2006 alone, the The growing number of Iraqi refugees and
Ministry of Education reported that more than internally displaced Iraqis has outpaced the
300 of its teachers and employees were killed, resources available to support them, and vio-
and an additional 1,158 were wounded.227 lence in Iraq has hindered humanitarian efforts
From 2003 to August 2006, the Ministry of to assist Iraq’s internally displaced population.
Higher Education reported that 154 professors
had been assassinated, and in the three months Refugees
between August and October 2006, 15 more
were killed.228 It has been estimated, that 90% During FY 2004, $105 million in IRRF funds
of the schools in the Diyala governorate are was allocated to assistance for conflict victims,
closed because of adverse security conditions, including refugees and internally displaced
threats, and attacks. Almost no schools in the persons (IDPs). In FY 2005, an additional $54
city of Ramadi in Anbar have opened because million was allocated; a further $27 million
of insurgent threats.229 in FY 2006 brings the total allocation to $186
Although maintaining security around these million.231 As of September 30, 2006, all alloca-
educational institutions is the responsibility of tions had been obligated, and $134 million
the Iraqi government, it is difficult to deter- had been expended. IRRF funds have been
mine how well these U.S.-refurbished facilities used to support the capacity-building efforts
are being protected and to what degree they of various Iraqi organizations, including the
are being used. Ministry of Displacement and Migration and
international groups, such as the International
Refugees and Human Rights Organization for Migration (IOM), the UN
The escalating violence in Iraq during 2006 High Commissioner for Refugees (UNHCR),
has caused an estimated 500,000 Iraqis to leave and the International Committee of the Red
their homes. Approximately, 2,000-3,000 Iraqis Cross (ICRC).232
leave for neighboring countries each day.230
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
Progress in U.S.-funded projects in this projects, funded by $1.4 million of the IRRF,
sector included completing permanent water had been closed out by the end of October
sources, continuing mobile health unit activi- 2006.235
ties, and implementing water and sanitation In FY 2007, the DoS Bureau for Interna-
activities, as well as training for the newly tional Narcotics and Law Enforcement Affairs
formed Iraq NGO, “Relief Iraq.” CERP is (INL) requested $14 million to fund additional
funding 146 additional humanitarian or recon- human rights programs to:
struction projects, which include construction • Build internal monitoring, reporting, and
of homeless shelters, providing orphanage enforcement systems in the Ministries of
supplies and food bags, and conducting shoe Interior and Defense.
drops.233 • Support development of a robust and inde-
pendent Human Rights Commission.
Resolution of Real Property Disputes • Develop the capacity of Iraqi NGOs to
monitor and report on human rights
IRRF funds ($10 million) have been com- violations.
mitted and expended to support the Commis- • Support the Human Rights Ministry.
sion for Resolution of Real Property Disputes, • Train Iraqi journalists.236
formerly the Property Claims Commission.
IOM implementation of the out-of-country Challenges
claims program continues to be delayed
pending additional funding that the UNHCR Continued Human Rights Violations
has committed. As of August 31, 2006, Iraqis The human rights situation continues to dete-
had filed 124,092 property claims, and 25,893 riorate in Iraq. UNAMI reports that attacks on
had been adjudicated. UNHCR reports that Iraqi civilians and professionals have increased
only 401 Iraqis returned to Iraq in 2006, over the past few months:
compared to 55,267 in 2005 and 191,645 in • Attacks on professionals, such as teachers
2004. Last quarter, the UNHCR shifted its and religious figures, have increased since
focus from aiding returning Iraqis to helping October 2006.
displaced citizens who continue to flee because • Freedom of the press is currently a conten-
of increased sectarian violence.234 tious topic in Iraq, as journalists and media
workers remain targets for attack and
Human Rights assassination.
• Women in the central and southern gov-
Fifteen million dollars in IRRF funds were ernorates are increasingly restricted from
allocated to promote human rights in Iraq. All accessing health and education services
funds have been obligated, and $12 million has because of the volatile security situation.
been expended. USAID Human Rights Furthermore, women continue to be the
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Development
victims of honor crimes, especially in the States and Canada increased 32% during the
northern governorates. same period.241 Some observers have advocated
• It has also been reported that minorities raising the quota for Iraqi refugees allowed to
living in Kirkuk are prevented from par- resettle in the United States.
ticipating in political, economic, and social The sheer number of displaced Iraqis
developments in the city.237 challenges the resources and services of host
communities and host countries, and Iraq’s
UNAMI also reports that the total number neighbors are becoming overwhelmed by the
of civilians violently killed in 2006 is 34,452— growing number of Iraqi refugees in their
94 civilians each day. The number of civilians countries. Syria has begun imposing new
killed throughout the country was 3,462 in restrictions, such as limiting access to health
November and 2,914 in December, although care and schools. Jordan has closed its borders
December’s figure does not include all gov- to young Iraqi men, and Lebanon has closed its
ernorates. The numbers of civilians killed in borders to all Iraqi refugees.242 The number of
Baghdad alone during these same months IDPs moving to the northern regions of Iraq is
were 2,230 and 2,501, respectively. On average, growing.243
3,338 Iraqis were killed each month between
July 1, 2006, and December 31, 2006.238 Security
Security concerns across Iraq limit access of
Increased Refugees and IDPs and the Resolution Iraqi ministries, humanitarian agencies, and
of Real Property Rights NGOs to many vulnerable displaced groups.
Although there are no exact figures for Iraqis Both the UN and local aid groups have report-
displaced internally and abroad, the UNHCR edly received threats for helping displaced
reported in January 2007 that approximately families of differing religious affiliations.244
500,000 Iraqis had been internally displaced On November 9, 2006, the head of the Iraqi
since the bombing of the Al-Askari Shrine in Red Crescent Society Administration was
Samarra in February 2006.239 Additionally, it kidnapped.245 On December 18, 2006, the Iraqi
is estimated that approximately 50,000 Iraqis Red Crescent (IRC) closed all of its Baghdad
flee their homes each month. Many of these branches until further notice after the kidnap-
internally and externally displaced people are ping of 30 IRC employees.246
urban professionals considered crucial to Iraq’s
stability and development.240 Figure 2-36 shows Funding
how the Iraqi population has been displaced. UNHCR operated in Iraq in FY 2006 with a
During the first half of 2006, more than budget of $29 million. On January 8, 2007,
8,100 Iraqis applied for asylum in Europe, a UNHCR launched a new appeal for $60
48% increase from the first half of 2005. The million for Iraqi operations over the next 12
number of Iraqis seeking asylum in the United months to deal with an estimated 2.3 million
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
Figure 2-36
Movement of Internally Displaced Iraqis and Iraqi Refugees
Source: “UNHCR Update on the Iraq Situation,” UNHCR, November 2006;
UNHCR “Iraq Situation Map; Situation as of October 2006”;
CIA 2006 World Factbook: Iraq.www.cia.gov/cia/publications/factbook/geos/iz.html;
UNHCR Press Release “UNCHR launches new appeal for Iraq operations” 1/8/2007
Erbil
500,000 - 700,000 Iraqis to Syria Ninewa
11,000 Estimated Net New Newly Internally Displaced Iraqis, as of October 2006
Arrivals per Week to Syria
Tameem Sulaymaniyah Northern Region 60,000
Central Iraq 170,000
Southern Iraq 191,000
20,000 to 40,000 Salah al-Din Kurdistan Regional Government 58,000
Iraqis to Lebanon Total 479,000
Diyala
Wassit
Kerbala Babylon
Returnees in Iraq,
as of October 2006
500,000 to 700,000 Qadissiyah Missan
Iraqis to Jordan 2006 401
2005 55,267
Thi-Qar 2004 191,645
Najaf
2003 50,524
20,000 to 80,000 2002 1,142
Iraqis to Egypt Basrah Total 298,979
Muthanna
Note:
Some Iraqis were displaced before 2003.
refugee_map2.ai
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Development
internally displaced persons. These funds will also manages the microfinance program, under
cover protection and assistance programs for Izdihar, started by the CPA.250
Iraqi refugees in Syria, Jordan, Lebanon, Egypt, Approximately $30 million of IRRF funding
and Turkey, as well as non-Iraqi refugees and was provided to the Overseas Private Invest-
IDPs within Iraqi.247 The increase in refugees ment Corporation in 2004 for expanding
also increases expenditures to pay for refugee the Iraq Middle Market Development Fund
status determination. The United States and (IMMDF),251 a loan program that provides
Iraq’s neighbors rely on the UNHCR to identify Iraqi companies with credit facilities of $35,000
the most vulnerable Iraqi refugees. The DoS to $5 million.252 The program was recently
Bureau for Population, Refugees, and Migra- provided an additional fund of $9.1 million for
tion has acknowledged that a lack of resources smaller loans ($35,000 to $500,000), and 30%
has hindered the UNHCR from doing settle- of this fund will be for agribusiness loans. As
ment referrals on behalf of the United States.248 of the first week of January 2007, IMMDF has
approved six loans, which have totaled approx-
Economic and Private-sector imately $14.8 million. In addition, 11 loans, or
Development $32.6 million, have been disbursed.253 IMMDF
This section presents the key U.S. economic also continues to support production in indus-
and private-sector development projects, as tries such as water, woodworking, milling, and
well as a general overview of the outputs of used vehicles.254
these projects. As of September 30, 2006, 43 CERP-funded
private-sector development projects had been
Projects Completed and Underway completed, and 54 were ongoing.
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Development
Izdihar continues to support the GOI on the Iraq Trade Information Center, which was
joining the World Trade Organization (WTO), established to encourage international inves-
assisting the government to draft the required tors through training and database/website
documentation, responding to questions posed development. USAID also supported the Iraqi
by WTO members, conducting conformity Securities Commission through rule and regu-
assessments, and appropriately training Iraqi lation implementation and document drafting.
government.268 The staff of the Iraqi Stock Exchange also
Izdihar has also helped create the Iraq received training for information technology,
Company for Bank Guarantees (ICBG), which public relations, and regulations through
offers loan guarantees to private banks. The seminars.275
ICBG allows Iraq’s microfinance industry to DoD’s Office of Business Transformation is
receive loans from private banks rather than exploring ways to help Iraq reinvigorate some
just international donors.269 ICBG began its of the most promising state-owned enterprises,
operations on November 1, 2006, and Izdihar using better market analysis that helps iden-
plans to develop operational policies, proce- tify potential demand for the products of the
dures, and manuals; train staff; and establish enterprises in Iraq and beyond. It is anticipated
headquarters to continue assisting ICBG that this activity will stimulate employment
through the end of 2006.270 and private businesses that traditionally spring
Also, Izdihar’s Sustainable Microfinance up around these state owned-factories.
program includes grants to microfinance
institutions (MFI), training for MFI staff, and Outputs of U.S. Projects in
technical assistance. USAID recently awarded Economic Development
$9.9 million in grants to establish or continue
the development of sustainable Iraqi MFI.271 EG project activities have yielded notable
Last quarter, one new microfinance institution results in tax reforms: a Tax Policy Unit
started operating and was awarded a $250,000 has been established within the Ministry
grant to be used for loan capital.272 From of Finance to create a taxation strategy as
November 14-16, 2006, USAID organized the mandated by the SBA. With assistance from
first Iraq Microfinance Summit in Erbil, with USAID, the Ministry of Finance drafted a plan
more than 100 participants in attendance.273 to overhaul Iraq’s outdated tax system. The
Izdihar also plans to train Iraqi MFI staff in the final plan is to be approved by the Council
near future.274 of Ministers and adopted by the GOI by the
Other activities under private-sector devel- end of December, and implementation of this
opment last quarter include providing mate- plan will meet a significant SBA requirement.
rials to the Iraqi Investment Promotion Agency Also, as of December 2006, all ministries and
and conducting strategic planning meetings. regional treasuries were using FMIS in parallel
Izdihar also continued building capacity for with the legacy manual system.276
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
As of September 2006, USAID was engaged likely to be met: Iraq’s Central Office for Statis-
in microfinance lending in 13 governorates, tics reported a surge of 7.6% in the Consumer
and its loan portfolios comprised 16,673 loans Price Index for December 2006 alone.281 The
totaling more than $17.8 million. Currently, Economic Intelligence Unit estimated that
more than 630 MFI staff have been trained.277 inflation averaged 52% in 2006, significantly
Last quarter, the first two indigenous microfi- higher than last year at 32%.282
nance institutions established with Izdihar’s sup- To cope with this increasing inflationary
port had extended 40 new loans for $100,000.278 pressure, the CBI began to implement policies
In addition to these two MFIs, located in Kirkuk in September 2006 designed to appreciate the
and Baghdad, the MFI in Fallujah was sched- dinar, as suggested by the IMF.283 Iraq is an
uled to open in January 2007.279 import-reliant country; therefore, a more valu-
able currency may help alleviate some pres-
Iraq’s Economy Remains Fragile sure. As of December 26, 2006, the exchange
rate was 1,360 Iraqi dinars to the dollar.284 The
Despite some positive results from U.S.-funded Central Bank has also raised its interest rate
projects, Iraq’s overall economic environment from 16% to 20%, as of December 24, 2006,
is still fragile. Inflation is a serious concern as to encourage holding dinar-based assets and
the volatile security environment, shortage of lower expectations of inflation.285 See Figure
goods, and supply disruptions in the non-oil 2-37 for historical and current information on
economy push prices upward.280 the currency exchange rate.
The 2006 SBA inflation goal of 15% is not Per capita GDP is rising in Iraq, from $949
Figure 2-37
Currency Exchange Rate
Currency (Auction Selling Price Dinar/$1 USD)
Source: IRMO, Weekly Status Reports (6/28/2004 - 12/26/2006);
Central Bank of Iraq
1500
1450
1400
1350
1300
JUN AUG OCT DEC FEB APR JUN AUG OCT DEC FEB APR JUN AUG OCT DEC
currency.ai
76 I SPECIAL INSPECTOR GENERAL FOR IRAQ RECONSTRUCTION
Water Oil and Gas
Sector Summaries
Democracy
Security, Education,
Justice Private sec
developme
Status of
Economic and
Societal
Development
per person in 2004 to an estimated $1,189 in activities going forward.290 The objectives of the
2005 and $1,635 in 2006.286 However, when Independent Media Programs are to develop
inflation is taken into account, real GDP democratic media laws, promote media excel-
growth is estimated to be only 4% in 2006, lence and professionalism, support media as a
well below the SBA’s 10.4% benchmark and the commercial enterprise, and strengthen media
medians of other Middle Eastern and oil-pro- associations and NGOs.291
ducing countries.287 The Iraq Civil Society Program has con-
Unemployment remains very high in Iraq. ducted media workshops to brief Iraqi journal-
As of July 2006, the Central Office for Statistics ists on the media and federalism to improve
estimated that unemployment was at 18% and participants’ understanding of federal systems
that underemployment was at 30.4%. However, and the concept of public broadcasting and the
officials believe that these numbers have been importance of citizen control over program
underestimated.288 content. This program also supports efforts to
promote the draft Iraqi Media Corporation
Challenges Law. USAID is in the process of redesigning
the scope of work for the follow-on project.292
Although there has been some economic prog-
ress in Iraq, economic development cannot Projects Completed and Underway
reach its full potential unless Iraq first resolves
its other challenges: The SIMI program has helped establish and
• security build capacity for the National Iraqi News
• corruption Agency and Iraqis for Public Broadcasting.
• lack of government capacity USAID reports that SIMI has increased the
• deteriorated infrastructure knowledge and skills of more than 1,000
journalists and media professionals and has
Media established an Iraqi media watchdog group.293
The Support for Independent Media in Iraq
(SIMI) program is the media component of Challenges
USAID’s $42 million Civil Society and Inde-
pendent Media Support Program. SIMI is Journalists and news publications in Iraq
implemented by the International Research continue to be the target of threats and attacks.
and Exchanges Board (IREX).289 IRRF funding Since March 2003, at least 132 journalists and
for Civil Society and Independent Media Pro- media workers have been killed in Iraq.294 The
grams ended on September 30, 2006, but alter- Committee to Protect Journalists reported
nate funding remains for continuing similar in December that 32 journalists were killed
Sector Summaries
Democracy,
Education,
Private sector
development
Status of
Economic and
Societal
Development
in Iraq during 2006—the highest one-year Iraqi journalists and other media workers in
death toll on record for journalists in a single the southern and central regions were banned
country.295 Media organizations have also been from attending parliament sessions, or threat-
targeted: Al-Shaabiya satellite television and ened. The GOI may close stations alleged to
Al Iraqiya satellite television were attacked in incite hate and violence.297
October 2006.296
Sector Summaries
SECTOR REPORT
Democracy,
Security, Education,
Justice Private sector
development
Figure 2-39
Sector Shares of ISFF Funds
Figure 2-38 $ Billions
Security and Justice Sector % of $8.32 Billion
as a Share of IRRF Funds Source: DoD Secretary of the Army Update (12/31/2006)
$ Billions
% of $18.44 Billion
Source: IRMO, Weekly Status Report (1/2/2007) Training & Sustainment
Operations $1.22
$1.32 2% Quick Response Fund
$.17
16% 14%
1% Detainee Ops,
34% Security & Justice Prosthetics Clinic
$6.31 $.08
33% 34%
Equipment &
Infrastructure Transportation
$2.73 $2.80
Sector Summaries
Democracy,
Security, Education,
Justice Private sector
development
SIGIR makes these observations on IRRF- target of 325,000 troops and police, the
and ISFF-funded activities in the sector: security situation in parts of Iraq contin-
• More U.S. funds have been committed to ues to deteriorate. Insurgent attacks and
security and justice than any other recon- continued infiltration of the ISF and Iraqi
struction sector—almost $15 billion from Police by militia members also contributes
the IRRF and ISFF. to the escalating violence in some parts of
• As of January 2, 2007, almost 90% of the the country.
$6.31 billion IRRF allocation in this sector • Critical infrastructure remains a target for
had been expended. insurgent attacks, and the effectiveness
• As of December 30, 2006, more than 54% of the Strategic Infrastructure Battalions
of the cumulative $8.32 billion ISFF alloca- (SIBs) remains questionable.
tion had been expended. • Transition of full security responsibilities
• An additional $1.7 billion was appropriated to the Iraqis faces significant challenges,
for ISFF in the FY 2007 Defense Appropria- including militia infiltration of the ISF, slow
tions Bill. These funds will remain available growth in the capacity of the Ministries of
until September 30, 2008. Defense and Interior to support the soldiers
• As of January 8, 2007, 323,000 Iraqi Secu- and police, and the need for additional
rity Forces (ISF), including military and training for the ISF. In addition, the Iraqi
police personnel, have reportedly been Army still struggles to plan and execute
trained, equipped, and fielded.303 DoD logistics and sustainment requirements.
notes that the actual numbers of active
soldiers and police on duty are significantly Activities in the Security and
lower because of scheduled leave, absence Justice Sector
without leave, and attrition.304 On January 10, 2007, President Bush
• As of December 2006, 91% of IRRF-funded announced his intention to increase the
projects had been completed in the security number of U.S. forces in Iraq to help stabilize
and justice sector. the security situation, particularly in Baghdad
and Anbar. He noted, however, that this surge
SIGIR also sees significant challenges in this would be in support of the ISF and the GOI’s
sector: ability to reach specific benchmarks.305
• Although the reported number of trained In the meantime, IRRF and ISFF funds
and equipped ISF has almost reached the continue to be used to further develop the
Sector Summaries
Security,
Justice
operational capacity of the ISF and the Minis- quarter, approximately 90% of IRRF funds for
tries of Interior and Defense, while also aiming this sector had been expended. For the status
to facilitate the rule of law in Iraq. of IRRF funding, see Figure 2-40. ISFF funds,
however, are used mostly to train, equip, and
Programs and Activities field members of the ISF. As of December 31,
Completed and Underway 2006, 54% of ISFF funding had been expended.
IRRF projects focus on constructing and For the status of ISFF funding, see Figure 2-41.
refurbishing facilities. By the end of the
Figure 2-40
Status of IRRF Funds - Security and Justice Figure 2-41
$ Billions Status of ISFF Funds – Security and Justice
Source: IRMO, Weekly Status Report (1/2/2007); $ Billions
DoS, Iraq Weekly Status (9/27/2006) Source: DoD Secretary of the Army Update (12/31/2006)
$6.28 $6.59
Obligated Obligated
Note:
Totals are produced by combining financial detail
from ISFF 2005 and ISFF 2006 funds.
Sector Summaries
Democracy,
Security, Education,
Justice Private sector
development
For a detailed list of projects funded by the 06-031 in October 2006). Generally, SIGIR
IRFF and ISFF, see Figures 2-42 and 2-43. found that MNF-I had established reasonable
Almost all of the committed $30.31 mil- processes to manage funds and projects. SIGIR
lion in CERP funding had been obligated, as also noted some data quality and reporting
of September 30, 2006. Additionally, $17.29 errors, as well as improvements in the manage-
million in CERP funding—57% of the com- ment of funds.
mitted amount—had been expended. Figure
2-44 shows sector funds as a percentage of the Military/Police Force Development
CERP. and Support
SIGIR has performed two audits on how
Multi-National Force-Iraq (MNF-I) has used Work in this sector has focused on building
CERP funds (Audit 05-014 in October 2005 military and police forces, mostly with funding
and Audit 05-025 in January 2006) and one from the ISFF; the effort has resulted in
audit on MNF-I’s use of the Iraqi Interim Gov- 323,000 trained and equipped military and
ernment Fund for CERP-like programs (Audit police personnel, as of January 8, 2007.306 The
Figure 2-42
Status of IRRF Security and Justice Projects
Source: IRMO Rollup (12/30/2006); USAID Activities Report (December 2006)
Sector Summaries
Security,
Justice
Figure 2-43
Status of ISFF Projects
Source: IRMO Rollup (12/30/2006)
Note:
ISFF projects are compiled by totaling and grouping projects from both ISFF FY 2005 and ISFF FY 2006.
425 Projects Planned
Figure 2-44
initial force-generation plans for the Ministry Security and Justice as a Sector Share of FY 2006 CERP Funds
of Interior and the Ministry of Defense are $ Millions
% of $511.16 Million
expected to be completed by the end of 2006 Source: Office of the Assistant Secretary of the Army
Financial Management and Comptroller (9/30/2006)
when the effort will shift to replacing force
losses and developing sustainment capacity.307
In addition to efforts by the United States
and its Coalition partners, the GOI has
announced an $800 million initiative to
expand the Iraqi Army by 3 division headquar-
ters, 5 brigade headquarters, 20 battalions, and
Security & Justice
1 special-forces battalion. This initiative should $30.31 6%
be completed within one year.308
concerns that required prompt attention. The
Construction original contractor has since left this project
and been replaced, but a SIGIR follow-up
In this sector, IRRF has funded the construc- inspection of the site this quarter identified
tion and rehabilitation of border forts, fire similar and additional issues. Although repairs
stations, police stations, public-safety training have been performed on this facility, other
academies, prisons and corrections facilities, deficiencies have been reported.311 Warranty
courthouses, and witness-protection and repair work at the facility is expected to be
facilities.309 The last IRRF-funded construction completed by April 2007.312 Last quarter, SIGIR
project in the sector is scheduled to be com- Inspections reported that construction of this
ISFF status of projects.ai
pleted by April 2008.310 site was not adequately designed and did not
Last quarter, SIGIR Inspections identified a meet the original objectives or design stan-
variety of construction deficiencies associated dards (Inspection 06-072). For details on these
with the Baghdad Police College and health inspections, see section 3 of this Report.
Sector Summaries
Democracy,
Security, Education,
Justice Private sector
development
Dahuk Prison
Rule-of-law Initiatives
Sector Summaries
Security,
Justice
The DoS Bureau of International Narcotics progress; 29 courthouse projects and 1 wit-
and Law Enforcement (INL) budget for rule- ness-protection security facility have been
of-law initiatives increased from $88.6 million completed.320
in FY 2006 to $254.6 million for FY 2007. The
largest portion of the funding ($89.1 million) Outputs of Programs Funded by
went to courts and criminal justice activities. IRRF and ISFF
The initiatives are designed to accomplish Outputs of U.S. projects in this sector include
several goals, including: completing construction and refurbishments
• strengthening judicial independence to various facilities, as well as fielding, training,
• supporting facility security to judges and and equipping Iraqi military and police forces.
court members
• providing secure housing for judges in Fielding and Equipping Trained
Baghdad Troops and Police
• building court capacity through training
As of January 8, 2007, 323,000 Iraqi mili-
Other planned rule-of-law programs under tary and police forces have been trained and
INL management include: equipped for security operations:
• outreach and access to justice ($49 million) • 134,700 Iraqi Army, Navy, and Air Force
• corrections ($31 million) personnel321
• anticorruption ($27 million) • 188,300 police, highway patrol, and other
• justice integration ($25 million) Ministry of Interior officers322
• human rights ($14 million)
• major crimes task force ($11 million)319 The goal of the Ministry of Interior is to
field 188,260 trained and equipped personnel;
For more information on anticorruption, the force-generation plan under the Min-
see the end of section 2 of this Report. istry of Defense proposes an end-strength of
GRD-PCO also reported this quarter that approximately 137,500 soldiers. However, the
9 courthouse projects, 4 witness-protection “actual number of present-for-duty soldiers
security facilities, and 3 prison projects are in is significantly lower due to scheduled leave,
Sector Summaries
Democracy,
Security, Education,
Justice Private sector
development
Sector Summaries
Security,
Justice
Police have completed initial training, as of the U.S.-funded initiatives include training and
end of the quarter.333 equipping the Strategic Infrastructure Bat-
Three Iraqi Training Battalions have been talions (SIBs) and partnering Coalition forces
formed and are fully operational for Iraqi with Iraq’s various energy infrastructure
Army units, allowing the Iraqis to indepen- protection forces.337 The Ministry of Defense
dently train soldiers in sufficient quantities to established 17 SIBs, and U.S.-funded projects
meet force generation and replacement needs. have trained and equipped 11 of those.338
After a 13-week program of basic training, Besides SIBs, the Facilities Protection
soldiers receive additional instruction based Service (FPS) protects stand-alone facili-
on their specific occupations; the length of this ties administered by individual ministries
specific training ranges from three to seven (for example, security guards at a ministry
weeks.334 building). Currently, approximately 150,000
In mid-December, Lt. Gen. Martin FPS personnel are working for the other min-
Dempsey, the MNSTC-I commander respon- istries and 8 independent directorates, such
sible for training and equipping the ISF, noted as the Central Bank of Iraq. DoD reported
that a four-phased training program has been anecdotal evidence that some FPS personnel
launched for the Iraqi Army. Its goal is to are unreliable, and some may even be respon-
provide the members of the Iraqi Army with sible for violent crimes and other illegal activi-
the necessary information and training to be ties.339 As a result, security reforms in 2007 will
better prepared to interact with the local popu- include helping the Iraqis consolidate the FPS
lation.335 under the control of the Interior Ministry.340
Finally, MNSTC-I has trained and equipped This will add to the estimated 17,800 FPS
approximately 28,300 Department of Border personnel already working for the Ministry of
Enforcement (DBE) and Department of Ports Interior.341
of Entry personnel, an increase of 4,400 since
August 2006. Although these two departments Construction
have not made much progress in improving the
TRA ratings of their personnel, the DBE is now Last quarter, SIGIR reported that when all of
in the lead on Iraq’s borders. Thirteen of 14 the prison facilities currently underway are
land points of entry are now functional.336 completed—tentatively scheduled for April
2007—Iraq’s prison capacity is expected to
Infrastructure Security increase by 4,800 beds. Despite this increased
capacity, however, it is estimated that an
The United States has invested more than $320 additional 20,000 beds will still be needed to
million to improve Iraq’s capacity to protect meet Iraq’s correctional facility needs. This
its oil and electric infrastructure, as SIGIR quarter, DoD reported that “pre-trial deten-
reported in Audit 06-038 (September 2006). tion facilities are currently overcrowded, with
Sector Summaries
Democracy,
Security, Education,
Justice Private sector
development
substandard facilities and poor accountability • Last quarter, SIGIR reported that the Iraqi
for persons detained.”342 Ground Forces Command assumed com-
Three training academy projects have been mand and control responsibilities for the
completed, and two are under construction. 8th Iraqi Army Division and the 4th Iraqi
The last training academy is scheduled to be Army Division in mid-September. A third
completed in April 2007.343 But the largest division was transitioned to Iraqi control
training facility, the Baghdad Police College, in early December 2006.347 However, these
has a number of significant infrastructure units still require substantial logistics
problems and may not be ready to transfer on and sustainment support from Coalition
schedule. For additional information on this forces.348
project, see section 3 of this Report. • As of October 2006, 52 of 110 Forward
Operating Bases (FOBs) had been turned
Outcomes of Programs Funded by over to Iraqi control; an additional three
IRRF and ISFF FOBs were scheduled to be transferred by
To better assess the outcomes of IRRF- and January 2007.349
ISFF-funded projects in the security and
justice sector, this section reviews the current The ISF is close to meeting the targeted
transition of security responsibilities to Iraqi number of 325,000 trained and equipped
control and the status of capacity development security forces, and more Iraqi army units are
at both the Ministries of Interior and Defense. taking the lead for counterinsurgency opera-
tions. Attacks, however, continue on Coalition
Transition to Iraqi Control forces, the ISF, and civilians. These attacks
reached record highs in October 2006 and
These transition events occurred this quarter: continued at elevated levels through the end of
• The governorate of Najaf was officially the year.350
transferred to Iraqi control on December Additionally, the Iraqi Army is still unable
20, 2006.344 Two other southern prov- to plan and execute logistics and sustainment
inces—Wassit and Missan—are planned requirements. As a result, the Iraqi Army will
to be transferred by February 2007.345 The continue to rely on Coalition forces for “key
Thi-Qar and Muthanna governorates were assistance and capacity development, including
transferred last quarter. quick-reaction reinforcement as required and
• Pending negotiations between the GOI provision of critical enablers, such as intelli-
and the Kurdistan Regional Government, gence, air reconnaissance, and airlift
security responsibility is expected to be support.”351
transferred to the northern governorates of
Dahuk, Erbil, and Sulaymaniyah.346
Sector Summaries
Security,
Justice
Sector Summaries
Democracy,
Security, Education,
Justice Private sector
development
Sector Summaries
Security,
Justice
and imbed programs have been implemented. security organizations and commands, such as
Force and leadership reorganization and for the FPS and the National Police, processes
reorientations also are continuing. In addi- for vetting and refining personnel roles are
tion to rationalizing the integration of various ongoing.369
Sector Summaries
Democracy,
Security, Education,
Justice Private sector
development
SECTOR REPORT
Healthcare
Figure
Figure 2-45
2-45
HealthCare
Health CareSector
Sectorasasa aShare
ShareofofIRRF
IRRFFunds
Funds
$% of $18.44 Billion
Billions
%Source: IRMO
of $18.44 Weekly Status Report (1/2/2007)
Billion
Source: IRMO, Weekly Status Report (1/2/2007)
4%
Health Care
$.82 Democracy,
Education,
Private sector
development
Figure 2-46
Status of IRRF Funds - Health Care
Healthcare $ Billions
Source: IRMO, Weekly Status Report (1/2/2007);
DoS, Iraq Weekly Status (9/27/2006)
Health Care
$.80
Obligated
Not Expended
$.22
Electricity
$.53
OCT 06
Expended
$.58
DEC 06
Transportation,
Healthcare
Communications
Figure 2-48
Health Care Sector as a Share of FY 2006 CERP Funds
$ Millions Health Care
% of $511.16 Million
Source: Office of the Assistant Secretary of the Army
Financial Management and Comptroller (9/30/2006)
Overview Electricity
Healthcare
Health Care
Electricity
Transportation,
Healthcare
Communications
Health Care
Overview Electricity
Sources: GRD-PCO, response to SIGIR, January 4, 2007 (Hospitals and Model PHCs); DoS Section 2207 Report,
Tab 5 (Selected Metrics), October 2006, p. 15 (all other data).
Table 2-12
Healthcare
Health Care
Electricity
SECTOR REPORT
Transportation,
Healthcare
Communications
STATUS OF transportation
and communications
This section examines the progress of recon- • U.S. projects have completed repairs at
struction in the transportation and commu- 90 of 98 railway stations, but the effects
Overview nications sector. Projects in this sector aim to of these projects are not yet apparent.Electricity
improve transportation systems in Iraq, such as Although the weekly average number of
shipping, railways, roads, bridges, and airports. train trips was 45 during the quarter, only
This sector also includes U.S.-funded telecom- a small number of trains continue to run
munications projects.396 nationwide because of security concerns.
SIGIR makes these observations about • Projects at the Basrah International Airport
progress in the transportation and communi- continue to make progress and are expected
cations sector this quarter: to be completed by September 2007;
• As of January 2, 2007, more than 67% of the projects at other airports have been com-
nearly $800 million in IRRF funds allocated pleted.
to this sector had been expended. Figure • Iraqis continue to subscribe to mobile
2-49 shows sector funding as a portion of phone services at a rapid pace although
Water Oil and Gas
total IRRF allocations; sector projects are the number of landline subscriptions has
currently 83% complete. remained constant. More than 8 million
• As of December 2006, U.S. reconstruction Iraqis now have access to mobile phone
efforts at the Port of Umm Qasr were 86% service.
complete.
Figure 2-50
Figure 2-49 Status of
IRRF Funds -
Figure x-x
Transportation and Communications Sector Status of IRRF and
Transportation Funds - Transportation and Communications
Communications
as a Share of IRRF Funds $ Billions
$ Billions
$ Billions Source:
Source: IRMOWeekly
IRMO, Weekly Status
Status Report
Report (1/2/2007);
(1/2/2007);
% of $18.44 Billion DoS,
DoSIraq
IraqWeekly
WeeklyStatus
Status(9/27/2006)
Report (9/27/2006)
Source: IRMO, Weekly Status Report (1/2/2007)
$.79 Democracy,
Security, Transportation & Obligated
4% Education,
Communications
Justice $.80 Not Expended Private sector
$.25
development
$.51
Expended OCT 06
$.54
DEC 06
Transportation,
Healthcare
Communications
Transportation and
Communications
Overview Electricity
Figure 2-51
Status of IRRF Transportation and Communications Projects
Source: IRMO Rollup (12/30/2006);
USAID Activities Report (December 2006)
Transportation,
Communications
Transportation and
Communications
Overview
Shipping Activities
motors, and security upgrades.400 Finally, 86% Oil tanker loading at Al Basrah Oil Terminal at the Port of Umm Qasr.
This is the major shipping port for Iraq.
of refurbishment work on the Nelcon cranes/
spreader had been delivered, as of December
29, 2006.401 The shipping program is expected Railway Activities
to be finished in February 2007.402
As of September 2006, allocations in this sub-
Outputs of IRRF-funded Shipping Projects sector amounted to $197 million. In October
As a result of U.S.-funded projects, 16 docks 2006, DoS reported that $1.2 million had been
are now in operation; only one dock was func- reallocated to civil aviation for upgrades to
tional at the end of the war.403 Other projects the Basrah International Airport.406 The bulk
focus on enhancing handling capacity and of expenditures in this sector—$131 mil-
operational efficiency, as well as augmenting lion—is for materials and equipment. Most of
security to provide a more reliable flow of this funding has been used to purchase track
cargo in and out of port.404 maintenance equipment, spare parts, tools, and
other materials.407
Outcomes of IRRF-funded Shipping Projects The Communications-Based Train
Although SIGIR did not receive any data on Control System (CBTC) comprises two dif-
the number of ships berthed at the port this ferent contracts. Phase I of this $57.6 million
quarter, Umm Qasr remains a busy port with project valued at $16 million and expected to
long queues of ships waiting to dock. The GOI be completed in September 2007, will provide
is considering constructing a new port with the Iraqi Republic Railroad (IRR) with a train
approximately 100 berths on the Al-Faw pen- control system for tracking movement of all
insula. At the time of this Report, no construc- locomotives on the rail system. The project
tion had begun, and the project remains in the is currently 88% complete.408 To allow the
planning phase.405 contractor to start installation of the backbone
Transportation,
Healthcare
Communications
Transportation and
Communications
Figure 2-53
Overview
Railroad Station Rehabilitation Projects by Governorate
Electricity
Anbar
Total Number of Projects Nationwide: 95
Wassit
Babylon Total Number of Projects by Governorate:
Kerbala
>20
Missan 10-20
Qadissiyah
<10
Thi-Qar No Data
Najaf
Railroad Line
Major Hub Location
Basrah
Muthanna
system, 33 site surveys have been completed contract modification to address the additional
for the communication towers between Mosul work at Baghdad Central Railway Station
and Basrah.409 Phase II will provide a $41.6 was issued on December 22, 2006.412 For the
million Digital Microwave Radio Communica- railway station projects by location, see Figure
tions Network (also referred to as the CBTC-
railroad_map.ai 2-53.
backbone); work has not yet begun.410
In other construction activities, $9 million Outputs of IRRF-funded Railway Projects
worth of upgrades at the Samawa Mainte- U.S. projects have helped bring the number of
nance Shop were completed,411 and a $33,000 operational locomotives to 125; immediately
Transportation,
Communications
Transportation and
Communications
Overview
Transportation,
Healthcare
Communications
Transportation and
Communications
Overview Electricity
Democracy,
Security, Education,
Justice Private sector
development
Baghdad Central Railway Station. SIGIR inspectors reviewed the renovations at this
facility in Summer 2006.
system, and renovations to the airport’s water troops have redeployed there as a result of
system. These projects are expected to be com- British base closures throughout the south.427
pleted by September 2007. The terminal and
tower renovation project is 95% complete, and Roads and Bridges
final completion is scheduled for May 2007.425
Table 2-13 summarizes the work done at the U.S.-funded projects in this subsector will
Baghdad, Basrah, and Mosul airports. U.S.-led not be completed until December 2008. The
reconstruction efforts in this subsector are near projects have focused on small village roads,
completion. several key highways, and bridges.428
Transportation,
Communications
Transportation and
Communications
Overview
this $15.5 million project is scheduled to be Exchange Center is located at the Ministry of
completed in February 2008.430 Construction and Housing,436 and the Ministry
Security,
The Village Roads Program, budgeted at is partnering with the U.S.
Justice Federal Highway
Transportation,
Healthcare
Communications
Transportation and
Communications
Overview Electricity
post office project is expected to be completed and furnished in December 2006.449 A contract
in July 2007.442 When finished, the projects ($2.5 million) for training all CMC staff was
are expected to bring mail service to approxi- also awarded, along with a $4.7 million con-
mately one million Iraqis.443 tract for LAN equipment.450
The Iraqi Telecommunications System
Water Oil and Gas
was allocated $48 million, almost all of which Outputs and Outcomes of
Telecommunications Projects
was obligated by the end of this quarter.444 This
funding is being used to construct a primary After the CMC is restructured, the Ministry of
switching facility at Al-Mamoom and a wire- Communications will likely manage telecom-
less broadband network (WBBN). The munications regulatory functions, operating
Security,
$26 million switch facility was 13% complete, licensing, and the wireless spectrum. The CMC
Democracy,
Education,
Justice as of December 29, 2006, and is estimated to willsector
Private retain responsibility for oversight of the
development
be finished by September 2007.445 Construc- media and broadcast licensing.451 One of the
tion for the Al-Mamoom Telephone Exchange priorities of the Ministry of Communications
facility also started this quarter.446 In late Sep- and CMC is to extend the wireless local loop
tember, O&M support began to supply labor, network in the volatile Anbar governorate.452
materials, equipment, tools, management, Although the United States has provided
transportation, and security to the WBBN some funding for wireless licenses, most of the
Network for 35 Iraqi ministries. The project is development of the mobile phone infrastruc-
currently 50% complete.447 ture has come from the private sector. Mobile
According to the October DoS Section 2207 phone subscribers continue to increase at a
Report, the funding allocation for the Consoli- rapid pace, from 7.2 million last quarter to
dated Fiber Network (CFN) was decreased to
$50 million in October 2006. Those funds were
to be transferred to the health care sector to Current Telephone Subscribers vs. Pre-war Levels
support completion of the Basrah Children’s Pre-war Last Quarter Status, Current Status,
Hospital. However, a contract valued at $1 mil- Outputs Metric Level (2003) as of 9/26/2006 as of 1/2/2007
lion was awarded for the CFN O&M.448 Landline Subscribers 833,000 1,046,027 1,046,027
Mobile Phone Subscribers 80,000 7,214,650 8,712,027
To modernize the Iraq telecommunications
Sources: Pre-war Levels: Economist Intelligence Unit, Country Profile 2005-Iraq, 2005, p.
operations system and support a regulatory 34; International Telecommunication Union, World Telecommunication/ICT Indicators, no
agency, the Communications and Media Com- date, p. A-30. Available online at http://www.itu.int/ITU-D/ict/statistics/at_glance/cellular03.
pdf; last quarter status: IRMO Iraq Weekly Status Report, September 26, 2006, p. 23; current
mission (CMC) was allocated $20 million. Last status: IRMO, Iraq Weekly Status, January 2, 2007, p. 23.
quarter, the CMC headquarters was completed Table 2-14
Transportation,
Communications
Transportation and
Communications
Overview
more than 8.7 million this quarter. The number Figure 2-54 shows the steady rise in cell
of landline telephone subscribers, however, phone subscribers, and Table 2-14 compares
stayed constant this quarter. Currently, there the current number of telephone subscribers
are an estimated 230,000 internet subscribers with pre-war levels.
in Iraq,453 using the State Company for Internet
Water
Services. Most Iraqis gain internet access
through cafes and hotels.
Security,
Justice
Figure 2-54
Figure X
Status of IRRF Funds - Transportation and Communications
Telecommunications Subscribers
Source: IRMO, Weekly Status Report (1/2/2007);
$ Millions
DoS, Iraq Weekly Status (9/27/2006)
Source: IRMO Weekly Status Reports (12/28/2005 - 12/26/2006)
Subscribers (Millions)
10
9
Cell Phone
8
7
6
5
4
3
2
Landline
1
0 Internet
JUL SEP NOV JAN MAR MAY JUL SEP NOV JAN MAR MAY JUL SEP NOV JAN
Transportation,
Healthcare
Communications
Transportation and
Communications
Overview Electricity
Democracy,
Security, Education,
Justice Private sector
development
Contracts
The Iraq Reconstruction Accountability Act contract-level detail. SIGIR will continue to
of 2006 expanded SIGIR oversight to include report on IRRF and ISFF contracts and collect
ISFF, CERP, ESF, and other FY 2006 recon- contract data for CERP and ESF activities.
struction-related funding activities. As a result, To date, approximately $18 billion of the
SIGIR is increasing its efforts to collect con- IRRF has been obligated, and more than $6.5
tract data to account for these funds. billion of ISFF funds has been obligated. At a
This quarter, SIGIR compiled more than contract level, SIGIR can account for 81% of
10,000 contracting actions funded by IRRF and IRRF monies and 98% of ISFF monies.
ISFF, totaling approximately $21 billion in obli- Table 2-15 summarizes IRRF and ISFF
gations and $16 billion in expenditures. The contracting actions recorded in the SIGIR Iraq
initial data collection effort for CERP and ESF Reconstruction Information System (SIRIS)
produced summary-level reports that lacked through January 7, 2007.
Table 2-15
Table 2-16
Table 2-17
Cost-to-complete Data
U.S. agencies executing reconstruction projects USAID. The same situation exists this quarter.
are required by Section 2207 of P.L. 108-106 As of January 20, 2007, SIGIR has not received
to provide quarterly estimates of the cost to the PAR for the quarter ending December 31,
complete each IRRF-funded project. Cost- 2006. An IRMO official told SIGIR that only
to-complete (CTC) data helps identify the GRD-PCO will again provide data because
funding status of all projects, both those that both MNSTC-I and USAID have nearly
may exceed their budget and those that may be finished their IRRF-funded projects, and the
completed under budget, and allows manage- remaining projects are being implemented
ment to prioritize activities. by GRD-PCO. For example, for IRRF-funded
In past Quarterly Reports, SIGIR high- construction projects as of January 2, 2007,
lighted CTC information from Project Assess- all but $2.38 billion of the $10.27 billion had
ment Reports (PARs). However, last quarter been expended. Of this, $2.24 billion belongs
DoS reported CTC data only for projects to GRD-PCO projects. Only $120 million in
managed by GRD-PCO; no CTC data was USAID projects remains to be expended.
provided for projects managed by MNSTC-I or
Figure 2-55 provides an overview of all the initiation of hostilities. On September 29,
sources of Iraq reconstruction funding. More 2006, the President signed the most recent
details are provided in Appendices G and H. appropriation for the Department of Defense
(P.L. 109-289). This included $1.7 billion in
U.S. Appropriated Funding ISFF funding and $375 million for CERP. His-
Since the 2003 conflict began, Congress has torically, Congress has also included additional
passed eight bills that provided $38.23 bil- funding in each year’s Department of State/
lion in Iraq reconstruction funding, excluding Foreign Operations bills. (FY 2007 appropria-
$40 million in ESF funding from P.L. 108-7 tions had not yet passed at the time of printing
counted toward reconstruction efforts before this Report.)
Figure 2-55
Sources of Iraq Reconstruction Funding—$103.924 Billion
$ Billions
Public Law 108-11 (April 2003) a. In accordance with P.L. 109-440, SIGIR has oversight of any U.S. funds made available for FY 2006 for the
recontruction of Iraq. When added to IRRF funding, this amounts to approximately $33 Billion.
Public Law 108-106 (November 2003) b. Congress provided DoD with authorization for drawdown authority for these funds.
Public Law 109-148 (January 2005) c. $75 Million is excluded under CPA for Special Inspector General for Iraq Reconstruction, which is
captured under "Other Reconstruction Accounts."
Spans Multiple Public Laws d. Where Iraq-only appropriations unavailable, SIGIR assigned 85% for Iraq based on historical trends.
e. Includes August 11, 2004 transfer of $86 Million cash from Central Bank of Iraq for CERP at the
Non-U.S. Appropriated Funds authorization of the Ministry of Finance.
f. Includes pledges for reconstruction only, not humanitarian aid or other types of assistance.
Over the past three years, more than half New SIGIR Mandate
of U.S. reconstruction funding has come from On December 20, 2006, the President signed
IRFF 1 and IRRF 2, created under P.L. 109-11 P.L. 109-440, the Iraq Reconstruction Account-
and P.L. 108-106, respectively. U.S. agencies ability Act of 2006. (For additional details,
involved in the execution of reconstruction see Section 3, Legislative Update). Under P.L.
funding include DoD, DoS, USAID, and 109-440, the IRRF is defined as including any
others. Projects highlighted earlier in this sec- U.S. funds made available for FY 2006 for
tion range from infrastructure development to the reconstruction of Iraq, regardless of how
refugee and migration assistance. The appro- they are designated. Figure 2-56 identifies the
priated funds are highlighted in Table 2-18. primary funding activities associated with the
new mandate, including ISFF, CERP, ESF, and
others, representing nearly $12 billion in addi-
tional oversight. SIGIR now oversees $32.96
billion in reconstruction funding.
Figure 2-56
Summary of SIGIR Oversight
$32.96 Billion
Source: SIGIR Analysis of U.S. Appropriated Funds
Other $1.35
P.L. 109-102, P.L. 109-148
CERP $.75 P.L. 109-234
P.L. 109-148
P.L. 109-234 IRRF 1 $2.48
P.L. 108-11
ISFF $8.40
P.L. 109-13
P.L. 109-234
IRRF 2 $18.44
P.L. 108-106
ESF $1.55
P.L. 109-234
P.L. 109-102
PUBLIC LAW # P.L. 108-7 P.L. 108-11 P.L. 108-106 P.L. 108-287 P.L. 109-13 P.L.109-102 P.L.109-148 P.L.109-234 P.L.109-289
DATE OF ENACTMENT 02/20/03 04/16/03 11/06/03 08/05/04 05/11/05 11/14/05 12/30/05 06/15/06 09/29/06
Iraq Relief and Reconstruction Fund (IRRF 2) $18,439,000,000 $18,439,000,000
Iraq Security Forces Fund (ISFF) $5,391,000,000 $3,007,000,000 $1,700,000,000 $10,098,000,000
Iraq Relief and Reconstruction Fund (IRRF 1) $2,475,000,000 $2,475,000,000
Commander’s Emergency Response Program
$140,000,000 $718,000,000 $408,000,000 $345,000,000 $375,000,000 $1,986,000,000
(CERP)
Economic Support Fund (ESF)a $40,000,000 $10,000,000 $60,390,000 $1,485,000,000 $1,595,390,000
Security Forcesc
Natural Resources Risk Remediation Fund
$489,300,000 $489,300,000
(NRRRF)
d
a
$40M from FY 2003 ESF base account that was not reimbursed; $10M from P.L. 108-11
b
Excludes $75M for Special Inspector General for Iraq Reconstruction under P.L. 108-106
c
Congress provided DoD with authorization for drawdown authority for these funds
d
As identified in GRD bi-weekly reports and P.L. 109-234
e
Where Iraq-only appropriations unavailable, based on historical trends SIGIR split 85% for Iraq and 15% for Afghanistan
f
Congress provided funding for PCO in other appropriations bills; more details will be available in future SIGIR reports
g
Includes Iraq Reconstruction Management Office salaries and expenses, mission travel, public diplomacy programs, and other operating expenses related to reconstruction.
h
CPA operating expenses under P.L. 108-106
Table 2-18
Sector Summaries
Original Additional
Madrid Pledge Pledges since
Donor October 2003 Madrid Conference Total Pledges
Australia $45,590,974 $81,042,221 $126,633,195
Austria 5,478,165 5,478,165
Belgium 5,890,500 5,890,500
Bulgaria 640,000 640,000
Canada 187,466,454 187,466,454
China 25,000,000 25,000,000
Cyprus 117,810 117,810
Czech Republic 14,659,023 14,659,023
Democratic Governance Thematic Trust Fund 100,000 100,000
Denmark 26,952,384 40,000,000 66,952,384
Estonia 82,467 82,467
Finland 5,890,500 5,890,500
France 32,288 32,288
Germany 10,000,000 10,000,000
Greece 3,534,300 3,534,300
Hungary 1,237,005 1,237,005
Iceland 2,500,000 2,500,000
India 10,000,000 10,000,000
Iran 5,000,000 5,000,000 10,000,000
Ireland 3,534,300 3,534,300
Italy 235,620,020 235,620,020
Japan 4,914,000,000 50,000,000 4,964,000,000
Jordan 75,000 75,000
South Korea 200,000,000 200,000,000
Kuwait 500,000,000 65,000,000 565,000,000
Lithuania 30,000 30,000
Luxembourg (EURO) 2,356,200 2,356,200
Malta 27,000 27,000
Netherlands 9,424,801 9,424,801
New Zealand 3,351,975 990,000 4,341,975
Norway 12,867,617 12,867,617
Oman 3,000,000 3,000,000
Pakistan 2,500,000 2,500,000
Qatar 100,000,000 100,000,000
Saudi Arabia 500,000,000 500,000,000
Slovenia 419,382 419,382
Spain 220,000,000 2,380,000 222,380,000
Sri Lanka 75,500 75,500
Sweden 33,000,000 33,000,000
Original Additional
Madrid Pledge Pledges since
Donor October 2003 Madrid Conference Total Pledges
Turkey 50,000,000 50,000,000
United Arab Emirates 215,000,000 215,000,000
United Kingdom 452,326,416 190,000,000 642,326,416
United States 10,000,000 10,000,000
Vietnam 700,000 700,000
Subtotal $7,807,467,293 $445,425,009 $8,252,892,302
European Commission 235,620,000 669,680,000 905,300,000
Subtotal $8,043,087,293 $1,115,105,009 $9,158,192,302
International Financial Institutions
IMF (low range) 2,550,000,000 2,550,000,000
World Bank (low range) 3,000,000,000 3,000,000,000
Islamic Development Bank 500,000,000 500,000,000
Subtotal $5,550,000,000 $500,000,000 $6,050,000,000
Note: Data not formally reviewed, audited, or verified. Pre-Madrid pledges for humanitarian assistance are not included in this table.
Table 2-19
Australia Denmark
* Rotating members
As most U.S. reconstruction funding is
Table 2-20
expended, the Iraqis and international donors
have become more aware of the need to
target donor funds with more planning and Development Programme (UNDP), con-
precision. Improving donor coordination tinues to improve as an assistance manage-
also continues to be a priority for the United ment tool to track all donor assistance. DAD
States; the Baghdad Coordination Group and shows the progress of pending and ongoing
sector working groups continue to meet with donor-supported projects and is available
increasing participation by Iraqi leadership. online at www.mop-iraq.org. Although the
The Ministry of Planning’s Donor Assis- database is not complete, more projects are
tance Database (DAD), supported by the UN added each quarter, and the Ministry of Plan-
ning is becoming more adept at using it. As • $45 million credit for two oil pipelines con-
of December 31, 2006, DAD included 17,430 necting Iran and Iraq
projects, totaling $17.13 billion, associated • $10 million grant to IRFFI460
with 20 donors. Against these projects, $14.78 • $1 billion line of credit461
billion had been committed, and $9.92 billion
had been expended. Although these numbers Japan
are not verified or audited, DAD lists 16,941 Japan has pledged and expended more assis-
U.S. projects, totaling $13.61 billion. Against tance to Iraq than any other country except
these projects, DAD reflects that the United the United States. By May 2005, Japan had
States had committed $11.99 billion and completely obligated its Madrid pledge of $1.5
expended $8.13 billion.458 billion plus an additional $50 million.
Japan has now committed approximately
Major Bilateral and $1.6 billion of the promised $3.5 billion in
Multilateral Programs concessional loans. In October 2006, Japan
announced a loan for six projects totaling $863
Iran million:
The economic ties between Iran and Iraq have • $259 million to a development project in
grown stronger after the Iranian Foreign Min- the port sector
ister’s visit in May 2006. In a joint statement, • $81 million to a loan program in the irriga-
the two countries referred to their deep-rooted tion sector
historical, cultural, and religious ties and called • $315 million to the Al-Mussaib Thermal
for promotion of bilateral ties in all fields based Power Plant rehabilitation project
on the principle of non-interference in each • $28 million to Samawah bridges and roads
other’s internal affairs and commitment to construction projects
bilateral agreements. The Iran-Iraq Coopera- • $20 million for engineering services to
tion Headquarters was created to facilitate eco- upgrade the Basrah Refinery
nomic cooperation. The governors general of • $160 million to the Khor Al-Zubair Fertil-
two border provinces in Iran and Iraq signed izer Plant rehabilitation project
a memorandum of understanding stating that
the Iranian Oil Ministry would export one In December 2006, the Japanese govern-
million liters of oil and its by-product to Iraq ment announced a loan for two additional
daily for three months. The Iranian Ministry projects to upgrade Iraq’s oil and electricity
of Oil is providing a credit to build oil pipe- sectors totaling $738 million—$447 million to
lines to move oil products between the two construct a pipeline to export oil from Basrah
countries.459 Direct financial support from Iran and $291 million to improve facilities for elec-
includes: tricity transmission.462 The Foreign Ministry
said the 40-year loan would be made through water improvements in the south, governance
the state-funded Japan Bank for International and institution-building in Baghdad and the
Cooperation. south, support for civil society and political
participation, and capacity building in the
United Kingdom Ministry of Interior. DFID funds a World Bank
The United Kingdom (UK) is one of the first advisor in Baghdad to speed up engagement in
major donors to fully expend all of its assis- oil and electricity issues and to help the GOI
tance to Iraq since 2003 ($920). This includes develop a plan for the energy sector.
its Madrid pledge of $452 million and humani-
tarian assistance of $468 million. An addi- European Commission
tional pledge of $190 million has recently been The European Commission (EC) has pledged
announced, bringing total UK assistance to approximately $905 million, of which $779
$1.11 billion. Table 2-21 shows UK expendi- million was for reconstruction assistance.
tures by program. Twenty-four percent of EC funding has been
The UK also has a quick-impact program used to support education initiatives; 14% has
($59 million) financed by the Ministry of supported health programs; 13% has supported
Defense, which has a similar mission to that of poverty-reduction initiatives; 21% has sup-
CERP. ported the electoral/constitutional processes;
The Department for International Develop- and the remaining 28% has supported capacity
ment’s (DFID) program for 2006-2007 focuses building.
on economic reform, delivering power and The $252 million program announced for
FCO Programmes 64
Total $1,000
Table 2-21
2006 focuses on improving the quality of life of • The remaining three, valued at $12 million,
the Iraqi people by funding programs to: are capacity building and technical assis-
• support basic services ($223.65 million) tance activities implemented by the World
• provide a technical assistance facility to Bank.
provide capacity building ($7.56 million) • Two World Bank projects financed by the
• support the Iraqi refugees inside Iraq ($12.6 ITF—the First Capacity Building Project
million) and the Emergency Textbook Provision
• enhance the capacity of the Trade and Cus- Project—are completed and closed.
toms Administration ($8.19 million)
Figure 2-57 reflects the status of World Bank
The Trade and Customs Administration ITF funds through December 31, 2006.
capacity-building initiative will support the The World Bank has approved three
EC-Iraq Trade and Cooperation Agreement. projects, totaling $275 million, through its
This agreement aims to improve the trade International Development Association loans.
arrangements between Iraq and the EU, cov- The third was signed on December 12, 2006,
ering a wide range of issues, including trade to support hydropower in Iraq. The Board of
in goods, services, measures to encourage Executive Directors approved a credit of $40
investment, customs, intellectual and indus- million for the rehabilitation of two hydroelec-
trial property rights, and public procurement tric power stations in the Kurdistan region.465
rules.463 Figure 2-58 shows international donor
contributions to the IRFFI, as of December 31,
World Bank 2006.
In January 2004, donors authorized the World
Bank to administer the World Bank ITF, which
Figure 2-57
began receiving funds in March 2004. Table World Bank - International Trust Fund
$ Millions
2-22 summarizes WB ITF and UNDG ITF Total Commitments $458.2 Million
allocations to IRFFI. Source: www.irffi.org, (12/31/2006)
Source: www.irffi.org
a
Iran has pledged $10 million, but funds have not been allocated between WB ITF and UNDG ITF.
Table 2-22
Figure 2-58
International Donor Contributions to IRFFI
Source: www.irffi.org, (12/31/2006)
All Other
Countries
3.6% Australia
Commitment
10.3% Donor $Millions
4.4% Spain
European Commission $150.2
European Japan $130.6
Committed to Commission 4.9% Canada
IRFFI World Bank 32.8% United Kingdom $71.4
$458.2 Million
Canada $22.3
15.6% Spain $20.0
United Kingdom
Australia $16.4
Japan 28.5%
All Others $47.3
Total $458.2
Committed to
IRFFI UN
$1.1 Billion
All Other
Countries
1.8% Australia Commitment
11.1% Donor $Millions
4.2% Spain
European Commission $471.4
4.1% Canada Japan $361.0
European United Kingdom $55.5
Commission 4.9% United Kingdom Canada $46.4
41.9%
Spain $47.5
Australia $20.1
Japan 32% All Others $124.5
Total $1,126.4
Figure 2-59 reflects the status of UNDG ITF International Monetary Fund
funds through December 31, 2006. International Monetary Fund (IMF) funding
Donors can earmark their contributions to remains available for balance of payments sup-
seven different clusters within the ITF. Infra- port:
structure rehabilitation (22%) and support • $297 million from the Emergency
for the electoral process (20%) are the most Post-conflict Assistance package
popular clusters among donors. Other popular • $475 million from the Stand-By
sectors among donors and Iraqis include agri- Arrangement (SBA)
culture, education, and health. The UN website
(www.irffi.org) posted $490 million in contract As of December 2006, Iraq had not drawn
awards: 17% to Iraq, 14% to Japan, 11% to the against any of its SBA funds.
UK, and 10% to China. U.S. firms account for
2% of these contracts. Islamic Development Bank
Figure 2-60 shows the UNDG ITF by UN The Islamic Development Bank (IDB) will
cluster. provide a soft loan of $12.9 million for con-
Figure 2-60
UNDG Iraq Trust Fund
Total Commitments $1.1 Billion
Source: www.irffi.org
(12/31/2006)
$ Millions
structing and furnishing 15 elementary schools only about 20% of Iraq’s $6 billion 2006 capital
and a technical assistance grant for capacity budget has been spent.
building in the Iraqi Ministry of Education. The 2007 budget has been approved by
The loan is part of a $500 million program the Council of Ministers and has been sub-
launched by IDB for supporting the recon- mitted to the Council of Representatives. Total
struction and rehabilitation effort in Iraq.466 revenues for the proposed Iraqi 2007 budget
are $33.4 billion, and budgeted expenditures
IRAQI FUNDS are $41 billion. The deficit of $7.6 billion will
One of the GOI’s commitments under the be financed by funds carried forward from
Compact is to ensure that legislation, regula- previous years. Operating expenditures will
tion, systems, and processes are in place that increase by 18.7% to $30.7 billion over 2006
will allow efficient and effective disbursement budgeted amounts. This amount includes $7.3
of its own budget. Overall, the GOI was able billion for security, a 35% increase from 2006.
to spend 65% of its 2006 budget. Table 2-23 Capital expenditures will increase by 22% to
shows budget execution by ministry. $10 billion. Special initiatives totaling $600
Iraqi ministries struggle to expend their million include:
capital budgets quickly. The president of the • DDR (disarmament, demobilization, and
Iraqi Board of Supreme Audit reported that reintegration, $150 million)
Table 2-23
Anticorruption update
Corruption continues to limit the ability of the commission permanent status or to dissolve
GOI to manage reconstruction efforts and key it and let the ministry IGs audit their own
areas of economic policy. The Iraqi Ministry agencies.
of Oil estimates that Iraq loses $700 million Meanwhile, the head of the CPI has been
of revenue each month because of oil smug- the subject of corruption investigations by the
gling.470 Transparency International ranks Iraq Parliamentary Anticorruption Committee.472
161st of 163 countries measured. This ranking, The CPI has nonetheless pushed for the
1.9 on the Corruption Perceptions Index, prosecution of several former ministers and
indicates high levels of perceived corruption.471 uncovered corruption in the Interior Ministry;
SIGIR’s October 2006 Report discussed ways 3,000 employees were dismissed in October
that Iraq, the United States, and international for corruption and sectarianism.473 Targets
donors were helping to combat corruption, have included former Ministers of Defense and
including new commitments and benchmarks Electricity.
for key actions that the Iraqis would agree to as CPI’s current investigations include the
part of the Compact. The U.S. Mission inter- quality of food purchased by the Ministry of
agency Anticorruption Working Group helped Trade for monthly rations, the disappearance
the GOI identify anticorruption initiatives of petroleum products under the supervision
for the Compact and will help Iraq imple- of the Ministry of Oil, the lack of progress
ment some of the key anticorruption priorities refurbishing the railroad system, and miscon-
outlined in the Compact. The U.S. Mission duct by 451 police officers in the Ministry of
is providing an advisor for each of the three Interior.
Iraqi anticorruption institutions—the Com-
mission on Public Integrity (CPI), the Board Board of Supreme Audit
of Supreme Audit (BSA), and the ministry The UN is coordinating with international
Inspectors General (IGs). audit boards to train BSA staff according to
modern audit systems.474 Members of the Arab
Commission on Public Integrity Organization of Supreme Audit Institutions
The future of the CPI is uncertain. It was cre- (ARABOSAI) would contribute to training the
ated by the Coalition Provisional Authority, BSA Iraqi staff as part of a plan created by the
but never written into Iraqi law. Iraqi legisla- ARABOSAI training committee when it met in
tors have stalled a vote on whether to give the Tunisia in January 2007.
SIGIR Audits
SIGIR Inspections
SIGIR Investigations
SIGIR Hotline
SIGIR Lessons Learned Initiative
Legislation
3
section
sigir oversight
SIGIR Audits
From November 1, 2006, to January 30, 2007, • a review of U.S. government plans and
SIGIR completed eight audits, which resulted programs for capacity development in the
in nine audit products. As of January 30, 2007, Government of Iraq (GOI) ministries
SIGIR has issued 82 audit products. This
quarter, SIGIR audits addressed a wide range SIGIR also has 16 ongoing audits. At least 8
of issues: more are planned to start next quarter. SIGIR
• a review of a Department of State (DoS) performs audit work under generally accepted
task order for Iraqi police training, training government auditing standards.
support, and the construction of several Details on SIGIR audits are presented
training support camps throughout this Report:
• an update on the status of medical equip- • For titles of the nine audit products issued
ment purchased to support the delayed during this reporting period, see Table 3-1.
Primary Healthcare Center (PHC) project • For information on all SIGIR audit work
and an assessment of other non-construc- completed as of January 30, 2007, and for
tion contracts supporting the PHC project the full text of all final audit products, see
• a follow-up on 17 recommendations that the SIGIR website: http://www.sigir.mil/.
SIGIR made in previous audit reports on
the control and accountability for contracts, This quarter, SIGIR continues to note
grants, and cash transactions using the problems caused by the lack of a single orga-
Development Fund for Iraq (DFI) nization responsible for the overall Iraq relief
• a review of government property manage- and reconstruction program. Progress con-
ment controls by the U.S. Agency for Inter- tinues to be hampered by the inability of U.S.
national Development (USAID) and its government agencies to fully cooperate in
contractor, Bechtel National, Inc. (Bechtel), conducting relief and reconstruction activi-
for contract SPU-C-00-04-00001-00 ties. For example, SIGIR’s ministerial capacity
• a review of improper IRRF obligations, the development review identified that there is
circumstances related to these obligations, no integrated plan for capacity development.
and subsequent actions taken or planned Most ongoing capacity-development activi-
regarding the use of these funds ties seem to be internally driven. SIGIR first
• a review of internal controls related to identified the need for an integrated capacity-
disbursements of IRRF apportioned to the development plan in October 2005, but after
DoS, Department of Defense (DoD), and 15 months of meetings, no plan has emerged.
USAID Without a plan, it is difficult for the many
• a report on security costs as identified by organizations involved to coordinate and
design-build contractors on IRRF projects prioritize activities, and no one office or person
Table 3-1
is clearly in charge of the overall U.S. govern- International Narcotics and Law Enforcement
ment capacity-development program. During Affairs (INL) and the DoS Office of Acqui-
the quarter, management performance by sition Management resulted in nearly $44
the IRRF-implementing agencies was mixed. million of potential unnecessary expenditures.
SIGIR found that USAID and its contractor, Also, $36.4 million in weapons and equipment
Bechtel, exercised adequate management con- could not be accounted for, including armored
trol over U.S. government-furnished property vehicles, body armor, and communications
purchased in support of its construction activi- equipment. SIGIR reported that the Joint Area
ties. SIGIR also found good management con- Support Group-Central (JASG-C) and the
trols over the payment of invoices for DoD and Joint Contracting Command-Iraq/Afghanistan
USAID. However, SIGIR identified problems (JCC-I/A) have made limited progress imple-
in DoD and DoS accounting and protection of menting recommendations made in previous
U.S. property investments, questionable obliga- SIGIR audits for improving accountability over
tions by the U.S. Army Corps of Engineers- the DFI. SIGIR also reported on security costs
Gulf Region Division (GRD), and the failure incurred by nine large design-build contractors
of DoS to provide SIGIR access to financial engaged in IRRF projects.
records during this assessment. During the quarter, SIGIR also assisted in
Other significant reviews during this the transfer of DFI records held by the United
quarter include a joint SIGIR/DoS OIG review States to the GOI. SIGIR also provided two
of a DoS contract for police training and auditors to assist in a procurement fraud inves-
training support. SIGIR reported that poor tigation in Kuwait.
contract administration by the DoS Bureau for
SIGIR chaired two meetings of the Iraq • SIGIR performance audits also evaluate the
Accountability Working Group (IAWG) on economy, efficiency, and effectiveness of
November 6, 2006, and January 23, 2007. Iraq relief and reconstruction projects.
Organization representatives, fellow auditors,
and internal management evaluators met to SIGIR audits generally have four distinct
discuss ongoing efforts and emerging issues. phases:
SIGIR has one review underway with the sup- • engagement planning to evaluate the
port of DoS OIG. In addition, SIGIR is coor- adequacy and effectiveness of controls built
dinating several other efforts with the various into a project or program and establish
accountability organizations, including the detailed plans for fieldwork in a design
Multi-National Force-Iraq (MNF-I) and the matrix
Multi-National Security Transition Command- • fieldwork to conduct detailed examina-
Iraq (MNSTC-I). tions, tests, and analyses to collect appro-
SIGIR continues to apply a balanced priate and adequate data
approach to provide insight, foresight, and • reporting of results and recommendations
oversight through audit and non-audit activi- • audit closure and follow-up on the imple-
ties to assist executing organizations in Iraq mentation of the audit recommendations
and those who support these organizations
outside Iraq. SIGIR communicates final audit findings
• SIGIR’s insight efforts advise the U.S. and recommendations resulting from the audit
reconstruction leadership on management engagement to the responsible program man-
issues, with the emphasis on creating an agers and senior management. SIGIR issues
environment of accountability, rule of law, audit reports or other IG communications,
and public trust in Iraq. depending on the complexity and significance
• SIGIR’s foresight efforts continue to focus of the issues involved.
on end-state issues, such as cost to com- The implementation of audit recommenda-
plete U.S. projects, transition of U.S.-funded tions is crucial. SIGIR auditors follow up on
projects to the GOI, sustainment of U.S.- all accepted recommendations until they are
funded projects and programs, and capacity fully implemented. Recommendations that are
building within the GOI and civil society. not accepted are resolved through the appli-
• SIGIR’s oversight efforts, an IG’s tradi- cable resolution process of each organization,
tional focus, address the ability to obtain normally at the Deputy level. Auditors seek the
maximum return on the U.S. taxpayer cooperation of program managers, who are
investment and promote transparency and expected to ensure compliance.
accountability of the U.S. administration for This quarter, as congressionally man-
any Iraqi resources used. dated by the Inspector General Act of 1978,
as amended, SIGIR includes its semiannual internal controls, and what is the salvage
report on the status of the implementation of value for unused assets?
SIGIR recommendations. SIGIR reports on the • What is the cost and program impact of the
recommendations closed since the last semian- stop-work order affecting the construction
nual Report and the recommendations that of police training facilities at the Adnan
remain open by report in Table 3-2. Palace?
• What is the status of construction of facili-
Final Audit Products ties to support provincial police training
Review of DynCorp International, LLC programs?
Contract Number S‑LMAQM-04-C-0030,
Task Order 0338, for the Iraqi Police
To respond to the audit objectives, SIGIR
Training Program Support
SIGIR 06-029, January 2007 structured the report in three sections:
• cost incurred under Task Order 0338
Introduction. This report discusses the results • construction of the Adnan Palace residen-
of SIGIR’s review of Task Order 0338, part tial camp and regional camps
of a DoS contract (S‑LMAQM-04-C-0030) • contracting and contract management
awarded to DynCorp International, LLC (Dyn-
Corp). The task order was to provide training The audit focused on supplies and ser-
services for international police liaison officers, vices provided under Task Order 0338, which
training support equipment, construction of a represented the bulk of spending under the
residential camp on the Adnan Palace grounds task order. Within supplies and services, SIGIR
in Baghdad to house training personnel, and narrowed the focus on the work to be done
construction of five regional camps in Iraq. and items to be provided for the $51.6 mil-
The report focuses on actions taken to estab- lion residential camp and the $36.4 million
lish the residential camp and the performance of equipment to be procured. SIGIR did not
of unauthorized work by DynCorp. This include an assessment of the regional camps
review was conducted jointly with the DoS in this review, but they will be addressed in
OIG. SIGIR’s continuing review of Task Order 0338,
Objectives. The objectives of this audit were DynCorp contract S‑LMAQM-04-C-0030, and
to answer these questions: other INL expenditures of IRRF.
• What were the costs associated with the Findings. Poor contract administration
subject contract Task Order 0338, including by INL and the DoS Office of Acquisition
amounts obligated and expended, potential Management resulted in millions of dollars
liabilities, and controls over these costs? put at unnecessary risk, and property that
• What is the status of property purchased cannot be accounted for that was acquired
under Task Order 0338, including related under Task Order 0338. Specifically, between
July 2004 and June 2006, DoS paid approxi- for the residential camp, as of September
mately $43.8 million for manufacturing and 2004. DynCorp issued the subcontract for
temporary storage of a residential camp that the residential camp to Corporate Bank on
has never been used, including $4.2 million August 15, 2004, and Corporate Bank in
for unauthorized work associated with the turn issued a subcontract to Cogim SpA on
residential camp. In addition, DoS may have September 1, 2004. According to an INL
spent another $36.4 million for weapons and internal review report, the manufacturing
equipment, including armored vehicles, body had actually begun in May 2004—more
armor, and communications equipment that than three months before the subcontract
cannot be accounted for because invoices were for the residential camp project was issued.
vague and there was no backup documentation In addition, on July 30, 2004, DynCorp
or property book specific to items purchased submitted an invoice to DoS that included
under Task Order 0338. $18 million in mobilization fees for the
A key part of the task order was the manu- residential camp for the period of April 17,
facture and installation of a residential camp 2004, to May 16, 2004. However, it is not
to house 1,040 police training and advisor clear what costs were attributable to the
personnel with associated facilities, including mobilization or whether these costs were
dining and office space. To accomplish this, a prepayment because DynCorp did not
DynCorp issued a subcontract valued at $55.1 issue a subcontract to Corporate Bank until
million to Corporate Bank Financial Services August 15, 2004. According to the DoS
(Corporate Bank) on August 15, 2004. On contracting officer, when DynCorp issued
September 1, 2004, the manufacture of 1,048 the stop-work order to Corporate Bank in
trailers was subcontracted with an Italian September 2004, DoS was told by DynCorp
manufacturing firm, Cogim SpA, for $47.1 that the residential camp had been com-
million. Because of security concerns, INL pleted.
officials decided to cancel the residential camp • SIGIR found no information to indicate
project in September 2004. On or about Sep- that any INL official or the Contracting
tember 23, 2004, the DoS contracting officer Officer Representative (COR) questioned
communicated to DynCorp INL’s decision not why DynCorp submitted an invoice for
to proceed. DynCorp, in turn, issued a stop- mobilization fees for the residential camp
work order to Corporate Bank on September before it had subcontracted for the manu-
25, 2004. facture of the trailers. Nor did INL seek
Based on the review, SIGIR identified these to determine the actual status of the work
concerns about the residential camp: when DynCorp was notified not to pro-
• SIGIR found contradictory information on ceed, given the $18 million paid to Dyn-
the actual status of trailer manufacturing Corp for mobilization fees for the residen-
tial camp. Rather INL relied on DynCorp’s residential camp to outside of the Adnan
representations. As such, the true status of Palace grounds, manufacturing an addi-
the manufacturing effort was unknown as tional 20 VIP trailers, and constructing an
of the issuance of the notice. Olympic-size swimming pool on the palace
• INL appears to be making some recent grounds.
progress after about two years of attempting
to find a resolution for the use of the resi- Weak and sometimes non-existent con-
dential camp trailers. In May 2006, SIGIR tract administration was the root cause of
communicated its concern to the COR the problems that SIGIR identified with work
about moving the residential camp compo- performed under Task Order 0338. Review
nents from one storage location to another of the actions taken by the DoS contracting
before formalizing plans for their ultimate officer and INL COR during the performance
use. Notwithstanding these concerns, the period of Task Order 0338 indicated that
COR moved the trailers to the Baghdad neither performed key responsibilities assigned
International Airport (BIAP). On June 24, by the DoS Foreign Affairs Handbook for
2006, DynCorp entered into a subcontract contract administration. For example, the INL
to obtain open and covered storage and COR was responsible for accepting contractor
security for the trailers at the BIAP for an work, informing the contracting officer of
initial period of three months to two years. performance failure, and maintaining a COR
On September 7, 2006, INL told SIGIR file. However, SIGIR found no evidence that
that it planned to use the trailers to house the COR performed or properly documented
INL’s personnel, but faced complications any of these activities. Further, for more than a
due to limited availability of land and high decade, the INL COR assigned to Task Order
demand that was driving up costs in the 0338 has also been responsible for monitoring
area near BIAP. As of January 18, 2007, INL other DynCorp police contracts and task
appears to be making progress in resolving orders for INL. Many of the problems identi-
the use of the trailers in that discussions are fied by SIGIR were associated with this COR’s
underway for an alternative use of the trail- performance on the task order and had been
ers at the Baghdad Embassy. identified and previously reported in a March
• Of the approximately $43.8 million spent 2002 DoS OIG report on U.S. police support in
on the residential camp, $4.2 million Bosnia.476
was for work that was not contractually The Foreign Affairs Handbook does not
authorized. The Iraqi Ministry of Interior address the maximum length of time personnel
directed the work, but DoS, as the con- should serve as a contracting officer or COR
tracting agency, never authorized it. The for the same contractor. In July 2006, corre-
unauthorized work included relocating the spondence on contract management477 pro-
vided to the House and Senate Armed Services accepting contractor work, did not ensure that
Committees and the Government Account- DynCorp maintained proper inventory control
ability Office (GAO) noted that tenure can records or maintain the records personally for
become a vulnerability if the control environ- the $36.4 million of proposed equipment that
ment in an organization is weak. The results of was to be procured under this task order.
SIGIR’s review of Task Order 0338 suggest that, Management Control Weaknesses. During
at least for this task order, the control environ- the audit, SIGIR identified management
ment has been weak. However, although there control weaknesses in the timely issue of task
have been several DoS contracting officers for order modifications, the process of docu-
Task Order 0338 over the past two years, the menting the review of contractor invoices,
INL COR has been assigned to this and other and the administration of the task order.
DynCorp contracts/tasks orders since 1994—a This report includes recommendations to
12-year period. strengthen internal controls needed to improve
In December 2005, INL issued an asset DoS contracting and administration of the task
verification report documenting that Dyn- order. Further, because INL reported similar
Corp could not provide a complete property conditions in its December 2005 INL asset ver-
book and backup documentation for items it ification report, SIGIR has no reason to believe
purchased for the U.S. government. The report that the management internal control weak-
concluded: nesses in this task order are isolated. Therefore,
• DynCorp invoices were frequently ambigu- SIGIR intends to continue the review of Task
ous and lacked the level of detail necessary Order 0338 and will announce a full review
to identify what was procured. of contract S-LMAQM-04-C-0030 and other
• DynCorp did not maintain a complete list expenditures by INL in Iraq.
of items procured. Management Actions. According to the
• DynCorp did not establish policy guidance DoS OIG, in November 2005, INL’s Principal
or accountability procedures. Deputy Assistant Secretary met with the DoS
Inspector General and subsequently with DoS
The report also concluded, “INL cannot Investigations to discuss concerns of potential
determine if the bureau received what it paid fraud with Task Order 0338. Specifically, INL
for.” SIGIR’s review found that the invoices disclosed that DynCorp had billed INL for 500
for Task Order 0338 lacked the level of detail trailers for the residential camp related to this
to determine what was procured and that the task order that may not have been manufac-
U.S. government or DynCorp did not maintain tured or completed at the time of billing. The
a complete list of items procured under Task preliminary investigation conducted by DoS
Order 0338. Further, SIGIR found that the investigations revealed that INL contacted DoS
COR, although responsible for inspecting and Office of Acquisition Management in October
2005 to discuss its concerns regarding the DynCorp task orders, including Task Order
number of trailers actually received and billed 0338. As of January 18, 2007, the DCAA
under this task order. DoS and SIGIR worked had not responded.
jointly on this investigation, and SIGIR has • On November 2, 2006, INL appointed an
taken the lead and the investigation is ongoing. overall COR for the DynCorp contract.
Beginning in 2005, according to INL senior • In January 2007, INL identified an Iraq
officials, INL initiated a number of steps to in-country COR. This person will be on
strengthen its contract and asset management duty once all human resource actions are
across the Bureau. INL senior managers pro- finalized.
vided the following information: • In January 2007, INL began a review to
• A series of internal reviews were under- complete contract files, which consisted
taken concerning property controls and an of contracts, task orders, and pertinent
inventory of the residential camp trailers documents exclusive of information, such
related to the DynCorp contract that are as contract evaluation sheets and private
discussed in this report. e-mail exchanges between a program office
• Between January and June 2006, INL and the contracting officer.
directed DynCorp to take action on • Over the past several months, INL has
asset management improvements. These developed a process for thoroughly review-
improvements were documented in a series ing invoices. This process has already
of letters INL exchanged with DynCorp in resulted in INL identifying billing errors
which INL documented defects in contract in a DynCorp invoice. For example, INL
performance and DynCorp responded by rejected a January 9, 2007, invoice for $1.1
identifying corrective actions it was taking million which was for a different DynCorp
or planned to take. Currently, INL is in the contract. This invoice was rejected because
process of following up on DynCorp inven- INL determined that the billed rate was
tory control corrective actions. outside the period of performance dates.
• In June 2006, INL requested assistance
from the Defense Contract Management INL also advised SIGIR that it was working
Agency (DCMA) in reviewing DynCorp to ensure internal and management con-
property management practices in Iraq and trols are in place and adhered to at all times,
Afghanistan (which the DCMA declined and intends to reconcile all past payments
due to property administrator staffing made since the inception of INL contracts in
shortages). Afghanistan, Iraq, and Jordan.
• In October 2006, INL attempted to con- SIGIR initially recommended that INL
tract for Defense Contract Audit Agency consider replacing the COR for the DynCorp
(DCAA) services to close out several contracts and task orders who had held that
position since 1994—a 12-year period. INL improperly authorized payment of $4.2 mil-
advised SIGIR on January 11, 2007: lion that represents contractually unauthor-
• The COR has been replaced. INL also pro- ized work directed by the Iraqi Ministry of
vided to SIGIR the appointment letters for Interior. This work included the relocation
in-country CORs for all INL contracts in of the residential camp, the manufacture of
Afghanistan and Jordan. additional VIP trailers, and the construc-
• The transition of contracting responsibili- tion of an Olympic-size swimming pool.
ties took place in November 2006. 3. Request that the DCAA take these actions:
• The Iraq in-country CORs, who will be a. Review the July 30, 2004 DynCorp
personal services contractors, had been invoice that included a residential camp
selected and are going through the clear- mobilization fee to determine whether a
ance process. prepayment of $18 million occurred.
b. Review the October 30, 2006 DynCorp
SIGIR considers INL’s actions to be respon- invoice for approximately $1.1 million
sive to the draft recommendation, and there- pertaining to labor costs associated with
fore removed it from the final report. Task Order 0338.
Recommendations. To ensure that DoS 4. On receipt of the DCAA audit report, the
conserves IRRF funds and other DoS funds, contracting officer should take the appro-
SIGIR recommends that the Assistant Secre- priate action.
tary for the Bureau of International Narcotics 5. Enforce procedures to ensure that the
and Law Enforcement Affairs: contracting officer and COR comply with
1. Present a plan to the U.S. Ambassador to the duties and responsibilities identified in
Iraq for review and approval on the use of the DoS Foreign Affairs Handbook. These
the residential camp to house police train- procedures should address:
ers, as originally intended, or make arrange- a. receiving and retaining technical and
ments to dispose of the camp. Because of financial reports
the lengthy consideration already given to b. examining invoice with supporting
deciding what to do with the trailers, this documentation before certification for
action should be taken within the next 60 payment
days. c. processing “receiving and inspection
To ensure that contracted work is properly reports” for equipment
invoiced, payments are proper, and the con- d. maintaining a COR file
tract is properly managed, SIGIR also recom- 6. Establish and enforce tenure limitations
mends that the DoS Director, Office of Acqui- for all contracting personnel, as part of the
sition Management should take these actions: Foreign Affairs Handbook.
2. Seek reimbursement from DynCorp for the
Management Comments and Audit throughout Iraq. This report updates the
Response. SIGIR received written comments status of the medical equipment and discusses
on a draft of this report from INL which SIGIR’s review of controls over and use of
incorporated comments from the DoS Office medical consumables and other non-construc-
of Acquisition Management, that they agreed tion purchases for the PHC project, which
with recommendations 1 through 5. INL stated has been subject to delay and de-scoping.
that the Office of Acquisition Management Although GRD’s contract to construct PHC
disagreed with recommendation 6, regarding facilities through Parsons was significantly
tenure limitations, because it has a Quality reduced, the overall PHC construction require-
Assurance Plan for reviewing and approving ment remained. GRD procured medical equip-
contract actions to ensure that all require- ment sets based on this overall requirement. To
ments of law, regulation, department policy, its credit, GRD did arrange to have the medical
and sound procurement practices are met. equipment sets, furniture, and consumables
SIGIR recognizes the importance of a Quality delivered to storage facilities, thus reducing an
Assurance Plan, but believes that the need extremely high risk of pilferage and suscepti-
for tenure limitations is underscored when bility to damage
the control environment in an organization is Objectives. SIGIR initiated this audit as a
weak. SIGIR, therefore, retained the recom- review of the medical consumables purchased
mendation. under contract W27P4B-05-A-5018 for the
In response to the draft of this report, PHCs. Subsequent work led to the expansion
INL provided SIGIR with information on its of the audit’s scope to include other sup-
management actions to strengthen its contract porting, non-construction contracts. SIGIR
and asset management across INL, which is modified the objectives to answer these ques-
detailed in the management actions section tions:
of this Report. INL also provided SIGIR with • Were the procured medical consumables,
technical changes, which were incorporated in medical equipment, and other
the final report as appropriate. non-construction items properly
controlled?
Status of Medical Equipment and Other • Were the plans for their utilization adjusted
Non-Construction Items Purchased for based on the delay and/or de-scoping of the
Primary Healthcare Centers
SIGIR-06-030, January 2007
PHC project?
In July 2006, SIGIR issued a report on medical Findings. At the time of SIGIR’s July 2006
equipment purchased by Parsons Delaware, report on medical equipment, 20 of the 151
Inc. (Parsons), in support of a contract, also medical and dental equipment sets procured
issued to Parsons, to construct 150 PHCs under the Parsons contract were physically
located at the sites of 20 PHCs that were fully SIGIR identified six other non-construction
or partially constructed by Parsons. Another contracts, awarded to various contractors, with
115 full or partial sets were located at a U.S. a combined value of about $43 million. Of
government-controlled warehouse in Abu these, three were affected by the termination of
Ghraib. Since then, 15 additional sets of equip- the PHC construction task orders:
ment have been delivered to the warehouse; • a $22.6 million contract for generators,
the total number of sets in Abu Ghraib was transformers, and cables
130, as of July 30, 2006. The location of one set • a $14.4 million contract for PHC furniture
is unknown. • a $5.5 million contract for consumable
SIGIR’s July 2006 report also stated that medical supplies478
no official government receipt, inspection,
or acceptance function had been performed Approximately $38 million had been
on any of the medical equipment sets at Abu disbursed for these three contracts. GRD and
Ghraib and that there were questions about the JCC-I/A modified the generator/transformer
equipment warranty because of the extended contract to have the contractor store and
storage. As of July 30, 2006, approximately $45 secure the items until required at the PHC
million had been disbursed for the medical sites. GRD and JCC-I/A, however, did not take
equipment. Since then, GRD, as the program effective action to protect all of the furniture
manager of the PHC project, has examined and consumable medical supplies. Specifically:
102 equipment crates that were damaged, and • The government contracted for 142 sets
opened and inspected 61 of the most dam- of furniture for the PHCs under contract
aged. In 59 of the crates, GRD found that all of W27P4B-05-C-0016. Six sets of furniture
the equipment was accounted for, and almost were delivered directly to PHC construc-
all of the equipment was missing in 2 crates. tion sites, 90 sets were delivered to the U.S.
GRD did not test the medical equipment to government-controlled warehouse in Abu
ensure that it was in working order. GRD did Ghraib, and 46 sets were delivered to the
not open the remaining crates to inventory Iraqi Ministry of Health warehouse in Erbil.
the equipment because of concern that doing JCC-I/A reports that the furniture deliv-
so without a manufacturer’s representative ered to Abu Ghraib was formally accepted,
present could void any remaining warranty; inventoried, and inspected. Damaged items
however, they did take pictures to docu- were corrected by the contractor. How-
ment the status of the equipment. On January ever, the furniture at Erbil was formally
19, 2007, GRD told SIGIR that JCC-I/A has accepted for payment purposes but was not
informed GRD that manufacturer warranties inventoried and inspected. The furniture at
are effective for 15 months from the invoice Erbil has also been reported as damaged.
date or 12 months from the commissioning The contractor was not notified in a timely
date (whichever is earlier). manner and is refusing to take responsibil-
ity for furniture reported damaged after items currently stored at the Erbil storage
delivery. facilities, take appropriate actions to recoup
• The U.S. government contracted for 118 the cost of all items found missing or dam-
sets of consumable medical supplies479 to aged, or determine how this missing or
provide an estimated 90-day supply for damaged furniture will be replaced.
each PHC. Under contract W27P4B-5- 3. Conduct a complete inventory and inspec-
A-5018, 112 sets of consumable medical tion of all of the consumable medical sup-
supplies were delivered to both the Abu plies as soon as practicable.
Ghraib warehouse and the Iraqi Ministry 4. Using the inventory list of consumable
of Health warehouse in Erbil. Six sets were medical supplies currently stored at both
delivered directly to PHCs under construc- the Abu Ghraib and Erbil storage facilities,
tion. GRD stated that it inventoried crates take appropriate action to recoup the cost
at Abu Ghraib but did not open the crates. of all items found missing or damaged,
At Erbil, SIGIR found no evidence that the or, if the items can not be replaced by the
U.S. government formally accepted, inven- contractor, determine how these items will
toried, or inspected the items. be replaced.
This Report also identifies a lesson learned Management Comments and Audit
about the need to fully examine the potential Response. SIGIR received written comments
impact of changes in contract terms on other on a draft of this report from GRD and
supporting contracts. In this case, a construc- JCC-I/A who generally concurred with the
tion contract was terminated, but supporting findings and recommendations. Actions are
non-construction items had already been planned or underway to implement the recom-
ordered. As a result, the U.S. government mendations. The comments received were
needed to develop plans to secure items fully responsive. These officials also provided
awaiting the completion of construction by technical comments which SIGIR has incorpo-
new contractors on the project. rated in the report where appropriate.
Recommendations. SIGIR makes these
recommendations: Follow-up on SIGIR Recommendations
The Commanding General, JCC-I/A, in Concerning the Development Fund
coordination with the Commanding General, for Iraq (DFI)
SIGIR-06-036, January 2007
GRD, should take these actions:
1. Conduct a complete inventory and inspec- This report follows up on actions taken by
tion of furniture at the Erbil storage facility U.S. government agencies to address recom-
as soon as practicable. mendations made in previous SIGIR audit
2. Using the inventory list of all furniture reports on the control and accountability for
contracts, grants, and cash transactions using • Management of Rapid Regional Response
the DFI. SIGIR made these recommendations Program Contracts in South-Central Iraq,
to the U.S. Ambassador to Iraq, JASG-C, and SIGIR-05-023, January 23, 2006
JCC-I/A. In April 2006, SIGIR reported that
appropriate actions had been taken to close 23 Findings. As of August 31, 2006, the U.S.
of 40 recommendations.480 Since then, SIGIR government had spent approximately $1.4 mil-
has redirected the recommendations that lion on audit services and computer equipment
were made to the U.S. Ambassador to the DFI to satisfy SIGIR recommendations but failed to
Administrator, who is also the Commanding effectively write the contract and monitor the
General, JCC-I/A. This report follows up on contractor’s work. The contract requirements
the remaining 17 open recommendations to were not specific enough and were changed
determine whether appropriate corrective twice, through modification, late in the
actions were taken to address the deficiencies. performance period. Inspections and quality
Objective. The objective of this review was assurance surveillance were not performed. As
to determine whether the U.S. Ambassador to a result, DFI accountability has only slightly
Iraq, JASG-C, and JCC-I/A have developed improved, and seven SIGIR recommendations
and implemented action plans to address directed to JASG-C remain open.
the deficiencies identified by SIGIR in these As of December 30, 2006, 8 of the 17 recom-
reports: mendations that SIGIR reported as open in the
• Control of Cash Provided to South-Central April 2006 follow-up report are now closed,
Iraq, SIGIR-05-006, April 30, 2005 and 9 remain open. SIGIR’s review identified
• Administration of Contracts Funded by the these actions taken in response to the open
Development Fund for Iraq, SIGIR-05-008, recommendations:
April 30, 2005 JASG-C. SIGIR’s April 2006 report identi-
• Management of Rapid Regional Response fied seven open recommendations made to
Program Grants in South-Central Iraq, the Commander, JASG-C. SIGIR reported
SIGIR-05-015, October 25, 2005 that JASG-C had taken action to address all
• Management of the Contracts and Grants seven recommendations by contracting with
Used To Construct and Operate the Baby- a private firm to review and reconcile all DFI
lon Police Academy, SIGIR-05-016, Octo- accounts throughout Iraq. The key deliver-
ber 26, 2005 able on the contract was a DFI accountability
• Management of the Contracts, Grant, and database with embedded scans of supporting
Micro-Purchases Used To Rehabilitate the DFI documentation. Since then, SIGIR has
Karbala Library, SIGIR-05-020, October 26, determined that the action did not satisfy any
2005 of the open recommendations because U.S.
government agencies failed to properly write
detailed requirements into the contract’s state- review grant disbursements made in other
ment of work and failed to effectively monitor regions of Iraq to determine if the same
contractor performance. Therefore, all seven condition exists as determined by SIGIR
recommendations remain open. Specifically, in the South-Central Region (open, no
since SIGIR reported in April 2006: action), and two recommendations requir-
• JASG-C has taken additional action on four ing that complete files supporting payment
of the recommendations for review and and contract/grant execution are main-
reconciliation of Statements of the Agent tained (open, action incomplete).
Officer’s Accounts. The JASG-C Comptrol-
ler has taken available records from the JCC-I/A. SIGIR’s April 2006 report identi-
DFI accountability database and entered fied six open recommendations made to the
them into a separate Access database. Commanding General, JCC-I/A. JCC-I/A
The JASG-C Comptroller has also devel- has implemented Procurement Management
oped a list of paying agent names whose Reviews to address these recommendations by
DFI accounts require reconciliation. providing enhanced monitoring of contracts.
SIGIR considers the actions underway to In addition, JCC-I/A has developed a Principal
be responsive to the recommendations; Assistant Responsible for Contracting-Iraq
however, a full review and reconciliation (PARC-I) Acquisition Instruction, which is a
of all DFI records has not yet been com- comprehensive guide to JCC-I/A contracting
pleted. Therefore, all four recommendations procedures in Iraq. All six recommendations
remain open. SIGIR’s recommendations have been closed.
were intended to ensure that the types of DFI Administrator. SIGIR’s April 2006
problems identified with the control and report identified four open recommendations
accountability of DFI cash disbursements in made to the U.S. Ambassador to Iraq. Because
South-Central Iraq would also be appropri- the recommendations directed to the U.S.
ately addressed if found during the con- Ambassador have now been identified as the
tracted accountability review of other Iraqi purview of the DFI Administrator, SIGIR has
regions. redirected the recommendations.
• The scope of work for the DFI accountabil- JCC-I/A representatives, acting under
ity contract did not address three remaining the direction of the DFI Administrator, have
recommendations, and there has been no taken action to close two of the recommen-
subsequent action by JASG-C to address dations, and action is underway to close one
them. Therefore, the status of these recom- other recommendation on the recovery of DFI
mendations was downgraded from open, funds disbursed for grants. In addition, action
actions underway. The three recommenda- is underway to satisfy a recommendation to
tions are: one to establish a special team to acquire a central database system to assemble
and maintain accurate and reliable historical the type of COR succession described in the
DFI records. JCC-I/A personnel have received JCC-I/A policy is a part of its internal control
training on the DFI accountability database procedures. In this case, those procedures were
and are in the process of reconciling records in not followed. This failure represents an internal
that database with records in JCC-I/A database control weakness; however, because the con-
of contracts. JCC-I/A actions are responsive to tract has now ended, no action is required.
the two open recommendations. Lessons Learned. During the course of
Recommendations. Of the 17 open rec- the review of the management of the DFI
ommendations in SIGIR’s April 2006 report, accountability contract, SIGIR noted that if the
nine remain open. SIGIR considers the actions statement of work had been written in suffi-
underway to be responsive for six of the cient detail, it could have improved the mutual
nine. Effective action is not underway on the understanding of requirements between U.S.
remaining three recommendations. SIGIR government officials and the contractor. SIGIR
makes no additional recommendations. found that the turnover of multiple govern-
Observations. SIGIR’s recommendations ment personnel and an unclear requirements
were intended to determine if the unsatisfac- statement resulted in an unsatisfactory result
tory conditions of the control and account- in the administration and execution of the
ability of the DFI present in the South-Central contract.
Region in 2004 existed in other regions of Iraq. Management Comments and Audit
More than two years after SIGIR first identi- Response. This report contained no addi-
fied these material control and accountability tional recommendations; therefore, no written
weaknesses, U.S. government agencies still do responses were required. JCC-I/A and JASG-C
not know the extent of the conditions of con- officials verbally concurred with the facts and
trol and accountability in the other regions. results of this report.
During the follow-up review, SIGIR also
observed that under JCC-I/A policy, when Review of USAID/Bechtel National, Inc.,
Property Management Controls for
a COR departs, the contracting officer has
Contract SPU-C-00-04-00001-00
discretion to either appoint a new COR on the SIGIR-06-039, January 2007
contract or to terminate the previous COR’s
appointment and take on the responsibility This report discusses SIGIR’s review of gov-
personally. The contracting officer for the DFI ernment property management controls by
accountability contract failed to follow USAID and its contractor, Bechtel National,
JCC-I/A policy and appoint a new COR or Inc.481 (Bechtel), for contract SPU-C-00-04-
terminate the departing COR’s appointment. 00001-00.
During the audit, SIGIR discussed this with To support its mission and related infra-
JCC-I/A officials, who acknowledged that structure reconstruction efforts in Iraq, USAID
awarded Bechtel two successive contracts • Was the property accurately inventoried
(Phase I and II): and safeguarded?
• The Phase I contract, EEE-C-00-03-00018- • Was the property controlled and disposed
00, was a cost-plus-fixed-fee award on April of in accordance with relevant regulations?
17, 2003, for $680 million. On September
30, 2003, the contract was modified and In performing the review, SIGIR learned
increased to a total of approximately $1.03 that in 2005, DCAA reviewed Bechtel’s man-
billion. It expired December 31, 2004. agement controls for the purchase and inven-
• The Phase II contract, SPU-C-00-04-00001- torying of government property, reporting
00, also a cost-plus-fixed-fee contract, was no significant deficiencies. Therefore, SIGIR
awarded on January 5, 2004 for about $1.82 concentrated the audit effort on USAID’s and
billion. In July 2006, the contract amount Bechtel’s property management controls over
was decreased to about $1.26 billion. On the disposition of government property under
January 7, 2007, the contract was modified the contract.
and further reduced to approximately $1.24 DCAA Audit and Report. On January 10,
billion. The contract is scheduled to expire 2005, the USAID Regional Inspector General
on January 31, 2007. requested that the DCAA Iraq Branch Office
perform audits to verify the physical existence
Under the contracts, Bechtel was required to (receipt, storage, and use) of the materials,
maintain the official property records. On July supplies, and equipment purchased under
18, 2005, USAID authorized the transfer of all Bechtel’s Phase I and Phase II contracts. DCAA
IRRF-funded property from Bechtel’s Phase I was also to evaluate if the government prop-
to Phase II property records—either supplied erty was (1) received, stored, or consumed; (2)
to or acquired by Bechtel or its subcontractors. required for the contract; and (3) accounted
Thus, all government property was consoli- for in the proper manner. Specifically, DCAA
dated in the Phase II contract property records. reviewed:
Objectives. This review was announced on • compliance with established government
September 7, 2006, with the objective of deter- purchasing policy and procedures
mining whether USAID and Bechtel had estab- • the adequacy of Bechtel’s internal control
lished and implemented adequate management policies and procedures for purchasing and
controls over government property acquired inventorying supplies and equipment
for Iraq reconstruction projects. The review • the existence and accuracy of inventory
announcement identified these questions: records for materials
• Was the property accurately documented, • the adequacy of internal controls over the
especially from purchase authorization to management of purchased services
disposition?482 • purchased services to determine if they
Findings. On January 28, 2006, GRD • $6.4 million still held for the defunct Office
developed an internal plan, including finan- of Reconstruction and Humanitarian Assis-
cial guidance. The purpose of the plan was tance, the original agency established for
to ensure that there were sufficient obligated Iraq reconstruction
funds in the expired IRRF 2 appropriation
to close out design-build contracts during On September 29 and 30, 2006, the Depart-
FY 2007 and beyond.485 The plan underwent ment of the Army reissued to USACE the
legal review at multiple levels within DoD. In $385.2 million in returned IRRF 2 funds.
February or March 2006, the senior official in These funds expired at midnight on September
the DoD Office of General Counsel (Fiscal) 30, 2006. On October 3 and 4, 2006, USACE
orally indicated to the Director, Management issued $385.2 million in expired IRRF 2 funds
and Control in the Army Budget Office,486 that to its subordinate command, GRD.
the proposed plan to obligate IRRF 2 funds for The Iraq Reconstruction Management
contingencies was permissible, but a written Office (IRMO) has developed procedures
opinion was not provided. In June 2006, after for the use of expired funds, Updated Proce-
a change in personnel, the new senior official dures for Iraq Relief and Reconstruction Fund
in the DoD Office of General Counsel (Fiscal) (IRRF) Expired Funds, November 28, 2006. The
reached the opposite conclusion—that the procedures require each IRRF-implementing
proposed plan was not proper. As of October organization to notify or receive approval
2006, this remains the DoD legal position, but from IRMO on the use of the expired funds,
no written guidance has been made available. depending on the amount involved. However,
A series of actions were taken between SIGIR found that GRD had been directed by
September 29, 2006, and October 4, 2006, to the USACE CFO, rather than IRMO, to use the
ensure that the funds in question remained $385.2 million of expired IRRF 2 funds to take
available consistent with appropriations law. actions to meet its contingency expectations.
These funds were returned to the Department This amount represents almost all (99%) of the
of the Army, moved to the custody of USACE, $389.2 million total expired funds that were
allowed to expire, and then returned to GRD deobligated and returned to the Department
for its use. On September 29 and 30, 2006, of the Army at the end of FY 2006 for all
$385.2 million in IRRF 2 funds were returned agencies.487
to the Department of the Army: The use of expired funds has been the sub-
• $378.8 million in deobligated funds that ject of considerable discussion between IRMO
were returned by GRD on September 29- and GRD and is but one aspect of a broader
30, 2006, which included the $362 million problem—how to manage future costs to com-
questioned in SIGIR’s interim report plete work across the range of IRRF projects.
USACE has conducted a detailed review of the
cost to complete its pre-September 30, 2006 their IRRF contracting activities; and (2) the
IRRF-funded contracts and has quantified its impacts of these security costs in relation to
need for the expired funds. While GRD has the overall original project estimates. This fact
quantified its requirements for the use of the sheet provides detailed responses to SIGIR’s
expired funds, IRMO’s procedures call for its request for information from nine contractors.
approval on a case-by-case basis to ensure the This detailed fact sheet is available on a need-
best use of limited funds. SIGIR believes that to-know basis because some of the contractor-
having IRMO’s approval is a good start, but it provided information is marked proprietary
may be challenging from a strategic perspective. by the provider. Requests by mail can be made
Recommendations. GRD has addressed to SIGIR Office of General Counsel, 400 Army
SIGIR’s previous recommendation to safe- Navy Drive, Arlington, VA, 22202.
guard the availability of the $362 million that
had been improperly obligated, and because Review of Iraq Relief and Reconstruction
actions are underway to clarify the use of the Fund Unmatched Disbursements
SIGIR-06-043, January 2007
expired IRRF 2 funds, SIGIR makes no further
recommendations. This report discusses SIGIR’s review of internal
Management Comments and Audit controls over disbursements of the IRRF
Response. This report contains no recom- apportioned to DoS, DoD, and USAID.
mendations; therefore no written response was Objectives. This review was announced
required. A draft of this report was provided to on July 21, 2006, to determine the amount of
USACE and IRMO. USACE officials responded IRRF unmatched disbursements and whether
with no comments to add. IRMO officials U.S. government agencies have established
provided technical comments, which were adequate management controls over IRRF 1
addressed in the final report. IRMO officials and IRRF 2 unmatched disbursements. To
concurred and had no additional comments. accomplish this objective, SIGIR addressed
these questions:
Fact Sheet on Major U.S. Contractors’ • How much of the IRRF has been identified
Security Costs Related to Iraq Relief and as unmatched disbursements?
Reconstruction Fund Contracting Activities
• How often are unmatched disbursements
(Restricted Distribution)
SIGIR 06-042, January 2007 reviewed by government officials, and who
makes the determination that the disburse-
SIGIR initiated this project in order to capture ment was an IRRF expenditure?
the following information: (1) the extent to • Have IRRF unmatched disbursements
which major U.S. contractors have identified, subsequently been identified to other IRRF
captured, and reported the security costs of projects?
• What management controls are in place to to USACE for DoD, USAID, and DoS. USACE
eliminate and resolve unmatched disburse- officials responded with no comments to add.
ments? USAID officials provided no response. DoS
officials provided technical comments, which
SIGIR’s results were limited to an assess- were addressed in the final report.
ment of DoD and USAID because DoS officials
did not provide access to the detailed IRRF Fact Sheet on Major U.S. Contractors’
obligations and disbursements data needed for Security Costs Related to Iraq Relief and
Reconstruction Fund Contracting Activities
the review. SIGIR plans to perform a separate SIGIR 06-044, January 2007
audit of unmatched DoS disbursements at a
later date. SIGIR initiated this project in order to capture
Findings. DoD has effective internal con- the following information: (1) the extent to
trols to prevent unmatched disbursements. which major U.S. contractors have identified,
SIGIR tested DoD controls over $9.2 billion in captured, and reported the security costs of
disbursements and found, in all instances, that their IRRF contracting activities; and (2) the
DoD disbursements could be matched with impacts of these security costs in relation to
obligations in accounting records. the overall original project estimates. SIGIR
SIGIR also tested USAID’s controls over requested that each of the nine major U.S.
$4.3 billion in disbursements and found no contractors conducting the physical recon-
unmatched disbursements. However, because struction of Iraq’s infrastructure provide the
USAID could not provide 2 of the 32 invoices following data to address the survey’s
that SIGIR randomly selected for testing, objectives:
SIGIR could not complete the assessment of • the total amount of their IRRF contract
the effectiveness of its internal controls before dollars spent on security costs
the audit concluded. However, based on the • the percentage of total IRRF funds
30 of the 32 USAID invoices reviewed, SIGIR disbursed comprising security costs
finds that USAID appears to have adequate • initial and subsequent revisions to the
controls. projected security costs of IRRF contracting
Recommendations. Because the DoD and activities
USAID management controls over disburse- • when the magnitude of these costs became
ments appear to be adequate to identify and evident, and what were the significant
resolve unmatched disbursements, SIGIR causal or contributing factors
makes no recommendations. • the contractor’s method(s) of record-
Management Comments and Audit keeping for capturing and differentiating
Response. This report contains no recom- between the types of security required, such
mendations; therefore no written response was as Personal Security Details, site/static,
required. A draft of this report was provided perimeter, convoy/materiel movement
• the breakdown, by category (billed, eral Counsel, 400 Army Navy Drive, Arlington,
charged, and estimated) of both the direct VA 22202.
and indirect security costs for IRRF con-
tracting activities Status of Ministerial Capacity
• any other additional security cost increases Development in Iraq
SIGIR 06-045, January 2007
from subcontractor work
SIGIR initiated this review to determine
The following contractors were asked to whether U.S. government organizations had
respond to SIGIR’s survey: Bechtel National, plans and programs in place for capacity devel-
Inc.; FluorAMEC, LLC; Kellogg, Brown, and opment in the Iraqi government ministries.
Root Services, Inc.; Lucent Technologies; Introduction. Iraq’s governing capacity
Parsons; Parsons Iraq Joint Venture; Perini has suffered from years of centralized control
Corporation; Washington International/Black that led to the decay of core functions in many
& Veatch; and Washington International, Inc. key institutions and ministries. Government
All nine contractors responded to SIGIR’s systems and processes were weakened in stra-
request for information. The contractors gener- tegic and policy planning, finance, information
ally provided security costs and security costs technology, and human resources manage-
as a percentage of total costs. Four of the nine ment. For almost 30 years, the central govern-
contractors did not provide a summary of all ment neglected to develop a professional civil
total cost data; in these cases SIGIR calculated service, which fostered poor management
total costs based on the information provided. practices. After the fall of Saddam Hussein’s
Contractor security costs ranged from a low regime in 2003, governing capacity continued
of 7.6% to a high of 16.7%. The average for all to deteriorate during the formation of multiple
contractors when identifying percentage of governments:
security costs to total costs was 12.5%. • provisional Iraqi Governing Council, estab-
Detailed responses to SIGIR’s request for lished by the Coalition Provisional Author-
information from each of the nine contractors ity, 2003
are included in SIGIR’s Fact Sheet on Major • Iraqi Interim Government, 2004
U.S. Contractors’ Security Costs Related to Iraq • Iraqi Transitional Government, 2005
Relief and Reconstruction Fund Contracting • elected Government of Iraq (GOI), which
Activities (Restricted Distribution), SIGIR- took office in May 2006
06-042, January 2007. This detailed fact sheet
is available on a need-to-know basis because The current government, in office for about
some of the contractor-provided information is seven months, must deal with the ongoing
marked proprietary by the provider. Requests sectarian strife and increased violence that
by mail can be made to SIGIR Office of Gen- continues to impede Coalition nation-building
and related capacity-development efforts. executive institutions and key ministries. Other
The staggering implications of Iraq’s poor participants in ministerial capacity building
governing capacity became fully apparent include IRMO’s senior consultants and the
when some infrastructure facilities constructed U.S. Embassy’s officers (Justice, Treasury, and
or rehabilitated by the U.S. reconstruction Economic Affairs). These organizations and
effort failed or operated in suboptimal condi- individuals receive strategic and policy guid-
tions after their handover in 2004 and 2005. ance from the Executive Steering Committee,
P.L. 108-106, the Emergency Supplemental which comprises U.S. Mission officials, U.S.
Appropriations Act for Defense and the Recon- military, and other Coalition representatives.
struction of Iraq and Afghanistan–2004, had In September 2006, the Joint Task Force on
encouraged U.S. organizations receiving recon- Capacity Development was created to coordi-
struction funds to provide significant financial nate the capacity-development initiatives of all
resources, technical assistance, and capacity U.S. government organizations and to make
building to counterpart organizations. SIGIR recommendations to the Executive Steering
found that those programs addressing Iraq’s Committee.
ministerial capacity-development needs were This audit examined the status of the minis-
just beginning at the time of the evaluation. terial capacity-development initiatives in Iraq
The November 2005 U.S. National Strategy as of December 2006.
for Victory in Iraq and the April 2006 Joint Objectives. The objectives of this audit were
Campaign Plan—issued by the Chief of Mis- to determine whether U.S. government orga-
sion, U.S. Embassy-Iraq, and the Commanding nizations had plans and programs in place for
General, MNF-I—together provided broad capacity development in the Iraqi government
policy and program guidance. These documents ministries. Specifically, SIGIR addressed these
identified Iraqi national capacity development questions:
as a key component of U.S. strategic, political, • Have U.S. government organizations, such
security, and economic objectives in Iraq. as DoS and USAID, assessed the competen-
Capacity development is defined as an cy of the responsible Iraqi ministries for the
activity or multiple activities that lead to long-term management of essential govern-
the transfer of knowledge, skills, and abili- ment functions and services?
ties across a range of functions over a period • What are their programs for addressing the
of time. It is also an essential prerequisite identified shortcomings?
for sustainment, thus enabling individuals, • What performance indicators or metrics
units, organizations, and systems to perform will be used to measure progress, and who
functions efficiently to establish sustainable has overall responsibility for measuring
operations. IRMO, USAID, USACE GRD, and progress?
MNSTC-I have designed internal programs to • Have U.S. government organizations
strengthen the management capability of Iraq’s identified adequate funding?
• Is the U.S. government working with other building across the ministries involved.
donor nations and institutions to coor- Similarly, budget execution is critical for the
dinate, fund, and develop solutions for delivery of services and security to the Iraqi
a comprehensive capacity-development public, and U.S. government officials remain
program in future years? concerned about the GOI’s inability to manage
and effectively use its own budget resources,
Findings. The first step in capacity-devel- yet there is no comprehensive program to
opment planning is a clear assessment of address the GOI’s budget execution problems.
the competencies and needs of the GOI. Yet U.S. government initiatives within Iraq’s
the crucial task of assessing Iraqi ministerial executive institutions and key ministries
competency has not been accomplished in a seem to be internally driven and responsive
unified or comprehensive way. Since the CPA to individual agency direction rather than
established the Iraqi Governing Council in a part of an overarching U.S. government
mid-2003, many U.S. government officials have capacity-building plan or program that defines
been working within the key Iraqi ministries. roles and responsibilities, goals, objectives,
Through their ongoing interaction with and milestones. Without a plan, SIGIR could
Iraqi ministers and subordinates, U.S. gov- not determine how these ongoing activities
ernment officials have developed first-hand contribute to overall U.S. government objec-
knowledge of the abilities and needs of the tives. The basic problem seems to be that no
respective institutions. However, this informa- one office or person is clearly in charge of the
tion is not always available, shared, or used overall U.S. government capacity-develop-
across all U.S. agencies, hampering overall ment effort. Rather, functional responsibility
coherence and possibly program effectiveness. for ministerial capacity development was
Without a clear understanding of what needs intentionally divided: IRMO’s Ministerial
are to be achieved, individual U.S. government Coordination Team (MCT) addresses imme-
organizations have initiated individual projects diate short-term process and system problems
to support the defined National Strategy for at the ministries, and USAID focuses on the
Victory in Iraq. Some organizations appear medium- to long-term institution building.
to address a crisis rather than projects that Additionally, other U.S. organizations and
have been defined and prioritized as a part offices conduct capacity-development activi-
of an overall detailed strategy. For example, ties at the ministries, including IRMO’s senior
obtaining fuel for the Iraqi Security Forces consultants, U.S. Embassy’s officers (Justice,
is a critical problem that must be addressed Treasury, and Economic Affairs), MNSTC-I’s
at multiple ministries, but at the time of the embedded advisors at the security ministries
review, SIGIR found no U.S. government (Defense and Interior), and GRD’s functional
programs that addressed management capacity experts at the essential services ministries (Oil,
Electricity, Water Resources, Municipalities or were in the process of developing, their own
and Public Works, and Health). Without a individual program objectives and perfor-
detailed plan identifying common expecta- mance measures, SIGIR noted the lack of a
tions that relate to both short- and long-term system to measure overall progress. And, most
initiatives, resources may be wasted because important, no single U.S. government office or
ongoing initiatives may not be compatible with official is responsible or accountable for mea-
overall program goals. suring and reporting on overall U.S. ministe-
In concept, these organizations’ discrete rial capacity-development progress.
efforts are to be coordinated by the recently U.S. government organizations could not
formed Joint Task Force on Capacity Devel- estimate how much funding would be neces-
opment. Although created to identify issues, sary to achieve the goal of a self-sufficient
critical paths, gaps, and redundancies in Iraqi government. Agency officials explained
capacity-development initiatives for all U.S. that their capacity-development budgets were
government organizations and, subsequently, structured around their respective programs
to make recommendations to the Executive and that their programs were based on the
Steering Committee for respective ministe- level of funding that was allocated to them, not
rial action, SIGIR found that the Joint Task on an assessment of requirements to achieve
Force was making limited progress in coordi- the overall U.S. government goal. For FY 2006,
nating the various activities and establishing IRMO and USAID received approximately
an overall capacity-development agenda. $125 million. USAID has requested an addi-
Task Force members were still at the stage of tional $310 million for activities in FY 2007
cataloguing their various activities and had yet and FY 2008, and IRMO has requested an
to identify critical programming paths or how additional $70 million for activities in FY 2007.
to leverage their resources and activities with Congress has not yet approved the FY 2007
each other or with their Iraqi counterparts. budgets for DoS and USAID; the agencies are
Committed to support sustainable infra- operating under a continuing resolution based
structure and services in Iraq, the U.S. gov- on their FY 2006 funding.
ernment, through multiple organizations and More than 40 nations and international
offices, has engaged the Iraqi ministries in institutions have pledged more than $15 billion
numerous capacity-development activities. for the reconstruction of Iraq, as of December
However, during the course of this review, 30, 2006. These bilateral and multilateral
SIGIR determined that U.S. government orga- donors have played a limited role in Iraqi min-
nizations introduced many of their activities isterial capacity-development programming.
without articulating clear achievable goals, However, SIGIR identified some capacity-
especially the basis for measuring progress. development programs—two by the United
Although some organizations had developed, Kingdom and several implemented through
the United Nations Development Group Iraq and outcome-related performance mea-
Trust Fund and the World Bank Iraq Trust sures, milestones for achieving stated objec-
Fund. Though the United States works in close tives, and future funding requirements,
consultation with the United Kingdom on for implementing a unified comprehensive
capacity-development activities at several Iraqi capacity-development program to enable
government offices, including the Ministry the GOI to provide sustainable security and
of Interior, SIGIR was unable to determine services to the Iraqi public.
whether U.S. government managers took any 4. Actively work with other bilateral and mul-
steps to jointly develop and fund capacity- tilateral donors through the International
development programs with other bilateral or Compact for Iraq process to assist in the
multilateral donors. The international com- planning, execution, and funding of a uni-
munity continues to negotiate the details of the fied comprehensive capacity-development
International Compact for Iraq,488 projected program in Iraq.
to be completed in early 2007. SIGIR believes 5. Assign clear responsibility for the overall
that the Compact presents the U.S. government U.S. capacity-development effort to one
with an excellent opportunity to actively work U.S. government official or organization.
with participating bilateral and multilateral
donors to assist in the planning, execution, and Management Comments and Audit
funding of a unified comprehensive capacity- Response. SIGIR received written comments
development program in Iraq. on a draft of this report from IRMO and
Recommendations. SIGIR recommends USAID. Although SIGIR anticipated com-
that the U.S. Ambassador to Iraq and the Com- ments from MNF-I, they were not received
manding General, MNF- I, take these actions: when due in order to incorporate into this
1. Develop a capacity assessment baseline Report. SIGIR anticipates having MNF-I’s
for each ministry based on an agreed-on comments prior to the release of the final audit
criterion that uses (a) the input from the report.
individual U.S. organizations that have had Overall, the organizations generally con-
an ongoing presence within the Iraqi min- curred with SIGIR’s five recommendations.
istries and (b) the assessment conducted by USAID disagreed on some of the methods of
IRMO/MCT. implementation. SIGIR is pleased to report
2. Develop a mechanism to share this infor- that IRMO indicated in its comments that it
mation among the U.S. organizations had or was in the process of implementing all
involved in the ministry capacity-develop- of the recommendations. IRMO, USAID, and
ment program. MNSTC-I also provided technical comments
3. Develop a detailed plan, in concert with the which were incorporated in the report where
GOI, including clearly defined objectives appropriate. SIGIR considers all comments
received responsive to the intent of the recom- addressing these organizational challenges.
mendations. USAID’s response even suggested it believed
However, for recommendation 5, “assign that, “the best scenario would be for a single
clear responsibility for the overall U.S. capacity organization to receive all funding for capacity
development effort to one U.S. government development with the head of that organiza-
official or organization,” SIGIR believes that tion named as the one U.S. government official
IRMO’s response of assigning this respon- responsible for U.S. capacity development
sibility to the Joint Task Force for Capacity efforts.”
Development may not resolve the organiza-
tional and program management challenges Ongoing Audits
confronting the U.S. capacity development Review of Close-out Processes and
initiative. As SIGIR observed during this Procedures for IRRF Contracts
SIGIR-6006
assessment, the Joint Task Force is a useful
mechanism for information sharing but lacks This audit will determine whether contracts
the authority to direct organizations in a funded by IRRF (including task orders, grants,
coordinated manner. This may change when and cooperative agreements) are being closed
its charter is briefed to the Executive Steering out on time and whether they comply with the
Group on January 23, 2007. However, as cur- Federal Acquisition Regulation (FAR) 4.804
rently operating, the Joint Task Force appears 1(a) and other applicable regulations, poli-
to be an organization that coordinates by cies, and procedures. SIGIR will also deter-
committee rather than having an accountable mine what steps the government program
management responsibility. SIGIR believes this and contract officials perform to ensure that
accountability, with the appropriate authority, the delivery of the goods or services meet the
is particularly important in addressing cross- identified requirements and the payments were
ministerial management problems with reasonable for goods and services received.
multiple implementing agencies and organiza-
tions. IRMO, itself, stated in its comments that Fact Sheet: U.S. Government Organiza-
tions’ Roles and Responsibilities for Iraq
the magnitude and complexity of the chal-
Relief and Reconstruction Activities
lenges faced in Iraq, combined with the many SIGIR-6012
U.S. government entities involved, presents
an organizational challenge of some magni- This report is being updated. It describes
tude. SIGIR agrees. As such, SIGIR continues the roles and responsibilities of the principal
to believe—and USAID’s response to the U.S. government organizations engaged in Iraq
draft report supports—that assigning overall relief and reconstruction. This report examines
responsibility to a single official or office with how officials in those organizations view their
directive authority is the best way forward in authority and role in the Iraq effort and how
the officials believe they interface with other Iraq Relief and Reconstruction Fund (IRRF)
organizations. (The validation of those authori- Financial Review: Unliquidated
ties, roles, and interface efforts is not in the Obligations
SIGIR-6026
scope of this review and, therefore, will not be
conducted.) The overall objective of this audit is to deter-
Objectives. The objectives of this review mine the amount of IRRF unliquidated obliga-
were to determine the roles and responsibilities tions and whether the U.S. government agen-
of each principal U.S. government organization cies responsible for reconstruction projects in
with programmatic, operational, or financial Iraq have established adequate management
stewardship for Iraq relief and reconstruction. controls over IRRF 1 and IRRF 2 unliquidated
Specifically, the review focused on these ques- obligations. SIGIR intends to answer these
tions: questions:
• Which U.S. government organizations have • How much IRRF monies remain as unliqui-
been authorized to perform a role in Iraq dated obligations?
relief and reconstruction activities? • Have unliquidated obligations or monies
• What are the authorized roles and respon- committed to complete projects been
sibilities of each organization and their deobligated, decommitted, and moved to
relationship to other organizations? cover unfunded requirements?
• How do these organizations coordinate • What management controls are in place to
policies, procedures, and activities with monitor unliquidated obligations?
each other?
• Of the U.S. government organizations that Review of Spending of Where the Money
have not had principal roles and responsi- Went under the USAID Bechtel Contract
and the Recording and Reporting of
bilities, which have provided staff to Iraq Associated Costs
relief and reconstruction? SIGIR-6028
• How much funding was provided to each
organization? What kind of funding was The objective of this review is to determine, in
provided? What was the purpose of the detail, the costs incurred by the contractor in
funding? performing work under selected contracts with
• What performance reporting does each USAID for reconstruction projects in Iraq, as
organization produce, to whom, and how well as the methods used to record and report
often? associated costs. SIGIR will also evaluate the
• What event triggers the cessation or trans- controls associated with program and contract
fer of each organization’s mission relating to management. Specifically, SIGIR intends to
Iraq relief and reconstruction? answer these questions:
• What was the original objective of the
contract?
U.S. Embassy-Iraq moves into its new com- Review of the Advanced First Responder
pound. For comparative purposes, SIGIR will Network Implementation and Sustainment
SIGIR-6039
look at similar services performed, associated
costs incurred, and which U.S. government The objective of this review is to answer these
agencies were responsible for each area under questions:
previous LOGCAP contracts, as well as similar • How effective is the Advanced First
life-support services provided under other Responder Network now that it has been
contracts in Iraq. implemented?
• Are there any sustainment issues regard-
Lessons Learned from Management and ing the operation and maintenance of the
Organizational Challenges of the Iraq system?
Relief and Reconstruction Fund
SIGIR-6032
Lessons Learned: Contracting in Iraq
This continues the SIGIR review (SIGIR-6012) Reconstruction: Design-build vs. Direct
Contracting
on how roles and responsibilities have been SIGIR-7001
assigned for the management of IRRF. This
study will identify leading practices that may The objective of this assessment is to under-
be used to guide future multi-organizational stand how the major construction contracts
interaction for managing similar relief and were managed in Iraq. SIGIR is comparing
reconstruction initiatives. The objective of this the two major project delivery systems used in
study is to answer these questions: Iraq—design-build and direct contracting—
• What is the ideal structure of a reconstruc- to U.S. industry-leading practices to identify
tion management office, in terms of roles the circumstances that enhance or limit their
and responsibilities, as it goes from train- successes. SIGIR is also assessing the outcomes
ing and planning to support deployment, of the use of each delivery system and how
pre-deployment actions, actual deployment, each met the U.S. strategic goals for relief and
and re-deployment? reconstruction.
• What should the skill set of the organiza-
tion be as it goes through these phases? Iraq Relief and Reconstruction Fund (IRRF)
• What is the ideal size during each of these Financial Review: DoS Unmatched
phases and, most especially, during the full Disbursements
SIGIR-7002
deployment phase?
The overall objective of this audit is to deter-
mine the amount of IRRF unmatched dis-
bursements and whether DoS has established
adequate management controls over IRRF 1
and IRRF 2 unmatched disbursements. SIGIR • What is the status of actions taken on
intends to answer these questions: implementing previous SIGIR recommen-
• How much IRRF monies have been identi- dations?
fied as unmatched disbursements? • What is the impact of the new sources of
• How often are unmatched disbursements funds to cost-to-complete and current
reviewed by government officials, and who financial management reporting of the Iraq
makes the determination that the disburse- relief and reconstruction efforts?
ment was an IRRF expenditure? • Are gaps in resource requirements identi-
• Have IRRF unmatched disbursements fied when comparing the cost-to-complete
subsequently been identified to other IRRF information to the funds available?
projects?
• What management controls are in place to Progress Review of the Transition of Iraq
eliminate and resolve unmatched disburse- Relief and Reconstruction Fund Projects to
the Government of Iraq
ments? SIGIR-7004
Review of Financial Reporting and Cost- The overall objective is to determine whether
to-complete Estimates for Iraq Relief and DoS, USAID, GRD, and MNSTC-I have devel-
Reconstruction U.S.-funded Programs and
oped and implemented plans for the transition
Projects
SIGIR-7003 of IRRF-funded projects to the GOI. The audit
will answer these questions:
The overall objective is to determine whether • Have U.S. agencies involved in U.S.-
IRMO, USAID, GRD, and MNSTC-I provide funded or U.S.-managed construction
accurate project financial data in required projects developed adequate procedures
reports to the Congress. The review will answer for transitioning completed projects to the
the following questions: GOI?
• Do the U.S. government reports submitted • Have there been delays transitioning
to comply with Section 2207 of Public Law projects to the GOI? If so, what have been
108-106 accurately report how estimates the cause and impact of those delays?
and assumptions contained in previous • What is the status of actions taken in
reports have changed? responding to implementing previous
• Have U.S. government agencies established SIGIR recommendations on transition and
effective internal control systems to ensure sustainment?
the accuracy of cost-to-complete estimates
and financial reports?
• What is the impact of inaccurate project
cost reporting?
Review of U.S. Sources and Uses of • What controls are in place to ensure the
Fiscal Year 2006 Funding for Iraq Relief accountability of CERP funds and project
and Reconstruction
SIGIR-7005 records?
• Were CERP funds used for intended and
The overall objective of this review is to assess authorized purposes?
how the funds from U.S. sources were used in • What performance measures are in place to
Iraq. These funds include the Economic Sup- evaluate the effectiveness of the individual
port Fund, CERP, ISFF, and any other funds CERP projects in relationship to the overall
identified during the review if used to support goals of the CERP program?
the Iraq relief and reconstruction mission in • How are commanders ensuring
FY 2006. sustainment of completed CERP projects by
the GOI?
Survey of the Department of State’s • How are CERP projects transitioned to the
International Narcotics and Law GOI?
Enforcement IRRF Projects and Efforts
in Support of Iraq Relief and
Reconstruction Further, this review will follow up on and
SIGIR-7006 assess actions taken by U.S. government
officials on the recommendations made in pre-
This review is a spin-off of the SIGIR review vious SIGIR reports on the use of CERP.
of INL efforts to build the Adnan Police
Academy. This review identified serious weak- Review of U.S.-funded Weapons Provided
nesses in contracting, contract administration, to Iraqi Security Forces
SIGIR-7008
accountability, and overall management. This
SIGIR review will also include INL’s program The overall objective is to determine whether
at the International Jordanian Police Training proper accountability has been established for
Center. U.S.-funded weapons provided to Iraqi security
forces. The review will answer these questions:
Review of the Commander’s Emergency • Has MNSTC-I taken steps to establish
Response Program (CERP) for Fiscal Year
accurate inventories for weapons provided
2006
SIGIR-7007 to Iraqi security forces?
• Has MNSTC-I determined the requisite
SIGIR plans to assess management controls spare parts and technical repair manual
and project documentation of FY 2006 CERP requirements by weapons type and, if
funds by answering these questions for a applicable, weapons model, and has it pro-
number of CERP 2006 projects: vided this information to the Ministries of
Defense and Interior?
Review of the Status of U.S. Government announced before the start of any audit field
Anticorruption Efforts in Iraq work. For the full text of the audit plan, see the
SIGIR-7009
SIGIR website: http://www.sigir.mil/.
The overall objective is to assess the U.S. These audits are planned to be announced
government’s anticorruption efforts in Iraq. To during the next quarter:
meet the objective, the audit will answer these • Review of the Effectiveness of U.S. Govern-
questions: ment Contracts To Enable Budgeting and
• Has the U.S. government developed a stra- Financial Management Capabilities in Iraqi
tegic anticorruption program with identi- Ministries
fied goals? • Comparative Analysis of the Air Force
• Do anticorruption activities conducted by Center for Environmental Excellence Ver-
all U.S. government agencies in Iraq sup- sus Gulf Region Division in IRRF (Project
port the U.S. anticorruption strategic plan? Management and Contracting)
• Have organizational roles and responsibili- • Review of Spending on Parsons Facilities
ties been clearly identified and resources and Transportation Sector Design-Build
provided to meet strategic program goals? Contracts and the Recording and Report-
• Have U.S. government agencies established ing of Associated Costs
programs to strengthen Iraq’s inspectors • Review of U.S. Government Organizations’
general? Efforts To Execute Job-producing Programs
• Have the appropriate U.S. government in Iraq
agencies developed action plans or imple- • Review of U.S. Government Organizations’
mented the recommendations made in Efforts To Expand Provincial Reconstruc-
previous reports? tion Teams in Iraq
• Controls Over U.S. Government Prop-
Planned Audits erty and Equipment in the Possession of
SIGIR will conduct performance audits that Design-Build Contractors
assess the economy, efficiency, effectiveness, • Review of the Use of Sector Project and
and results of Iraq reconstruction programs Contracting Office Contractors (SPCOCs)
and operations as necessary. These audits will in Managing IRRF Projects
be accomplished through individual audit • Review of U.S. Government Efforts To
projects of specific issues, as well as an audit Expand the Micro-loan Program
series that will evaluate several components
of related topics. Each of these audits will be
Recommendations
Report
Number Report Title Date Issued Total Closed In-process
Note: Since the July 2006 semiannual Report, the number of open recommendations was adjusted to more accurately reflect components of
recommendations that are being tracked as iterative corrective actions are addressed.
Table 3-2
SIGIR Inspections
During this quarter, SIGIR visited, assessed, As of December 31, 2006, SIGIR has com-
and reported on 15 construction projects pleted 80 project assessments, 96 limited on-
across Iraq, yielding a variety of results. SIGIR site inspections, and 266 aerial assessments.
found several well-constructed projects with
sufficient contractor quality control (QC) Project Assessments:
and effective U.S. government quality assur- Findings at a Glance
ance (QA) programs in place. In one notable These are the highlights of SIGIR’s inspection
instance, however, SIGIR found serious work this quarter.
construction deficiencies that stemmed from
insufficient government oversight and inad- Al Alwaiya Maternity Hospital
equate contractor performance. Recurrent ($1.99 million)
construction problems included contractor • The project was sufficiently well-designed
failure to comply with international standards to renovate the facility.
required in the contract, construction on • Construction work was consistent with the
non-compacted soil, deficient concrete pours, standards of the contract design.
substandard plumbing installation, and unsafe • The contractor’s QC plan was sufficiently
electrical wiring. detailed to effectively guide the contractor’s
Lack of security continued to impede quality management (QM) program.
construction and SIGIR assessments. Because • The government’s QA program effectively
of safety concerns, personal security details monitored the contractor’s QC program.
would not escort SIGIR assessment teams to • The city of Baghdad should receive a reno-
several sites. vated and modernized maternity hospital.
