Daily Progress Report

Engineer Name: Sangay Tenzin Name of Site: 30 M Pedestrain Bridge Fabrication Brg. Location: Open outfall 1
DPR Date: 8/6/2023 Report Date: 8/7/2023

Sl.No. Description of item Total No. No. (Progress) % (Progress) Length (M) Width (M) Height (M) Qty (M) Qty (Kg) Remarks

Fabrication
RHS 240x120x6mm @ 32.05 132.252 4238.677
Length-6m A 20 20 100% 6 120.000
-2.891 m A1 2 2 100% 2.891 5.782
-0.962 m A3 4 4 100% 0.962 3.848
1
-1.311 m A2 2 2 100% 1.311 2.622
12mm MS plate A3 4 4 100% 0.24 0.120 0.012 10.852
132.252

RHS 122x61x5.4mm @ 14.1 62.622 882.970 Fitting in position and


Length-6m C 10 10 100% 6 60.000 welding completed
-1.311 m C1 2 2 100% 1.311 2.622 (Pending: Assembling and
Fabrication at site)
2 -3.94 m C2 16 0 0% 3.94 0.000
-3.999m C3 29 0 0% 3.999 0.000
62.622

RHS 96x48x4.8mm @ 9.660 165.748 1601.126


Length-1.341m B1 112 112 100% 1.432 160.384
3 B2 4 4 100% 1.341 5.364
165.748
6733.624
Staff personal Labour Machine Material consumed
BoQ
Description of work DPR Qty. % (Progress)
No. Eng. Sup. Sury. Sury. helper Skilled Unskilled Type Qty. Type Qty. (Kg)

Fitting in postion and welding Welding RHS


322 800.563 1 - - - 73% 6 4 3
(30M Pedestrain Bridge) Machine 240x120x6mm

RHS
Grinder 2
122x61x5.4mm

Gas Cutter 1 12mm MS plate

RHS
96x48x4.8mm
Primer painting of 20M
322 Pedestrain Bridge (45%) - One Hydra 1
side frame completed

Total 0.000

Prepared By: