PROPOSED UPGRADING WORKS FOR PARIT MAHANG, KUALA SELANGOR (PHASE 2)

PO: -
BAR CHART
JALAN RIZAB HAJI ALI 1-3, JALAN RIZAB SUDAR 1-2, JALAN 4 PARIT MELINTANG & JALAN PARIT BARU

Bil Description Date Start Date Finish Weeks 2023 2024


NOV-DEC JAN FEB MAC APRIL MAY JUN JULY AUG

1 Contract Period ( 9 Month) 3-Nov-23 2-Aug-24 39

2 Site Possession 3-Nov-23 3-Nov-23 0

3 Permit Application 3-Nov-23 11-Jan-24 9

4 Material Order & Delivery


a) HDPE 180mm (2,955m) 11-Jan-24 11-Feb-24 4

b) HDPE 32mm (1,000m) 11-Jan-24 11-Feb-24 4

5 Pipelaying
a) Mainpipe HDPE 180mm (2,955m) 11-Feb-24 28-May-24 15

6 Pressure & leakage test


a) HDPE 180mm (2,955m) 28-Apr-24 30-May-24 4

7 Installation fitting
a) S-Bend (7nos) 10-May-24 28-May-24 2

b) Hydrant (1nos) 15-May-24 15-Jun-24 4

8 Communication Pipe
a) Communacation pipe laying (1,000m) 8-May-24 9-Jun-24 4

b) Tapping saddle (32nos) 8-May-24 9-Jun-24 4

c) Meter stand (80nos) 8-May-24 9-Jun-24 4

d) Leakage test (1,000m) 9-Jun-24 5-Jul-24 3

9 Connection (8nos) 1-Jun-24 1-Jul-24 4

10 Sterilizing & flushing 20-Jun-24 15-Jul-24 3

11 Decommission (15nos) 1-Jul-24 15-Jul-24 2

12 Flow Measurement
a) Initial Flowmeasurement 25-Feb-24 10-Mar-24 2

b) Final Flowmeasurement 1-Jul-24 10-Jul-24 1

13 Mill & pave (100m) 15-Jun-24 20-Jul-24 5

14 Handing over 2-Aug-24 2-Aug-24 0