SIGIR’s presence across Iraq continues to
positively affect reconstruction efforts. For Al Alwaiya Children’s Hospital
example, last quarter, after receiving com- ($1.29 million)
plaints about substandard construction work at • The project was sufficiently well-designed
the Baghdad Police College, SIGIR conducted to renovate the facility.
a quick reaction report on the site. The SIGIR • Construction work was consistent with the
report prompted a rapid response by the U.S. standards of the contract design.
government, prime contractor, subcontractors, • The contractor’s QC plan was sufficiently
and additional contractors hired to begin to detailed to effectively guide the contractor’s
remediate problems and complete work not QM program.
performed by the original prime contractor. At • The government’s QA program effectively
the time of this report, these actions still have monitored the contractor’s QC program.
not been fully successful. • This renovation/modernization will result
in a modern facility that provides a healthy • When the system of tanks is filled with
and safe environment for patients, visitors, water, it is designed to remain in place and
and employees. supply clean water to the water distribu-
tion system. If completed as designed, the
Dahuk Rehabilitation Center project will likely be sustainable for years to
($5.63 million) come.
• The contract’s design and specifications
were specific enough to complete construc- Al Kasik Waste Water Treatment Plant
tion of the facility because the U.S. Army ($2.7 million)
Corps of Engineers (USACE) conducted a • In general, project components were
prudent evaluation of pre-existing condi- adequately designed before construction.
tions and current requirements. However, because the chlorination system
• Closely supervised craft-specific crews per- disinfected wastewater at the pre-filter
formed the construction work, and effective stage, the unfiltered suspended solids
QM practices ensured adherence to design reduced the efficiency of the disinfection.
standards. • Construction at the plant met design stan-
• Project sustainability was adequately dards, with two exceptions—the clarifier
addressed in the contract. tank’s sweep-arm assembly and the G-3
• When completed, the Dahuk Rehabilitation pump station were deficient.
Center project should be a modern self- • The contractor’s QC and the U.S. govern-
contained prison facility, as designed. ment’s QA programs were found to be
generally effective.
Al Kasik Water Storage Tanks • Some aspects of project sustainability were
($4.9 million) not adequately addressed in the contract.
• The completed construction work complied First, the inventory of backup replacements
with the design standards for the Al Kasik and spare parts provided was not sufficient
Water Storage Tank project. to effectively maintain components to
• The contractor’s QC and the U.S. govern- sustain operations. Second, it is likely that
ment’s QA were adequate and ensured insufficient operational/run testing, and
effective QM during construction. ineffective plant operator training before
• The construction of the water storage tanks turnover, contributed to the failure of the
comprised a system of eight tanks of the clarifier tank.
same design and size. The covered, non- • The plant did not operate between March
pressurized water-holding tanks offer a 19, 2006, and August 8, 2006, when the
high degree of sustainability when properly assessment team completed the site visit.
constructed. Until repaired, raw sewage in excess of
the daily holding capacity will continue to • The project has resulted in the construc-
be pumped into the countryside through tion of new buildings and facilities for Iraqi
a surface ditch; this practice creates a Army soldiers. SIGIR noted concerns with
potential health hazard to local people and the motor pool that require follow-up by
groundwater. USACE.
• During initial fieldwork, SIGIR confirmed
that action was underway to correct defi- Al Hillah Police Firing Range ($.43 million)
ciencies with the sweep-arm in the clarifier • The firing range components were ade-
tank. On October 2, 2006, representatives quately designed before construction.
of the Air Force Center for Engineering • The work completed at the time of SIGIR’s
Excellence (AFCEE) confirmed that recon- on-site inspection met the standards of the
struction of the G-3 pump pad structure design.
was to begin on December 12, 2006. • USACE ensured quality and compli-
ance with the contract requirements. The
51st Brigade Iraqi Army Barracks completed project work will result in a fully
($.99 million) functioning firing range with 12 rifle-firing
• The USACE design package was adequate stations and 12 pistol-firing stations for the
to construct the buildings and most of the Iraqi Police.
facilities that were included in the contract
scope. 402nd Battalion Iraqi Army Headquarters
• Most of the construction appeared to meet Barracks ($.74 million)
the standards of the Statement of Work • The USACE design package was adequate
(SOW) and design. to construct the buildings and most of the
• The contractor’s QC plan was sufficiently facilities that were included in the contract
detailed to effectively guide the contractor’s scope.
QM program. • In general, the construction appeared to
• The government’s QA program effectively meet the standards of the SOW and design.
monitored the contractor’s QC program. However, a noticeable crack in the class-
• Sustainability was not adequately addressed room building exterior requires further
in the basic contract and was not men- assessment by USACE. In addition, because
tioned in the task order requirements. In the water-tank design lacked sufficient
addition, this report identified low-quality detail, the water-tank construction should
plumbing fixtures and barracks building be assessed for structural adequacy.
doors used by the contractor. The use of • The contractor’s QC and the government’s
these items will present the Iraqi Army with QA program were effective.
continual maintenance problems. • Sustainability was not adequately addressed
in the basic contract and was not men- and did not comply with the international
tioned in the task order requirements. In standards required by the contract and task
addition, this report identified low-quality orders.
plumbing fixtures and barracks building • The government’s QA program was essen-
doors used by the contractor. The use of tially non-existent in terms of monitoring
these items will present the Iraqi Army with the contractor’s performance. The govern-
continual maintenance problems. ment did not review the contractor’s daily
• The project has resulted in the construc- QC reports. In addition, the government
tion of new buildings and facilities for Iraqi QA representatives tracked project progress
Army soldiers. SIGIR noted concerns about but did not identify quality issues. They did
the classroom building and water tank that not identify any construction deficiencies
require USACE to follow up and possibly noted in the contractor’s daily QA reports.
take remedial action. Consequently, USACE was not aware of
significant construction deficiencies at the
Baghdad Police College ($72.25 million) project site.
• Project components were not adequately • Sustainability was addressed in the task
designed before construction. The con- order requirements, yet not adequately
tractor did not provide, and the govern- administered by USACE.
ment did not review, the required number • The Baghdad Police College construction
of design drawings. For the design draw- and renovation results were not consistent
ings that were reviewed, the government with the original contract objectives. The
determined that the submittals were project was poorly designed and con-
generally incomplete and inadequate. For structed, and the contractor and USACE
several buildings, the 100% design drawing did not effectively manage the project.
submittals were rejected by the government
reviewer. Electrical Substation Sustainment
• Most of the work that SIGIR observed did ($28.27 million)
not meet the standards of the contract and • The facilities were secured and in good
task orders. SIGIR identified significant repair.
construction deficiencies, such as poor • The substation operation was staffed by
plumbing installation, expansion cracks, personnel with adequate skills to manage
concrete segregation and honeycombing, and operate them.
reinforcement bar exposure, and poor • Spare parts, drawings, and operating
brickwork. Also, the construction and manuals were provided as required by the
equipment installation were performed at a contract.
low level of workmanship by the contractor
NA Al Kasik Waste Water Treatment Plant Ninewa $2,700 AFCEE Shaw North
23025 51st Brigade Iraqi Army Barracks Babylon $999 GRD Local South
23540 Al Hillah Police Firing Range Babylon $434 GRD Local South
Table 3-3
Figure 3-1
Project Assessments
1
2
2
2 3 2 1
1
8 1
2 1 1
2
4
66
3 2
1 7
1 1
3 5
4 35
This Quarter
Other Quarters
Appendix J. Figure 3-1 shows the approximate 2006, the current Iraqi contractor had com-
location of each project assessed. pleted 7% of the remaining project require-
ments.
SIGIR Project Assessments The objective of the project was to reha-
Al Alwaiya Maternity Hospital, bilitate the Al Alwaiya Maternity Hospital in
Baghdad, Iraq central Baghdad, originally constructed in
SIGIR PA-06-064
1969. Before the start of the renovation project,
This project was originally started under Task the hospital’s capacity was 300 beds. When
Order 0006 of Contract W914NS-04-D-0006, the project began, the hospital’s infrastructure
an indefinite delivery/indefinite quantity was in very poor condition: the hospital was
design-build contract, awarded in March 2004 capable of supporting only 70 of the original
by the Coalition Provisional Authority (CPA) 300 beds. The contract scope of work included
to Parsons Delaware, Inc. In May 2006, the installing new updated equipment and
USACE Gulf Region Division-Project and replacing critical hospital systems (mechan-
Contracting Office (GRD-PCO) novated its ical, electrical, structural, and sanitary). The
contract with Parsons Global Services, Inc. contract scope also included a complete
On May 11, 2006,
project GRD-PCO awarded a firm
asses_map.ai architectural renovation of the hospital’s ten
fixed-price contract (W91GXZ-06-C-0011) buildings, including repairing and replacing
to an Iraqi subcontractor of Parsons Global windows and doors, repairing and repainting
Services, Inc. (Parsons). According to USACE, exterior and interior walls, repairing ceilings
when the project was terminated, Parsons had and installing suspended acoustical ceilings
completed 60% of the project requirements. in main corridors, and installing new flooring
When SIGIR inspected the project in June throughout the hospital buildings.
Renovation in progress:
• Building B1 (ground floor), women’s health
and laboratory (rear portion of building)
• Building B8, kitchen and laundry
• Building B9, patient wards
• Water storage and distribution system
Site Photo 2. Patient room in women’s health and laboratory building.
Building B1 (Site Photo 1) and the Reverse
Osmosis Purification Unit were completed
under the Parsons contract. Renovation work
was in progress on the remaining buildings
and facilities included in the contract scope.
The work that SIGIR observed appeared to
comply with the contract requirements. The
Al Alwaiya Maternity Hospital modernization
project results were consistent with the original
contract objectives. When complete, the hos-
pital renovation/modernization project should
improve healthcare facilities and services in
Baghdad.
Site Photo 3. Patient ward in Building B9 after demolition of wall plaster
and flooring.
This project was originally started under Task What SIGIR Found
Order 0006 of Contract W914NS-04-D-0006, The SIGIR assessment team reviewed the
an indefinite delivery/indefinite quantity construction design and bill of quantities
design-build contract, which the CPA awarded and found them sufficient for the renovation
to Parsons Delaware, Inc., in March 2004. A project. SIGIR’s on-site assessment included
modification to the basic contract changed the inspections of these buildings and facilities:
name of the contractor from Parsons Delaware
to Parsons Global Services, Inc. (Parsons). Completed renovation work:
In May 2006, GRD-PCO novated its con- • Building B2, emergency wards
tract with Parsons. On May 11, 2006, GRD- • Building B5, outpatient clinic
PCO awarded a firm fixed-price contract • Building B7, laundry
(W91GXZ-06-C-0010) to the subcontractor • Reverse Osmosis Purification Unit
of Parsons. According to USACE, Parsons had
completed 65% of the project requirements Renovation in progress:
at the time of its termination. When SIGIR • Building B1, wards, laboratories, and x-ray
inspected the project in June 2006, the cur- rooms
rent Iraqi contractor had completed 8% of the • Building B10, administration and doctor
remaining project requirements. residences
The objective of the project was to reha-
bilitate the Al Alwaiya Children’s Hospital All completed renovation work noted above
in central Baghdad. Originally constructed was accomplished under the Parsons contract.
in 1956, the hospital required a major repair The ongoing renovation work was performed
and reconstruction effort. The contract scope by the current Iraqi contractor.
Site Photo 4. Pharmacy entrance in outpatient clinic. Site Photo 5. Construction in Building B1 (wards, laboratories, and
x-ray rooms).
The completed work and work in progress original contract objectives. As a result of the
observed by the team appeared consistent with renovation, this hospital, when completed,
the contract requirements. The government should provide modern healthcare facilities for
QA was effective in monitoring the contractor’s Iraqi citizens.
QC. The USACE QA Representative (QAR)
maintained daily QA reports that documented Sustainability
any deficiencies noted at the site. The Deputy Sustainability was addressed in the contract. It
Resident Engineer and the QAR ensured that required a one-year warranty for all building
the deficiencies cited during QA inspections equipment, construction, and components
were corrected. and commonly offered extended warranties
The Al Alwaiya Children’s Hospital project for equipment and machinery purchased. In
results, to date, were consistent with the addition, the task order required three legible
PA-06-070
Site Photo 7
copies of O&M manuals, written in English plans and specifications of the work previously
and Arabic, for all new equipment, finishes, started and stopped as a 90% design
fixtures, and hardware. submission.
• Contract Line Item 1 included the design
Dahuk Rehabilitation Center, and complete repair of the existing struc-
Dahuk, Iraq ture based on a pre-construction defi-
SIGIR PA-06-070
ciency assessment conducted by USACE,
The objective of the Dahuk Rehabilitation including the main structure, grounds, and
Center project was to finish discontinued con- all associated utilities, excluding the power
struction of a modern self-contained prison plant, equipment, and water tanks. Addi-
facility designed to house 1,490 inmates so tionally, design completion included all
that juveniles, women, and other inmates with necessary modifications to existing draw-
varied sentences (light to maximum security) ings to match dimension measurements
would be housed separately. The GOI started with the actual existing physical structure.
the project in late 2000, but discontinued work • Contract Line Item 2 included the complete
Site Photo 9
in mid-2001 because of political and funding design and construction of a power plant,
issues. When halted, the facility’s structural equipment, and water tanks specifically
concrete framework was completed. This excluded from Contract Line Item 1.
concrete skeleton from the previous work • Contract Line Item 3 included require-
served as a starting point for new construction. ments for the contractor to provide designs
USACE performed a detailed assessment of the only, without any construction, for con-
existing concrete structure to baseline current tractors providing items or work that were
contract requirements. “furnished by others.”
The contract’s SOW included three distinct
lump-sum contract line items. Overall, the What SIGIR Found
contractor was required to provide all of the The contract’s design and specifications were
design, labor, and material to complete the specific enough to construct the facility
three contract line items, using the existing because USACE conducted a prudent evalu-
PA-06-070
Site Photo 7
Site Photo 9
ation of pre-existing conditions and current contractor established a fabrication shop with
requirements. In addition to reviewing rel- a variety of metal-working tools to construct
evant project documentation and conducting reinforced frames with metal bars for window
discussions with selected government repre- and door applications throughout the facility.
sentatives, the assessment team conducted a Contractor performance appeared to meet the
site visit on July 31, 2006, when the project standards of the design. SIGIR did not identify
was estimated to be 60% complete. During any negative findings or recommendations for
the site visit, the assessment team observed corrective action. When completed, the project
closely supervised craft-specific crews working should meet the intended objective if past con-
throughout the facility. struction and oversight practices continue.
The SIGIR report described various tech- The U.S. government’s QA and the contrac-
niques used by the contractor to ensure tor’s QC programs were effective. QA and QC
acceptable construction work. For example, the functions were performed by the same people
since the project’s beginning—a key to the Al Kasik Water Storage Tanks,
effectiveness of the QC and QA programs. The Al Kasik, Iraq
benefit of such continuity was apparent during SIGIR PA-06-071
the assessment team’s on-site visit. Specifically, The objective of the project was to construct
QA and QC personnel were well-informed a storage tank system for potable water, with
about the project’s history, progress, and status. a capacity of no less than 7.7 million liters.
The SOW specified the contractor’s roles and
Sustainability responsibilities and provided details on the
Project sustainability was adequately addressed specifications and testing requirements. The
in the contract. In addition to completing contract SOW also addressed the piping,
construction of the main facility—which valves, meters, pumps, and control equip-
included a power generating and distribution ment required to incorporate the system of
system and a heating and cooling plant—the storage tanks with existing water distribution
contractor was required to provide a design and treatment systems. Based on the final
package for all furnished items or work to be design, most of the physical construction was
completed by other subcontractors. Including devoted to building a system of eight equally
a design package requirement from a single configured tanks to yield a minimum system
source should increase the cohesiveness of capacity of 7.7 million liters. The water storage
work to be completed by an array of tank project was initiated to replace inadequate
subcontractors. water storage facilities with facilities that have
greater capacity and are in better condition.
Al Kasik Waste Water Treatment Plant, the facility was not operating or processing
Al Kasik, Iraq wastewater because of a catastrophic failure of
SIGIR PA-06-074
the sweep-arm assembly in the clarifier tank
The project objective was to plan and construct on March 19, 2006. As a result, since the failure
a wastewater treatment plant that complies occurred, raw sewage has been pumped off the
with the specifications of World Health Orga- site. Until the sweep-arm assembly is repaired,
nization 2000. The contractor was required sewage will continue to be pumped into the
to develop a work plan to select, provide, and countryside through a surface ditch, which
install a complete wastewater treatment plant. creates a potential health hazard to local people
Specifically, the SOW required the full range of and groundwater. AFCEE representatives
construction and engineering activities to meet confirmed that repairs to the facility started in
all customer requirements and project early December 2006.
objectives. In general, project components were
adequately designed before construction.
What SIGIR Found However, the assessment team noted that the
In addition to reviewing relevant project installed chlorination system disinfected the
documentation and conducting discussions wastewater at the pre-filter stage. During this
with selected government representatives and stage, suspended solids reduced disinfection
Iraqi wastewater treatment plant operators, the efficiency. As an alternative, a post-filter stage
assessment team visited the site on August 1, 3, chlorination process would have been more
7, and 9, 2006, to conduct a thorough inspec- effective because suspended solids would have
tion of the wastewater treatment plant. No been significantly reduced before the chlori-
construction was in progress because construc- nation process. In addition, the chlorination
tion was completed and accepted by the U.S. solution used, per design, may not have been
government on February 13, 2006, and the compatible for storage in the high-temperature
contractor departed from the site on February extremes of the local environment.
18, 2006. However, at the time of the site visit,
Site Photo 13. Crumbling mortar at the surface of the vehicle ramp.
What SIGIR Found that GRS assess the adequacy of the concrete
The SIGIR assessment team reviewed con- vehicle ramps and the structural steel frame
tract documentation, construction drawings supporting the facility’s roof.
and specifications, and QC and QA reports,
and the team conducted interviews with GRS Sustainability
personnel. SIGIR concluded that the USACE- SIGIR concluded that sustainability was not
developed design was adequate to construct adequately addressed in the basic contract and
the buildings and facilities included in the not mentioned in the task order requirements.
scope of work. However, there were no struc- The basic contract did not address spare parts
tural drawings for the motor pool facility, and lists, major catalog cuts, or a specific one-year
there were no drawings for the paving work warranty on all materials and workmanship
defined in the scope of work. for the buildings and facilities constructed
The SIGIR assessment team concluded that or renovated in this project. In addition,
most of the construction appeared to meet the assessment team identified low-quality
the standards of the SOW and design. How- plumbing fixtures and barracks building doors
ever, the team identified some punch-list item used by the contractor. The use of these items
deficiencies that should be corrected by the will present the Iraqi Army with continual
contractor before final acceptance by USACE. maintenance problems.
The assessment team also noted deficiencies
with the motor pool vehicle maintenance
ramps and details associated with the struc-
tural steel. Because the motor pool design
lacked sufficient detail, SIGIR recommended
Al Hillah Police Firing Range, At the time of the assessment, the project
Hilla, Iraq was 95% complete. The range-control building
SIGIR PA-06-076
and 24 firing stations were substantially fin-
The objective of this project was to construct a ished, except for punch-list items. Remaining
combination rifle and pistol range for the Iraqi work included completing the installation of
Police at the Police Academy in Hilla, Iraq. the generator fuel tank and constructing a
This project was constructed under a fixed- sunshade for the electrical generator.
price contract awarded by USACE GRS. The
scope of work included construction of these What SIGIR Found
buildings and facilities: Based on the SIGIR assessment team’s review
• 12 cast-in-place reinforced concrete pipes of contract documentation, construction
(rectangular tubes) for rifle-firing stations drawings, and specifications, the team con-
• 12 cast-in-place reinforced concrete pipes cluded that the design developed by USACE
(rectangular tubes) for pistol-firing stations was adequate to construct the 12 rifle-firing
• range-control building with armory, bath- stations and the 12 pistol-firing stations.
rooms, first-aid room, and waiting area for Each firing station included a sunken firing
students pit covered by a steel sunshade, as well as a
• generator pad and sunshade, 100-kilovolt- reinforced concrete firing tube for the shooter
amp (kVA) generator, 2,000-liter fuel tank, to fire into at a target located in a concrete
and main distribution panel with automatic and masonry enclosure at the other end of the
transfer switch firing tube. The design for the range con-
• four 9.1-meter aluminum light standards trol building, added to the project scope by
with 250-watt high-pressure sodium modification, comprised a single architectural
luminaries drawing. There were no structural, electrical,
• site work, including sidewalk construction or mechanical drawings for the building, but
Site Photo 15. Rifle-firing stations. Site Photo 16. Pistol-firing station showing shooter’s pit,
firing tube, and target enclosure.
the contractor had substantially completed by USACE GRS. The scope of work included
construction of the building with no signifi- construction of these buildings and facilities:
cant deficiencies observed during SIGIR’s on- • two 75-man barracks
site assessment. In addition, the construction • two ablution buildings with 8 water closets,
of the rifle-firing and pistol-firing stations met 7 showers, and 8 hand-washing stations
the standards of design. USACE GRS per- • medical clinic addition
sonnel from the Babil Resident Office ensured • classroom building
quality and compliance with the contract • armory
requirements. The completed project work will • water storage tank (300 cubic meters)
result in a fully functioning firing range with • asphalt concrete roads and pads
12 rifle-firing stations and 12 pistol-firing sta- • covered parking (sunshades) for 48 vehicles
tions for the Iraqi Police.
At the time of the assessment, the project
Sustainability was 95% complete. The buildings were sub-
Sustainability was addressed in the contract stantially complete, except for punch-list items.
requirements. The contract specifications Remaining work included completion of the
required a one-year warranty on all materials water storage tank and road paving.
and workmanship for the buildings and facili-
ties constructed in this project. In addition, What SIGIR Found
the contract required the training of at least The SIGIR assessment team reviewed contract
two people designated by the police in the documentation, construction drawings and
operation and maintenance of the generator. specifications, and QC and QA reports. The
Further, the contract stated that all operating, team also interviewed GRS personnel. They
maintenance, and repair manuals be provided found that the design developed by USACE
in Arabic. was adequate to construct the buildings
and facilities included in the scope of work,
402nd Battalion Iraqi Army although the design of the water tank and the
Headquarters Barracks, architectural drawings lacked some details.
Hilla, Iraq The inspection team did not observe signifi-
SIGIR PA-06-077
cant deficiencies. However, the team observed
The objective of this project was to construct a noticeable settlement crack in the class-
new buildings and facilities for the 1/2/8 (for- room building exterior. In addition, because
merly 402nd) Battalion Garrison, Iraqi Army, the design of the water tank lacked sufficient
in Hilla, Iraq. This project was constructed detail, SIGIR recommended that GRS review
under a task order issued under an indefinite the water tank construction for structural
delivery/indefinite quantity contract awarded adequacy.
Site Photo 26
Site Photo 25. Evidence of improperly placed exposed reinforcement bar, PVC conduit, and rust.
the common practice of local subcontractors fix,” this facility was removed from the SOW
is to cement joints in the bathroom areas (Site under the contract after the government paid
Photo 23); however, the IPC strictly prohibits approximately $350,000 for the poor construc-
this practice. As a result of not complying tion work. Demolishing the facility will require
with the IPC requirement, the BPC will be approximately $100,000. Site Photo 25 depicts
faced with continual maintenance problems, the poor construction of the central laundry
including the backup and overflow of facility.
wastewater.
SIGIR also observed significant expan- Quality Management Program
sion cracks on the exterior and interior of the The contractor’s QC plan was sufficiently
instructors’ barracks buildings (Site Photo 24). detailed to effectively guide the contractor’s
SIGIR determined that the contractor’s as-built QM program, including the use of daily QC
drawings did not reflect the reality of what was reports and NCRs to document construction
actually constructed at the instructors’ bar- deficiencies. However, the contractor’s QC
racks. Representative did not identify significant con-
Construction was so poor for the central struction deficiencies, such as poor plumbing
laundry facility that the contractor issued a installation practices and substandard expan-
Nonconformance Report (NCR), and work sion joints. Even when the NCRs identified sig-
was stopped while independent assessments nificant construction deficiencies, there was no
were conducted to determine whether the assurance that corrective actions were taken. In
construction deficiencies could be corrected. addition, it appears that the contractor did not
The independent assessments determined that provide the NCRs to the government’s Con-
it would be too costly to attempt to correct tracting Officer Representative, which the QC
the structural construction deficiencies. Even plan required.
though the subcontractor agreed to “take The government QA program was essen-
financial responsibility for the engineering tially non-existent in terms of monitoring the
contractor’s QC program. Neither the USACE of the original contract and TOs. The contract
Gulf Region Central (GRC) Project Engineer SOW called for providing the “Iraqi people
nor the QAR reviewed the contractor’s daily with necessary basic public facilities and
QC reports. In addition, the QAR was used to infrastructure with sufficient space accommo-
track project progress—not to identify quality dations and reliable public works, electrical,
issues. The QAR did not identify any con- plumbing, mechanical, and communications
struction deficiencies in the daily QC reports. resources that are easy to maintain, upgrade
Consequently, USACE GRC was not aware and repair….” The completed barracks
of significant construction deficiencies at the buildings continue to experience significant
project site. plumbing failures; the massive expansion
USACE GRC will receive a fee of 4% of cracks on the interior and exterior of the
the cost of both task orders for what it stated buildings will leave the Iraqis with continual
was a “limited Quality Assurance role.” This maintenance issues.
included using the on-site QAR to “track In addition, this project’s construction
progress toward” project completion instead costs were originally estimated to be approxi-
of identifying construction deficiencies. mately $73 million. In an effort to complete
According to USACE GRC personnel, the the project, which was experiencing signifi-
daily QA reports given to the QAR did not cant cost overruns and schedule slippages,
“contain a block for quality issues.” USACE 24 items were removed from the scope of
GRC believed that the PCO “assumed the work under the contract, such as the laundry
responsibility for project oversight and review facility, fire protection, and the communica-
of the Quality Assurance Reports….” As a tions building. The laundry facility was 51%
result, USACE GRC will be paid approxi- complete, and the communications building
mately $2.5 million for simply tracking the was 38% complete. Other items—such as the
progress of the project completion instead of driving course, connection to the power grid,
enforcing the procedures set forth in its own and structural repairs—were de-scoped with
guidance on the QA program. no work done at all.
Finally, as a result of USACE’s poor project The U.S. government estimates that it
management and lack of oversight, the U.S. will pay Parsons approximately $62 million
government paid Parsons approximately for work both fully and partially completed.
$5.3 million in base and awards fees for sub- Additional contracts with other contractors
standard work. in excess of $8 million have been awarded
to complete some of the construction work
Conclusions not finished by Parsons. However, most of
The BPC construction and renovation project the de-scoped items, which were originally
results were not consistent with the objectives determined to be essential to a functioning
police training college, will either be left as a 3. Require the USACE QARs to become thor-
shell (the communications building) or not oughly familiar with the IPC standards.
even begun (the driving course and fire protec- 4. Require the USACE Project Engineer and
tion). USACE has been unable to provide the QARs to supervise the contractor’s instal-
original estimated costs and amounts paid for lation of all plumbing rework to ensure
each of the de-scoped items; therefore, it is not compliance with the IPC.
possible to determine how much new funding 5. Require the USACE GRD Resident Engi-
will be required to complete all of the objec- neer to thoroughly review the as-built
tives of the TOs. drawings submitted by the contractor.
The BPC construction and renovation Specifically, walk through each facility and
project results were not consistent with the compare the as-built drawings to the actual
original contract and TO because the project construction completed.
was poorly designed and constructed, and 6. Require the contractor to resubmit, at no
the contractor and the USACE GRC Project cost to the government, accurate as-built
Engineer and QAR did not effectively manage drawings for any deviations noted during
the project. the walk-through of the facility.
7. After completing the thorough review of
Recommendations the as-built drawings, verify the contractor’s
SIGIR recommended that the Commanding individual charges against the confirmed
General, GRD: work performed. Determine if the con-
1. Require the contractor to replace all tractor was paid for work claimed, but not
existing plumbing fixtures and fittings in performed. Specifically, determine if the
all newly constructed buildings to comply contractor charged, and was paid, for engi-
with the IPC in accordance with contract neered expansion joints in the instructors’
specifications. Specifically, eliminate the barracks. If so, then recover the money paid
use of cemented joints, abnormal fittings, to the contractor.
and improperly sealed pipe connections. In 8. Require the USACE QARs to be present
addition, require the use of cleanouts, traps, for any future plumbing tests. In addition,
and proper sealing techniques. require the QARs to document the tests
2. Require the USACE GRC QARs to be performed, equipment used, and test setup
responsible for identifying quality issues as information.
required by the contract and USACE ER 9. Require the Project Engineer and QARs to
1180-1-6, instead of simply tracking project review the 95 NCRs submitted by Parsons
progress. for construction deficiencies and determine
if corrective actions were previously taken.
If corrective actions were not taken, require classrooms—to train a substantial number
that necessary corrective actions be taken. of cadets. Instead, the poor construction and
oversight forced the Baghdad Police College to
Indications of Potential Fraud relocate cadets from one barracks to another—
During this inspection, SIGIR found indica- and in at least one case, into a classroom—as
tions of potential fraud and referred these temporary living quarters to protect cadets
matters to SIGIR Investigations. from leaking urine and fecal matter.
In view of GRD’s admission that “estab-
Management Comments lished international standards” were not fol-
GRD generally concurred with the conclu- lowed by the contractor and enforced by the
sions in the draft report; however, GRD did government, SIGIR continues to believe that
not concur with all of the draft report’s rec- the recommendations are appropriate and will
ommendations. GRD noted that the stra- work with GRD to reach a mutually satisfac-
tegic and urgent need to quickly provide a tory resolution.
training capability for the Iraqi Police has been
achieved. And despite identified shortfalls in Electrical Substation Sustainment
workmanship of the sewer, water, and electrical SIGIR PA-06-082-Al Hakamia
SIGIR PA-06-083-AL Hamdan
infrastructure of the facilities, not one gradua- SIGIR PA-06-084-Al Kaffat
tion has been delayed, nor has a single class of SIGIR PA-06-085-Al Serajii
cadets been delayed. SIGIR PA-06-086-Shat al Arab
GRD’s comment regarding the ability
of the Baghdad Police College to graduate The SIGIR Inspections directorate is assessing
cadets is irrelevant to the issues raised in this completed projects to determine whether they
report. The contract and task orders specifi- are likely to remain operational after transition
cally required the construction of the Baghdad from the U.S. government to the GOI.
Police College to comply with international This report addresses SIGIR’s assessments
building standards and diligent quality man- of five electrical distribution substations
agement by the contractor and the govern- completed in Basrah in September 2005 and
ment. In its comments, GRD confirmed that transitioned to the Southern Distribution
international building standards were not Company, which reports to the Iraqi Minister
followed and that the quality management of Electricity. The substations were designed to
program of the contractor and the govern- convert high-voltage transmission electricity
ment was not adequate. The intent of the to low-voltage electricity and feed it through
contract and task orders was to provide the distribution lines to support local electrical
Baghdad Police College staff an adequate demands. SIGIR originally performed con-
training facility—including cadet barracks and struction assessments of all five substations in
Site Photo 26. Al Hamdan substation distribution: 11 kV switchgear Site Photo 27. Al Hamdan substation distribution: 11 kV
panels at the time of the initial assessment. switchgear panels at the time of the second assessment.
Site Photo 28. Al Serajii 33/11 kV transformer, first assessment. Site Photo 29. Al Serajii 33/11 kV transformer, second
assessment.
July 2005 and found the construction quality substations. The transmission lines to the
adequate and consistent with contract require- fifth substation at Shat Al Arab were being
ments. However, the report noted that none routed, but had not yet been completed. On
of the five substations were energized because October 19, 2006, SIGIR observed two of
incoming transmission lines and outgoing the five substations, but because of security
distribution lines were not connected. conditions, personal security representatives
PCO491 informed SIGIR at that time would not escort SIGIR inspectors to the other
that plans to energize the substations were three. However, through representations made
underway. A $10 million transmission feeder by the Resident Engineer USACE GRS and
contract funded with IRRF funds had been Iraqi Southern Distribution Company rep-
awarded to an Iraqi company on April 30, resentatives and a review of documentation
2005. The distribution feeders were the respon- and analysis of satellite imagery of the unob-
sibility of the Iraqi Ministry of Electricity. served substations, SIGIR believes that none
of the unobserved substations have suffered
What SIGIR Found any significant deterioration since they were
At the time of this second assessment, SIGIR transferred to the Ministry of Electricity. Two
was informed that transmission and distribu- of the three unobserved substations appear to
tion lines were connected to four of the five be operating, and the third is waiting for the
transmission line connection before it can be formal training that the subcontractor pro-
energized. vided to ten Iraqis appears to have provided
The facilities were secured and in good no value to the substation operations because
repair and showed no significant deteriora- none of the Iraqis selected by the Ministry of
tion since the first assessment. Four of the five Electricity for training were assigned to opera-
substations were operational, and the fifth was tions or management positions in the Southern
awaiting the connection of the incoming trans- Distribution Company.
mission line. SIGIR was informed that the fifth Spare parts, drawings, and operating
substation became operational during the week manuals were provided as required by the
of November 26, 2006. contract. However, confusion over the official
Although the substations were capable of acceptance process appears to have caused
distributing power to the grid at the time of the spare parts to be left in unopened boxes next to
second assessment, they were operating at only at least one substation for more than one year.
36% capacity, partly because of insufficient Neither the contractor nor the GRS Resident
input from upstream transmission substations Engineer was notified by Southern Distribu-
and partly because of excess switching capa- tion Company personnel that the spare parts
bility designed into the substations to meet boxes had not been opened.
long-term demand. The substations should SIGIR recommended that the USACE
achieve their stated objective when the trans- GRD-Electric Sector Program Office take these
mission lines are connected to the Shat Al actions:
Arab substation and the transmission capacity 1. Continue actions to connect the transmis-
is increased to provide adequate power to ener- sion lines to the Shat Al Arab substation.
gize distribution feeders to meet local demand. 2. Execute a memorandum of understanding
Protective relays used to manage power with the Iraqi Minister of Electricity that
surges in the distribution feeders may not be would require assigning formally trained
robust enough for the current environment. Iraqis to specific positions that directly
The absence of replacement relays required the benefit the project. Absent a formal agree-
cannibalization of non-energized lines. If left ment, the Ministry of Electricity should be
unresolved, degradation in distribution could required to pay the training costs.
diminish the power supply to the Basrah area. 3. Modify the project transfer process to
ensure that there is no misunderstanding or
Sustainability confusion over responsibility and delivery
The substation operations appeared to be procedures for spare parts, drawings, and
staffed by personnel with adequate skills to operating manuals.
manage and operate them. However, the
Aerial Image 2. Time-phase overview of a water treatment facility in the Al Muthanna region. Imagery on the left shows the
construction of support buildings on October 3, 2004. Imagery on the right shows the completed water treatment facility on
February 25, 2006.
3 9 2
provided imagery to support SIGIR audits 10 1
2
7
5
and investigations during previous quarters, This Quarter
in addition to its standard role of supporting Other Quarters
SIGIR Investigations
SIGIR fields the largest number of fraud inves- tional Working Committee (IWC). The IWC
tigators in Iraq. This quarter, SIGIR continued serves as a valuable link between federal law
to work closely with the Major Procurement enforcement agencies and DoJ, as well as a
Fraud Unit (MPFU) of the U.S. Army Criminal vehicle to discuss issues concerning additional
Investigation Command (CID). Also, SIGIR funding for corruption/fraud investigations,
welcomed the arrival of two criminal investi- prosecutorial venue, extra-territorial jurisdic-
gators from the DoD OIG Defense Criminal tion, liaison with DoS and foreign govern-
Investigative Service (DCIS) to Iraq. SIGIR ments, and coordination with legal attachés,
has extended its investigative arm into Kuwait, agencies with deployed investigators, and
joining two investigators from DCIS and four auditors.
from Army CID MPFU. SIGIR continues to work with MPFU on
Currently, SIGIR investigators are working suspensions and debarments of individuals
on 78 cases. Thus far, their work has resulted and companies. SIGIR investigators also work
in 5 arrests and 4 convictions, and another 23 closely with the DoJ Commercial Litigation
cases await prosecution at the Department of Section, Civil Division, pursuing civil rem-
Justice (DoJ). edies against individuals and companies, and
During this quarter, SIGIR and five other in many cases proceeding with side criminal
agencies established the International Contract investigations.
Corruption Task Force (ICCTF):
• MPFU, U.S. Army CID SIGIR-issued Subpoenas
• DoS OIG Criminal Investigations This quarter, SIGIR investigators have issued
Directorate four Inspector General (IG) Subpoenas. The
• USAID OIG legal authority for issuing these subpoenas is
• DCIS the Inspector General Act of 1978, as amend-
• Federal Bureau of Investigation (FBI) ed. The act empowers IGs to conduct and
supervise audits and investigations relating to
The task force identified 36 cases; SIGIR agency programs and operations.
contributed 9 cases to this effort. SIGIR is still
working on 37 cases for presentation to the International Contract
task force. This quarter, SIGIR investigations Corruption Task Force/
opened 27 cases and closed 43 of the prelimi- Joint Operations Center
nary and open cases. There are currently 78 On October 2, 2006, a Joint Operations Center
open investigations. (JOC) was established at SIGIR headquarters
SIGIR is also a member of several subcom- in Arlington, Virginia, to gather intelligence
mittees of the DoJ National Procurement and disseminate information on corruption
Fraud Task Force, most notably the Interna- and fraud investigations. On November 20,
2006, the ICCTF was created as a force multi- the country. In addition, as part of a unique
plier for all federal agencies engaged in investi- federal law enforcement agreement, the FBI
gating complex matters in combat and austere will run investigative leads for SIGIR at the
international environments. preliminary stages of investigations even
The ICCTF-JOC will coordinate the process before acceptance by the task force. The use of
of gathering intelligence, and sharing intel- resources with FBI field offices throughout the
ligence and appropriate case information. It country and legal attachés around the world
will also provide analytical and target linkage will add immeasurable value to criminal inves-
data response reporting for use by all partner tigations originating in Iraq and Kuwait. SIGIR
agencies. When fully functioning, the JOC will has also received a further personal commit-
allow case agents in the United States to work ment from FBI senior leadership regarding
together with special agents and prosecutors continued support for SIGIR and ICCTF.
outside the United States, reducing travel time
and expense, eliminating case overlap, and Suspensions and Debarments
providing valuable analytical case support. The Since December 2005, SIGIR has worked
ICCTF will also find prosecutorial jurisdiction closely with DoJ, CID, DCIS, and the Army
to determine suitable venue. Legal Service Agency’s Procurement Fraud
Initially designed for the smooth transi- Branch to suspend and debar contractors in
tion of investigations when SIGIR was to have cases of fraud or corruption within the Army,
terminated, the ICCTF-JOC will now con- including those involving Iraq reconstruc-
tinue SIGIR’s efforts, ensuring transparency tion or Army support contracts in Iraq. These
with other law enforcement agencies through cases arise both from criminal indictments
coordination and partnerships on all SIGIR filed in federal district courts and allegations of
cases—an unprecedented sharing within the contractor irresponsibility requiring fact-based
federal law enforcement community. examination by the Army’s Suspension and
To accomplish its mission more efficiently Debarment Official.
and cost-effectively, SIGIR leverages the In June 2003, DoD designated the Army as
resources of other law enforcement agencies the Executive Agent for contracting support
and the 20 SIGIR Investigations personnel in to the CPA; therefore, the Army’s Suspension
Kuwait and Iraq. This quarter, the startup of and Debarment Program is at the forefront of
this initiative generated momentum and set up ensuring the integrity of contractors perform-
a steady flow of federal law enforcement action ing these contracts. The goal of this program is
during the next several quarters. to ensure that these contracts are awarded to,
As part of the ICCTF-JOC, the FBI has and performed by, contractors who are honest,
assigned eight significant SIGIR criminal ethical, and have the ability to successfully per-
investigations to FBI field offices throughout form this important work. The Procurement
SIGIR Hotline
The SIGIR Hotline facilitates the reporting Summary of SIGIR Hotline Cases
of fraud, waste, abuse, mismanagement, and Open Cases
Table 3-4
New Cases
During this reporting period, the SIGIR Hot-
line received 19 new complaints. The new com-
plaints were classified in these categories:
• 11 involved fraud Closed Cases
• 3 involved mismanagement During this quarter, 31 hotline cases were
• 5 involved miscellaneous/personnel issues closed:
• 5 were referred to other inspector general
The SIGIR Hotline receives most reports agencies.
of perceived instances of fraud, waste, abuse, • 12 were dismissed for lack of sufficient
mismanagement, and reprisal by electronic information.
mail. SIGIR’s 19 new hotline complaints were • 11 complaints were closed based on infor-
received in these ways: mation received from SIGIR investigations.
• 17 by electronic mail • 2 complaints were closed based on informa-
• 1 by SIGIR Hotline phone call tion received from SIGIR audits.
• 1 by conventional mail • 1 complaint was closed based on assistance
provided by SIGIR public affairs.
Referred Complaints
After a thorough review, five complaints were
referred to outside agencies for proper resolu-
tion:
• 2 were sent to the OIG, U.S. Army.
• 1 was sent to the OIG, U.S. Air Force.
• 1 was sent to the OIG, Multi-National
Forces-Iraq.
• 1 was sent to the Joint Contracting
Command-Iraq/Afghanistan.
Capping Report: The Story $103 billion to Iraq reconstruction; more than
of Iraq Reconstruction $38 billion comes directly from bills passed
In keeping with SIGIR’s mandate from Con- by Congress. The Story of Iraq Reconstruction
gress—to provide recommendations that will provide a narrative history of the plan-
promote economy, efficiency, and effective- ning and execution of this reconstruction, with
ness in the administration of the reconstruc- a primary focus on the roles of the Office of
tion program in Iraq—SIGIR is producing a Reconstruction and Humanitarian Assistance,
cumulative account of these efforts, The Story CPA, USAID, DoD, and DoS. The report will
of Iraq Reconstruction. This capping report begin with preparations for reconstruction in
draws together SIGIR’s Quarterly Reports to 2002, follow progress through 2006, and con-
Congress, audits, inspections, investigations, clude with recommendations on how recon-
interviews with key decision-makers, and struction efforts can be better carried out in
SIGIR’s three reports on the lessons learned the future. SIGIR will publish The Story of Iraq
from Iraq reconstruction. Reconstruction at the end of 2007.
The United States, Iraq, and the interna-
tional community have committed more than
Legislation
Public Law 108-106, as amended, requires This act provides:
SIGIR to submit semiannual reports that meet Section 3001(o) of the Emergency Supple-
the requirements of Section 5 of the Inspector mental Appropriations Act for Defense and
for the Reconstruction of Iraq and Afghani-
General Act of 1978, as amended. Appendices
stan, 2004 (Public Law 108-106; 117 Stat.
A and B provide cross-references of this Report 1238; 5 U.S.C. App., note to section 8G of
with the Section 5 requirements. Public Law 95-452), as amended by sec-
In addition, Section 4(a)(2) of the Inspector tion 1054(b) of the John Warner National
General Act of 1978, as amended, which was Defense Authorization Act for Fiscal Year
applied to SIGIR by P.L. 108-106, as amended, 2007 (Public Law 109-364), is amended to
read as follows:
requires SIGIR to:
review existing and proposed legislation (o) Termination- (1)(A) The Office of the
and regulations relating to programs and Inspector General shall terminate 10
operations of such establishment and to months after 80 percent of the funds
make recommendations in the semiannual appropriated or otherwise made available
reports... concerning the impact of such to the Iraq Relief and Reconstruction Fund
legislation or regulations on the economy have been expended.
and efficiency in the administration of
programs and operations administered (B) For purposes of calculating the
or financed by such establishment or the termination of the Office of the Inspector
prevention and detection of fraud and General under this subsection, any United
abuse in such programs and operations. States funds appropriated or otherwise
made available for fiscal year 2006 for
the reconstruction of Iraq, irrespective of
Legislative Update the designation of such funds, shall be
On December 20, 2006, President Bush signed deemed to be amounts appropriated or
into law the Iraq Reconstruction Accountabil- otherwise made available to the Iraq Relief
ity Act of 2006 (P.L. 109-440). This legislation and Reconstruction Fund.
modified SIGIR’s termination date—repeal-
ing the October 1, 2007 date and returning (2) The Special Inspector General for
Iraq Reconstruction shall, prior to the
the termination formula of 10 months after
termination of the Office of the Special
80% “of the funds appropriated or otherwise Inspector General under paragraph (1),
made available to IRRF have been expended.” prepare a final forensic audit report
U.S. funds made available in FY 2006 for on all funds deemed to be amounts
Iraq reconstruction are also included in this appropriated or otherwise made available
termination calculation, bringing the total to to the Iraq Relief and Reconstruction Fund.
Introduction
Other Agency Audits
Other Agency Investigations
4
section
other agency oversight
introduction
The Special Inspector General for Iraq Recon- • Department of Defense Office of Inspector
struction (SIGIR) formed the Iraq Account- General (DoD OIG)
ability Working Group (IAWG) to coordinate • Department of State Office of Inspector
U.S. audit efforts in Iraq. The forward-deployed General (DoS OIG)
audit personnel of the various federal agencies • Department of the Army Inspector General
with audit presence in Iraq use the IAWG to • U.S. Army Audit Agency (USAAA)
coordinate audits, share Iraq relief and recon- • U.S. Agency for International Development
struction data, minimize audit disruption to Office of Inspector General (USAID OIG)
clients, and avoid duplicative efforts. • Government Accountability Office (GAO)
SIGIR also formed the Iraq Inspectors • Defense Contract Audit Agency (DCAA)
General Council (IIGC)494 in March 2004 to • Project and Contracting Office (PCO)
provide a forum for discussion of oversight in • Defense Intelligence Agency Office of the
Iraq and to enhance collaboration and coop- Inspector General
eration among the IGs of the agencies that • SIGIR
oversee Iraq reconstruction funds. Representa-
tives of member organizations meet quarterly Each quarter, SIGIR requests updates from
to exchange details about current and planned member organizations on their completed,
audits, identify opportunities for collaboration, ongoing, and planned oversight activities. This
and minimize redundancies. section summarizes the audits and investiga-
The most recent meeting was held on tions reported to SIGIR this quarter by DoD
November 13, 2006, at the SIGIR office in OIG, DoS OIG, USAID OIG, GAO, and
Arlington, Virginia. The organizations in USAAA. See Appendix K for DCAA updates.
attendance included: The U.S Department of the Treasury and the
Department of Commerce did not complete or
initiate any new audits this quarter.
Table 4‑1
Table 4-2
Table 4‑3
endnotes
1. $18.439 billion represents the amount appropriated by Congress for Iraq programs in IRRF 2 under
P.L. 108-106, enacted in November 2003. Congress had initially appropriated $18.649 billion to IRRF 2,
but also earmarked that $210 million be transferred to other accounts for programs in Jordan, Liberia,
and Sudan. Of the remaining $18.439 billion, the Administration transferred out of the IRRF to other
accounts roughly $562 million for Iraq-related programs that could be implemented only in other
accounts, such as a $352 million Iraq bilateral debt forgiveness program to the United States that required
funding in a Treasury account. Congress was notified of all transfers out of the IRRF. In addition, in FY
2006 appropriations, Congress earmarked that $9.95 million be transferred into the IRRF from the DoS
Economic Support Fund account.
2. These figures do not add up to 100% because of rounding and administrative costs.
3. UN Assistance Mission for Iraq, www.uniraq.org, January 16, 2007.
4. UNHCR, Supplementary Appeal Iraq Situation response, January 2007, p. 3; UN Assistance Mission
for Iraq, Human Rights Report, September 1-October 31, 2006, pp. 15-17; UNHCR, Update on the Iraq
Situation, November 2006, p. 1-2.
5. Committee To Protect Journalists, Special Report 2006, www.cpj.org, December 20, 2006.
6. PCO-I (Iraq) ceased operations on October 14, 2006 (in conjunction with the change of command), and
PCO-W (Washington D.C.) will cease operations in May 2007. The succession orders were signed by
Assistant Secretary of the Army (ALT) Bolton on October 13, 2006.
7. All IRRF 2 financial data in Section 2 is derived from the DoS Iraq Weekly Status report. At the time of
publication, the financial data in these status reports was the most accurate and current information
available on IRRF 2 funding.
8. GRD-PCO, response to SIGIR, January 18, 2007.
9. Department of Defense Secretary of the Army Update, December 31, 2006.
10. IRMO Rollup, Iraq Reconstruction Management System, December 30, 2006.
11. Multi-National Force-Iraq, Commander’s Emergency Response Program (CERP) Senior Leader’s
Meeting, September 20, 2005, p. 8.
12. IRMO, response to SIGIR, January 17, 2007.
13. NEA, response to SIGIR, January 16, 2007.
14. NEA, response to SIGIR, January 16, 2007, and GRD-PCO, response to SIGIR, January 17, 2007, note
that 4,500 MW represents the peak pre-war generation capacity and that published generation-capacity
numbers have ranged from 4,200-4,500 MW. GRD-PCO reports U.S. projects as having added or restored
2096 MW to Iraq’s generation capacity and state that the planned U.S. goal is 2555 MW.
15. IRMO, Load Served October–December 2006, December 2006.
16. GRD-PCO response to SIGIR, January 20, 2007, notes that the “Average daily load served is a better
measure of how much power is produced for the national grid because it measures generation over a
period of time rather than peak produced during the day. Average daily load served does not measure
distribution or how much power reaches the consumer.”
35. Weelock, Tom and McGuckin, Robyn, “Iraqi Power Sector: CPAs Legacy and Lessons,” Middle East
Economic Survey, Volume 47, Number 29, July 18, 2005.
36. DoS, Iraq Weekly Status, January 4, 2007, p. 13.
37. Al-Khalisi, Isam, “Iraq’s Electricity Ten-Year Plan—Is it Credible?” November 6, 2006, Middle East
Economic Survey, Volume 49, Number 45, p. 1.
38. DoS, Section 2207 Report, December 2006, electricity sector, p. I 56.
39. NEA response to SIGIR data call, January 16, 2007.
40. SIGIR, Quarterly Report to the United States Congress, October 30, 2006, p. 25.
41. GRD, Bi-Weekly Situation Report, November 13, 2006, p. 8.
42. DoS, Section 2207 Report, December 2006, electricity sector, p. I 54.
43. GRD-PCO, response to SIGIR, January 20, 2007.
44. IRMO electricity expert, response to SIGIR, December 27, 2006.
45. IRMO electricity expert, response to SIGIR, December 27, 2006.
46. Weelock, Tom and McGuckin, Robyn, “Iraqi Power Sector: CPAs Legacy and Lessons,” Middle East
Economic Survey, Volume 47, Number 29, July 18, 2005.
47. IRMO electricity expert, response to SIGIR, December 21, 2006.
48. USAID electricity expert, response to SIGIR, December 31, 2006.
49. USAID electricity expert, response to SIGIR, December 31, 2006.
50. GRD-PCO, response to SIGIR, January 20, 2007.
51. GRD-PCO, “FY 2007: Reconstruction Way Ahead,” July 15, 2006, slide 8.
52. USACE-GRD, Bi-Weekly Situation Report, December 25, 2006, p. 6.
53. IRMO, Weekly Status Report, Electricity Demand vs. Capacity, December 14–26, 2006.
54. NEA, response to SIGIR, January 16, 2007.
55. IRMO, response to SIGIR, “MW Additions Through 2007 (New/Repairs/Mods),” December 11, 2006.
56. DoE, “Iraq Country Analysis Brief,” December 2005. Available online at http://www.eia.doe.gov/emeu/
cabs/Iraq/Electricity.html.
57. IRMO electricity expert, response to SIGIR, December 27, 2006.
58. USAID electricity expert, response to SIGIR, December 31, 2006.
59. USAID electricity expert, response to SIGIR, December 31, 2006.
60. IRMO electricity expert, response to SIGIR, December 27, 2006.
61. DoS, Iraq Weekly Status, January 4, 2007, p. 13.
62. IRMO compiles Station Performance statistics in spreadsheet format. This figure is the average of the
daily fuel shortage amounts reported in the Station Performance spreadsheet.
63. GAO, 06-1094T, “Stabilizing Iraq: An Assessment of the Security Situation,” September 11, 2006.
64. IRMO electricity expert, response to SIGIR, December 27, 2006.
86. Al-Khayat, Faleh, “Iraqi ‘missing barrels’ increase to 140,000 b/d in third quarter; Production from
the south of Iraq rockets, but analysts believe the increase cannot be justified,” Platts Oilgram News,
November 6, 2006, Volume 84, Number 213, p. 2.
87. GRD-PCO expert, SIGIR interview, November 30, 2006.
88. GRD-PCO, response to SIGIR, January 6, 2007, p. 10.
89. USACE-GRD, Bi-Weekly Situation Report, November 13, 2006, p. 11.
90. IRMO, Action Memorandum, “Recommended Solutions to Relieve the Ministry of Oil from Hampering
Budgetary, Spending, and Procurement Constraints,” July 29, 2006, p. 3.
91. DoS, 2007 Budget Summary, December 24, 2006, p. 3.
92. Assumes a price of $50 per barrel of crude oil. Source: DoS, 2007 Budget Summary, December 24, 2006.
93. DoS, Section 2207 Report, Oil Infrastructure, October 2006, p. I-66.
94. SIGIR, Audit 06-038, “Unclassified Summary of SIGIR’s Review of Efforts To Increase Iraq’s Capability To
Protect Its Energy Infrastructure,” September 27, 2006, p. 1.
95. IRMO, response to SIGIR, January 19, 2007.
96. DoS, Section 2207 Report, December 2006, p. 166.
97. IRMO, Weekly Status Report, November 28, 2006.
98. DoS oil expert, SIGIR interview, December 14, 2006.
99. IRMO, Senior Consultants Meeting, response to SIGIR, November 28, 2006.
100. DoS oil expert, SIGIR interview, December 14, 2006.
101. IRMO, response to SIGIR, January 19, 2007.
102. IRMO, Weekly Status Report, November 14, 2006, p. 6.
103. GRD-PCO, response to SIGIR, November 30, 2006.
104. DoS oil expert, response to SIGIR, January 9, 2007.
105. IRMO, Weekly Status Report, November 28, 2006, p. 6.
106. Platts Oilgram News, Volume 84, Number 194, October 10, 2006.
107. DoS oil expert, SIGIR Interview, January 11, 2007.
108. Platts Oilgram News, Volume 84, Number 194, October 10, 2006.
109. DoS oil expert, SIGIR interview, December 14, 2006.
110. Iraqi 2005 and 2006 Budget, November 2006.
111. DoS oil expert, SIGIR interview, December 14, 2006.
112. DoS oil expert, SIGIR interview, December 14, 2006.
113. GAO, “Securing, Stabilizing, and Rebuilding Iraq: Key Issues for Congressional Oversight,” January 18,
2007, p. 69.
114. IRMO oil expert, response to SIGIR, January 2, 2007.
230. Testimony of Michel Gabaudan, regional representative for the United States and Caribbean at the Office
of the UNHCR, before the U.S. Senate Committee on the Judiciary, January 16, 2007.
231. DoS, Section 2207 Report, July 2006, p. I-115; DoS, Section 2207 Report, October 2006, p. I-104.
232. Ibid.
233. Office of the Assistant Secretary of Army–Financial Management and Comptroller, September 30, 2006.
234. UNHCR, “UNHCR Briefing Notes: Iraq Displacement,” November 3, 2006, p. 2. DoS, Section 2207
Report, October 2006, pp. I-107-108. UNHCR, Iraq Situation Map, Situation as of October 2006.
235. DoS, Section 2207 Report, October 2006, p. I-112; USAID Supplemental Update to the October 2006
Report, p. 2, December 13, 2006.
236. U.S. Embassy Baghdad International Narcotics and Law Enforcement (INL) “Rule of Law,” slide 17,
December 2006.
237. UNAMI, UN Human Rights Report, September 1-October 31, 2006, p. 4. UNAMI, UN Human Rights
Report, July 1-August 31, 2006, p. 3. Four-month average of casualties calculated from the following: July
2006–3,590; August 2006–3,009; September 2006–3,345; October 2006–3,709; November 2006–3,462;
December 2006–2,914; Total = 3,338.16.
238. Ibid.
239. UNHCR, “Supplementary Appeal Iraq Situation Response,” January 2007, p. 3. UNAMI, Human Rights
Report, September 1-October 31, 2006, pp. 15-17; UNHCR, Update on the Iraq Situation, November
2006, pp. 1-2.
240. UNCHR Press Release, “UNHCR launches new appeal for Iraq operations,” January 8, 2007, p. 1.
241. UNHCR, “Asylum Levels and Trends in Industrialized Countries, Second Quarter 2006,” September 2006,
pp. 10, 15.
242. Human Rights Watch, “The Silent Treatment, Fleeing Iraq, Surviving in Jordan,” November 2006, p. 5.
Refugee International Bulletin Iraq Refugee Crisis: International Response Urgently Needed, December 5,
2006, pp. 1-2.
243. UNAMI, UN Human Rights Report, November 1-December 31, 2006, p. 17.
244. UNAMI, UN Human Rights Report, July 1-August 31, 2006, p. 10.
245. UNAMI, UN Human Rights Report, November 1-December 31, 2006, p. 9.
246. DoS, Iraq Weekly Status, December 20, 2006, p. 10.
247. UNHCR, “UNHCR Briefing Notes: Iraq displacement,” UNHCR, November 3, 2006, p.1. UNHCR Press
Releases, “UNHCR launches new appeal for Iraq Operations”, January 8, 2007, p. 1. http://www.unhcr.
org/news/NEWS/45a243a54.html.
248. DoS, interview with Robin Young, National Public Radio – Ellen Sauerbrey, Assistant Secretary for
Population, Refugees, and Migration, December 12, 2006, http://www.state.gov/g/prm/rls/2006/77900
html.
249. IRMO, response to SIGIR, January 16, 2007.
250. USAID, response to SIGIR, October 17, 2006.
251. IRMO, response to SIGIR, January 18, 2007.
252. IRMO, response to SIGIR, October 17, 2006.
309. PCO, “Facilities and Transportation Sector–GRD-PCO Historical Narrative [DRAFT],” March 21, 2006.
310. GRD-PCO, response to SIGIR, January 17, 2007.
311. GRD-PCO, response to SIGIR, December 18, 2006.
312. GRD-PCO, response to SIGIR, January 4, 2007.
313. GRD-PCO, response to SIGIR, January 4, 2007.
314. GRD-PCO, response to SIGIR, January 17, 2007.
315. GRD-PCO, response to SIGIR, January 4, 2007.
316. SIGIR, PA-06-052, Summary Report: Ground Projects for the Quarter Ended March 31, 2006, July 31, 2006.
317. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 8.
318. DoD, “Measuring Stability and Security in Iraq,” August 29, 2006, pp. 10, 12.
319. U.S. Embassy Baghdad International Narcotics and Law Enforcement, Draft Rule of Law presentation,
December 17, 2006; FY 2007 budget subject to final action by the U.S. Congress; in addition to these INL
programs, an additional $8.5 million is slated for miscellaneous programs.
320. GRD-PCO, response to SIGIR, January 17, 2007.
321. DoS, Iraq Weekly Status, January 10, 2007, p. 8; These numbers are further broken down as approximately
132,700 soldiers, 900 Air Force personnel, and 1,100 Navy personnel.
322. DoS, Iraq Weekly Status, January 10, 2007, p. 8; These numbers are further broken down as approximately
135,000 police officers, 24,400 National Police, and 28,900 other Ministry of Interior forces.
323. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 31. GAO reports that the Ministry
of Defense does not include the numbers of troops who are absent without leave (AWOL). The Ministry
of Interior includes AWOL troops, thereby overstating the number of police on duty.
324. DoD, “Measuring Stability and Security in Iraq,” July 2005, p. 13.
325. GAO Audit 07-308SP, “Securing, Stabilizing, and Rebuilding Iraq,” January 9, 2007, p. 21.
326. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 27.
327. GAO Audit 07-308SP, “Securing, Stabilizing, and Rebuilding Iraq,” January 9, 2007, p. 23.
328. DoS, Iraq Weekly Status, January 4, 2007, p. 6.
329. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 32.
330. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, pp. 33, 36, 37.
331. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 18.
332. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 35.
333. DoS, Iraq Weekly Status report, January 4, 2007, p. 6.
334. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 43.
335. DoD, News Briefing with Lt. Gen. Martin Dempsey from Iraq, December 19, 2006, (www.defenselink.
mil/Transcripts/Transcript.aspx?TranscriptID=3831).
336. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 37.
337. SIGIR Audit 06-038, “Unclassified Summary of SIGIR’s Review of Efforts To Increase Iraq’s Capability To
Protect Its Energy Infrastructure,” September 27, 2006, pp. 1-3.
338. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 31; Office of the Secretary of
Defense, response to SIGIR, January 17, 2007.
339. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 38.
340. Transcript from Lt. General Martin Dempsey, December 19, 2006, http://www.defenselink.mil/
Transcripts/Transcript.aspx?TranscriptID=3831.
341. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 38.
342. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 9.
343. GRD-PCO, response to SIGIR, January 4, 2007.
344. DoD website, http://www.defenselink.mil/home/dodupdate/iraq-update/Handovers/index.html.
345. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 29.
346. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 29.
347. MNC-I, “Third Iraqi Army Division Assumes Responsibility, “ Press Release on December 5, 2006, http://
www.mnf-iraq.com/index.php?option=com_content&task=view&id=7798&Itemid=21
348. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 27.
349. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 29.
350. GAO Audit 07-308SP, “Securing, Stabilizing, and Rebuilding Iraq,” January 9, 2007, pp. 20-21.
351. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 29.
352. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, pp. 39, 46.
353. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, pp. 39, 47.
354. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, pp. 43-44.
355. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 3.
356. GAO Audit 07-308SP, “Securing, Stabilizing, and Rebuilding Iraq,” January 9, 2007, p. 25.
357. UN Assistance Mission for Iraq, Human Rights Report: November 1-December 31, 2006, pp. 2, 4.
358. UN Assistance Mission for Iraq, Human Rights Report: September 1-October 31, 2006, p. 2.
359. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 23.
360. DoD, “Measuring Stability and Security in Iraq,” August 29, 2006, pp. 33, 53.
361. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 23.
362. NEA, response to SIGIR, December 14, 2006.
363. DoD, News Briefing with Lt. Gen. Martin Dempsey from Iraq, December 19, 2006, www.defenselink.
mil/Transcripts/Transcript.aspx?TranscriptID=3831.
364. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, p. 31.
365. DoD, “Measuring Stability and Security in Iraq,” August 29, 2006, p. 51.
366. DoD, “Measuring Stability and Security in Iraq,” August 29, 2006, p. 18.
367. DoD, News Briefing with Lt. Gen. Martin Dempsey from Iraq, December 19, 2006, www.defenselink.
mil/Transcripts/Transcript.aspx?TranscriptID=3831.
368. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, pp. 25-26.
369. DoD, “Measuring Stability and Security in Iraq,” December 18, 2006, pp. 34, 36, 38.
370. IRMS and USAID project data for December 30, 2006; many of the Equipment Procurement projects that
were previously reported as IRRF 2 are currently classified as either IRRF or non-IRRF and therefore are
not included in the current project totals.
371. GRD-PCO, response to SIGIR, January 17, 2007.
372. USACE-GRD, Bi-Weekly Situation Report, September 29, 2006, p. 15.
373. GRD-PCO, response to SIGIR, January 4, 2007.
374. GRD-PCO, response to SIGIR, January 17, 2007.
375. A punch-list is a list of deficiencies identified during the pre-final or final inspection.
376. GRD-PCO, response to SIGIR, December 18, 2006.
377. GRD-PCO, response to SIGIR, January 17, 2007.
378. GRD-PCO, response to SIGIR, January 17, 2007.
379. GRD-PCO, response to SIGIR, January 4, 2007.
380. GRD-PCO, response to SIGIR, January 17, 2007.
381. GRD-PCO, response to SIGIR, January 4, 2007.
382. GRD-PCO, response to SIGIR, January 17, 2007.
383. GRD-PCO, response to SIGIR, January 17, 2007.
384. PCO, response to November 30, 2006 interview notes, December 6, 2006.
385. GRD-PCO, response to SIGIR, January 17, 2007.
386. GRD-PCO, response to SIGIR, January 17, 2007.
387. DoS, Section 2207 Report, October 2006, p. I-91.
388. USAID, responses to SIGIR, December 29, 2006.
389. GRD-PCO, response to SIGIR, January 4, 2007.
390. GRD-PCO, response to SIGIR, January 4, 2007.
391. GRD-PCO, SIGIR interview, November 30, 3006.
392. GRD-PCO, response to SIGIR, January 11, 2007.
393. DoS, Iraq Weekly Status, November 22, 2006, p. 14.
394. UN Assistance Mission for Iraq, Human Rights Report: November 1–December 31, 2006, p. 15.
395. IRMO, BSP Health Brief, Fall 2006; NEA, SIGIR interview, December 20, 2006.
396. This report combines two subsectors of the DoS Section 2207 Report: Transportation and
Communications, and Roads, Bridges, and Construction. For definitions of these and other sectors, see
Appendix C.
397. GRD-PCO, response to SIGIR, January 4, 2007.
398. IRMO, response to SIGIR, October 13, 2006.
399. GRD-PCO, response to SIGIR, January 4, 2007.
400. Security upgrades include perimeter security, wharf security, and remote monitoring.
401. GRD-PCO, response to SIGIR, January 4, 2007.
402. Ibid.
403. DoS, Section 2207 Report Selected Metrics, October 2006, p. 14.
404. GRD-PCO, response to SIGIR, June 19, 2006.
405. NEA, response to SIGIR, January 4, 2007.
406. DoS, Section 2207 Report, October 2006, p. I-83.
407. GRD-PCO, response to SIGIR, January 17, 2007.
408. GRD-PCO, response to SIGIR, January 17, 2007.
409. DoS, Section 2207 Report, October 2006, pp. I-83-84.
410. GRD-PCO, response to SIGIR, January 4, 2007.
411. DoS, Section 2207 Report, October 2006, pp. I-83-84.
412. GRD-PCO, response to SIGIR, January 4, 2007.
413. IRMO, response to SIGIR, July 20, 2006.
414. GRD-PCO, response to SIGIR, January 4, 2007.
415. IRMO, Iraq Weekly Status Report, October-December, 2006.
416. DoS, Section 2207 Report, Selected Metrics, October 2006, p. 14.
417. IRMO, Information Memorandum from Acting IRMO Director to Deputy Chief of Mission, April 19,
2006.
418. IRMO, response to SIGIR, October 13, 2006.
419. IRMO, Transportation Talking Points, November 2, 2006.
420. NEA, SIGIR interview, December 20, 2006.
421. GRD-PCO, response to SIGIR, January 4, 2007.
422. DoS, Section 2207 Report, October 2006, p. I-81.
423. DoS, Section 2207 Report, October 2006, p. I-81.
424. NEA, response to SIGIR, January 4, 2007.
425. GRD-PCO, response to SIGIR, January 4, 2007.
426. IRMO, Iraq Weekly Status Report, October–December, 2006.
427. IRMO, Iraq Weekly Status Report, November 21, 2006, p.10.
428. GRD-PCO, response to SIGIR, October 4, 2006.
429. GRD-PCO, response to SIGIR, January 4, 2007.
430. GRD-PCO, response to SIGIR, January 17, 2007.
431. GRD-PCO, response to SIGIR, July 18, 2006.
432. GRD-PCO, response to SIGIR, June 19, 2006.
433. GRD-PCO, response to SIGIR, January 4, 2007.
434. PCO, “Facilities and Transportation Summary,” March 24, 2006, p.8.
435. GRD-PCO, response to SIGIR , January 4, 2007.
436. IRMO, “Transportation Talking Points,” November 16, November 30, and December 7, 2006.
437. DoT FHA, Public Roads, November/December 2006, Vol. 70, No. 3.
438. GRD-PCO, response to SIGIR, January 4, 2007.
439. GRD-PCO, response to SIGIR, January 17, 2007.
440. GRD-PCO, response to SIGIR, January 4, 2007.
441. DoS, Section 2207 Report, October 2006, p. I-84.
442. GRD-PCO, response to SIGIR, January 4, 2007.
443. GRD-PCO, response to SIGIR, October 10, 2006.
444. DoS, Section 2207 Report, October 2006, p. I-85.
445. GRD-PCO, response to SIGIR, January 4, 2007.
446. DoS, Section 2207 Report, October 2006, p. I-85.
447. GRD-PCO, response to SIGIR, January 4, 2007, and January 17, 2007.
448. DoS, Section 2207 Report, October 2006, p. I-85.
449. GRD-PCO, response to SIGIR, January 4, 2007.
450. DoS, Section 2207 Report, October 2006, p. I-86.
451. IRMO, Iraq Weekly Status Report, November 14, 2006, p. 10.
452. IRMO, “Office of Communications and Information Technologies: Priorities and Programs,” November
7, 2006.
453. IRMO, Iraq Weekly Status, January 2, 2007, p. 23.
454. Available at http://www.irffi.org.
455. World Bank, responses to SIGIR, January 3 and 10, 2007.
456. The 19 permanent Paris Club members (Austria, Australia, Belgium, Canada, Denmark, Finland, France,
Germany, Ireland, Italy, Japan, Netherlands, Norway, Russian Federation, Spain, Sweden, Switzerland,
United Kingdom, United States) reached an agreement to forgive 80% of GOI’s debt. GOI is negotiating
bilaterally with non-Paris Club countries to reduce its external debt.
457. SIGIR tracks progress in the Energy sector in its electricity, oil and gas, and water sectors of this Report.
458. Ministry of Planning, Donor Assistance Database (DAD), January 3, 2007, http://www.mop-iraq.org/
dad.
459. IRNA, “Iran Oil Ministry to invest 45 million dollars in oil pipeline to Iraq,” December 4, 2006.
460. Available at http://www.irffi.org.
461. “Iran grants Iraq $1 billion loan,” spokesman of IRI government, www.spokesman.gov.ir.
462. Embassy of Japan, response to SIGIR, January 4, 2007.
463. European Commission, response to SIGIR, January 4, 2007.
464. World Bank, Iraq Data Sheet, December 31, 2006. Expenditures for project processing, supervision,
monitoring, administration costs, and external audits total approximately $9 million, bringing total
expenditures to $85.4 million.
483. Report on Material Existence Performed at Bechtel National, Inc. (BNI) on Iraq Infrastructure Reconstruc-
tion Phase I Contract No. EEE-C-00-03-00018-00 and Phase II Contract No. SPU-C-00-04-00001-00
(DCAA Report No. 2131-2005R10320003), September 11, 2005; Report on Purchases Existence and Con-
sumption—FY 2005 Bechtel National, Inc.—Iraq Infrastructure Reconstruction Contract USAID Prime Con-
tract Nos. EEE-C-00-03-00018-00 and SPU-C-00-04-00001-00 (DCAA Report No. 4281-2005D10320002,
Revised), September 23, 2005.
484. SIGIR-06-037, Interim Audit Report on Improper Obligations Using the Iraq Relief and Reconstruction Fund
(IRRF 2), September 22, 2006.
485. A design-build contract places the design and building phases of a project under the same contract.
486. This official is now the USACE CFO.
487. Of the $389.2 million in expired funds, GRD controlled $385.2 million, and other agencies controlled the
balance of $4 million.
488. The International Compact for Iraq is a joint GOI-UN effort launched in July 2006 to bring together the
international community and multilateral organizations to spur political, economic, and social develop-
ment in Iraq.
489. SIGIR report, PA-06-078.1 & 079.1, “Quick Reaction Report on the Baghdad Police College, Baghdad,
Iraq,” September 27, 2006.
490. A cleanout is a soil (wastewater) pipe fitting and associated piping connected to a building sewer or lateral
sewer line.
491. The Project and Contracting Office was transferred to the U.S. Army Corps of Engineers Gulf Region
Division on December 4, 2005.
492. SIGIR uncovered this scheme to defraud the CPA of more than $8.6 million. For complete details of this
conspiracy, see the SIGIR October 2006 Report, Appendix J.
493. On August 4, 2006, Salam pled guilty to one count of a violation of the Foreign Corrupt Practices Act of
1997.
494. IIGC members: SIGIR (Chair), DoS IG (Co-Vice Chair), DoD IG (Co-Vice Chair), Army IG, USAID
IG, Treasury IG, DoC IG, DCAA, USAAA, GAO (observer member), USACE Chief Audit Executive
(observer member).
Appendix Name Page Number
Acronyms Definitions
ABOT Al Basrah Oil Terminal
ACWG Anti-corruption Working Group
AFCEE Air Force Center for Engineering Excellence
ARABOSAI Arab Organisation of Supreme Audit Institutions
ARDI Agriculture Reconstruction and Development Program for Iraq
Bechtel Bechtel National, Inc.
BIA Basrah International Airport
BIAP Baghdad International Airport
BPC Baghdad Police College
BPD Barrels Per Day
BSA Board of Supreme Audit
CAG Community Action Group
CAP Community Action Program
CBI Central Bank of Iraq
CBTC Communications-Based Train Control
CCCI Central Criminal Court of Iraq
CDP Capacity Development Program
CERP Commander’s Emergency Response Program
CFN Consolidated Fiber Network
CID U.S. Army Criminal Investigation Division
CMC Communications and Media Commission
Compact International Compact for Iraq
COR Contracting Officer Representative
Corporate Bank Corporate Bank Financial Services
CPA Coalition Provisional Authority
CPI Commission on Public Integrity
CRRPD Commission for Resolution of Real Property Disputes
CSRC Civil Society Resource Center
CTC Cost-to-complete
DAD Donor Assistance Database
DBE Department of Border Enforcement
DCAA Defense Contract Audit Agency
Acronyms Definitions
DCIS Defense Criminal Investigative Service
DCMA Defense Contract Management Agency
DFI Development Fund for Iraq
DFID Department for International Development (United Kingdom)
DoD Department of Defense
DoD OIG Department of Defense Office of Inspector General
DoE Department of Energy
DoJ Department of Justice
DoS Department of State
DoS OIG Department of State Office of Inspector General
DynCorp DynCorp International, LLC
EAC Estimate at Completion
EC European Commission
EG Economic Governance (USAID)
EPC Engineering, Procurement, and Construction
ESF Economic Support Fund
FBI Federal Bureau of Investigation
FMIS Financial Management Information System
FOB Forward Operating Base
FPS Facilities Protection Service
FY Fiscal Year
GAO Government Accountability Office
GOI Government of Iraq
GOSP Gas-oil separation plant
GRC Gulf Region Division Central District (USACE)
GRD Gulf Region Division (USACE)
GRD-PCO Gulf Region Division – Project and Contracting Office
GRS Gulf Region Division South District (USACE)
GW Gigawatt
IAER Iraq Agriculture Extension Revitalization Project
IAMB International Advisory and Monitoring Board
IAPG Investment and Action Plan for Growth
IAWG Iraq Accountability Working Group
ICBG Iraq Company for Bank Guarantees
ICCTF International Contract Corruption Task Force
ICRC International Committee of the Red Cross
ICSP Iraq Civil Society Program
IDB Islamic Development Bank
IDP Internally Displaced Persons
IG Inspector General
IMF International Monetary Fund
IMMDF Iraq Middle Market Development Fund
Acronyms Definitions
INL Bureau of International Narcotics and Law Enforcement Affairs
IOM International Organization for Migration
IPC International Plumbing Code
IRC International Red Crescent
IREX International Research and Exchange Board
IRFFI International Reconstruction Fund Facility for Iraq
IRI International Republican Institute
IRMO Iraq Reconstruction Management Office
IRRF Iraq Relief and Reconstruction Fund
ISF Iraqi Security Forces
ISFF Iraq Security Forces Fund
ISRB Iraqi Strategic Review Board
ITF Iraq Trust Fund
ITP Iraq-Turkey Pipeline
JASG- C Joint Area Support Group-Central
JCC-I/A Joint Contracting Command-Iraq/Afghanistan
JOC Joint Operations Center
KRG Kurdistan Regional Government
kV Kilovolt
LOGCAP Logistics Civilian Augmentation Program
LPG Liquefied Petroleum Gas
MBPD Million Barrels Per Day
MCT Ministerial Coordination Team (also IRMO MCT)
MFI Microfinance Institution
MNC-I Multi-National Corps-Iraq
MNF-I Multi-National Force-Iraq
MNSTC-I Multi-National Security Transition Command-Iraq
MOU Memorandum of Understanding
MPFU Major Procurement Fraud Unit
MSCFD Million Standard Cubic Feet Per Day
MW Megawatt
MWh Megawatt Hours
NCDP National Capacity Development Program
NCR Nonconformance Report
NCT National Coordination Team
NDI National Democratic Institute
NEA Bureau of Near Eastern Affairs (DoS)
NGA National Geospatial-Intelligence Agency
NGO Non-governmental Organization
NRDP National Reconciliation and Dialogue Project
NRRRF Natural Resources Risk Remediation Fund
O&M Operations and Maintenance
Acronyms Definitions
OIG Office of Inspector General
OMS Operations, Maintenance, and Sustainment
P.L. Public Law
P.L. 108-106 National Defense Authorization Act for FY 2004
P.L. 109-234 FY 2006 Emergency Supplemental Appropriations
P.L. 109-440 Iraq Reconstruction Accountability Act of 2006
PAR Project Assessment Report
Parsons Parsons Delaware, Inc.
PCO Project and Contracting Office
PDS Public Distribution System
PHC Primary Healthcare Center
PMP Performance Monitoring Plan
PRDC Provincial Reconstruction Development Committee
PRT Provincial Reconstruction Team
PTT Police Transition Team
QA Quality Assurance
QAR Quality Assurance Representative
QC Quality Control
QM Quality Management
RFP Request for Proposal
RRT Regional Reconstruction Team
SBA Stand-By Arrangement (IMF)
SCADA Supervisory Control and Data Acquisition
SIB Strategic Infrastructure Battalion
SIGIR Special Inspector General for Iraq Reconstruction
SIMI Support for Independent Media in Iraq
SIRIS SIGIR Iraq Reconstruction Information System
SOW Statement of Work
SSN Social Safety Net
TO Task Order
TPD Tons per Day
TRA Transition Readiness Assessment
Treasury U.S. Department of Treasury
UK United Kingdom
UN United Nations
UNAMI United Nations Assistance Mission for Iraq
UNDG United Nations Development Group
UNDG ITF United Nations Development Group Iraq Trust Fund
UNDP United Nations Development Program
UNHCR United Nations High Commissioner for Refugees
UNICEF United Nations International Children’s Emergency Fund
USAAA U.S. Army Audit Agency
Acronyms Definitions
USACE United States Army Corps of Engineers
USAID United States Agency for International Development
USAID OIG United States Agency for International Development Office of Inspector General
USDA United States Department of Agriculture
USIP United States Institute of Peace
WB World Bank
WB ITF World Bank Iraq Trust Fund
WBBN Wireless Broadband Network
WSIS Water Sector Institutional Strengthening Program
WSSP Water Sector Sustainment Program
WTO World Trade Organization